Beruflich Dokumente
Kultur Dokumente
July 2, 2018
Figure 671.2A
Tapering Into a Previously Overlaid Pavement
NOTES:
(1) Minimum thickness should match thickness of previous overlay.
(2) No Scale.
HIGHWAY DESIGN MANUAL 670-3
December 30, 2015
Figure 671.2B
New Structure Approach Pavement Transition Details
NOTES:
(1) Use Maximum Overlay Thickness or 3x maximum aggregate size, whichever is less.
(2) Cold plane as needed to conform overlay with existing pavement.
(3) No Scale.
670-4 HIGHWAY DESIGN MANUAL
July 2, 2018
(1) Tapers into an Existing Asphalt Pavement. (c) For rehabilitation projects, do not grind the
Where a new pavement structure or an overlay concrete pavement to accommodate a
is tapering into an existing asphalt pavement taper. Instead, remove concrete pavement
that is not part of the project, the following within the taper section and replace with a
apply: new pavement structure that will meet the
design life requirements for the project as
(a) For preventive maintenance projects (thin
defined in Topic 612.
asphalt overlays of 0.10’ or less), the
Design Engineer should follow the taper (d) When grinding concrete pavement, meet
details in Figure 671.3A. the following two conditions:
(b) For CAPM projects, taper the overlay using • Use a diamond grinder, not a planing
the same details used for OGFC taper to machine.
existing OGFC or HMA pavement surface
course (See Figure 671.3A) • Never grind more than 1 inch or reduce
the thickness of the concrete pavement
(c) For rehabilitation projects, taper the slab to less than 0.65 foot.
overlay using the taper details shown in
Figure 671.3A for HMA taper to existing If neither of these conditions can be
HMA surface course. attained with the taper detail, then remove
and replace the concrete pavement slabs
(2) Tapers into an Existing Concrete Pavement. and the underlying base as needed for the
Where a new pavement structure or an overlay transition taper section to match the
is tapering into an existing pavement that is not existing pavement surface.
part of the project or into/under a structure,
grinding existing concrete pavement to create a (3) Longitudinal Tapers at Shoulders, Curbs,
taper is not recommended because it shortens Dikes, Inlets, and Guardrail. Detailed
the life of the concrete pavement. Because it is drawings and information on the best design
not always practical to remove and replace practices for longitudinal tapers at shoulders,
concrete pavement for every overlay, the curbs, dikes, inlets, and guardrail are shown in
following guidance should be followed Figure 671.3B.
regarding tapers for concrete pavement. (4) Tapers Into or Under Structures. Figure
(a) For preventive maintenance projects (thin 671.3C provides a layout and information for
asphalt overlays of 0.10’ or less), the taper transition tapers under an existing structure.
should follow the taper details for OGFC The following guidance should be followed
overlay over asphalt pavement found in when designing tapers underneath over-
Figure 671.3A or reduce the thickness of crossings or into bridges:
overlay to 0.08’ at end of taper and roll (a) Compare the cost and constructability of
down edge to minimize raveling. For under very flat tapers (400:1 or flatter) vs.
structures, existing concrete surface may engineered profiles to ensure that the less
remain. expensive and easier to construct
(b) For CAPM projects, either taper the alternative is used when replacing
overlay down using the same details used pavement underneath a structure.
for OGFC (See Figure 671.3A) or replace (b) The minimum thickness of the pavement
the concrete pavement slab. For under structure for transition tapers into or under
structures, the existing concrete surface bridges must meet the minimum design life
may remain but should be repaired and requirements discussed in Index 671.2(4)
ground or rebuilt as needed in accordance for new construction, widening,
with CAPM strategies for concrete rehabilitation, and reconstruction projects.
pavement in Index 624.2.
HIGHWAY DESIGN MANUAL 670-5
December 30, 2015
Figure 671.3A
Transverse Transition Tapers for Pavement Preservation Projects
NOTES:
(1) Minimum thickness should match thickness of the top lift.
(2) See HDM for minimum thickness.
(3) Same thickness as OGFC overlay or 0.10’, whichever is less.
(4) Do not use HMA to bring the shoulders up to grade when traveled way is OGFC.
LEGEND:
HMA = Hot Mix Asphalt
OGFC = Open Graded Friction Course
670-6 HIGHWAY DESIGN MANUAL
July 2, 2018
Figure 671.3B
Longitudinal Tapers at Shoulders, Curbs, Dikes, Inlets, and Guardrail
NOTES:
(1) Additional design and safety criteria may apply for guardrail, for further info, see Traffic Safety Systems
Guidance or District Traffic.
(2) When grinding or paving next to guardrail or obstacle, reconstructing guardrail will be necessary to
accommodate grinding machines and compaction equipment.
(3) Contact District Landscape and Maintenance regarding the appropriate treatment for weed abatement.
(4) OGFC applies only when used as a surface course, omit details for this course when OGFC is not used.
(5) See HDM Topic 302 for maximum allowable cross-slopes.
(6) For additional information on dikes, see HDM Topic 303, and Standard Plan A78B.
(7) Verify with Hydraulics to see if dike needs to be raised to maintain capacity of gutter.
(8) Verify with District Hydraulics if additional drainage is required at the conform on the shoulder or at bridge
approach slabs in order to avoid ponding.
HIGHWAY DESIGN MANUAL 670-7
December 30, 2015
Figure 671.3C
Transition Taper Underneath Overcrossing/Bridge
NOTES:
(1) Pavement structure thickness needs to provide the proposed pavement design life. This may require that
the pavement structure be removed and replaced.
(2) Verify that the existing drainage facilities will continue to function properly after transition is completed.
(3) For minimum vertical clearance requirements, see HDM Index 309.2
(4) Creation of a sag may require additional drainage features.
670-8 HIGHWAY DESIGN MANUAL
December 30, 2015
Figure 672.3A
Typical Application of Shoulder Backing
Figure 672.3B
Alternative Placement for Existing Slopes Steeper than 6:1
NOTES:
(1) Minimum Hinge Width (HW) is 2 feet. When HW is less than 3 feet, District Materials Engineer should
be consulted regarding structural stability due to width reduction.
(2) Edge treatment shown are for asphalt overlay thickness of 0.45 foot or less. For asphalt thickness of more
than 0.45 foot, see Standard Plans for edge treatment details.
HIGHWAY DESIGN MANUAL 670-11
December 30, 2015
Figure 672.3C
Placement of Shoulder Backing Thickness Greater Than 0.50 foot for
Slope Repair
NOTES:
(1) See HDM Topic 304 for additional information on side slopes. See Standard Specifications for additional
information on side slope construction.
See District Materials Engineer for material recommendations. (Roadway Geotechnical also needs to be
consulted for slopes steeper than 2:1.).
Figure 672.3D
Placement of Shoulder Backing Behind Dikes
670-12 HIGHWAY DESIGN MANUAL
December 30, 2015
Figure 672.3E
Longitudinal Drainage (Roadside Ditches/Gutters)
NOTES:
(1) Consult with area Maintenance personnel and District Materials Engineer regarding erodability of ditch,
alternative materials to shoulder backing, slope sloughing, and rockfall catchment in ditch.
Consult with District Hydraulics Engineer regarding acceptable change in ditch capacity.
Consult with District Stormwater Coordinator regarding water quality issues.