Beruflich Dokumente
Kultur Dokumente
SECUNDERABAD DIVISION
SECUNDERABAD
(Mechanical Branch)
(Tender No: CS.186.Outsourcing.RR.Bidar.29.2018-19 dt: 01.11.2018)
TOP SHEET
e-TENDER DOCUMENT
(NON-TRANSFERABLE)
Issued by
Divisional Railway Manager (Mechanical)
South Central Railway, Secunderabad Division
Secunderabad – 500 071
for and on behalf of President of India
***********
Signature Not
Verified
Digitally signed by
RAMA KRISHNA
RAJU NIDADAVOLU Signature of tenderer Sr.DME/Co-ord/SC
Date: 2018.11.01
18:52:55 IST Page 1 of 76
Reason: IREPS-CRIS
Location: New Delhi
INDEX
Pages
Sl. No. Contents
From To
1 Top Sheet 1 1
2 Index 2 2
3 Check list to be submitted by the Tenderer 3 3
4 NIT 4 4
5 Note to tenderer 5 6
6 Tender form 7 7
8 Conditions of Tender 14 16
9 Part-I- Eligibility criteria of tender 17 19
10 Part-II Schedule of Rate & Quantities 20 24
11 Part- III: Scope of work 25 34
12 Part-IV: Other Conditions of Contract 35 44
1. Tender details:
1.1 Name of the tenderer
1.2 Identification of tenderer:
a) In case of Partnership Firm: A copy of partnership deed with
latest modifications of the deed, if any, attested by any
Gazetted Officer.
b) In case of Company: A copy of articles of association
attested by any Gazetted Officer.
c) In case of Proprietary Firm: Notarized copy of affidavit.
2. Particulars of online payment towards cost of tender form.
3. Particulars of online payment towards EMD.
4. Engineering Organization in Annexure-A
5. Acceptance/Deviation schedule as per Annexure-B
6. Attested copy of Experience Certificate in Annexure-C
7. List of works completed during the last 3 financial years as per
Annexure-D
8. List of works on hand Annexure-E
9. Banking reference for liquidity as per Annexure-G
10. NEFT Mandate form with tenders in Annexure-H
11. Tenderer information as per Annexure-I
12. Affidavit format as per Annexure-03
13. Any other information/ Certificates required as per Tender
document.
The tender schedule and tender notice can be down loaded from Website
“http://www.ireps.gov.in//”
To,
The President of India,
Acting through Sr. Divisional Mechanical Engineer/Co-ordination,
3rd floor, Sanchalan Bhavan, Mechanical branch -SC Division,
South Central Railway
Secunderabad-500 071.
2. I/We also hereby agree to abide by the Indian Railway General Conditions of contract for
services, with all correction slips up-to-date and to carry out the work according to the special
conditions of contract and specification of materials and works as laid down by Railway in the
special conditions of contract, schedule of rates with all correction slips up-to-date for the
present contract.
3. A sum of rupees _____________ is herewith forwarded as earnest money deposit. Full value
of earnest money shall stand forfeited without prejudice to any other rights or remedies in
case my/our Tender is accepted and if:-
a) I/we do not execute the contract documents within 7(Seven) days after receipt of notice
issued by the Railways that such documents are ready, and
b) I/We do not commence the work within 15 (Fifteen) days from the date of issue of letter of
acceptance.
4. I/We am/are a Micro and Small Enterprise registered from ____________ (body approved by
ministry of MSME) with registration No. ________ and terminal validity up to ________ for
similar service contracts.
5. Until a formal agreement is prepared and executed, acceptance of this tender shall constitute
a binding contract between us subject to modifications, as may be mutually agreed to
between us and indicated in the letter of acceptance of my/our offer for this work.
Signature of Tenderer/s
Date
Address
Note: However, expenditure for engaging cook & masalchi cum bearer per shift i.e., minimum of 3
cooks + 3 masalchis-cum-bearers in a day in the kitchen & dining hall shall be borne by the
contractor since already included in the cost of subsidized meals.
SCHEDULE – 2 (Material cost i.e., cost of cleaning chemicals for maintenance of running room):
S.No Description Rate
1 Material cost i.e., cost of cleaning chemicals for
₹ 79,450.94
maintenance of running room
GST @ 18% ₹ 14,301.17
Total cost of schedule -2 including GST ₹ 93,752.11
Note: Chemicals to be supplied as detailed in scope of work.
Magazines – Weekly:
India today(English) -1
2 India today(Hindi) -1 6656.00
Swathi (Telugu)-1
Maharastra Magzane-1
Estimated cost for 24 months 17,606.00
GST @ 18% 3,169.08
Total cost of Schedule-6 including GST 20,775.08
1. LPG cylinders shall be provided by the contractor himself for preparing food.
2. However, railways will reimburse the cost of gas cylinders as per price prevailed @
300 meals per cylinder for the quantum of meals prepared in a month.
3. Payment shall be made based on the original bills issued by PSU oil company submitted
by the contractor issued by the gas agency for the quantity as per the prorata mentioned
in point-2 above i.e., one cylinder cost (unit rate prevailed as per the bill) will be
reimbursed for supply of every 300 meals.
I/We offer the following rates for the work of “Outsourcing of maintenance of Running Room and
supply of subsidized meals to the occupants at Running Room at Bidar”.
On Schedules At Par Below (-) Above (+)
1 Not to be quoted
2
3
4
5
6 Not to be quoted
7 Not to be quoted Not to be quoted
Railways will pay 90% of the cost of meals/breakfast or Rs.41/- whichever is less per
meal/breakfast to the contractor towards subsidy. Balance will be borne by the occupant.
Occupants have to pay for the food item not covered under subsidy. (Railway Board letter no.
2006/M (L) 467/2 dt.23.10.2015)
1.4. The following additional/extra items shall be supplied by the contractor on demand to the
occupants by collecting the amount as mentioned against each from the occupants :
Any deficiency in preparation and late serving of food, Cleanliness of Kitchen and dining
room will attract fine as per penalty clause applicable.
1.9. One Meals Ordering Register as per Annexure-6 shall be maintained. Each of the
occupants shall place the order for Meal/Breakfast in the Ordering register. The
availability, preparation and service time of food items shall be strictly followed.
1.10. The contractor shall arrange to provide Meals/Breakfast as per the stipulations given in
schedule- 3 of Part-II.
1.11. The contractor shall arrange to prepare the food items and serve to the occupants in
hygiene/hot condition.
1.12. Contractor shall maintain separate cooking utensils for preparing Veg items and Non-
Veg item i.e. Boiled egg/omelets.
1.13. Only reputed, branded (Agmark or ISI) and certified provision items shall be used in
preparation of subsidized meals by the contractor.
1.14. If the occupant does not wish to have subsidized meals of standard schedule menu as
per the prescribed rates mentioned in Schedule of Rates, the contract staff shall prepare
only vegetarian meals with the raw materials supplied by the occupants on payment of
Rs.10/- meal to be paid by the occupants to the contractor.
2.1.2. All civil works including plumbing work, from raw water tank to R.O plant, then to
waste water pipeline endpoint and electrical wiring work shall be done by contractor.
2.1.3. Two purified water tanks of 500 litres or more capacity are to be arranged by
contractor.
2.1.4. Railways will provide only open cover roof shed, raw water and electrical single phase
power supply source.
2.1.5. Contractor should cover the comprehensive AMC with OEM/ OEM authorized service
provider to maintain break free & efficient working of R.O plant in such a way that the
TDS of water is maintained at any point of time, will be less than 125 ppm and fluorine
content will be less than 1.5 ppm.
Sl.
Designation 1st Shift 2nd Shift 3rd Shift Total
No
Housekeeping Manager
1 1 1 1 3
(Supervisor)
Helper for housekeeping and
2 2 2 2 6
serving call book etc.
Helper for loading of sand in
3 1 1 1 3
to locomotives
4 Safaiwala(RR) 1 1 1 3
5 Cook 1 1 1 3
6 Masalchi cum bearer 1 1 1 3
Total Manpower 7 7 7 21
At the commencement of the contract (first month), the contractor shall deposit 45 days
consumption stock to RR care taker. Thereafter, the contractor shall hand over all the
cleaning materials for one month requirement during 1st week of every month to the care-
taker well in advance in the presence of Running Room in-charge (CLI/CCC /Bidar).
4.6. All the rooms, dining hall, kitchen of running room shall be cleaned twice in a day.
Beds, tables, chairs, lockers, almarahs, shelves & other furniture’s and windows & doors of
the Running Room shall be cleaned once in a day and shall be kept neat and free from
dust.
4.7. All the fans, coolers & lights shall be cleaned at least once in a week.
4.8. Cleaning of bathrooms, lavatories, urinals, wash basins’ surface area, etc., shall be done
thrice in a day and also to be cleaned on demand by the occupants.
4.9. Water filter & water cooler shall be cleaned once in fortnight.
4.10. The contract staff shall tie up with the Railway sanitary staff for disinfestations of running
room and its circulating areas once in a month and ensure free from cockroaches, bugs &
other insects.
4.11. Contractor shall maintain all assets available in Running Room in proper condition duly
attending very minor repairs, if needed. However, any engineering or electrical repairs shall
be attended by the Railways for which intimation has to be given to CLI/CCC/BIDAR or
DME/O&F for immediate rectification.
4.12. Necessary instructions shall be given to the watchman/gardener to prevent
outsiders/miscreants entering into the running room.
5.1. All the above items shall be taken over by the contractor and the details of quantities
available at the commencement of the contract and any further additions to these items
shall be made available in a register. The availability of these items can be checked at
any of time by the Railways.
Officers of Railways Administration may carry out surprise checks about the execution of
various activities of Running Room contract at any point of time. Penalty will be imposed in case
of any reported deviations about quality, quantity and timely arrangement of food and other
activities of Running Room Contract execution.
Any adverse remarks passed during inspections by the inspecting officers in execution of the
work, the penalties shall be imposed as below:
Sl. Inspecting authority Maximum penalty per
No occasion (in Rs.)
1. Sr.DME or its equivalent level authority 3000/-
2. CMPE/DSL or its equivalent level authority 3500/-
3. CME or its equivalent authority or higher authority 5000/-
All the penalties stated above will be deducted from the monthly bill of the contactor and
decision of railway administration will be final and abided by contractor.
6.0 PENALTY CLAUSE:
Penalty will be imposed against the contractor if any deviations observed during inspection by
Railway representative/officials & complaints received during execution of contract work by the
contractor, as detailed below, which will be deducted from the CC bill of the contractor.
S.
Nature of deviation Penalty
No.
For any written complaint registered in Up to Rs.1000/- shall be levied per
Running Room complaint register by occasion after due verification of
running staff for supply of un- genuineness of compliant followed with
1. hygienic/perished/sub-standard meals recommendation of Running Room in-
other than complaints related to taste or charge (CLI/CCC) and also approved by
increase/ decrease levels of Sr.DME/Co-ord/SC or by any Higher
oil/salt/spiciness in the food items. authority for levy of quantum of penalty.
Rs.100/- per hour or part of hour shall be
2. For delay in serving of meals
levied per occasion after counter check by
(breakfast/lunch/dinner/parcel meal)
Running Room in-charge (CLI/CCC)
For non-usage of Specified/accepted Up to Rs.1000/- shall be levied per
3. provisions as stipulated in clause 1.2 Part- occasion after counter check by
II Detailed Scope of Work. DME/O&F/SC or by any Higher authority.
4. In case Total Dissolved Solids (TDS) of
Rs.500/- shall be levied per occasion.
water exceeds 125 PPM.
Failure to supply the required quantity of Rs.500/- shall be levied per day besides
5. purified R.O. water per day as per clause recovering the amount as per the accepted
2.1.7 & 2.1.8 of Part-II Detailed Scope of schedule rate per day as per clause 2.0 of
Signature of tenderer Sr.DME/Co-ord/SC
Page 38 of 76
work. Part-I schedule of rates & quantities.
Rs.250/- shall be levied per occasion after
6. For improper cleaning of linen/availability
counter check by Running Room in-charge
of any stains.
(CLI/CCC)
For not washing linen/woollen
7. blankets/curtains as per the periodicity of
Rs.100/- shall be levied per occasion.
washing mentioned in Clause 3.1 of Part-
II Detailed scope of work.
8. For not changing linen for every change of
Rs.50/- shall be levied per occasion.
occupant.
For non-usage of approved Cleaning
Rs.2000/- shall be levied per occasion after
9. Agents/Chemicals for washing & ironing of
counter check by ADME/ DME/O&F/SC or
linen/woollen blankets, as per clause 3.4
by any Higher authority.
of Part-II Detailed Scope of Work.
For reported washing & ironing of linen
10. within running room premises, in
Rs.500/- shall be levied per occasion.
contravention to clause 3.6 of Detailed
Scope of Work, Part-II.
Rs.500/- shall be levied as penalty per
For failure to deploy specified contract occasion besides recovering minimum
11. staff as stipulated in clause 4.2 of Part-II, wages in force for un-skilled/skilled staff
Detailed Scope of work falling short of specified men in the
contract.
For delay in depositing one month stock of
12. cleaning chemicals/implements to the Rs.100/- shall be levied per day or part of
Caretaker as specified in Clause -. 4.3, day
Part-II Detailed Scope of work.
13. Improper cleaning of running room/crew
Rs.500/- shall be levied per occasion.
lobby/rest room.
Detention caused to train services due to
14. late/non-serving of call to crew by
Rs.1000/- shall be levied per occasion.
contract staff, as per clause 4.15 of Part-II
Detailed Scope of work
For not wearing uniform/ID cards by any
contract staff and/or Not wearing hand
15. Rs.10/- shall be levied per person per
gloves, head scarf and chappals
occasion.
(exclusively earmarked for usage in
kitchen) by kitchen staff.
16. Non wear of uniforms Rs.10/- per person per occasion
17. For abrupt stoppage of work for any
Rs.500/- shall be levied per day.
reasons whatsoever
Rs.500/- shall be levied after verification of
genuineness of complaint followed with
recommendation of Running Room in-
18. For reported misbehavior with running charge (CLI/CCC), on first occasion. If
staff/Railway officials repeated by one and the same person,
Rs.1000/- shall be levied and the person
shall be disallowed to work further in
Running Room.
1 to 5 145-
6 to 10 285/-
11 to 25 717/-
26 to 50 1044/-
51 to 100 1402-
101 to 200 1760/-
8.0 Termination of contract:
8.1 However, the Railway Administration shall be entitled to terminate the contract at any
time should in the opinion of the Railway, cessation of work becomes necessary owing to
paucity of funds or for any other reason whatsoever by giving 7 (seven ) days notice to the
contractor. The contractor is entitled for payment to the extent of work actually done to
the Railway. Notice in writing from the Railway for such termination and reasons thereof
shall be the conclusive evidence.
8.2 The Railway Administration will terminate the contract, if the work executed by the
contractor is consistently unsatisfactory for 10 consecutive days in any three out of five
sub-activities of the work.
8.3 The contract can be terminated before completion of contract period by the Sr DME/Co-
Ord/SC due to any administrative reasons with proper notice to the contractor.
9.0 CONDITIONS OF OTHER IMPORTANT LABOUR & OTHER ACTS AND STATUTORY
REQUIREMENTS.
1.1 The stipulated standard relevant provisions of the following Acts (amended from time to
time) should be strictly adhered to by the contractor during the course of contract period.
The contractor is responsible for the maintenance of necessary records in this connection
and also complies with all statuary requirements in force from time to time. The contractor
is solely responsible for violation of such provisions and its consequences.
a. Minimum Wages Act, 1948.
b. Payment of Wages Act, 1936.
a. The Contractor shall comply with the provisions of EPF & MP Act, 1952 and obtain code number
from the concerned authorities whenever workmen employed by him are 20/10 or more. He
shall also indemnify Railways from and against any claim, penalties, recoveries under the above
Act and Rules. Contractors to get the code number under the EPF so as to enable the PF
Commissioners to extend the social security benefits to the workmen engaged by the Railway
contractors. The first month’s bill will be released only after code number is taken from the PF
Office and a copy of coverage intimation produced. Subsequently for each month, bills will be
released only on submission of challans & 12 A monthly return copy in proof of remittance of PF
dues for previous month.”(Authority: CGE/SC letter No.W.148/P.Vol.IV dt.04-8-2004).
b. As per minimum wages Act, 1948 and payment of wages Act 1986, the contractor has to pay
minimum wages in force as per the type of labour on or before 5th of every month for the
previous month wages. For this purpose, he has to ensure that all his labour have taken Saving
Bank Account in any Nationalized Bank within 45 days from physical execution of work. Payment
in cash disbursed in presence of Railway Supervisor (consignee) is allowed for two months wages
of new persons only. From third month wage period onwards, contractor shall deposit the wages
of the new labour to the respective saving bank accounts. Proof of the depositing of wages of
the respective bank accounts along with acknowledgment from the labour concerned and
submit the same along with the bill.
c. The following records/registers are to be maintained by the contractor, as per the Contract
labour (Regulation and Abolition) Central rules, 1971.
i. Register of persons employed: As per from No. XIII.
ii. Employment card: As per form No.XIV.
iii. Muster roll: As per form No.XVI.
iv. Register of wages: As per form No. XVII
v. Register of overtime: As per form No. XXIII.
vi. Record of ESI paid (As per applicability to this contract – Ten or more manpower): The
records shall have particulars like payment of ESI made by the contractor for each of the
contract staff engaged.
vii. Record of EPF paid (As per applicability to this contract):: The records shall have particulars
like payment of EPF made by the contractor for each of the contract staff engaged.
viii. Contractor shall be responsible for providing medical aid to contract labour in case injury
sustained during execution of contract work.
ix. Before entering the contract, the contractor shall submit the license certificate issued by
the Assistant Labour Commissioner (Central), Hyderabad for awarding the contract as per
the contract labour (Regulation & Abolition) Act, if applicable to this contract.
11.0 Obligations of Railway representative & Contractor/his representative.
a. The register showing the contract staff engaged by the contractor is checked by the supervisor
nominated at least twice in a week.
27. All the terms & conditions of General Conditions of Contract for Services will apply to this
contract unless or otherwise mentioned.
2. Engineering Organization Proposed to be engaged for this work from the above.
(A suitably worded consent Letter From such a person should be obtained and enclose).
General Conditions:
Special Conditions:
Name of the
Name organization Agreement Date of Date of
Agreement to whom Value at the actual Final value
S.No of Actual
No and Date. work time of Completion of contract.
Work. start.
executed. award. of work.
Railway Works
Designation
and Bill
Name Agreement Address of Agreement Amount Number of
S. Due date of
of No and Agreement Value in paid so Extensions
No Completion
Work Date signing Lakhs far in taken.
Authority Lakhs
Railway Works
This is to certify that M/s .................................................... is a reputed company with a good financial
standing.
If the contract for the work, namely.............................................................................. is awarded to
the above firm, we shall be willing to provide overdraft / credit facilities to the extent of
₹...................... to meet their working capital requirements for executing the above contract.
___Sd.___
Name of Bank:__________
Senior Bank Manager_____________
Address of the Bank_______________
To,
Senior Divisional Financial Manager,
Secunderabad Division, South Central Railway,
Secunderabad.
Sub: NEFT Payments.
We prefer to the NEFT being set up by S.C.Rly. For remittance of our payments using RBI’s
NEFT scheme. Our payments may be made through the above scheme to our under noted account.
Signature of Supplier/Tenderer
Stamp & Address
TENDERER’S SEAL
ARTICLES OF AGREEMENT made this ___________ day of ___________ 20__ between the
President of India acting through the Railway Administration hereafter called the “RAILWAY” of
the one part and _____________________herein after called “Contractor” of the other part.
WHEREAS the Contractor has agreed with the Railway for performance of the services
_____________________ set forth in the Schedule hereto annexed upon the General Conditions
of Contract for service contracts corrected up to latest Correction Slips here-into annexed AND
WHEREAS the performance of the said works is an act in which the public are interested.
NOW THIS INDENTURE WITNESSETH that is consideration of the payments to be made by the
Railway, the contractors will duly perform the said services in the said schedule set-forth and shall
execute the same with great promptness, care and accuracy in a worker like manner to the
satisfaction of the railway and will complete the same in accordance with the said specifications
and said of conditions of contract on or before the _____________ day of ______ and will
observe, fulfil and keep all the conditions therein mentioned (Which shall be deemed and taken to
be part of this contract as if the same had been fully set-forth herein) AND the RAILWAY do hereby
agree that if the CONTRACTOR shall duly perform the said work in the manner aforesaid and
observe and keep the said terms and conditions, the Railways will pay or cause to be paid to the
tenderer for the said works on the final completion there of amount due in respect thereof at the
rates specified in the schedule hereto annexed.
VERIFICATION
I/We above named tenderer do hereby solemnly affirm and verified that the content of my/our
above affidavit are true and correct. Nothing has been concealed and no part of it is false.
Date:
**The contracts in italics are only for guidance purpose. Details as appropriate are to be filled in
suitably by tenderer. Attestation before Magistrate/Notary public.
4. We, -------------------------------(indicate the name of bank) further agree that the guarantee
herein contained shall remain in full force and effect during the period that would be taken
for the performance of the said Agreement and that it shall continue to be enforceable till all
the dues of the Government under or by virtue of the said Agreement have been fully paid
and its claims satisfied or discharged or till -------------------------Office/Department) Ministry of
----------------------- certifies that the terms and conditions of the said Agreement have been
fully and properly carried out by the said Contractor(s) and accordingly discharges this
guarantee. Unless a demand or claim under this guarantee is made on us in writing on or
before the --------------------------- we shall be discharged from all liability under this guarantee
thereafter.
5. We, ---------------------(indicate the name of the Bank) further agree with the Government
that the Government shall have the fullest liberty without our consent and without affecting
in any manner our obligations hereunder to vary any of the terms and conditions of the said
Agreement or to extend time of performance by the said contractor(s) from time to time or
to postpone for any time or from time to time any of the powers exercisable by the
Government against the said Contractor(s) and to forbear or enforce any of the terms and
conditions relating to the said agreement and we shall not be relived from our liability by
reason of any such variation, or extension being granted to the said Contractor(s) or for any
6. This guarantee will not be discharged due to the change in the constitution of the bank or
the Contractor(s) / Supplier(s).
7. We, ---------------------- (indicate the name of the bank) lastly undertake not to revoke this
guarantee during its currency except with the previous consent of the Government in writing.
Annexure – 06
(For each Type of meal i.e. Breakfast, Lunch, Dinner & Parcel meal, separate registers to be
maintained)
Annexure – 07
in-charge (CLI/CCC)
Actually deployed
Date
No. of Guards
Total Meals
Parcel meal
No. of ALPs
supervisor
Break fast
No. of LPs
Dinner
Lunch
Annexure – 09
Signature of
Signature of
Contractor
Supervisor
Care taker
Date OUT Quantity IN Quantity
Woolen blankets
Woolen blankets
window curtains
Mosquito nets
Mosquito nets
Door/Window
Pillow covers
Pillow covers
Bed Covers
Bed Covers
Bed sheets
Bed sheet
Door/
Annexure – 10
Housekeeping of running room and Crew lobby/crew rest room:
Annexure – 12
SL. Date Time Train Loco Crew Boxes No. of Name Signature On Remarks
No. of No. Nos. loaded sand of LP of LP duty CC
loading (Yes/NO) bags
loaded
(write
in
words)