Beruflich Dokumente
Kultur Dokumente
Lube Oil Blending Plant: Provision of Permanent Perimeter Fence Manila Harbour Center, Tondo, Manila February 6, 2018
COMPLETION DATE EXTENSION REQUEST
REQUESTED EXT. (IN DAYS) JUSTIFICATION (Attach additional information, if necessary)
74 Calendar Days Provision of Perimeter Fence Works at corresponding area was hampered due to the following; along line C-D, conflict with road stripping works,
NEW ETC (IF APPROVED) along line N-O, obstructed by relocation of temporary perimeter fence, along line A-B, obstructed by fabrication area, service road and temporary
entry/exit gate, along line R-S, property line encroachment by adjacent lot tenants, along line Q-R, obstructed by delayed completion of pipe
April 10, 2018 laying works, along line P-Q, current location of temporary gate, along line S-T, delayed completion due to delayed handover of area and along E-
F, waiting for final drawing and layout.
ADDITIONAL WORKS/REVISIONS REQUEST
DESCRIPTION AMOUNT JUSTIFICATION
ADDITIONAL WORKS:
DEDUCTIVE WORKS:
MC Ventura
NOTED BY: SSC SUPERVISOR / DCG HEAD ENDORSED BY: (FUELS PROJECT GROUP HEAD)
Budget Excess/Shortfall
ATTACHMENTS
Submitted By:
P. R. AREVALO
VECO CDC
VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park
Submitted By:
P. R. AREVALO
VECO CDC
VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park
Submitted By:
P. R. AREVALO
VECO CDC
VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park
Submitted By:
P. R. AREVALO
VECO CDC
Lube Oil Blending Plant Project Weekly Progress Report No.43 01 February 2018 ; Page 20 of 30
CHANGE ORDER REQUEST
CONTRACTOR CONTRACT No. CONTRACT ETC CONTRACT AMOUNT
Lube Oil Blending Plant: Provision of Permanent Perimeter Fence Manila Harbour Center, Tondo, Manila July 2, 2018
COMPLETION DATE EXTENSION REQUEST
REQUESTED EXT. (IN DAYS) JUSTIFICATION (Attach additional information, if necessary)
DEDUCTIVE WORKS:
MC Ventura
NOTED BY: SSC SUPERVISOR / DCG HEAD ENDORSED BY: (FUELS PROJECT GROUP HEAD)
Budget Excess/Shortfall
ATTACHMENTS
Submited by:
PASCUAL R. AREVALO
Lube Oil Blending Plant: Provision of Permanent Perimeter Fence Manila Harbour Center, Tondo, Manila August 14, 2018
COMPLETION DATE EXTENSION REQUEST
REQUESTED EXT. (IN DAYS) JUSTIFICATION (Attach additional information, if necessary)
31 Calendar Days
NEW ETC (IF APPROVED)
DEDUCTIVE WORKS:
MC Ventura
NOTED BY: SSC SUPERVISOR / DCG HEAD ENDORSED BY: (FUELS PROJECT GROUP HEAD)
Budget Excess/Shortfall
ATTACHMENTS
Prepared by:
Pascual Arevalo
VECO Construction and Development Corporarion