Beruflich Dokumente
Kultur Dokumente
Puente Nigale
Rojas, Maiker
Engineer at Odebrecht Venezuela S.A.
Miquilena, Irene
Engineer at Odebrecht Venezuela S.A.
Souza, Antonio
Engineer at Odebrecht Venezuela S.A.
ABSTRACT: This document presents PDA Tests performed as part of monitoring and con-
trol of Pile Driving at Offshore Foundations in the construction of Puente Nigale. The project
consists of a 12 km cable stayed link for both road and rail traffic located in Maracaibo, eastern
Venezuela and will support the existing 8.6 km link, Puente General Rafael Urdaneta by releas-
ing traffic load. The design proposes a curved alignment with two separated but parallel super-
structures, carrying road and rail respectively. The foundations and pile caps will be common
for both superstructures. At the present time, 9 piles with an inner diameter of 1.8m were moni-
tored as part of control of driving activities and verification of capacities using Impact Hydrau-
lic hammers obtaining a set-up of 1.14 for all piles after PDA Test. Driving equipment was ver-
ified by reaching bearing capacity and minimum tip level established by designers.
1 INTRODUCTION
1.1 Project description
The urban and industrial growth in the area, the need to establish new routes and the idea of re-
leasing traffic load from the original bridge engender the construction of a second overcrossing
on the Maracaibo strait, Puente Nigale.
The project consists of a 12 km link for both road and rail traffic connecting Santa Cruz de
Mara on the east coast to Punta de Palmas on the west coast, subdivided in two viaducts, a low
level bridge, two elevated bridges and cable-stayed bridge over the Maracaibo lake navigation
channel.
In case of the Foundations, piers with 18, 21 and more piles will be built to support road and
rail superstructures. In total, 128 piers will be executed in offshore conditions, including two
pylons at both sides of navigation channel. It was planned the execution of the foundations lo-
cated approximately at center of alignment, P54 to P64, at the Low Level Bridge section. Those
piers require driving 21 steel pipe piles with 1.8 meters of inner diameter. The target depth
fixed as tip level ranging from -43 to -65 meters below Medium Level of Maracaibo's Lake
(MLMN). The minimum Pile Capacity in compression for these piles is 27 MN according to the
geotechnical design report submitted by designer.
Calculations of Axial Bearing Capacity were carried out with CPTu data by direct CPT
methods (AASHTO, 2010) and, as part of construction specifications, PDA Test was defined as
a verification technique of End Bearing Capacity, including CAPWAP analysis after collection
of data on site.
Design states that, in general, the highest utilizations are found in the corner piles and their
nearest neighboring piles, as indicated in the figure below.
Figure 3. Plan view of a pile cap. Darker piles have the highest
utilizations, meanwhile lighter ones have lowers.
After completion of driving with a major unit, CGL 590 from BSP with a 590 kN-m as maxi-
mum energy could be applied per stroke; capacities higher than 27 MN were reached. In gen-
eral, according to the maximum energy rated by each unit (CG300 and CGL 590) more than
50% of time the energy applied exceeded 70% of maximum energy for both hammers as shown
in figures 6 and 7. The frequency distribution analysis from all monitoring recorded by PDA
model PAX-8 is expressed in percentage and obtained by dividing the load transferred to the
hammer and bearing capacity of the hammer.
After complete installation, a setup phenomenon was analyzed. In case of piles at P54 and P55,
an average value 1.14 after 8 days in average was observed. In case of piles 3 and 10 on P54
setup analysis was made with superimposed capacity as reported by CAPWAP report.
In figure 8 is shown the comparison for this values reported at piles P54 and P55.
5 CONCLUSIONS
From Pile Dynamics Test at piers 54 and 55 in offshore activities for Puente Nigale project was
found that unit CGL590 has enough capacity for mobilized total resistance established by de-
signer. The Setup factor for those piles was 1.14 after 8 days in average; those values could be
adopted at least for Piers 56, 57, 58 and 59 as references values for planning activities and con-
siderations for PDA Tests which will be performed in the piles of those piers. It is highly rec-
ommended to perform EOD and BOR monitoring at least on opposite corners of piles for each
pier as indicated by construction specifications. In the same way, is recommended increase ca-
pacity for vibratory driving, reducing the use of unit CGL590 consequently.
6 REFERENCES