Project:

Subject: AC load

Referring to the above Subject project, As per client request to reduce the load, please note
that this can be done given the condition that the FAHU (Fresh Air Handling Unit) shall be
operating and not switched off during the operation of the project. As in our design (and as
per our experience) we assume some client tend to switch off the FAHUs to reduce the
monthly bill. Hence we put some margin for that reason. So, In this case the load can be
reduced to 900TR, Given that condition.