Sie sind auf Seite 1von 3

TOURISM INFRASTRUCTURE AND ENTERPRISE ZONE AUTHORITY (TIEZA) v.

GLOBAL-
V BUILDERS CO.
GR No. 219709, 3 October 2018, J. Peralta

In 2007 and 2008, the Philippine Tourism Authority (PTA) entered into five MOA with Global for
the (1) construction of stamped concrete sidewalk and installation of streetlights located at
Boracay, Aklan; (2) Boracay Infrastructure Project – Extension Drainage Component System; (3)
additional sidewalk, street lighting and drainage system, Boracay, Aklan; (4) Widening of Boracay
Road along Willy’s Place; and (5) Perimeter fence at Banaue Hotel in Banaue, Ifugao.

No. 2 and 5 of the above projects were procured through competitive bidding, while the rest of
the projects were obtained through negotiated procurement. On July 2012, Global filed a request
for arbitration and a complaint before the Construction Industry Arbitration Commission (CIAC)
seeking payment from TIEZA, as it took over the functions of the PTA, of unpaid bills in
connection with the 5 projects including payment of interest, moral and exemplary damages. The
claims of Global amounted to Php 16 million.

On August 2012, TIEZA filed a Refusal of Arbitration argued that it has no jurisdiction over the
case and the contracts do not contain an arbitration agreement in accordance with Sec. 2.3 and
2.3.1 of the CIAC Rules. However, Global, in its reply, asserted that the pertinent provision of RA
9184 governing the subject infrastructure projects are deemed part of the contracts entered into
by the parties. TIEZA maintained that the arbitration clause is a condition sine qua non before
CIAC can acquire jurisdiction over the subject matter.

CIAC constituted an Arbitral Tribunal to handle the case and directed the parties to submit their
respective memorandum on TIEZA’s motion to dismiss. In December 2012, the Tribunal dismissed
TIEZA’s motion to dismiss for lack of merit ruling that the absence of an arbitration clause in the
main body of the MOA is not fatal to the case of the claimant; that Global has correctly pointed
that RA 9184 are deemed incorporated in the MOA, as the applicable provision of RA 9184 are
found in the “General Conditions of the Contract.” On the of exhaustion of administrative
remedies, Global has satisfied the condition that there is unreasonable delay in acting upon the
claim by the government office/r to whom appeal is made. In this case, more than 3 years have
elapsed since the date of final demand for payment before the head of TIEZA himself.

A motion for reconsideration was filed by TIEAZA but was dismissed thereafter by the Tribunal. A
Terms of Reference (TOR) was drafted during the preliminary conference and was signed by
Global and its counsel, but TIEZA did not affix their signatures, as it was to be submitted for
review and approval of the OSG. A second preliminary conference was conducted for the purpose
of amending the TOR, and it was signed by the parties and with reservations on the side of
TIEZA, in view of the non-inclusion of the jurisdictional issue in the amended TOR (on projects 2
and 5).

The Tribunal ruled: (1) Global is entitled to the release of retention fees for the No. 5 project; (2)
the contracts for No. 3 and 4 are valid; (3) Global is entitled to the payment of the cost of
undertaking the No. 4 project; (4) Global is entitled to its claim over the No. 3 project; (5) Global
not entitled to moral and exemplary damages only for recovery of atty’s fees; (6) TIEZA to bear
the cost of arbitration.

TIEZA filed an appeal to the CA. It dismissed Global’s complaint on the ground that CIAC has no
jurisdiction over the case because the parties did not agree to submit to arbitration any and all of
their disputes arising from the construction contracts. Global filed an MR, and the CA revered its
former decision and upheld the final award of the Tribunal citing the General Conditions of the
Contract. On the exhaustion of administrative remedies, the CA elucidated that the non-
compliance with the precondition set forth under the CIAC rules will only suspend the arbitration
proceedings, but will not cause the dismissal of the complaint, more so affect the jurisdiction of
CIAC to conduct the proceedings (because TIEZA here made a manifestation that Global should
file with COA first for money claim).

ISSUE: (1) Whether or not CIAC has jurisdiction over the case; (2) Whether or not it is the COA
who has primary jurisdiction over the case; (3) whether or not the negotiated contracts is valid
under 9184.

(1) TIEZA’s contention is unmeritorious. CIAC was created through EO 1008, which is an arbitral
machinery to settle disputes in the construction industry expeditiously in order to maintain and
promote a healthy partnership between the government and the private sector in the furtherance
of national developmental goals. EO 1008 provides that CIAC to acquire jurisdiction over a
construction controversy, the parties to a dispute must be bound by an arbitration agreement in
their contract or subsequently agree to submit the same to voluntary arbitration, and that an
arbitration clause in a construction contract or a submission to arbitration of a construction
dispute shall be deemed an agreement to submit an existing or future controversy to CIAC’s
jurisdiction. The CA found that there was an agreement to arbitrate in the General Conditions of
the Contract, which formed part of the MOA.

It provides clearly that all disputes arising from the implementation of the contract covered by RA
9184 shall be submitted to arbitration in the Philippines. Hence, the fact that the process of
arbitration was not incorporated in the contract by the parties is of no moment. The contracts in
this case is covered by RA 9184 which provides that all disputes arising from the implementation
of the contract covered by it shall be submitted to arbitration in the Philippines, and disputes that
are within the competence of the CIAC to resolve shall be referred thereto. Further, there is no
vagueness in the process of arbitration to follow even if it was not incorporated as a provision in
the contracts.

(2) TIEZA’s contention is unmeritorious. The jurisdiction of courts and quasi-judicial bodies is
determined by the Constitution and law. EO 1008 provides that the CIAC shall have original and
exclusive jurisdiction over disputes arising from, or connected with, construction contracts, which
may involve government or private contracts, provided that he parties to a dispute agree to
submit the dispute to voluntary arbitration. Further, Global has complied with the condition of
exhaustion of administrative remedies that “there is unreasonable delay in acting upon the claim
by the government office or officer to whom appeal is made. The period of almost five years of
nonpayment can already considered as unreasonable delay, which would exempt Global from the
rule on exhaustion of administrative remedies.
(3) TIEZA’s contention is unmeritorious. MOAs were valid and it granted Gobal claims except on
project No. 1. As they complied with the requirements of negotiated procurement under RA 9184.
The additional project should be considered as similar or related to the scope of work as in the
original project. The Court provides that the procuring entity may, in order to promote economy
and efficiency, resort to alternative methods of procurement, including negotiated procurement.
Hence, PTA must have considered the construction the additional sidewalk and street lighting
economical and related to the original contract to fund them together with other construction
projects.

Das könnte Ihnen auch gefallen