Sie sind auf Seite 1von 9

KARNAPHULI WATER SUPPLY

PROJECT PHASE 2
Request of Change Design
For
Mixing Chamber Embedded Pipe

CONTRACT No. KWSP2/W-1

(Construction of Intake Facilities, Water Treatment Plant, Reservoir and Elevated Tank)

A 25.April.2018 For Approval Khan SM Lee GH Lee


Rev Date Description Orig. by Chk’d by App By Remarks
References
Chittagong Water Supply & Spec. Tag No.

Sewerage Authority (CWASA)

DWG No.

Kolon Global Corporation


Kubota Construction Co., Ltd
ISSUE PURPOSE
NJS Consultants Co., Ltd INFORMATION

(NJS) REVIEW
ACCEPTANCE x
CONST.

REV
DEPARTMENT DOCUMENT NO. NO

Kolon Global Corporation A


TABLE OF CONTENTS

1. General.................................................................................................................................3

2. Condition..............................................................................................................................3

3. Comparison B/W Ductile Iron Pipe THK., and Stainless Schedule Pipe THK....................3

5. Ductile Iron Pipe Specification.............................................................................................4

6. Stainless Pipe Specification..................................................................................................5

7. Mixing Chamber Detail Drawing ( DN 150 X 5 Nr )...........................................................6

8. Mixing Chamber PLAN Drawing.........................................................................................7

9. Clarifier De-Sludge Piping Detail Drawing ( DN 200 x 32 Nr )..........................................8

10. Clarifier De-Sludge Piping PLAN Drawing.........................................................................9

11. Embedded Pipe Sleeve Detail Drawing ( Stainless SCH20 Sleeve Detail )…………….10

2
1. General

The Contractor would like to request the Engineer to approve Stainless Pipe Sleeve as the for the following items instead
of Ductile Iron Pipe Sleeve

2. Condition

Description Working Drawing Proposed Drawing Reamrks

Mixing Chamber Ductile iron Pipe K9 Stainless Pipe SCH20 DN 150 x 5 Nr


Drain Pipe

De-Sludge Piping Ductile iron Pipe K9 Stainless Pipe SCH20 DN 200 x 32 Nr

Remark The Mix chamber area Rebar installation of is finished, But Ductile iron pipe delivery
(Reasons) around takes 8 Month , In case Stainless Pipe materials , Site delivery around takes 2
month

3. Comparison B/W Ductile Iron Pipe THK., and Stainless Schedule Pipe THK

Description Pipe Diameter THK (Thickness ) Remarks

Ductile iron Pipe DN 150 6 mm Drain Pipe Line


K9 DN 200 6.3 mm

Stainless Pipe DN 150 5.0 mm Sludge Pipe Line


SCH20 DN 200 6.5 mm

* Reference Data : No.4 Ductile Iron Pipe Specification

No.5 Stainless Pipe Specification

No.6 Mixing Chamber Plan and Detail Drawing

No.7 Embedded Pipe Sleeve Detail Drawing.

2
4. Ductile Iron Pipe Specification

5. Ductile Iron Pipe Specification

2
6. Stainless Pipe Specification

7. Mixing Chamber Detail Drawing ( DN 150 X 5 Nr )

2
8. Mixing Chamber PLAN Drawing

2
9. Clarifier De-Sludge Piping Detail Drawing ( DN 200 x 32 Nr )

2
10. Clarifier De-Sludge Piping PLAN Drawing

2
11. Embedded Pipe Sleeve Detail Drawing ( Stainless SCH20 Sleeve Detail )

Das könnte Ihnen auch gefallen