Pipeline construction process

The QCLNG Project involves building the longest large-diameter pipeline in Australia.

1 2 3 4 5 6

Survey Clear and grade Stringing and bending Welding and Weld joint coating Pre-trenching
Detailed engineering, environmental easement The 42 inch steel pipes are hauled by ultrasonic testing Each weld is grit blasted and covered A trench is dug for the pipeline. As part
and cultural surveys are conducted truck to the easement. The pipes are laid with a protective coating to prevent of the fauna management program, the
to determine the most suitable A 40 metre easement is cleared and end-to-end. The pipe can be bent using The pipe is welded above ground. All the corrosion and protect against trench is monitored and soil ramps are
construction techniques. graded along the pipeline route . specialised equipment to match changes welds are subject to ultrasonic testing mechanical impacts. built to enable animals to exit the trench
in terrain or direction in route. to ensure they meet Australian and easily.
international standards.

7 8 9 10 11 12

Lowering in Tie-ins Padding and backfilling Pressure testing Reinstatement Signage


Side boom tractors are used to lower the A tie-in is when two lowered-in pipe Fine soil is placed around the pipe in the The integrity of the pipeline is further The easement is restored to its original As a safety measure, signs are erected
welded pipe into the trench. strings are welded together in the trench to act as padding, protecting the verified using hydrostatic testing in state as much as possible. Where to warn of the location of the buried
trench. pipeline. After padding is completed the accordance with Australian Standard required, erosion control mechanisms pipeline.
About one kilometre of pipe is lowered trench is backfilled and compacted with 2885 (AS2885). The pipeline is capped are constructed and additional topsoil is
into the trench at a time. the subsoil and the original topsoil. with test manifolds and water is spread to encourage soil retention and
pumped in to a pressure higher than vegetation growth.
the maximum allowable operating gas
pressure.