Please clarify.
3. General 0003 LOC: REV 3
A
ALE to provide daily maintenance checklist for power packs and
SPMT prior to commencement of each loadout activity.
4. Batch 1 Modules 0004 LOC: REV 2
Barge A
Arrangement It is noted that the modules will be set down on stools on the
barge, please provide the strength checks and detailed drawings
for the stools for review.
5. NOV Reference 0005 LOC: REV 2
Drawings / A
Documents Please provide the jetty ground bearing analysis for review.
6. Batch 1 Modules 0006 LOC: REV 2
Barge Mooring A
Analysis Please provide single line failure for the barge mooring analysis.
7. Barge Intact 0007 LOC: REV 2
Stability A
Please provide barge damage stability (single tank damage) for
review.
8. Barge Structural 0008 LOC: REV 2
Analysis A
There is no attachment? Please provide attachment.
9. Appendix N - Tide 0009 LOC: REV 2
Tables A
Please provide updated tide tables for the scheduled loadout.
10. Tug and Barge 0010 LOC: REV 2
Suitability Survey A
Tug and barge to be surveyed by LOC; all comments to be
satisfactorily closed prior to the commencement of the loadout
operations
11. General 0011 LOC: REV 2
A
All the seafastening welding to the deck of the barge to be NDT
tested and NDT report to be provided to attending surveyor.
Assigned To: Approved By: Issued By: Date:
Jeremy Tan Jeremy Tan Jeremy Tan 30 November 2018