DESIGN DATA & REFERENCES

UNIT TAG
STATION RIFFA
Basement Corridor Grid 2-3
LOCATION
L1-14
MANUFACTURER MAICO-DYNAIR
MODEL NO CC-HT 1004-T 6-12°
SERIAL NO 1CY1206
CHECK LIST

Sr. No. Description


T&C Engineer

1 Pre-Requisite For PSAT

1.01 Record details & visullay inspect all connected systems

1.02 Varify availabilty of approved IRN

1.03 Varify all duct access doors are securely closed.

1.04 Varify Electrical circuits are completed, inspected and approved

1.05 MCC panels are installed and commissioned

1.06 ATS panels are installed and commissioned

1.07 Ensure that lock out tag out in place.

1.08 Ensure HSE in place.

1.09 Ensure availabilty of approved drawings.

1.10 Ensure T & C Procedure is approved

2 Pre-Commissioning Checks

2.01 Check motor & fan name plate and compare with approved submittal

Fan casing free of debris and transit bolts removed. Check the
2.02
connection of fan inlet & outlet are done with proper alignment
2.03 Fan rotates freely

2.04 Varity all respective electrical components before starting the fan.
2.05 Direction of Rotation of fan

2.06 varify that there are no abnormal sounds or vibrations

2.07 Anti-vibration mountings in good condition and secure.


Check the fan is installed as per the approved shop drawings and
2.08
manufacturer’s instructions.
2.09 Casing access covers secure and airtight.

2.10 Motor holding down / adjusting bolts secure.

2.11 Guards secure (If Applicable)

2.12 Flexible connections are properly installed and are in good condition

2.13 Flow direction as per the marking on the fan casing

2.14 Fan belts fitted and correct in type (If Applicable)

2.15 Check pulley alignment and check belt tension. (If Applicable)

2.16 Check fan and motor bearings for lubrication. (If Applicable)

2.17 Check Electrical isolaor for access and varify circuits & operation.

2.18 Check Electrical isolaor for access and varify circuits & operation.
Comments

Description T&C Engineer Specialist/ Vendor*

Name

Position

Signature

Date
1- All relevant Drawings and Document must be attached with it
2- * If Applicable

Form No M009-REI-QMS-FRM-00134
MPS Meter Per Second SQM Square Meter
PSAT/ PRE-COMMISSIONING CHECKLIST FOR
PRESSURIZATION FAN

IRE REF NO
DATE _______/ ________/ _________________

M009-SPH-MHV-DWG-GWST080-L1-11001
DWG REF Nos.
M009-SPH-MHV-DWG-GWST080-AA-17005

PRO/ITP M009-SPH-MEP-ITP-00067
TEST BASIS REPORTS M009-SPH-MEP-CLN-00001

VARIFIED BY
Specialist/ Supervision
SPH T&C Date REMARKS
Vendor* Engineer
Supervision Engineer SPH T&C PMC (Witness)

Revision 2
Pa Pascals LPS Liter Per Second ESP Ext. Static Pressure
UNIT TAG PF-01 - Duty IRE REF NO
STATION RIFFA DATE
Basement Corridor Grid 2-3
LOCATION
L1-14 DWG REF Nos.
MANUFACTURER MAICO-DYNAIR
MODEL NO CC-HT 1004-T 6-12° PRO/ITP
SERIAL NO 1CY1206 TEST BASIS RE
Article DESIGN DATA TEST DATA
Fan Flow (LPS) 6,801 6,186

Fan Ext. Static Pressure (Pa) 507 396

Motor V / Ph / Hz 415/3/50 415/3/50

Motor Rating (kW) 7.5 5.9

Motor Rated FLC (Amps) 14.2 10.23

Motor Speed (RPM) 1440 -

Fan Speed (RPM) 1440 -


System Electrical Components
Source MDB-1 / 2 ATS MCC
Location L1-16 L1-18 L1-18
System Description
Flow for Ea.
T. No. Of Total Flow Terminal
System Terminal
Terminals LPS Type
LPS

Stair Pressurization System Stair-1 3 2267 6801 Grill


A. Test Design Conditions
A1. TEST DESIGN CONDITION 1 - "Analysis with all Door Closed" Maximum Pressure Within
LOCATION DOOR ΔP Door Force
Comments FLOOR
FLOOR STATUS Pa Max. 133N

L1 Closed 51 52 AG
CL Closed 50 45

A2. TEST DESIGN CONDITION 2 - "Analysis with Opened Doors - Veloctiy & Pressure" (Area
Velocity Min. Req.
Test LOCATION DOOR LOCATION DOOR
@ Door Velocity
STATUS STATUS
Scenarios FLOOR MPS MPS FLOOR
1 L1 Open 2.22 1.00 AG Open

2 CL Open 1.90 1.00 AG Open

Flow Test Resuts


Total Measured Traverse % Design Terminals % Design ESP
Air Flow (LPS) 6,186 91.0 6,042 88.8 (Pa)
Comments

Description T&C Engineer Specialist/ Vendor* Supervision

Name

Position

Signature

Date
1- All relevant Drawings and Document must be attached with it
* Where Applicable
Form No M009-REI-QMS-FRM-00135
MPS Meter Per Second SQM Square Meter Pa Pascals
B. Fan & System Performance Tests
B1. Main Duct Traverse Test Data
Design
Duct Size MM Duct Area Measured Aver
Velocity
Duct Traverse W H SQM MP
MPS
Measurements & Details
1000 950 0.95 7.16 6.5
Readings 1 2 3 4 5 6
i 5.14 5.56 6.10 6.53 6.53 6.63
ii 5.78 5.99 6.42 6.96 6.63 6.85
iii 6.85 7.17 7.60 7.28 6.74 7.06
iv 5.78 7.60 7.17 7.28 6.74 7.28
v 5.14 8.03 7.70 6.74 6.63 7.17
vi 5.03 6.96 7.28 6.31 6.21 6.85
vii 4.92 5.67 6.21 6.10 6.10 6.27
viii
B2. Terminals Test Data - TEST DESIGN CONDITION 3 - "Analysis With Exterior Door
Total Measured Flow Total Required Flow % Measured/
Terminal Velocity LPS LPS Required
Measurements & Details
6,042 6,801 88.8%

Terminal Size Required Average


Location
S.No. MM Velocity Velocity
Floor W H MPS MPS
Terminal-1 L1 900 700 4.80 4.25
Terminal-2 AG 900 700 4.80 4.20
Terminal-3 CL 900 700 4.80 4.33
Terminal - 1 @ Basement (L1)
Readings 1 2 3 4 5 6
i 4.62 4.99 5.23 4.36 4.25 4.14
ii 5.66 5.77 5.46 4.25 4.14 3.27
iii 5.23 5.34 5.34 4.62 4.68 4.36
iv 4.46 4.79 5.01 4.46 4.46 4.14
v 4.03 4.03 4.79 4.36 4.36 4.03
vi 3.70 3.81 4.68 4.14 4.03 4.25
vii 3.38 3.59 4.36 3.81 3.48 3.70
viii
ix
x
Terminal - 2 @ Grade Level (AG)
Readings 1 2 3 4 5 6
i 3.29 5.14 4.49 5.58 5.34 5.90
ii 4.08 4.84 4.83 5.33 5.13 5.07
iii 5.09 5.28 5.32 5.66 5.75 5.43
iv 2.19 2.62 2.77 3.76 3.76 3.55
v 4.59 4.81 3.90 4.60 4.81 4.28
vi 3.55 4.46 3.87 4.03 3.92 3.24
vii 3.24 3.03 2.42 2.30 2.13 2.51
viii
ix
x
Terminal - 3 @ Concourse (CL)
Readings 1 2 3 4 5 6
i 6.01 5.48 5.23 6.18 6.38 6.36
ii 5.95 5.23 5.23 5.99 6.18 6.27
iii 4.94 5.61 5.80 5.61 6.18 6.08
iv 4.76 4.57 4.95 6.22 4.85 5.05
v 4.56 5.23 4.66 4.47 3.92 3.52
vi 3.74 4.09 2.28 3.33 1.60 1.57
vii 3.92 2.50 1.68 2.19 0.70 0.79
viii
ix
x
Comments

Description T&C Engineer Specialist/ Vendor* Supervision


Name

Position

Signature

Date
1- All relevant Drawings and Document must be attached with it
* Where Applicable
Form No M009-REI-QMS-FRM-00135
MPS Meter Per Second SQM Square Meter Pa Pascals
STANDALONE TEST (SAT)
COMMISSIONING CHECK LIST FOR
PRESSURIZATION FAN
IRE REF NO M009-SPH-TCH-IRE-23172
DATE 21/Nov/18

M009-SPH-MHV-DWG-GWST080-L1-11001
DWG REF Nos.
M009-SPH-MHV-DWG-GWST080-AA-17005

PRO/ITP M009-SPH-MEP-ITP-00067
TEST BASIS REPORTS M009-SPH-MEP-CLN-00001
TEST DATA COMMENTS
6,186 91.0% of Design @ Traverse

396

415/3/50

5.9

10.23

LOCAL ISOLATOR
L1-14

Terminal Size T. No. Of


Terminal Vendor / Model Remarks
W x H (MM) Doors

2000 x 1000 CADNET 3

ximum Pressure Within Enclosure » 50 Pa ±10%


DOOR ΔP Door Force
Comments
STATUS Pa Max. 133N
** Door Closer Not
Closed 49 **
Installed
ctiy & Pressure" (Area considered for ea. Open Door » 1 SQM @ 50% Open)
LOCATION DOOR ΔP
Comments
STATUS
FLOOR Pa
CL Closed 17

L1 Closed 20

Suction Discharge Total


320 76 396

Supervision Engineer SPH T&C PMC (Witness)

Revision 4/21/2018
LPS Liter Per Second ESP Ext. Static Pressure
Measured
Measured Average Velocity
% Design Flow % Design
MPS
LPS

6.51 91.0% 6186 91.0%


7 8 9 10
6.10
6.21
6.21
6.74
6.53
6.30
6.02

With Exterior Door Opened @ AG Level"


% of Terminal Vs Traverse Flow Remarks

97.7%

Area Effective Total


% Design
Factor Area Flow
Ak SQM LPS %
0.75 0.47 2,010 88.7
0.75 0.47 1,987 87.6
0.75 0.47 2,045 90.2

7 8 9 10
4.14 4.25 4.68
3.70 3.38 4.68
3.81 3.43 4.57
3.38 3.92 4.79
3.05 3.70 5.55
2.94 3.59 5.34
2.83 3.27 3.48

7 8 9 10
6.28 6.06 3.97
5.75 6.01 4.70
5.24 5.17 3.86
4.02 3.57 3.66
4.83 5.03 3.44
3.18 3.06 3.24
2.53 2.46 2.93

7 8 9 10
5.70 5.99 5.13
5.51 5.70 4.94
5.04 5.13 4.39
4.66 4.66 4.18
3.57 3.90 3.33
1.59 1.33 3.33
0.88 1.24 2.72

Supervision Engineer SPH T&C PMC (Witness)

Revision 4/21/2018