Sie sind auf Seite 1von 5

Power Planning for renewable energy grid integration

- Case Study of South Africa


Mobolaji Bello Clinton Carter-Brown
Group Technology: Power Delivery Engineering Group Technology: Power Delivery Engineering
Eskom Holdings SoC Limited Eskom Holdings SoC Limited
Johannesburg, South Africa Johannesburg, South Africa
bellomm@eskom.co.za

Riaan Smit Innocent E. Davidson


Group Technology: Power Delivery Engineering Department of Electrical Engineering
Eskom Holdings SoC Limited Faculty of Engineering and Information Technology
Johannesburg, South Africa University of Namibia, Ongwediva, Namibia
idavidson@unam.na

Ahstract- South Africa's Government policy embraces the situated in the KwaZulu-Natal province. Open Cycle Gas
inclusion of distributed energy resources (DER), namely: Turbines (OCGTs) provide 2416MW installed capacity.
renewable energy generation, embedded generation (EG) or
distributed generation (DG) in the future national generation South Africa is a net exporter of power (2000 MW) and
mix. The renewable energy program incorporates wind power, interconnected with five neighboring countries; Namibia at
concentrated solar power (CSP), solar photo-voltaic (PV), 220 and 400kV, Botswana at 400kV, Swaziland at 400kV,
landfill, and mini/micro hydro, and envisages a total of 17.8 Mozambique at 275 and 400kV, and Lesotho at 132kV.
GW of electricity generation from renewable energy sources Energy import into South Africa is from Mozambique via 2
by 2030. By implication, the number of generators connected x 533kV DC lines (l700MW). The 2012 national peak load
to the Eskom Transmission and Distribution networks will was approximately 38GW.
increase significantly over this period. Eskom, South Africa's
dominant national electric power utility is responsible for the
Power transmission voltage levels in South Africa are at
distribution network in predominately rural areas and smaller 765kV, 400kV, 275kV and 220kV; while 132kV, 88kV,
towns. The distribution in the cities is performed by the local 66kV, 44kV, 33kV, 22kV, llkV and 6.6 kV form part of the
municipalities. Most of the new initiatives such as increased sub-transmission and distribution network. Electric power
distributed generation, advanced demand side management delivery systems are predominantly overhead lines in South
and plug-in electric vehicles will affect the way in which the Africa; while medium voltage (MV) distribution networks
distribution network is planned, designed and operated. This within urban areas are llkV buried cables. Power networks
paper addresses South Africa's renewable energy program in rural areas are predominately 22kV overhead lines [1].
and Eskom's renewable energy generation grid connection
process. It then proposes a standardized approach on the best The South African generation capacity is mainly coal
practice in which distribution networks should be planned, based due to large coal reserves. The Government's plan is
designed and operated in South Africa using the SMART Grid to change this and the expected 17 800 MW for renewable
approach. energy is to represent about 20% of installed capacity by
2030 as illustrated in Table I.
Keywords: Renewable Energy, Grid Connection, planning
criteria and network studies, SMART Grid. TABLEL SOUTH AFRICAN GENERATION CAPACITY

Existing Generation & 20 year plan


Energy Source Capacity Energy 2011 Integrated
I. INTRODUCTION
MW GWh Resource Plan MW
The electric power network in South Africa is divided Coal fired 37 715 218 212 6 250
into seven geographical operating units, each with a Hydro-electric 661 1 904 2 609
transmission and a distribution network (sub-transmission, Pump storage 1400 2 962
Gas turbines 2 426 709 6 280
distribution voltages), including re-distributors (e.g.
Nuclear 1910 23 502 9600
municipalities). Most of the country's base generation is Renewable energy 3.15 2 17 800
thermal and is situated in the northern and north eastern Availale Capacity 44 115 237 291
regions (Limpopo and Mpumalanga provinces respectively). Foreign imports 13 038
A nuclear power station with 2x 955MW units is situated in LocallPP & co-gen 4107

the Western Cape Province. Pumped storage schemes at


Drakensberg (lOOOMW) and Palmiet (400MW) are
supplemented by Ingula (l300MW) under-construction;

978-1-4799-1303-9/13/$31.00 ©2013 IEEE


II. SOUTH AFRICA'S RENEWABLE ENERGY SITUATION
Renewable Energy lPP program phase

A. Background 700

In March 2009, the National Energy Regulator of South


600
Africa (NERSA) released the Renewable Energy Feed in
Tariff (REFIT). The new REFIT is the culmination of a c 500
0
study initiated in 2007 designed to facilitate the introduction '.gu
of renewable energy generation into the electricity network. 0 400
This is in an attempt to meet the target of 10 000 GWh from 16
300
renewable energy sources by 2013, a target set in the 2003 3:
Government White Paper on Renewable Energy [2]. ::=:
200
The REFIT was replaced by the Department of Energy
100
(DoE) Renewable Energy Independent Power Producer (RE
IPP) program. This is a bidding program that is in line with 0
government policy and its tender process. The South African W i nd PV CSP Sm all Other
government's department of energy and NERSA are Hydro
targeting the addition of 17.8GW of embedded generation Techno logy
(EG) by 2030 [3].
Figure 1. Department of Energy Renewable Energy TPP program.

B. Projected Energy from South Africa's Integrated


RE IPP 1 and 2 show allocations for bid 1 (1416 MW)
Resource Plan (IRP) and bid 2 (1044 MW), while RE IPP 3 shows the remaining
There is a large interest from local and overseas capacity still to be allocated (1165 MW) between bids 3 to
developers in the various renewable energy technologies. 5. The geographical locations of the preferred bidders to
Currently, there has been an expression of interest to date are shown in Figure 2.
connect varying sizes and technologies of renewable
generation to Eskom networks. These includes about 637 ProLTech
projects totaling 36 523 MW, being discussed and analyzed D Small Hydro
by Eskom engineers. The expression of interest is • Solar CSP
• Solar Photovo�aic
summarized in Table II. It highlights the need for proper . V\Ilnd
models, data and skills to connect these renewable energy
generating plants to Eskom networks.
• Bid 1
The Department of Energy (DoE) is working closely
! Bid2
with National Treasury (NT) on the renewable energy
program for independent power producers. The size of the
first program announced in August 2011 is 3625 MW from
wind, solar PV, CSP and other renewable technologies. (See
Table II).

TABLE n. SUMMARY OF EXPRESSION OF INTEREST

Independent power Prodncer

Technology Interest
Nr of DoE RE IPP
and ideas
projects Program MW
MW
Wind l75 19 150 1 850
Solar photovoltaic 374 14 466 1 450
Concentrating solar 25 2 409 200
Figure 2. Renewable energy preferred bidders on South Africa high
power
voltage power system
Biomas 63 (rest) 498 (rest) 12.5
Biogas 12.5
Landfill 25 The bid submissions were closely spaced: November
Small Hydro 75 2011 to March 2012. The 3rdbid has been postponed from
TOTAL 637 3652 3 3 625 August 2012 to May 2013 to resolve outstanding issues and
improve the process. RE IPP 1 projects should be completed
The program also includes a 100MW allocation for by mid-2014, while the others are expected to be completed
projects in the 1-5 MW generating plant sizes categories, but by December 2016.
has not been formally released. The total program available
then is 3 725 MW. There is currently no formal program for
III. ESKOM RENEWABLE ENERGY GENERATION GRID
the <:: 1 MW size projects, or for low voltage (LV) connected
CONNECTION PROCESS
renewable energy generating plants or facilities.
It is expected that new programs will be announced to The consultation and advising phase to the IPP's (as
support a sustainable program as proposed in the Integrated shown in Figure 3) is used by Eskom Planning sections in
Resource Plan (IRP) [4]. Transmission and Distribution to:
Figure 1 shows MW per technology in the RE IPP • Check the high level feasibility of project connection.
program as for the preferred bidders.
• Identify the proposed point of connection to the grid networks which have been designed to mitigate the effects
and the scope work, i.e. independent of other of voltage drop. Step voltage changes may be caused by
applications, as if it is the only project. inrush currents, which occur when transformers and/or

induction generators are energized from the network. A
Identification of any technical issues that may require
sudden voltage reduction can be experienced when a
further consideration during budget quote phase, and
generator is disconnected. See Table III for the maximum
• Assist the Grid Access Unit to issue indicative cost deviation from standard or declared voltages used for
estimate letters free of charge planning studies.

A budget quote is provided only to the preferred bidders,


after payment of a commitment fee. TABLE lll. MAXIMUM DEVIATION FROM STANDARD OR DECLARED
VOLTAGES
Quotation, Voltage level [V] Compatibility level [%]
Contracting and
Connection
"i,-------------\ \-----:---\ <500 ±10

\ Request EtA
\ , Re �IVe � 2: 500 No contract ±5
2: 500 With contract ±7.5

t.
" for project

_____________
";4__________
I
approval
1 '
Ij

1---------,
I •

: Application \
: Form �
• Fault levels:
L _______ �/
- - - Connecting a generator to a network has the effect of
! ';cce p���:;\ increasing the fault levels in the network at the point of
� �imate : ...
t Letter ,
I
generation connection (POC). This may result in the
I
1 ______- -,
- violation of equipment fault level ratings. Generators
1---- ----��
� Accept ,
Perform
/Approve Construct
Test & contribute fault currents in response to network faults. The
Commission
� Budget � Detaile d Connectl ----7 fault level is sensitive to the future location of other

j I
connection
: Quote { Desi n on Works.
g ass.et
·---- generation, and the future is uncertain and difficult to
,----�----.
W.\��� ertorm-
r -\ u ct--�
\--Con-str- predict. The future fault level could increase significantly
Detailed
, Design (Self
'.
,
'Connection
II Work (Self
',
l
\ Project \ and as such, the generation developer must also ensure that
I Close out t
L����?Jl_t�o_nJ) !_�u�l_d_�����l: !_________ J their generation plant is rated as per Table IV. This will
ensure that the generating plant will be adequately rated if
Operation of IPPs
Eskarn the fault level at the point of connection increases up to the
and generators
I Depl. of Energy I limit in Table IV. Table IV is a design requirement. The
actual fault level (as required for protection studies and
Figure 3. Eskom renewable energy connection process [4] settings) may be significantly lower and will change as fault
levels in the network change. The equipment fault levels
(considering the impact of existing generators and proposed
IV. TECHNICAL ISSUES AND CONNECTION CRITERIA generators) must not exceed 90% of their fault level rating.
Historically, Eskom sub-transmission ( :S; 132kV and
>33kV) and distribution (:S;33kV) networks were designed TABLE IV. EQUIPMENT DESIGN FAULT LEVEL LIMITS [6]
to transfer power from the high voltage grid to load centers
Equipment voltage Short circuit rating
at lower voltages. Urban distribution cable networks are level [kV] at POC [kA]
usually looped and operated as radial feeds to reduce fault 11 25
levels and simplify protection. Rural distribution overhead 22 25
networks are radial, often with limited interconnectivity [5]. 33 25
66 25
Widespread EG will change the manner in which Eskom's
88 40
distribution networks are planned, designed and operated. In 132 40
addition to delivering energy to end customers, distribution • Equipment thermal Ratmgs:
networks will also be used to connect geographically
dispersed generation. Generators may cause the loading levels of individual
elements (transformers, lines and cables) and to increase,
A. Planning limits for renewable energy generation grid specifically in cases of maximum generation and minimum
connection (MV, HV and Transmission)[6) load. Thermal ratings could be exceeded. The line loading
The relevant information on the network planning might increase or decrease, depending on the size and
technical limits includes: location of the generator as well as the existing load. When
connecting a generator to the network, existing lines, cables
• Steady state voltage limits: and transformers must be checked to be adequately rated to
handle any increasing current. Probabilistic ampacity ratings
During all loading and generation patterns, voltage rise
are calculated for normal, contingency and emergency
and voltage drop need to be kept within specific limits so
ratings for specified template temperature, e.g. 70°C.
that voltage variation at customer points of supply are within
required limits, as specified in the South African electricity • Rapid voltage change (RVC):
quality of supply regulatory standards [7] and voltage
regulation and apportionment limits standards [8]. The Rapid voltage change (RVC) is a phenomenon in which
reverse flow of power from EGs may cause voltage rise in there are changes in voltages noticeable by other customers
at the point of connection. These voltage changes can be
caused by changes in generation output. Rapid voltage need to be performed for the combinations of generators and
changes can be caused by changes in generation output, load to identify any potential problems. The EG generator
tripping of plant and switching of devices. For more stable connections are not designed with n-l criteria; unless
generating plants, such as a combined-heat and power specifically requested by the IFP.
(CHP) unit, cogeneration or CSP plant (which seldom trips), • Technical losses:
an RVC value of 5% is specified because rapid output
changes and tripping of plant occurs infrequently. For Generators may have a significant effect on network
generating plants such as solar PV and wind, their output losses. A generator can lower or increase losses depending
power changes rapidly. In networks with these types of on its location and the network configuration. Technical
generation, Eskom needs to limit the operations of the losses may increase or decrease due to changes in equipment
upstream voltage control equipment and ensure that the loading. The impact of technical losses is dynamic and will
voltage variations seen by other generation and load vary significantly as the network changes, load changes and
customers are within acceptable limits. Hence, a 3% limit is additional generation is connected. A generator could
applied to all types of generation that change output power initially cause a reduction in losses, but as the local
rapidly, such as solar PV and wind generation. generation grows so it may cause technical losses to
increase. Technical loss optimization is done when assessing
The RVC limit is tested by individually tripping each
technically viable connection options.
generating plant (a plant may for e.g. consist of a number of
turbines/generators) without allowing any voltage control • Transient stability:
correction or remedial action. The change in voltage at all
points in the Eskom network must be within the limits Transient stability studies are not performed for
described above «3% for highly variable generation, and generators connected to distribution MV networks,
<5% for relatively stable generation). Refer to Table V for depending on the size and location of the generating
the planning rapid voltage change limits. plant(s).

For all Eskom connected embedded generators, it is a B. Renewable energy generation grid connection
requirement that they be operated in fixed power factor for philosophy[6}
all planning studies. The default is unity power factor but
It is a grid code requirement that all grid connected
the planning engineer will allow some movement from unity
generators must have certain capabilities e.g. the generator
as per the limits for rapid voltage change. Power factor
must be able to provide the PQ capability as required by the
greater than or less than unity generally result in increased
codes.
technical losses. Voltage control will typically only be
considered for operational scenarios, and must not be a It must be noted that for all grid connected generators,
requirement for normal network operation. Eskom specifies the control mode and associated power
factor which must be within the generator capability. In
TABLE Y. RAPID VOLTAGE CHANGE PLANNING LIMITS [6]
distribution and sub-transmission networks, the voltage at
the medium voltage level is typically controlled with on load
Criteria Basis Limit tap changing transformers (OLTC). Here, the XIR ratio is
Normal Contingency typically lower than in transmission systems, the effect of
<=5%, at reactive power (Q) is less for voltage control (transmission
minimum leading
networks are in fact more sensitive to voltage drop). In
Non-fluctuating power factor of
generation i.e. 0.975 for gen
<=5%, at transmission networks, XIR ratio is high; this implies that a
minimum slight change in Q has significantly high changes in
more stable plants >= 20MW
leading power
(disconnection and <=5%, at voltages. Renewable generation (e.g. solar PV and wind)
factor of 0.95
due to fault or minimum leading
for all gen
cannot be scheduled; hence active power P can only be
Rapid inadvertent trip) power factor of constrained, but not ramped up. The reactive power Q can
plants
voltage 0.9875 for gen
>=20MWand be controlled in Q control, power factor control and voltage
change plants <20MW
<=5%, at control modes. Power factor control means that the reactive
(sudden Fluctuating <=3%, at
minimum
loss of generation such minimum leading power output of the generating unit is maintained in
leading power
generation) as solar PY or power factor of proportion to the MW output such that the power factor
factor of 0.975
wind generation 0.975 for gen
for all gen remains constant regardless of the terminal voltage. PF
plants >= 20 MW
plants < 20 control can result in excessive Q flow if set to account for
and <=3%, at
minimum leading
MW the worst case voltage contingency (for example during light
power factor of load conditions), which in turn can result in increased losses.
0.9875 for gen Voltage control is achieved by adjusting the amount of
. .
plants <20MW reactive power injected or absorbed into the network. The
• Network relIabIlIty: ability of a generator to regulate its voltage is hence
dependent on its reactive power range AND the inductance
The ability of local generation to improve network
of the network supplying the generator. Q control is
performance may be dependent on the ability to island and
achieved by setting the generator to produce a constant
supply customer loads in the event of network faults that
value of reactive power; irrespective of the power output or
would otherwise result in outages. In South Africa,
voltage level.
generating plants are generally not allowed to island [1]. An
n-l condition means that one single circuit, or one item of All distribution and sub-transmission network connected
plant is out of service. For each n-l condition, the technical generators should be planned to be operated in fixed power
thermal, voltage, rapid voltage change and fault level studies
factor (PF) control mode. Voltage control is only considered • Review protection systems
for operational scenarios. • Constantly updating Grid Codes
In the transmission systems, where the XIR ratio is high, • Communication systems to support data exchange
the voltage magnitudes are almost solely determined by the
reactive power flows. The main voltage control is performed • Mechanisms in place for grid users to provide ancillary
by generating plants which are connected to the services
transmission system. However, switchable shunt capacitors
and reactors are used to compensate for reactive power
VI. CONCLUSION
imbalances.
The introduction of widespread embedded generation
presents technical, planning and human resource challenges
V. SUGGESTED STANDARDIZED APPROACH FOR
to South Africa and Eskom in particular. Eskom has met
NETWORK DESIGN WITH SMART GRID
these challenges by developing standards and processes
Smart Grid (Active Management) is a new distribution based on international practices. Eskom connection process
paradigm about bidirectional power and data flows. With provides for quick high level feedback followed by a more
smart grid implementation, network planning is no longer a detailed quotation. The use of standards and interoperability
way to solve operational issues at distribution level (e.g. are fundamental principles that will enable most utilities
voltage regulation, power flow management and electrical have flexibility to adjust to the changing grid requirements
losses minimization). This implies that network planning while integrating renewable generation, implementing smart
and operation need to be brought closer together. It is also grid systems and ensuring reduced costs. Grid Codes are
vital for network planners to understand the long-term critical, as it allows simple data exchange for connection
implications and evolution of SMART Grids. Planning studies. Currently, about 800 MW renewable energy
methodologies by network planners should be revised to projects per annum are envisaged for commissioning in
consider the following [9]: South Africa, as suggested by the DoE Integrated Resource

Plan. New skills and processes need to be continuously
Move to probabilistic or stochastic grid-based
developed which will help ensure that high volume, lower
approaches (not only for DER or load, but to simulate
capacity projects are processed efficiently.
human behaviour). Deterministic approach can be no
longer used-Deterministic algorithms hide the
potential benefit of DG due to the worst case approach. ACKNOWLEDGMENT

• Risks have to be explicitly considered in planning - The authors would like to thank Eskom and the Faculty
Each time a decision has to be taken in an uncertain of Engineering and IT, University of Namibia for supporting
scenario the risk comes. The future distribution system this paper. The contributions of the Eskom renewable
will be affected by many uncertainties. generation grid integration and Independent power
producers (lPP) working group members are also
• Planning tools should be multi-faceted - Planners have acknowledged.
to face with contrasting objectives: multi-objective
programming and decision theory can help to find a
REFERENCES
"good" solution within a set different from planning
[I] Eskom integrated report 2012. www.eskom.co.za
alternatives.
[2] DME, 2003 "White Paper on renewable Energy Policy of the
• Planning should explicitly consider system operation - Republic of South Africa" Depmtment of Minerals and Energy,
The concept of active network strongly impacts the Pretoria, November, 2003, pages 1-59. Available at
http://www.dme.gov.zaJenergy/renewable.stm on 9th August, 2008
network expansion planning since it may allow
[3] Government Department of Energy Request for Proposal (RFP) for
withstanding load and DG growth postponing network
TPP's. www.ipp-renewables.co.za
investments.
[4] Mobolaji Bello and Riaan Smit, "Eskom's network planning
• Consider move to meshed network topologies technical strategy to support renewable generation integration to
Eskom networks" Proceedings of Solar Integration Workshop,
• Continuous feedback loop is required from operation to Lisbon, Portugal, Nov. 2012.
planning [5] M.M. Bello and CG Carter-Brown, "Eskom Distribution process and
challenges for the connection of embedded generation" Proceedings
• Plans should also be based on smart metering data. of CTGRE Canada Conference on Power system, Winnipeg, October
With the evolution of the MV distribution network 19-21, 2008.
management (Active networks, Smart grids) there is [6] Mobolaji Bello, "Network and grid planning application standard for
the need to include operational aspects into the generation grid connection", DGL 34-1946, Eskom controlled
document, October, 2012.
planning process. Data from Smart Metering will allow
[7] NRS 048-4: Electricity Supply - "Quality of Supply" Standard, 2006.
a full load profile and daily load profiles can and
Available at http://www.nrs.eskom.co.zaJ on 9th August, 2008.
should be used in modern planning
[8] C. G Carter-Brown, "Distribution voltage regulation and
• Consider reliability assessment in all network planning apportionment limits standard", DST 34-542, Eskom controlled
document, February, 2012.
aspects.
[9] F. Pilo, "Planning in the era of smartgrid" Tutorial at Cigre 2011
Planning for advanced smart grid systems needs to be Bologna Symposium - The Electric Power System of the Future.
done now, before all new generation and load devices are [10] R. Yinger and Ae Kamaiab, "Good Vibrations", IEEE Power and
grid connected [10]. The following have been suggested for Energy magazine, pp.23-32, Vol 9, No. 5, OctINov, 2011
grid operations:

Das könnte Ihnen auch gefallen