Sie sind auf Seite 1von 6

SHOTCRETE DESIGN FOR IRRIGATION CANAL LINING

Syed Hasan1, Gunvant Vaghela2, James Yip3, Ben Chung4

ABSTRACT: The major artery of Lake Wyangan irrigation system is the 16km long Lake View Branch Canal (LVBC)
which was installed mainly in 1928. The 75mm thick reinforced concrete lining is currently in a poor condition with
significant water loss through seepage and needs replacement as part of Lake Wyangan Modernisation project.

The main factors to be considered in the selection of a lining type include durability, seepage loss, construction cost
and time, and maintenance cost. For irrigation canals, the use of concrete (cast in place or precast) with or without
reinforcement is the most common practice of canal lining. A shotcrete lining (unreinforced or fibre reinforced) is
uncommon for irrigation canals and there has been limited (if any) documentation of its recent usage in Australia. A
trial comprising approximately 27m long prototype (with fibre reinforced and unreinforced) shotcrete lining of different
joint configurations constructed on ground having similar properties to the LVBC was undertaken. On the basis of the
trial result together with cost and performance, unreinforced shotcrete lining with transverse and longitudinal control
joints was selected as the preferred canal lining option for un-obstructed flow of water without excessive seepage. This
paper provides details of the LVBC renewal, including a literature review of irrigation canal lining, the development of
design and the validation process.

KEYWORDS: Shotcrete, Prototype model, Fibre-reinforced, Unreinforced.

1 INTRODUCTION
Lake Wyangan Modernisation project (a key component Canal bed lining will be retained where lining
of Murrumbidgee Irrigation’s Modernisation Program) condition is good, otherwise the bed will be
involves the replacement of the ageing concrete lined upgraded by overlaying 75mm thick
irrigation channel system with a modern and efficient unreinforced concrete.
water delivery system to service around 200 land
holdings in Lake Wyangan catchment. The Australian 2 CURRENT PRACTICES OF LINING
Government is providing funding of $50 million for this
project as part of the Private Irrigation Infrastructure
CONSTRUCTION
Operators Program in NSW. An Alliance, MIA Renewal A limited literature review of canal linings has indicated
Alliance, comprising Murrumbidgee Irrigation Limited,
the following:
GHD, UGL Infrastructure and John Holland Group was
set up to plan, design and construct the modernisation Most concrete linings installed in older channels
project. in the United States were reinforced. Recently,
to reduce construction cost, reinforcement has
The 16km long Lake View Branch Canal (LVBC) was been omitted wherever possible. (Stevenson,
built mainly in 1928. The existing 75mm thick
reinforced concrete canal [1] is at the end of its design 1999) has reported that it is generally better to
life and is being refurbished as follows: use unreinforced concrete [2]. Reinforcement
cannot be justified, except under unusual
Canal bank lining is being demolished and
replaced with 85mm thick unreinforced conditions such as high back pressure, high
shotcrete lining. flow velocities and where movement of the
Majority of the canal is being widened to subgrade is a possibility. Unreinforced concrete
increase its capacity. linings are more susceptible to damage by

1
Syed Hasan, GHD Pty Ltd, Sydney. Email: syed.hasan@ghd.com
2
Gunvant Vaghela, GHD Pty Ltd, Sydney. Email: gunvant.veghela@ghd.com
3
James Yip, GHD Pty Ltd, Sydney. Email: james.yip@ghd.com
4
Ben Chung, GHD Pty Ltd, Sydney. Email: ben.chung@ghd.com
hydrostatic pressure and subgrade movement, (CRCP) [5] [It must be noted that these
however this is more than offset by the channels are designed for vehicular traffic,
difference in cost when compared to a hence the use of the term “pavement”].
reinforced lining. Unreinforced concrete
Unreinforced shotcrete is considered suitable
fractures more readily than reinforced concrete,
for applications where there are no applied
thus relieving the pressure and reducing the area
loads, or when, tension is not applied to the
of damage. Steel reinforcement , controls crack
shotcrete material [6].
widths however it complicates construction and
will lead to deterioration associated with Channels, reservoirs and spillways can be
corrosion. A recent option for reinforcement in constructed by excavating the required shape
concrete involves the addition of fibre and shotcreting directly freeform onto the
reinforcement, synthetic or steel fibres exposed rock or earth. Shotcrete has the ability
(approximately 20-40mm long) [2]. to be placed, compacted and finished (possibly
in one pass) in cases requiring high access,
A successful concrete lined channel must be
freeform or very thick linings. Some examples
durable and remain substantially watertight to
include the Olympic Whitewater Stadium
give many years of low-maintenance service
Channel in Sydney and Shannon Creek Dam
life. The success of a concrete liner is highly
Spillway in Grafton NSW [6].
dependent on its installation and materials used.
[2]. Unreinforced shotcrete canal lining was used in
North Unit Canal, USA with excellent condition
Concrete, cast in place or pre-cast, with or
after 10 years of service [7].
without reinforcement is a common type of
lining for irrigation canals. The disadvantages 3 DESIGN OF CANAL LINING
of this type of lining are its relative high cost,
the long period of time required for its
3.1 DESIGN CRITERIA
installation and its lack of capability to adjust
itself to differential settlement of the underlying The criteria used in the design of canal lining are as
soil [3]. follows:
Convey the required flow (as defined by the
A nominal weldmesh reinforcing layer in canal hydraulic analysis, this requires an increase in
lining has proved to be of assistance in keeping the available waterway area);
maintenance and repair costs to a minimum by Be constructible and suitable for construction
distributing stresses caused by temperature within the window available at the winter
effects and other minor operational loading. For shutdown;
this reason it is usual practice in the Department Substantially water tight but not required to be a
of Water Affairs, South Africa [4] to place this water retaining structure;
reinforcement. However, there are certain cases Prevent erosion and dispersion of the soil
where an unreinforced concrete lining is both behind the canal lining;
preferable and acceptable. Construction joints, Retain the existing canal bed where the
placed transversely across the canal at about 3m condition of the existing bed allows this;
intervals, are convenient for hand-lining in Level of durability sufficient to achieve design
which alternate slabs are cast sequentially life of 80 years (with maintenance as required);
thereby limiting tensile stress development. and
Corps practice [5], prior to the 1960’s, was to Not to be designed for equipment or traffic
utilise concrete pavement with expansion and loading
contraction joints for paved trapezoidal
channels. The experience with these channels 3.2 DESIGN DEVELOPMENT OF CANAL
shows that substantial joint maintenance is LINING MATERIAL
required. When concrete paving is used for The main factors considered in the selection of canal
trapezoidal channels in soils, it should be lining material include; durability for 80 years design
continuously reinforced concrete pavement life, seepage loss, maintenance cost, construction cost
and time (for construction during winter shutdown at 3m spacing and expansion joints at 30m spacing was
periods). The lining materials considered during selected.
detailed design stage are covered below.
3.3 DETAILED DESIGN OF UNREINFORCED
3.2.1 Reinforced concrete lining cast-in-situ or CANAL LINING
precast During the detailed design of the unreinforced canal
The existing lining design of approximately 75mm thick lining, comprising a shotcrete bank and a concrete bed,
reinforced concrete was reviewed and discounted on the the following design considerations were taken into
basis of inadequate cover to the reinforcement to comply account :
with current design standards. A conventionally
reinforced concrete lining would need to be in the order 3.3.1 Hydrostatic uplift pressures
of 140mm thick to provide longevity and robustness. The results of the geotechnical investigation have
However, it will result in a substantially higher cost than indicated that the canal is predominantly underlain by
unreinforced lining. For this reason reinforced concrete low permeability clay material. On this basis,
cast-in-situ or precast lining was not considered to offer groundwater inflow beneath the canal lining is unlikely
value for money. to develop damaging uplift pressure when the canal is
empty, and as such, no treatment has been specified. At
3.2.2 Fibre-reinforced shotcrete localised areas of the canal where high ground water and
Fibre reinforced shotcrete has higher capital cost and sandy soil are encountered, weep holes and flap valves
greater difficulty in construction in comparison with are proposed to allow drainage of the subgrade to
unreinforced shotcrete. minimise the effect of hydrostatic uplift.
Two types of fibre reinforcement were considered in this
project: steel and synthetic (polypropylene) fibres. 3.3.2 Shrinkage and temperature effect
Steel fibres can assist with the long term control of To prevent cracking of unreinforced lining due to
drying shrinkage cracking by providing resistance to shrinkage and temperature effects, transverse contraction
widening of cracks. To achieve this, sufficiently high joints are designed at 3m spacing. The short panel length
dosage of steel fibres will be required, with the following will minimise any cracking and enable easy replacement
implications: of panel in the event of further cracking or breaking.
Cons: significant capital cost, and difficulty in Transverse expansion joints at 30m spacing are also
achieving homogeneity and finishing of the provided. Rearguard waterstops under contraction and
shotcrete; and expansion joints are required to mitigate seepage losses.
Pros: provide an added degree of tensile
strength and larger contraction joint centres 3.3.3 Reactive soil movement
could be achieved. Due to the presence of medium to high plasticity clay
Synthetic fibres provide no material benefit for long along the canal alignment, an average 50mm of
term drying shrinkage, but can assist in the reduction of foundation movement is expected normal to the canal
plastic cracking (cracking while the shotcrete is in a lining [8]. Such movement is expected to occur
fresh state) and slumping during construction. predominantly in the upper soil strata. A finite element
model using STRAND-7 software was used to analyse
3.2.3 Unreinforced shocrete/concrete lining the effect of soil heave on unreinforced panels. Heave
Unreinforced shotcrete/concrete lining requires effects in the transverse direction is expected to occur at
contraction joints at close intervals to reduce the risk of the top of the bank with the potential to lead to the canal
crack development from drying shrinkage, temperature lining panels being unsupported. The structural analysis
and moisture variation. A panel length of 3m was carried out has indicated that the resulting lifting is likely
selected to match the typical existing panel joints of 6m to lead to longitudinal stresses and cracking in the
spacing. unreinforced lining. Therefore a longitudinal control
joint at the mid height of the panel was introduced to
3.2.4 Selection of canal lining material allow the panel to articulate with the movement in the
On the basis of cost, durability and performance of upper soil profile. A longitudinal joint at the junction of
prototype trial test panel’s unreinforced the canal base and bank was also provided to allow
shotcrete/concrete lining with transverse control joints further articulation in the event of soil movement.
Furthermore, to limit direct infiltration and evaporation foundation movement. Rear-guard waterstop is provided
behind the lining, a bitumen coated geofabric is under longitudinal control joints. A 3mm wide wet
incorporated behind the crest of the bank extending formed tooled joint (D/3 depth) is provided to initiate
500mm back from the shotcrete lining. cracking at the joint, where D is the thickness of
shotcrete lining.
3.3.4 Durability
According to AS3735 the exposure classification of Longitudinal joints in base slab
canal water is B2. The 80 year design life calls for a The effect of foundation movement can extend to the
85mm thick unreinforced S40 shotcrete lining, which junction between the base and bank of the canal causing
includes15mm sacrificial thickness as an allowance for rotation of the lining. A longitudinal joint is therefore
surface erosion . provided at the base of the canal, 200mm away from the
junction to mitigate the risk of an uncontrolled crack. A
3.3.5 Joint detailing 3mm wide wet formed tooled joint and a rear-guard
Joint details were developed in consultation with MIA waterstop are provided.
Renewal Alliance taking into consideration the design
Details at top of bank
requirements. The canal bank subgrade would be
The shotcrete at the top of the bank is provided with a
covered with geofabric (Bidim A29) before placing
100mm return to avoid “hanging up” the shotcrete
shotcrete in order to reduce the risk of fine material loss
during placement. This will mitigate the formation of
through the lining cracks. The types of joints used in
horizontal cracks at the top of bank as the fresh shotcrete
the canal lining are covered below:
naturally seeks to move down-slope.
Transverse contraction joints
Transverse joints are provided in the shotcrete lining for 4 TRIAL AND POST DESIGN
shrinkage and temperature movement in the longitudinal VALIDATION
direction. Bending due to heave effect along the canal is In order to validate the performance of the lining design,
negligible for joint spacing of 3.0m. Cold jointed 3m a trial was carried out in April 2013. Approximately
wide shotcrete panels are constructed with a “hit and 27m long prototype canal, comprising nine panels was
miss” fashion and application of bond breaker at the cold constructed in ground having similar properties to the
joints thereby removing the need for a saw cut or crack LVBC. The panels were either fibre reinforced or
initiator. A rear-guard waterstop is provided to mitigate unreinforced shotcrete. The performance of the lining
against seepage loss. “Sika” the supplier of the was reviewed and the following observations were
nominated waterstop confirmed that the waterstop will made:
accommodate the calculated joint movement. Joint Addition of fibre in the shotcrete did not result in an
sealant was not selected due to its lower design life, improved performance when compared with the
requiring maintenance and periodic replacement. unreinforced panels.
Transverse expansion joints More time was required to clean the pump and hoses
With the provision of expansion joints at 30m spacing for fibre reinforced shotcrete.
thermal expansion is estimated as 6mm and short term (7 Shotcreting alternative panels controls thickness as
days after curing) shrinkage movement as 2mm. edge forms act as thickness guides.
Therefore net movement of expansion joint is estimated Between the shotcrete panels, crack widths up to
to be approximately 4mm. The proposed 10mm wide 1.5mm were observed. The cracks did not follow the
expansion joint is capable of accommodating this cold joint due to bonding between adjacent panels as
movement. Similar to the transverse contraction joints, a no bond breaker was applied during trail test.
rear-guard waterstop is provided without any joint
sealant. 5 CONCLUSION

Longitudinal joints The trial test result validated the canal lining design and
Longitudinal joints are required to cater for bending of assisted in fine tuning the design to achieve better
the lining resulting from reactive soil movement, service performance.
covered in Section 3.3.3. A longitudinal control joint is A 85mm thick unreinforced shotcrete lining with
provided at the mid-level of the bank shotcrete lining to transverse contraction joints at 3m c/c and expansion
allow articulation of the panels in the event of
joints at 30m c/c was selected on the basis of cost, trial
test and performance.
The construction of the canal lining commenced in May
2013 with all the works scheduled to be completed by
August 2014. Two winter shutdown periods will be
required to complete the upgrading work. Photograph 1
to 4 shows the construction work of canal lining.

Photograph 4: Concrete pouring on canal bed

Photograph 1: Preparation for shotcrete application

Photograph 5: Completed lining showing joints

ACKNOWLEDGEMENT
The author would like to acknowledge the contributions
made by the entire Alliance Team. The innovations that
are outlined in this paper are a direct result of successful
Photograph 2: Application of shotcrete to canal bank Alliancing relationships. The author would also like to
acknowledge Murrumbidgee Irrigation Limited, and the
Department of Environment, Commonwealth of
Australia for their approval to present this paper.

REFERENCES
[1] Canal Condition Assessment – Lake View Branch;
Report by GHD, 20 July, 2012.
[2] http://www.irrigation.org.au/seepage/4_2_9_concret
e.html.
[3] http://idup.gov.in/wps/UpidHm/UPWSRP/WSRP_St
andardsAndGuidelines/Canal%20Lining.htm.
[4] Guidelines for the design of canals and related
Photograph 3: Roller finish to bank shotcrete panel
structures; Department of Water Affairs, Forestry
and Environmental Conservation, Pretoria, Republic
of South Africa.
[5] Structural Design of Concrete Lined Flood Control
Channels; US Army Corps of Engineers Department
of the Army, EM 1110-2-2007, 30 April, 1995.
[6] Recommended Practice – Shotcreting in Australia;
Prepared by Australian Shotcrete Society for the
Concrete Institute of Australia, 2nd Edition,
September, 2010.
[7] Canal lining demonstration project year 10
durability report; US Department of the Interior,
Bureau of Reclamation, November, 2002.
[8] LVBC Lining – Uplift and Reactive Ground
Movement; GHD Geotechnical Memorandum,
21/20216/187610, 05 February, 2013.

Das könnte Ihnen auch gefallen