Beruflich Dokumente
Kultur Dokumente
Control
Correlation
Monitor
information
Techniques of Scheduling
List of Activities
Bar chart / Gantt Chart
Critical Path Method (CPM)
Precedence Diagram Network (PDM)
PERT (Programme Evaluation & Review
Technique)
Line of Balance Method
Time Chainage Diagram (Mass Haul
Diagram)
Project Scope
Scope statement
a document that provides an understanding,
justification, and expected result of a project
Statement of work
written description of objectives of a project
Work breakdown structure
breaks down a project into components,
subcomponents, activities, and tasks
Blind base
Formwork
Reinforcement
Concrete
Project Scheduling
Steps
• Excavate base (4d)
Define activities
Sequence activities • Blind base (2d)
Estimate time /duration
• Formwork (5d)
Develop schedule
• Reinforcement (4d)
• Concrete (1d)
TIME (weeks)
ACTIVITY
Week 1 Week 2 Week 3
Excavate base (4d)
Blind base (2d)
Formwork (5d)
Reinforcement (4d)
Concrete (1d)
Example of Gantt Chart
Month
0 | 2 | 4 | 6 | 8 | 10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
Month
Copyright 2006 John Wiley
& Sons, Inc. 9-16
Gantt Chart Advantages ?
(Mawdesley, 1997) Disadvantages ?
Bar Chart
Advantages & Disadvantages
Advantages :
1. Simple
2. Easy to make
3. Easy to understand, as it provides visual display of project
schedule
Disadvantages :
1. No clear links between activities
2. If delays occur, the impact on the project is not clear
Linked Bar Chart (Mawdesley, 1997)
Resource Bar Chart (Mawdesley, 1997)
Check the plan (Mawdesley, 1997)
A plan should be checked for:
Completeness
The sequence of the work
Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
1.
2.
1. Define the scope of the project
3. 2. Make a list of activities
3. Put the activities in order
4. 4. Define the durations of the activities
5. Define when the activities starts
5.
Steps of making a bar chart
Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
1. Foundation
2. Wall
4. Roof
5. Finishing (tiles, painting
walls, etc)
Linking activities in the project
predecessor successor
foundation wall
Finish to Start (FS)
Activity Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10
1. Foundation
2. Wall
4. Roof
5. Finishing (tiles, painting
walls, etc)
Network
A network is a diagram showing all
activites which are needed to complete a
project and the order which they must
be done.
It therefore comprises two parts :
The activities
Some method of displaying the
technological logic of construction.
Network (Mawdesley, 1997)