CHANGE ORDER REQUEST

CONTRACTOR CONTRACT No. CONTRACT ETC CONTRACT AMOUNT

11 Nov. '16 (30 Jun '17 FCA


VECO Construction & Development Corporation PO 4020081908 Time Extension) Php35,700,000.00
PROJECT/DEALER LOCATION DATE OF FORM FILL-UP

Lube Oil Blending Plant: Provision of Permanent Perimeter Fence Manila Harbour Center, Tondo, Manila February 6, 2018
COMPLETION DATE EXTENSION REQUEST
REQUESTED EXT. (IN DAYS) JUSTIFICATION (Attach additional information, if necessary)

74 Calendar Days Provision of Perimeter Fence Works at corresponding area was hampered due to the following; along line C-D, conflict with road stripping works,
NEW ETC (IF APPROVED) along line N-O, obstructed by relocation of temporary perimeter fence, along line A-B, obstructed by fabrication area, service road and temporary
entry/exit gate, along line R-S, property line encroachment by adjacent lot tenants, along line Q-R, obstructed by delayed completion of pipe
April 10, 2018 laying works, along line P-Q, current location of temporary gate, along line S-T, delayed completion due to delayed handover of area and along E-
F, waiting for final drawing and layout.
ADDITIONAL WORKS/REVISIONS REQUEST
DESCRIPTION AMOUNT JUSTIFICATION
ADDITIONAL WORKS:

TOTAL ADDITIVE COST: PHP 0.00 (VAT ex)

DEDUCTIVE WORKS:

TOTAL DEDUCTIVE COST: PHP 0.00 (VAT ex)

ESTIMATED AMOUNT PHP 0.00


PREPARED BY: (CONSTRUCTION MANAGER - CONSTRUCTION MANAGEMENT GROUP) ENDORSED BY: (CONSTRUCTION MANAGEMENT GROUP HEAD)

MC Ventura
NOTED BY: SSC SUPERVISOR / DCG HEAD ENDORSED BY: (FUELS PROJECT GROUP HEAD)

Rosendo Ariola JS Villarin/CC Adorable VM Castillo

A. Approved Budget B. Actual Cost

Civil Works Contract Amount 35,700,000.00


SS Equipment 10% Contingency
Signages SS Equipment (estimated cost)
Signages (estimated cost)
Proposed Add'l Cost -

Budget Excess/Shortfall

ATTACHMENTS

Please see attached initial proposal of Veco

ENDORSED FOR APPROVAL:

W.R. Buencamino / B.O. Fallaria Jr. NS Ventigan


VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park

Schedule of Permanent Fence


JANUARY
S/N Description Start Duration Finish
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1

1 Line D-E CHB (SM Side)

2 Line U-N (Blk 13 West Side)

3 Line F-G (Serv Sta Side)

4 Line C-D (Road 20) 20-Jan-18 50 10-Mar-18

5 Line N-O (Blk 13 North Side) 25-Jan-18 30 23-Feb-18

6 Line A-B (Road 21) 25-Jan-18 50 15-Mar-18

7 Line G-H CHB (Service Station Side) 20-Jan-18 14 2-Feb-18

8 Line R-S (Blk 13) 01-Feb-18 55 27-Mar-18

9 Line Q-R (Blk 13) 22-Jan-18 60 22-Mar-18

10 Line P-Q (Blk 13 Road 20) 15-Feb-18 40 26-Mar-18

11 Line S-T ( Blk 13 Road 21) 22-Jan-18 40 2-Mar-18

12 Line E'-F (Blk 12 entrance area) 31-Jan-18 60 31-Mar-18

13 Fence Grill Fabrication, Delivery and Installation 01-Feb-18 70 11-Apr-18

14 Demobilization 10-Apr-18 6 15-Apr-18

Submitted By:

P. R. AREVALO
VECO CDC
VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park

Schedule of Permanent Fence


FEBRUARY
S/N Description Start Duration Finish
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5

1 Line D-E CHB (SM Side)

2 Line U-N (Blk 13 West Side)

3 Line F-G (Serv Sta Side)

4 Line C-D (Road 20) 20-Jan-18 50 10-Mar-18

5 Line N-O (Blk 13 North Side) 25-Jan-18 30 23-Feb-18

6 Line A-B (Road 21) 25-Jan-18 50 15-Mar-18

7 Line G-H CHB (Service Station Side) 20-Jan-18 14 2-Feb-18

8 Line R-S (Blk 13) 01-Feb-18 55 27-Mar-18

9 Line Q-R (Blk 13) 22-Jan-18 60 22-Mar-18

10 Line P-Q (Blk 13 Road 20) 15-Feb-18 40 26-Mar-18

11 Line S-T ( Blk 13 Road 21) 22-Jan-18 40 2-Mar-18

12 Line E'-F (Blk 12 entrance area) 31-Jan-18 60 31-Mar-18

13 Fence Grill Fabrication, Delivery and Installation 01-Feb-18 70 11-Apr-18

14 Demobilization 10-Apr-18 6 15-Apr-18

Submitted By:

P. R. AREVALO
VECO CDC
VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park

Schedule of Permanent Fence


MARCH
S/N Description Start Duration Finish
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6

1 Line D-E CHB (SM Side)

2 Line U-N (Blk 13 West Side)

3 Line F-G (Serv Sta Side)

4 Line C-D (Road 20) 20-Jan-18 50 10-Mar-18

5 Line N-O (Blk 13 North Side) 25-Jan-18 30 23-Feb-18

6 Line A-B (Road 21) 25-Jan-18 50 15-Mar-18

7 Line G-H CHB (Service Station Side) 20-Jan-18 14 2-Feb-18

8 Line R-S (Blk 13) 01-Feb-18 55 27-Mar-18

9 Line Q-R (Blk 13) 22-Jan-18 60 22-Mar-18

10 Line P-Q (Blk 13 Road 20) 15-Feb-18 40 26-Mar-18

11 Line S-T ( Blk 13 Road 21) 22-Jan-18 40 2-Mar-18

12 Line E'-F (Blk 12 entrance area) 31-Jan-18 60 31-Mar-18

13 Fence Grill Fabrication, Delivery and Installation 01-Feb-18 70 11-Apr-18

14 Demobilization 10-Apr-18 6 15-Apr-18

Submitted By:

P. R. AREVALO
VECO CDC
VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park

Schedule of Permanent Fence


APRIL
S/N Description Start Duration Finish
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 Line D-E CHB (SM Side)

2 Line U-N (Blk 13 West Side)

3 Line F-G (Serv Sta Side)

4 Line C-D (Road 20) 20-Jan-18 50 10-Mar-18

5 Line N-O (Blk 13 North Side) 25-Jan-18 30 23-Feb-18

6 Line A-B (Road 21) 25-Jan-18 50 15-Mar-18

7 Line G-H CHB (Service Station Side) 20-Jan-18 14 2-Feb-18

8 Line R-S (Blk 13) 01-Feb-18 55 27-Mar-18

9 Line Q-R (Blk 13) 22-Jan-18 60 22-Mar-18

10 Line P-Q (Blk 13 Road 20) 15-Feb-18 40 26-Mar-18

11 Line S-T ( Blk 13 Road 21) 22-Jan-18 40 2-Mar-18

12 Line E'-F (Blk 12 entrance area) 31-Jan-18 60 31-Mar-18

13 Fence Grill Fabrication, Delivery and Installation 01-Feb-18 70 11-Apr-18

14 Demobilization 10-Apr-18 6 15-Apr-18

Submitted By:

P. R. AREVALO
VECO CDC
Lube Oil Blending Plant Project Weekly Progress Report No.43 01 February 2018 ; Page 20 of 30
CHANGE ORDER REQUEST
CONTRACTOR CONTRACT No. CONTRACT ETC CONTRACT AMOUNT

11 Nov. '16 (30 Jun '17 FCA


VECO Construction & Development Corporation PO 4020081908 Time Extension) Php35,700,000.00
PROJECT/DEALER LOCATION DATE OF FORM FILL-UP

Lube Oil Blending Plant: Provision of Permanent Perimeter Fence Manila Harbour Center, Tondo, Manila July 2, 2018
COMPLETION DATE EXTENSION REQUEST
REQUESTED EXT. (IN DAYS) JUSTIFICATION (Attach additional information, if necessary)

107 Calendar Days


NEW ETC (IF APPROVED)
Provision of Perimeter Fence Works was hampered due to collision of different contractors, i.e. pipe laying along line R-S and R-Q, some area at
line T-S has been used as temporary access and additional work - increase the height of perimeter fence along along Service station line F-H
July 31, 2018

ADDITIONAL WORKS/REVISIONS REQUEST


DESCRIPTION AMOUNT JUSTIFICATION
ADDITIONAL WORKS:

TOTAL ADDITIVE COST: PHP 0.00 (VAT ex)

DEDUCTIVE WORKS:

TOTAL DEDUCTIVE COST: PHP 0.00 (VAT ex)

ESTIMATED AMOUNT PHP 0.00


PREPARED BY: (CONSTRUCTION MANAGER - CONSTRUCTION MANAGEMENT GROUP) ENDORSED BY: (CONSTRUCTION MANAGEMENT GROUP HEAD)

MC Ventura
NOTED BY: SSC SUPERVISOR / DCG HEAD ENDORSED BY: (FUELS PROJECT GROUP HEAD)

Rosendo Ariola JS Villarin/CC Adorable VM Castillo

A. Approved Budget B. Actual Cost

Civil Works Contract Amount 35,700,000.00


SS Equipment 10% Contingency
Signages SS Equipment (estimated cost)
Signages (estimated cost)
Proposed Add'l Cost -

Budget Excess/Shortfall

ATTACHMENTS

Please see attached initial proposal of Veco

ENDORSED FOR APPROVAL:

W.R. Buencamino / B.O. Fallaria Jr. NS Ventigan


VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park

Schedule of Permanent Fence


S/N Line Description Start Duration Finish JUNE JULY
24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 DE Line D-E CHB (SM Side)


2 DE Repair and Rectification 26-Jun-18 15 10-Jul-18
3 DE Installation of Fence - 2 Panels 05-Jul-18 2 06-Jul-18
4 AB Line A-B (Road 21)
5 AB Repair and Rectification 27-Jun-18 18 14-Jul-18
6 AB Mould forms , casting and finishing (40 nos) 27-Jun-18 18 14-Jul-18
7 CD Line C-D (Road 20)
8 CD Repair and Rectification 27-Jun-18 10 6-Jul-18
9 CD Mould forms, casting and finishing (15 nos) 07-Jul-18 5 11-Jul-18
10 GH Line G-H CHB (Service Station Side)
11 GH Repair and Rectification 30-Jun-18 4 3-Jul-18
12 FG Line F-G (Serv Sta Side)
13 FG Repair and Rectification 27-Jun-18 3 29-Jun-18
14 FG Painting 05-Jul-18 7 11-Jul-18
15 E'F Line E'-F (Blk 12 Exit area)
16 E'F Installation of Fence - 2 Panels 07-Jul-18 2 8-Jul-18
17 E'F Mould forms , casting and finishing (2 nos) 07-Jul-18 3 9-Jul-18
18 PQ Line P-Q (Blk 13 Road 20)
19 PQ Repair and Rectification 07-Jul-18 3 9-Jul-18
20 PQ Installation of Fence - 2 Panels 03-Jul-18 2 4-Jul-18
21 PQ Mould forms , casting and finishing (2 nos) 10-Jul-18 3 12-Jul-18
22 QR Line Q-R (Blk 13)
23 QR Repair and Rectification 27-Jun-18 5 1-Jul-18
24 RS Line R-S (Blk 13)
25 RS Repair and Rectification 02-Jul-18 5 6-Jul-18
26 ST Line S-T ( Blk 13 Road 21)
27 ST Repair and Rectification 27-Jun-18 5 1-Jul-18
28 ST Installation of Fence - 1 Panel 27-Jun-18 1 27-Jun-18
29 ST Mould forms , casting and finishing (5 nos) 26-Jun-18 6 1-Jul-18
30 UN Line U-N (Blk 13 West Side)
31 UN Repair and Rectification 27-Jun-18 5 1-Jul-18
32 F'F Line F'-F (Road 10 Side)
33 F'F Installation of Fence - 9 Panels 09-Jul-18 5 13-Jul-18
34 F'F Mould forms , casting and finishing (3 nos) 10-Jul-18 2 11-Jul-18
35 F'F Repair and Rectification 04-Jul-18 10 13-Jul-18
36 NO Line N-O (Blk 13 North Side)
37 NO Repair and Rectification 02-Jul-18 5 6-Jul-18
38 NO Mould forms , casting and finishing (3 nos) 07-Jul-18 4 10-Jul-18
39 NO Installation of Fence - 1 Panel 02-Jul-18 1 2-Jul-18
40 Inspection, Punchlist,Punchlist Clearing and Acceptance 01-Jul-18 30 30-Jul-18
41 Demobilization 20-Jul-18 12 31-Jul-18

Submited by:

PASCUAL R. AREVALO

VECO Construction and development Corporation


CHANGE ORDER REQUEST
CONTRACTOR CONTRACT No. CONTRACT ETC CONTRACT AMOUNT

11 Nov. '16 (30 Jun '17 FCA


VECO Construction & Development Corporation PO 4020081908 Time Extension) Php35,700,000.00
PROJECT/DEALER LOCATION DATE OF FORM FILL-UP

Lube Oil Blending Plant: Provision of Permanent Perimeter Fence Manila Harbour Center, Tondo, Manila August 14, 2018
COMPLETION DATE EXTENSION REQUEST
REQUESTED EXT. (IN DAYS) JUSTIFICATION (Attach additional information, if necessary)

31 Calendar Days
NEW ETC (IF APPROVED)

Extension of schedule is due to unpredictable weather.


August 31, 2018

ADDITIONAL WORKS/REVISIONS REQUEST


DESCRIPTION AMOUNT JUSTIFICATION
ADDITIONAL WORKS:

TOTAL ADDITIVE COST: PHP 0.00 (VAT ex)

DEDUCTIVE WORKS:

TOTAL DEDUCTIVE COST: PHP 0.00 (VAT ex)

ESTIMATED AMOUNT PHP 0.00


PREPARED BY: (CONSTRUCTION MANAGER - CONSTRUCTION MANAGEMENT GROUP) ENDORSED BY: (CONSTRUCTION MANAGEMENT GROUP HEAD)

MC Ventura
NOTED BY: SSC SUPERVISOR / DCG HEAD ENDORSED BY: (FUELS PROJECT GROUP HEAD)

Rosendo Ariola JS Villarin/CC Adorable VM Castillo

A. Approved Budget B. Actual Cost

Civil Works Contract Amount 35,700,000.00


SS Equipment 10% Contingency
Signages SS Equipment (estimated cost)
Signages (estimated cost)
Proposed Add'l Cost -

Budget Excess/Shortfall

ATTACHMENTS

Please see attached initial proposal of Veco

ENDORSED FOR APPROVAL:

W.R. Buencamino / B.O. Fallaria Jr. NS Ventigan


VECO Construction and Development Corporation
LOBP , Manila Harbor Center and Industrial Park
Schedule of Permanent Fence
S/N Line Description Start Duration Finish JULY AUGUST
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

1 DE Line D-E CHB (SM Side)


2 DE Repair and Rectification 16-Jul-18 20 4-Aug-18
3 DE Installation of Fence - 2 Panels 23-Jul-18 2 24-Jul-18
4 AB Line A-B (Road 21)
5 AB Repair and Rectification 20-Jul-18 18 6-Aug-18
6 AB Mouldings Finishing (14nos) 20-Jul-18 18 6-Aug-18
7 AB Grinding, Touch up Painting of Fence 25-Jul-18 10 3-Aug-18
8 CD Line C-D (Road 20)
9 CD Repair and Rectification 20-Jul-18 10 29-Jul-18
10 CD Mouldings Finishing (10 nos) 29-Jul-18 10 7-Aug-18
11 CD Grinding, Touch up Painting of Fence 23-Jul-18 10 1-Aug-18
12 GH Line G-H CHB (Service Station Side)
13 GH Repair and Rectification 23-Jul-18 4 26-Jul-18
14 FG Line F-G (Serv Sta Side)
15 FG Repair and Rectification 27-Jul-18 3 29-Jul-18
16 FG Painting 20-Jul-18 7 26-Jul-18
17 E'F Line E'-F (Blk 12 Exit area)
18 E'F Repair and Rectification 21-Jul-18 3 23-Jul-18
19 E'F Installation of Fence - 2 Panels 25-Jul-18 3 27-Jul-18
20 E'F Mould forms , casting and finishing (2 nos) 22-Jul-18 3 24-Jul-18
21 PQ Line P-Q (Blk 13 Road 20)
22 PQ Repair and Rectification 23-Jul-18 3 25-Jul-18
23 PQ Installation of Fence - 2 Panels 04-Aug-18 2 5-Aug-18
24 QR Line Q-R (Blk 13)
25 QR Repair and Rectification 27-Jul-18 5 31-Jul-18
26 RS Line R-S (Blk 13)
27 RS Repair and Rectification 31-Jul-18 5 4-Aug-18
28 ST Line S-T ( Blk 13 Road 21)
29 ST Repair and Rectification 27-Jul-18 5 31-Jul-18
30 UN Line U-N (Blk 13 West Side)
31 UN Repair and Rectification 27-Jun-18 5 1-Jul-18
32 F'F Line F'-F (Road 10 Side)
33 F'F Installation of Fence - 9 Panels 28-Jul-18 7 3-Aug-18
34 F'F Mould forms , casting and finishing (3 nos) 22-Jul-18 3 24-Jul-18
35 F'F Repair and Rectification 25-Jul-18 10 3-Aug-18
36 NO Line N-O (Blk 13 North Side)
37 NO Repair and Rectification 20-Jul-18 7 26-Jul-18
38 NO Mould forms , casting and finishing (3 nos) 20-Jul-18 4 23-Jul-18
39 NO Installation of Fence - 1 Panel 06-Aug-18 1 6-Aug-18
40 Inspection, Punchlist and Acceptance 01-Aug-18 31 31-Aug-18
41 Demobilization 25-Aug-18 7 31-Aug-18

Prepared by:

Pascual Arevalo
VECO Construction and Development Corporarion