Beruflich Dokumente
Kultur Dokumente
and Methods
of Testing
PRESTRESSED
CONCRETE
Wire
and Strand
nsile test on
gh strength
re using file
:e grips.
INTRODUCTION
The ACI-ASCE Joint Committee, having
recently submitted a preliminary report on
"Recommended Practice for Prestressed Con-
By H. J. Godfrey crete," it may be an opportune time to rc-
John A. Roebling's Sons Corporation fleet momentarily on some of the physical
characteristics of steel wire and strand re-
Trenton, New Jersey ferred to in the above report,, and atteffIX
to visualize their significance. In this discus-
sion of the properties of steel wire °td
strand we shall describe some of the testing
methods by which they are determined 0d
make certain recommendations in regard to
specifications.
38 PCI JOUR'AL
MATERIALS
This presentation will be limited to ti
two principal high strength materials use
in prestressed concrete — cold drawn ste
wire and 7-wire strand. Although the prof
erties of these materials are quite differe]
from those of reinforcing bars used in con
ventional reinforced concrete, it is of intere
to know that all of these materials are mac
with the same basic elements, namely, ca
bon, manganese, silicon and iron.
The iron content of steel used in reinfor^
ing bars is approximately 99% and for ste
wire is approximately 98%. It is for th
reason they have some properties which ai
very similar. However, a 1% difference i
the other ingredients and the methods c
manufacture make them quite dissimilar i
a great many respects. Of primary impor
ance is the carbon content, which, in prc
stressed concrete wire, may be 4 to 5 tirm
that in ordinary reinforcing steel.
It is quite important for the fabricator
prestressed concrete structures to recogniz
these differences so that unnecessary difficu
ties may be avoided.
PHYSICAL PROPERTIES
1. TENSILE STRENGTH AND ELONGATION
The tensile strength of a prestressing el(
ment is of primary importance since th.
value generally determines the design stress(
in a prestressed concrete structure. The ac
tual ultimate load of a prestressed concret
beam, however, may be dependent upo
other factors, such as design and type c
loading.
The testing of a wire of such a high ter
sile strength requires special type grips t
insure a reliable test. An example of suit
able grips is illustrated in Fig. 1. Thes
grips are lined with replaceable file face in
sorts which are ground with a small taper o.
the leading edge of the insert. The load i
picked up gradually by the grip and genes
ally, fracture takes place within the tet
length between the grips.
The hardness of the high tensile wire is Fig. 2—Tensile test on 3/a" dia. strand using "V"
such that even the file hard inserts become grips-2 t/2" long.
worn and have to be replaced periodically.
TABLE
DECEMBER 1956 39
The tensile strength of strand is generally
expressed in pounds rather than pounds per
square inch. For example, the catalog
strength of a 3/s" diameter 7-wire strand is
20,000 lbs., which is equivalent to 250,000
pounds per square inch.
A satisfactory test on high strength strand
requires a properly designed grip so that the
true tensile strength may be obtained. A
series of tensile tests were made on a 3/s"
.i.P.i
tures in a tensile test after only 6% elonga defective material.
tiOn can stretch 20% in a wrap test. The wrap test was inadequate in this in
An examination of the elongation which stance because the surface quality of th
takes place in a 10” gage length of a tensile ‘ire was satisfactory but the very center c
specimen will show that possibly 95% of ,ae wire was below standard. The center
the gage length will have stretched only 5%
to 6% but at the point of fracture the elon
St,enqlh ot 02%
Not
)
trand extensometer.
Fig. 12—Top clamp on strand extensometer.
say be over 50%. For example, a
ch has a reduction of area of 50%
)oint of fracture must necessarily
100% in this same area. We should
herefore, that the nominal elonga
e is an average for the entire gage
md does not indicate the large
of local plastic deformation that
ce at the fracture.
trap test is of value, particularly Elongation—inch per inch
face defects are present. However,
found that the best index of ductil a
een the reduction of area as deter- Fig. 14
the tensile test. Experience in the
indicated that wires having a low
i of area may not be satisfactory
e high sustained stresses used for
ning. Wire may meet all of the the wire lies on the neutral axis of the speci
uirements but based on past expe men during the wrap test and therefore is
e now reject all material having a ant stressed in tension.
i of area of less than 30%. This The reduction of area test is affected by
ent allows for a good margin of both interior and surface defects, and for
d our inspection procedure includes this reason is recommended as a ductility re
rmination of the tensile strength, (Itisrement for prestressed concrete materials.
o and reduction of area on both 4a 3. Yucen STRENGTH
ach coil of wire processed. 4 1-laying discussed the strength and ductil
shall illustrate, the wrap test does ity of wire and strand, we should now con
vs reflect low ductility, particularly sider their behavior under working loads. In
low ductility is not the result of a conventional reinforced concrete design, it is
ondition. general practice to keep the design stresses
of prestressed concrete wire which within the elastic range of the material and
rejected for low reduction of area considerably below the stresses at which ex
d for its ductility as measured by cessive yielding takes place in the steel. Fig. 13—Dial gages and base plate of strand
test. The reduction of area of this In contrast to reinforcing bars, steel wire
and strand do not exhibit a definite yield
zz
aa
point but yield in such a gradual manner
that their plastic behavior must be deter-
mined from a stress-strain curve. The
method of measuring the stress-strain rela-
tionsi p of wire is illustrated in Fig. 9,
where a 2" gage length optical extensometer
is being used to measure the elongation of
the wire. After obtaining the required data,
the stress-strain curves are then plotted on a
graph, as illustrated in Fig. 10. The yield
strength in this instance was determined by
the offset method using an arbitrary value of
0.2% or .002 inch per inch permanent strain.
The offset method assumes that if the load
is released from any point on the curve, the
stress-strain relationship will be described by
a line drawn parallel to the straightline por-
tion of the original stress-strain curve.
The yield strength is thus determined by
constructing a line from zero stress at a
strain of .002 inch per inch parallel to the
straightline section of the original curve.
The yield strength is the stress at which the
constructed line intersects the original curve.
Other arbitrary values, such as 0.1%, can
be used for determining the yield strength
but the 0.2% value is more frequently used.
The yield strength should represent that
stress at which the strain increases very
rapidly when the yield strength is exceeded.
A prestressed concrete structure when loaded
beyond this value would develop large per- Fig. 16
manent deflections.
The tentative specifications require that characteristics of stress-relieved prestressed
the minimum yield strength of wire be 80% concrete wire, and no additional tests are
of the specified ultimate tensile strength. necessary.
This requirement, together with the specifi- The yield strength of 7-wire strand is also
cations for strength, elongation and reduc- determined in a similar manner except that
tion of area, completely define the physical a different type extensometer is used. A gen-
F;. 17
Creep Test
on
.308° diam. 7 Wire Strand
Creep Load— 7310 lbs.
No.1— Stress Relieved after Stranding.
No.2— Wires Stress Relieved before Stranding.
.0004
N o. 2
n .0003
I
C
.0002
N o.
m
V .0001
C
0 20 40 60 80 100 120 140 160 180
Time— Hours
DECEMBER 1956 45
tensile strength, it is often interpreted as rep-
resenting the ultimate load. In order to an-
swer this and other questions we are pre-
senting Fig. 15, the data for which was ob-
tained in the following manner:
An initial load of 100 pounds was applied
so that the strand would be rigid enough to
hold the extensometer steady. Elongation
readings were then observed up to a load of
14,000 pounds after which the load was re-
duced to 100 pounds. During this loading
cycle the strand behaved elastically as the
elongation readings were the same on both
loading and unloading.
The strand was then loaded to 20,000
pounds, which was approximately the yield
strength of this particular specimen. At this
load the steel was deforming plastically and
after reducing the load again to 100 pounds
we found that the strand did not return to
its original length.
eral view of the strand extensometer is Upon reloading the strand to 20,000
shown in Fig. 11. The instrument consists pounds the elongation values traced a differ-
of a metal tube which is attached to the ent line and formed what is known as a
strand at the upper end by means of split hysteresis loop. In loading beyond 20,000
collars inside a flexible coupling, as shown in pounds the strand continued to stretch at a
Fig. 12. very rapid rate, and after 4% elongation the
The lower end of the extensometer con- range of the extensometer dials was ex-
sists of a flat plate which is attached to the ceeded. The total elongation at fracture as
strand at a point 50" below the top clamp indicated by the curve was from 6 to 8%.
(Fig. 13) . The elongation in the 50" gage The large amount of stretch between the
length is measured by two 2" travel dials yield strength and ultimate strength makes
reading to .001", which is equivalent to a the stress-relieved strand an ideal material
strain of .00002 inch per inch. for prestressed concrete.
A typical load-elongation curve obtained
in this manner is illustrated in Fig. 14. The The high elastic properties of strand are
yield strength was determined in the same obtained by stress - relieving the finished
manner as used for the single wire test. strand and not by making the strand with
Because the highest plotted value on the stress-relieved wire. If the latter method is
load-elongation curve is above the required used, the elastic properties of the stress-
46 PCI JOURNAL
relieved wire are destroyed during the The result of the relaxation test is shown
stranding operation, as illustrated in Fig. 16 in Fig. 19. The test indicated that under the
where the load-elongation curves for the two initial prestressing load of 14,000 lbs. the
types of strand are presented. Up to loads loss in stress over the first 18 hours was only
included in Fig. 16 the curve representing 360 lbs. After the load was intentionally re-
strand made with stress-relieved wire is very duced 1040 lbs. to simulate the transfer of
similar to strand not stress-relieved during stress to the concrete, very little stress loss
any manufacturing stage. was observed. In practice, therefore, we
The creep properties of the material stress- may assume that any appreciable stress loss
relieved after stranding were also consider- in the strand after transfer of load would be
ably better than the strand manufactured due to shrinkage or plastic flow of the con-
with stress-relieved wire, as shown in Fig. 17. crete.
4. CREEP AND RELAXATION 5. EFFECT OF WELDS
The subject of creep and relaxation of pre- During the fabrication of strand it is nec-
stressed concrete materials has been dis- essary to make welds in the individual wires.
cussed to considerable extent in previous These welds are necessary in order to make
meetings on prestressed concrete. At this a long continuous length of strand. In any
time we would like to present the results of one wire position in a 7-wire 3/s" diameter
a relaxation test, which, to some extent du- strand these welds occur at approximately
plicates the loading conditions that might be each 10,000 feet. With 7 wires in the strand,
placed on a 3/8" diameter strand in a pre- however, it is possible to have several welds
tensioned beam. in the same section of strand if suitable care
The loading cycles were as follows: is not taken during the stranding operation.
a. Pretensioned to 14,000 lbs. In practice, the welds are limited to one in
b. Ends fixed for 18-hour period (during any 150 -foot length of strand.
which time relaxation took place) Special lengths of strand were fabricated
c. Load intentionally reduced 1040 lbs., containing from one to four welds in each
or 13,000 p.s.i. test length. Only one weld was made in
(The 13,000 p.s.i. was obtained from each wire and where more than one weld
the Bureau of Public Roads Criteria, was in the strand the welds were approxi-
which provides a loss of 3,000 p.s.i. for mately one foot apart. The results of the
shrinkage in the concrete that takes tensile tests are presented in Table II.
The Effect of Welds on the Tensile Strength of 3/s' Dia. 7 -Wire Strand
1 0 22,300 111.5
2 1 19,400 97.0
3 1 18,800 94.0
4 2 16,400 82.0
5 2 17,300 86.5
6 3 17,000 85.0
7 3 16,800 84.0
8 4 16,000 80.0
9 4 15,600 78.0
TABLE 1I
place during the first 18 hours plus a As indicated in Table II, the tensile
steel stress equal to 5 times the con- strength of the strand generally decreased as
crete stress, which was assumed to be the number of welded wires increased. Since
2,000 p.s.i.) welds are limited to one in any 150 foot
d. Ends fixed and relaxation of the strand length of strand it should be possible to
measured. safely apply the recommended pre-tension-
ing load of 14,000 pounds.
The above relaxation test can be readily
made in a mechanical type testing machine Welding is not recommended for use in
or in a test setup as illustrated in Fig. 18. the manufacture of larger diameter single
The 3/8" diameter strand specimen was ap- wires for prestressed concrete. Any high
proximately 20 feet long and was held at temperature heat treatment such as welding
each end with reliable grips. A steel "H" will seriously affect the properties of high
beam was used to take the thrust developed carbon steel wire. The users of these high
by the strand which was tensioned by a nut strength steels should be cognizant of this
and screw arrangement on the end of a cali- heat effect and make sure that all necessary
brated dynamometer. precautions are taken in the field.
DECEMBER 1956 47