Brooklyn - Queens Interconect All Lump Sum Bids -- Initial &

Revised RFP Responses

§ Description Include Est Qty


Option? UOM (Mutliplier)
Michels (Orig) Michels (rev)
I. FIRM LUMP SUM PRICING "I-A" - 8,300 FEET OF 26" 1 = Yes,
5/31/12
STEEL GAS MAIN 0 = No

I-A.1 Firm Lump Sum Price - Total Project for all 26" steel gas main installation, Tie-ins, directional drilling and Lump Sum 1 $7,168,378 $7,168,378
full restoration as described in section I.

I-A.2 Pricing Breakdown (NOTE: Total Must Equal Firm Lump Sum Price Above)
Mobilization & Pipe Stringing:
I-A.2.a. Contractor Mobilization and Pipe Stringing Lump Sum 1 $156,069 $156,069
Gas Main Installation - Trenching Operations Only (No Welding)
I-A.2.b. Install 26 Inch Steel Gas Main - South Section (Drill to Bch 169th) Lump Sum 1 $206,000 $206,000
I-A.2.c. Install 26 Inch Steel Gas Main - North Section (Drill to proposed Gate Sta.) Lump Sum 1 $525,864 $525,864
Welding Operations:
I-A.2.d. Welding of 26" Steel Gas Main for DIRECTIONAL DRILL Lump Sum 1 $1,481,086 $1,481,086
I-A.2.e. Welding of 26" Steel Gas Main for South Section of Project Lump Sum 1 $211,584 $211,584
I-A.2.f. Welding of 26" Steel Gas Main for North Section of Project Lump Sum 1 $423,168 $423,168
Directional Drilling Operations:
I-A.2.g. Directional Drill Contractor Mobilization Lump Sum 1 $112,000 $112,000
I-A.2.h. Directional Drill of 26" Steel Gas Main Under Inlet Lump Sum 1 $2,514,000 $2,514,000
Testing:
I-A.2.i. Prehydrostatic Test of 26" Directional Drill Pipe Lump Sum 1 $182,827 $182,827
I-A.2.j. Hydrostatic Test of Entire 26" Steel Project Lump Sum 1 $242,352 $242,352
I-A.2.k. Caliper Testing of Directional Drill Pipe upon completion of installation. Lump Sum 1 $50,711 $50,711
Cathodic Protection Work
I-A.2.l. Cathodic Protection Work for 26" Steel Gas main Lump Sum 1 $114,020 $114,020
Valves
I-A.2.m. Prefab of all 26" Ball Valves / Perform Valve Hydrostatic Test Lump Sum 1 $203,294 $203,294
I-A.2.n. Cut Valves into 26" Gas Mains After Hydrostatic Test Lump Sum 1 $81,318 $81,318
Restoration Work:
I-A.2.o. Paving & Restoration Lump Sum 1 $664,085 $664,085
Pricing Breakdown = Lump Sum? (Y/N) Y Y

OPTIONAL PRICES:
I-B. Option Price "I-B" – ELECTRICAL WORK - Firm Lump Sum Price for the contractor to install the telemetry 1 Lump Sum 1 $282,000 $282,000
and electrical associated with the Electrical Specification for all conduit and cables to the 26” Valve
Actuators.

I-C. Option Price "I-C" - FLATBUSH AVE, NIGHT OPERATIONS DIFFERENTIAL. This price is being requested for 1 Lump Sum 1 $0 $0
the cost differential only of completing the 26” steel gas main on the Flatbush Ave section between the
hours of 8:00 PM and 5:00 AM, in lieu of daytime hours. This will include all work that would require
shutting any lanes while performing the gas main in the shoulder of the road as well as the road crossing
to the future Gate Station. Previous discussions with the NYC DOT have indicated that they will make
National Grid work at night, however, negotiations hope to revise this ruling.

I-D. Option Price "I-D" - JERSEY BARRIERS, FLATBUSH AVE - Firm Lump Sum Price for the contractor to install 1 Lump Sum 1 $651,000 $537,600
approximately 6000 feet of concrete jersey barriers along Flatbush Ave for the prefabrication of the
directional drilling pipe.
I-E. Option Price "I-E" - BOAT RENTAL - Firm Lump Sum Price for the rental of a boat during Directional Drilling 1 Per Day 30 $225,000 $225,000
operations to inspect for frac-outs or when any NY State or City agency requests. This price will be for a
per day rental and include a crew to operate and all pertinent safety gear per US Coast Guard regulations.

I-F. Option Price "I-F" - CREDIT FOR WELDING OPERATIONS. This credit is being requested for those 1 Lump Sum -1 $0 $0
contractors who choose to utilize National Grid Welders to perform all 26" welding operations on this
project. Leaving this item blank or inputting a dollar value of zero indicates that you do not choose to
utilize these welders.

I-G. Option Price "I-G" - OFFICE TRAILER. Firm Lump Sum Price for the rental of ONE (1) expanded Office 1 Lump Sum 1 $30,550 $30,550
Trailer to include Office, Storage, and Bathroom facilities. Price must include room for a minimum of 6
National Grid inspectors.

II. FIRM LUMP SUM PRICING "I-A" - 8,300 FEET OF 12" 1 = Yes,
STEEL GAS MAIN 0 = No Est Qty
(Mutliplier) Ext. $ Ext. $
II-A.1 Firm Lump Sum Price - Total Project for all 12" steel gas main installation, Tie-ins, directional drilling and Lump Sum 1 $5,465,200 $5,465,200
full restoration as described in section II.

II-A.2 Pricing Breakdown (NOTE: Total Must Equal Firm Lump Sum Price Above)
Mobilization & Pipe Stringing:
II-A.2.a. Contractor Mobilization and Pipe Stringing Lump Sum 1 $92,000 $92,000
Gas Main Installation - Trenching Operations Only (No Welding)
II-A.2.b. Install 12 Inch Steel Gas Main - South Section Lump Sum 1 $198,062 $198,062
II-A.2.c. Install 12 Inch Steel Gas Main - North Section Lump Sum 1 $455,147 $455,147
Welding Operations:
II-A.2.d. Welding of 12" Steel Gas Main for Directional Drill Lump Sum 1 $761,695 $761,695
II-A.2.e. Welding of 12" Steel Gas Main for South Section of Project Lump Sum 1 $197,088 $197,088
II-A.2.f. Welding of 12" Steel Gas Main for North Section of Project Lump Sum 1 $334,016 $334,016
Directional Drilling Operations:
II-A.2.g. Directional Drill Contractor Mobilization Lump Sum 1 $112,000 $112,000
II-A.2.h. Directional Drill of 12" Steel Gas Main Under Inlet Lump Sum 1 $1,841,778 $1,841,778
Testing:
II-A.2.i. Prehydrostatic Test of 12" Directional Drill Pipe Lump Sum 1 $146,384 $146,384
II-A.2.j. Hydrostatic Test of Entire Project Lump Sum 1 $219,577 $219,577
II-A.2.k. Caliper Testing of Directional Drill Pipe upon completion of installation. Lump Sum 1 $44,844 $44,844
Cathodic Protection Work
I-A.2.l. Cathodic Protection Work for 12" Steel Lump Sum 1 $89,500 $89,500
Valves
I-A.2.m. Prefab of all 12" Ball Valves / Perform Valve Hydrostatic Test Lump Sum 1 $185,520 $185,520
I-A.2.n. Cut Valves into 12" Gas Mains After Hydrostatic Test Lump Sum 1 $95,094 $95,094
Tie-ins:
II-A.2.o. Tie-ins to 8" at Beach 169th St. Lump Sum 1 $63,396 $63,396
II-A.2.p. Tie-ins to 8" at Flatbush Ave. Lump Sum 1 $63,396 $63,396
Restoration Work:
II-A.2.q. Paving & Restoration Lump Sum 1 $565,703 $565,703
Pricing Breakdown = Lump Sum? (Y/N) Y Y

OPTIONAL PRICES:
II-B. Option Price "II-B" – ELECTRICAL WORK - Firm Lump Sum Price for the contractor to install the telemetry 1 Lump Sum 1 $275,000 $275,000
and electrical associated with the Electrical Specification for all conduit and cables to the 12” Valve
Actuators.
II-C. Option Price "II-C" - FLATBUSH AVE, NIGHT OPERATIONS DIFFERENTIAL. This price is being requested for 1 Lump Sum 1 $0 $0
the cost differential only of completing the 12” steel gas main on the Flatbush Ave section between the
hours of 8:00 PM and 5:00 AM, in lieu of daytime hours. This will include all work that would require
shutting any lanes while performing the gas main in the shoulder of the road as well as the road crossing
to the future Gate Station. Previous discussions with the NYC DOT have indicated that they will make
National Grid work at night, however, negotiations hope to revise this ruling.

II-D. Option Price "II-D" - CREDIT FOR WELDING OPERATIONS. This credit is being requested for those 1 Lump Sum -1 $0 $0
contractors who choose to utilize National Grid Welders to perform all 12" welding operations on this
project. Leaving this item blank or inputting a dollar value of zero indicates that you do not choose to
utilize these welders.

III. TOTAL LUMP SUM BIDS - BOTH 26" AND 12" 1 = Yes, Est Qty
0 = No (Mutliplier) Ext. $ Ext. $
I-A.1 Firm Lump Sum Price - Total Project for all 26" steel gas main installation, Tie-ins, directional drilling and full Lump Sum 1 $7,168,378 $7,168,378
restoration as described in section I.

II-A.1 Firm Lump Sum Price - Total Project for all 12" steel gas main installation, Tie-ins, directional drilling and full Lump Sum 1 $5,465,200 $5,465,200
restoration as described in section II.
TOTAL OF LUMP SUM BIDS = $12,633,578 $12,633,578

OPTIONAL PRICES:
I-B PLUS II-B Option Price "I-B" and Option Price "II-B" – ELECTRICAL WORK - Firm Lump Sum Price for the contractor to 1 Lump Sum 1 $557,000 $557,000
install the telemetry and electrical associated with the Electrical Specification for all conduit and cables to
the 26” and 12" Valve Actuators.

I-C PLUS II-C Option Price "I-C" and Option Price "II-C" - FLATBUSH AVE, NIGHT OPERATIONS DIFFERENTIAL. This price 1 Lump Sum 1 $0 $0
is being requested for the cost differential only of completing both the 26" and the 12” steel gas mains on
the Flatbush Ave section between the hours of 8:00 PM and 5:00 AM, in lieu of daytime hours. This will
include all work that would require shutting any lanes while performing the gas main in the shoulder of
the road as well as the road crossing to the future Gate Station. Previous discussions with the NYC DOT
have indicated that they will make National Grid work at night, however, negotiations hope to revise this
ruling.

I-D Option Price "I-D" - JERSEY BARRIERS, FLATBUSH AVE - Firm Lump Sum Price for the contractor to install 1 Lump Sum 1 $651,000 $537,600
approximately 6000 feet of concrete jersey barriers along Flatbush Ave for the prefabrication of the
directional drilling pipe.

I-E Option Price "I-E" - BOAT RENTAL - Firm Lump Sum Price for the rental of a boat during Directional Drilling 1 Per Day 30 $225,000 $225,000
operations to inspect for frac-outs or when any NY State or City agency requests. This price will be for a
per day rental and include a crew to operate and all pertinent safety gear per US Coast Guard regulations.

I-F PLUS II-D Option Price "I-F" and Option Price "II-D" - CREDIT FOR WEDLDING OPERATIONS. This credit is being 1 Lump Sum -1 $0 $0
requested for those contractors who choose to utilize National Grid Welders to perform all 26" and 12"
welding operations on this project. Leaving this item blank or inputting a dollar value of zero indicates
that you do not choose to utilize these welders.

I-G Option Price "I-G" - OFFICE TRAILER. Firm Lump Sum Price for the rental of ONE (1) expanded Office 1 Lump Sum 1 $30,550 $30,550
Trailer to include Office, Storage, and Bathroom facilities. Price must include room for a minimum of 6
National Grid inspectors.

GRAND TOTAL (I-A.1 + II-A.1) EXCLUDING OPTIONS & WELDING CREDIT = $12,633,578 $12,633,578
OPTIONS EXCLUDING WELDING CREDIT = $1,463,550 $1,350,150
GRAND TOTAL (I-A.1 + II-A.1) + (OPTIONS EXCLUDING WELDING CREDIT) = $14,097,128 $13,983,728
WELDING CREDIT = $0 $0
GRAND TOTAL (I-A.1 + II-A.1) + (ALL OPTIONS INCLUDING WELDING CREDIT) = $14,097,128 $13,983,728

BID ADDENDUM 3 - OPTIONAL PRICES: (additional


items not included in original bid)
I-I. Option Price "I-I" – GYRO GUIDANCE SYSTEM - Firm Lump Sum Price for the contractor to utilize a Gyro 1 Per Day or $0.00
Guidance System. Under UOM (Unit of Measeur) indicate if this will be a per day or per foot basis. Per Foot

I-J. Option Price "I-J" - HYDROSTATIC TESTING OF VALVE ASSEMBLIES SEPERATERLY. This price is being 1 Lump Sum $0.00
requested for the contractor to weld the pup pieces onto the valves as well as the western purge
assemblies and perform a seperate Hydrostatic Test that will determine there are no manufacturor
defects on the valves. If this work was already included in your lump sum bid, then input $0 for this
price.

I-K. Option Price "I-D" - MUD MOTOR AND ROCK CUTTING HEADS - Optional pricing to cover any rock 1 Per Foot $0.00
formations that may be encountered during the HDD process. This price will not be used in the lump sum
bid determination. Under UOM (Unit of Measeur) indicate if this will be a per day or per foot basis.

ORIGINAL OPTIONAL PRICES: (needing clarification)


I-C.1. Option Price "I-C.1" - FLATBUSH AVE, NIGHT OPERATIONS DIFFERENTIAL. This price is being requested for 1 Lump Sum
the cost differential only of completing the 26” steel gas main on the Flatbush Ave section between the
hours of 8:00 PM and 5:00 AM, in lieu of daytime hours. This will include the same work as previously
outlined in the bid documents, however, this item will include the CONTRACTOR WELDERS.

0
I-C.2. Option Price "I-C.2" - FLATBUSH AVE, NIGHT OPERATIONS DIFFERENTIAL. This price is being requested for 1 Lump Sum
the cost differential only of completing the 26” steel gas main on the Flatbush Ave section between the
hours of 8:00 PM and 5:00 AM, in lieu of daytime hours. This will include the same work as previously
outlined in the bid documents, however, this item will include the CREDIT FOR NATIONAL GRID WELDER
USAGE.
0
BID ADDENDUM 3 - OPTIONAL PRICES: (additional
items not included in original bid)
II-I. Option Price "I-I" – GYRO GUIDANCE SYSTEM - Firm Lump Sum Price for the contractor to utilize a Gyro 1 $52,500.00
Guidance System. Under UOM (Unit of Measeur) indicate if this will be a per day or per foot basis.

II-J. Option Price "I-J" - HYDROSTATIC TESTING OF VALVE ASSEMBLIES SEPERATERLY. This price is being 1 Lump Sum
requested for the contractor to weld the pup pieces onto the valves as well as the western purge
assemblies and perform a seperate Hydrostatic Test that will determine there are no manufacturor
defects on the valves. If this work was already included in your lump sum bid, then input $0 for this
price.
0
II-K. Option Price "I-D" - MUD MOTOR AND ROCK CUTTING HEADS - Optional pricing to cover any rock 1 Per Foot $0.00
formations that may be encountered during the HDD process. This price will not be used in the lump sum
bid determination. Under UOM (Unit of Measeur) indicate if this will be a per day or per foot basis.

ORIGINAL OPTIONAL PRICES: (needing clarification)


II-C.1. Option Price "I-C.1" - FLATBUSH AVE, NIGHT OPERATIONS DIFFERENTIAL. This price is being requested for 1 Lump Sum
the cost differential only of completing the 26” steel gas main on the Flatbush Ave section between the
hours of 8:00 PM and 5:00 AM, in lieu of daytime hours. This will include the same work as previously
outlined in the bid documents, however, this item will include the CONTRACTOR WELDERS.

0
II-C.2. Option Price "I-C.2" - FLATBUSH AVE, NIGHT OPERATIONS DIFFERENTIAL. This price is being requested for 1 Lump Sum
the cost differential only of completing the 26” steel gas main on the Flatbush Ave section between the
hours of 8:00 PM and 5:00 AM, in lieu of daytime hours. This will include the same work as previously
outlined in the bid documents, however, this item will include the CREDIT FOR NATIONAL GRID WELDER
USAGE.
0
BID APPENDIX B-10 - Revised 4/05/2012
BROOKLYN - QUEENS INTERCONNECT PHASE 1 - UNIT PRICE SCHEDULE
Work Description UOM Unit $
SECTION 1.0 CLEAN FILL
1.0 These units apply to trench excavations when the National Grid representative
determines that acceptable backfill material needs to be provided.

1.1 Furnish and place acceptable clean sand backfill from non-site excavated material.
Includes removal and disposal of associated excess material. This unit applies to trench
work only.

1.1.1 Clean Fill - 26 In. Pipe (UP TO 500 FEET) / trench foot $7.00
1.1.2 Clean Fill - 26 In. Pipe (501 FEET - 2000 FEET) / trench foot $7.00
1.1.3 Clean Fill - 12 In. Pipe (UP TO 500 FEET) / trench foot $7.00
1.1.4 Clean Fill - 12 In. Pipe (501 FEET - 2000 FEET) / trench foot $7.00

1.2 Furnish & place acceptable washed sand backfill obtained from non-site excavated material.
Includes removal and disposal of associated unsuitable fill.

1.2.1 Furnish & place acceptable washed sand backfill obtained from non-site / cubic yard $43.00
excavated material. Includes removal and disposal of associated unsuitable fill.
UP TO 100 CUBIC YARDS.

1.2.2 Furnish & place acceptable washed sand backfill obtained from non-site / cubic yard $43.00
excavated material. Includes removal and disposal of associated unsuitable fill.
101 TO 1000 CUBIC YARDS.

1.2.3 Furnish & place acceptable washed sand backfill obtained from non-site / cubic yard $43.00
excavated material. Includes removal and disposal of associated unsuitable fill.
Greater Than 1000 CUBIC YARDS.

1.3.0 Handling of Contaminated Soil per NationaL Grid Specifications:

1.3.1 Stockpile contaminated soil from areas other than those identified in the project / cubic yard $70.00
specification.
1.3.2 Disposal of contaminated soil from project site at a DEC certified disposal facility. / cubic yard $152.00

SECTION 2.0 TEMPORARY PAVING


2.0 These units apply to the installation of temporary paving above the scope of work
identified in the lump sum bid. All inclusive price to furnish and install hot and/or
cold patch.

2.1 2 in. thickness (hot patch) / square yard $27.50


2.2 2 in. thickness (cold patch) / square yard $26.60
2.3 4 in. thickness (hot patch) / square yard $50.29
2.4 4 in. thickness (cold patch) / square yard $47.50

SECTION 3.0 WELDING


3.0 These units applicable to complete steel welds for the pipe diameters indicated
below. These units to be used for both the addition and deletion to the original work
scope.

3.1.0 Butt Weld Steel Pipe:


3.1.1 12 In. dia. pipe / each $1,200.00
3.1.2 26 In. dia. Pipe / each $2,600.00

3.2.0 Butt Weld Steel Fittings or Valves:


3.2.1 12 In. dia. pipe / each $1,200.00
3.2.2 26 In. dia. Pipe / each $2,600.00

3.3.0 Valve Installation - Contractor to furnish all labor, consumable material and equipment
required to install steel valves. Unit price includes all welds, excavation, shoring and
corrosion control required to complete the installation.

3.3.1 Valve Installation - 12 In. dia. pipe / valve $1,276.00


3.3.2 Valve Installation - 26 In. dia. pipe / valve $121,915.00

3.4.0 Butt Weld Steel Tees


3.4.1 Butt Weld Steel Tees - 12” X 12” X 12” / each $3,600.00
3.4.2 Butt Weld Steel Tees - 26” X 26” X 26” / each $7,800.00

3.5.0 Western Purge


3.5.1 Complete western purge and install to main per National Grid Standard / each $40,638.00
PURG-6010

SECTION 4.0 OBSTRUCTIONS


4.0 Unit prices shown below are for increased work scope connected with unknown
obstructions not shown on prints or that cannot be field identified as a potential
interference.

These unit prices cover excavating, supporting and providing clearance and
installation at the obstruction location. This unit also covers vertical excavations to
maintain a minimum of 12" clearance from obstruction.

4.1 Separate obstruction up to 18 inch diameter or width / each $40,638.00


4.2 Separate obstruction over 18 inch up to and including 36 inch diameter or width. / each $81,276.00

4.3 Separate obstruction over 36 inch diameter or width and up to and including 60 / each $112,007.00
inch diameter or width.

Note: Prices shown above are for additions and deletions. If a relocation of the pipe route
eliminates going under a "BID" or a designed profile obstruction, National Grid shall receive
a credit in the appropriate amount stated above.

SECTION 5.0 ADD / DELETE COMPLETE SYSTEM


5.0 All inclusive unit price to install pipe at "Bid" defined depths. Includes, but not
limited to, costs for test holes, excavation, pipe welding and installation, backfill,
dewatering, etc. Pavement removal and temporary pavement are to be included in
this price. Dewatering is included up to, but not including, a well point system.
Permanent Paving will be covered by the applicable unit price in this appendix.

5.1.0 Add Steel System


5.1.1 5.1.1.1 Paved Roads - 12" Steel Pipe / linear foot $78.00
5.1.1.2 Paved Roads - 26" Steel Pipe / linear foot $89.00

5.1.2 5.1.2.1 Paved Sidewalks - 12" Steel Pipe / linear foot $78.00
5.1.2.2 Paved Sidewalks - 26" Steel Pipe / linear foot $89.00
5.1.3 5.1.3.1 In Unpaved areas – 12” Steel Pipe / linear foot $62.00
5.1.3.2 In Unpaved areas – 26” Steel Pipe / linear foot $70.00

5.2.0 Steel Detail - all inclusive unit price to cut and prep the end of damaged steel gas pipe that
has been identified by National Grid upon delivery.
5.2.1 Cut & Prep the end of damaged steel gas pipe - 12" Steel Pipe each $144.00
5.2.2 Cut & Prep the end of damaged steel gas pipe - 26" Steel Pipe each $312.00

SECTION 6.0 ADDITIONAL TEST HOLES


6.0 It is understood that this item will cover only the additional test holes NOT covered
under the Lump Sum Bid. The lump sum price covers test holes for all mains, ducts,
services, pipes, structures, etc. that are shown on the drawings or can be deduced.

6.1.0 Size of additional test holes is approx. 3 ft by 4 ft by 5 ft deep. The unit price includes
pavement removal, patch etc.

6.1.1 Additional Test Holes / each $250.00

6.2.0 Unit price to expand an existing test hole.


6.2.1 Expand an existing test hole up to two feet distance from existing test hole. / each $350.00
6.2.2 Expand an existing test hole from two ft to four ft / each $450.00
6.2.3 Expand an existing test hole from four ft to six ft / each $750.00

6.3.0 Unit price for Vacuum Excavated Test Hole


6.3.1 Vacuum Excavated test hole / each $350.00

SECTION 7.0 MISCELLANEOUS PITS


7.1 TIE-IN PITS - An all inclusive unit price to excavate, sheet and steel plate an 8 ft X NOT REQUIRED
10 ft tight sheeted tie-in pit, to a maximum of 8 ft in depth. This unit price covers pits FOR THIS BID
not included on drawings, specifications or bid documents, and must include
backfilling and pulling sheeting. This unit price covers dewatering by means of mud
suckers, maximum of 3 pumps.

7.1 Installation of Tie-In Pits /pit $40,658.00

7.2 WELD PITS - An all inclusive unit price to excavate, sheet and steel plate an 8ft x 8
ft tight sheeted weld pit, to a maximum of 8 ft in depth, within the paved area of a NYC
roaway. This unit price covers pits not included on drawings, specifications or bid
documents, and must include backfilling and pulling sheeting. This unit price covers
dewatering by means of mud suckers, maximum of 3 pumps.

7.2 Installation of Weld Pits in Paved Roadway /pit $52,305.00

7.3 Install miscellaneous timber / steel sheeting (for out of scope tie-in pits, jacking pits, misc.
pits) and associated work. Includes furnishing material, labor, equipment, transportation,
and removal of sheeting.

7.3.1 Install Miscellaneous Timber/Steel Sheeting - to a maximum depth of 10 ft / cubic yard $130.00
7.3.2 Install Miscellaneous Timber/Steel Sheeting - greater than 10 ft / cubic yard $130.00

SECTION 8.0 ROAD PLATES


8.0 Total steel plate rental rate for a period exceeding 60 days use at the tie-in pits or
misc. pits installed.

8.1 8.1 Steel plate rental rate - Daily Rate /day/pit $55.00
8.2 8.2 Steel plate rental rate - Weekly Rate /week/pit $216.00
8.3 8.3 Steel plate rental rate - Monthly Rate /month/pit $638.00

SECTION 9.0 REMOVALS


9.0 The unit prices below cover out of scope requirements for the removal of paving. It
includes markout, sawcut or vermeer cut, removal and disposal of paving.

9.1 Unit price for Pavement Removal


9.1.1 Removals - Concrete Sidewalk / square yard $8.00
9.1.2 Removals - Concrete road paving / square yard $12.00
9.1.3 Removals - Blacktop paving / square yard $5.25

9.2 Unit price for out of scope requirements for the removal and disposal of debris caused by
others, such as scrap metal, construction and residential debris.
9.2.1 Removals - Debris / cubic yard $152.00

SECTION 10.0 TUNNELING / MISSILING


10.0 This unit price is for the hand tunneling under driveway aprons, tree roots,
structures, etc. for out of scope work. Includes the installation of gas main.

10.1.0 Hand Tunneling


10.1.1 Tunnel length up to 5 ft. / linear foot $52.00
10.1.2 Tunnel length over 5 Ft. to 10 Ft. / linear foot $75.00

SECTION 11.0 PROTECTION FOR REDUCED COVER


11.0 Contractor to furnish and install one inch thick steel plate as protection over the gas
main installed at reduced cover when directed by National Grid.

11.1.0 Steel Plate Installation


11.1.1 One Inch Steel Plate Installed / square foot $3.50

SECTION 12.0 OFFSET INSTALLATION EXPENSE


12.0 Covers incremental costs associated with all inefficiencies and resultant delays when
out of scope offsets are installed. Does not include fusions / welds which are
covered under Unit 3. The application of this unit is limited to unplanned offsets only,
necessitated by obstructions during actual excavation for main installation, where no
prior markout, drawing, test hole or other prior information could have been available.

12.1.0 All inclusive unit price covering installation from layout to backfill for vertical offset.

12.1.1 Vertical Offset Installation - price per 12" Elbow / 12" steel elbow $2,500.00

12.1.2 Vertical Offset Installation - price per 26" Elbow / 26" steel elbow $5,400.00

12.1.0 All inclusive unit price covering installation from layout to backfill for horizontal offset.
12.2.1 Horizontal Offset Installation - price per 12" Elbow / 12" steel elbow $17,500.00

12.2.2 Horizontal Offset Installation - price per 26" Elbow / 26" steel elbow $35,334.00

SECTION 13.0 PERMANENT PAVING UNIT PRICES


13.0 Unit prices shown below are for increased work scope for permanent paving and
restoration items.

13.1.0 Permanent Paving


13.1.1 Permanent Paving - 1-1/2" Blacktop / square yard $22.50
13.1.2 Permanent Paving - 2" Blacktop / square yard $27.50
13.1.3 Permanent Paving - 4" Blacktop / square yard $47.50
13.1.4 Permanent Paving - 4" NYS Type 3 Dense Binder Base and 2" 6F Top Mix / square yard $65.30
13.1.5 Permanent Paving - 6" NYS Type 3 Dense Binder Base and 2" 6F Top Mix / square yard $85.00
13.1.6 Permanent Paving - 10" NYS Type - Dense Binder Base and 2" 6F Mix Top / square yard $105.00
13.1.7 Permanent Paving - 6" RCA Sub Base Mix – NYS Quality / square yard $34.00
13.1.8 Permanent Paving - 6" RCA Sub Base Mix – County/Town Mix / square yard $34.00
13.1.9 Permanent Paving - 4" Concrete (no steel) / square yard $150.00
13.1.10 Permanent Paving - 6" Concrete (reinforced) / square yard $220.00
13.1.11 Permanent Paving - 8" Concrete (reinforced) / square yard $280.00
13.1.12 Permanent Paving - 6" x 18" curb / linear foot $83.00
13.1.13 Permanent Paving - 18" x 6" x 24" Monolithic Concrete Curb & Gutter / linear foot $70.00
13.1.14 Permanent Paving - Type III Concrete with Calcium Chloride (18502.6028) / cubic yard $150.00
13.2.0 Testing $0.00
13.2.1 Soil compaction testing services from NY State / County approved consultant to / day $1,200.00
verify municipality requirements.
13.3.0 Suffolk / Nassau County pavement restoration in those area where offsets move into the NOT REQUIRED
pavement area or out of scope pavement areas. This price will include a square yard price FOR THIS BID
that will include 1. Milling of 2" of existing pavement, 2. Install 2" Top Coat, 3. Sealnt of all
seams.

13.3.1 Final pavement restoration / square yard $39.00


13.3.2 Thermoplastic Line Striping - KEEP THIS ITEM / linear foot $1.78

SECTION 14.0 SOD / SEED AND TOPSOIL


14.0 Unit prices shown below are for increased work scope for topsoil and seeding.

14.1.0 Prices include all labor and furnishing of material.


14.1.1 Sod / square foot $1.00
14.1.2 Seed / square foot $0.06
14.1.3 Hydro Seed / square foot $10.00
14.1.4 Topsoil Only – 2” Lift / square foot $1.50
14.1.5 Topsoil Only – 4” Lift / square foot $3.00

SECTION 15.0 DEWATERING


15.0 In order to control normal dewatering conditions, the contractor is liable for the use
of two pumps per day for gas main installations. This unit price is to relieve the
burden for dewatering above the use of these 2 pumps.

15.1.0 Mudsuckers and Pumps


15.1.1 Cost of Additional Pump above the 2 pumps stated above. / daily rate $582.00
15.1.2 Cost for the operation of up to 5 pumps per day. / daily rate $1,500.00
15.2.0 Well Point System
15.2.1 Daily rate to setup and operate Well Point System. Includes all labor and / daily rate $970.00
equipment.

SECTION 16.0 CORROSION CONTROL


16.0 Unit price for out of scope work for corrosion and cathodic protection work.

16.1.0 Installing Anodes


16.1.1 Install 17 lb. anode with test station / anode $395.00
16.1.2 Install 17 lb. anode w/o test station / anode $295.00

SECTION 17.0 CASING BORES AND JACKS


17.0 Unit Prices for additional piping jacks/bores and the adjustment in length of bid jacks.

17.1.0 Unit price for out of scope casing bores or jacks not shown on the drawings or requested in
the Option Lump Sum Bid. Pits for additional jacks or bores will be in accordance with Unit
7.0.

17.1.1 Increase or (decrease) Bored or Jacked Casing - up to 50' / foot $650.00


17.1.2 Increase or (decrease) Bored or Jacked Casing - > 50' - 100' / foot $650.00

17.2.0 Unit price for Jacking of Trees


17.2.1 Jacking of Trees - 15' to 25' / linear foot $468.00
17.2.2 Jacking of Trees - > 25' - 50' / linear foot $468.00

17.3.0 Unit price for out of scope casing bores or jacks not shown on the drawings or requested in
the Option Lump Sum Bid. Pits for additional jacks or bores will be in accordance with Unit
7.0. All work includes set up and removal of equipment in pit, supplying / placing / welding
and pushing casing pipe and installing gas carrier pipe. Installation of all venting lines to be
included. Casing sleeve to be supplied by contractor. Venting material and casing spacers
supplied by National Grid.

17.3.1 New Casing Sleeve up to 100 feet in length - 12" diamter sleeve / foot $216.00
17.3.2 New Casing Sleeve up to 100 to 200 ft in length - 12" diamter sleeve / foot $216.00
17.3.3 New Casing Sleeve up to 100 feet in length - 16" diamter sleeve / foot $290.00
17.3.4 New Casing Sleeve up to 100 to 200 ft in length - 16" diamter sleeve / foot $290.00

SECTION 18.0 DIRECTIONAL DRILLING


18.0 Unit Prices for additions and deletions of directional drilling operations. Includes, but
is not lilited to, the set up and removal of drilling equipment and complete installation
of gas main including welds and wrapping of joints.

18.1.0 12" Directional Drill - Increase or Decrease the length of designed drill.
18.1.1 Increase or (decrease) Dirctional Drill - up to 100 feet / foot $200.00
18.1.2 Increase or (decrease) Dirctional Drill - 101 - 500 feet / foot $188.00
18.1.3 Increase or (decrease) Dirctional Drill - 501 - 1000 feet / foot $178.00

18.2.0 26" Directional Drill - Increase or Decrease the length of designed drill.
18.2.1 Increase or (decrease) Dirctional Drill - up to 100 feet / foot $223.00
18.2.2 Increase or (decrease) Dirctional Drill - 101 - 500 feet / foot $212.00
18.2.3 Increase or (decrease) Dirctional Drill - 501 - 1000 feet / foot $200.00

18.4.0 Delays incurred by drill team if work cannot proceed due to a suspension of operations for
reasons above the contractors control, such as permitting, material shortages, work
exceeding the scope of work or directives from National Grid, the following daily rate shall
be applicable.

18.4.1 Day Rate for Directional Drilling Crew / day $27,250.00

SECTION 19.0 DEC / ENVIRONMENTAL REQUIREMENTS


19.0 Unit Prices for the installation of hay bales and silt fencing due to environmental
factors.

19.1 19.1 Install silt fence and hay bale / day 21.00/each
19.2 19.2 Install hay bale only / ft $18.00
19.3 19.3 Install silt fence only / ft $8.00

SECTION 20.0 TREE PROTECTION


20.0 Unit Prices for the installation of tree protection per AKRF documents.

20.1 20.1 Install Orange Construction Fencing around trees, at least four layers thick. / each $150.00
20.2 20.2 Install wood protection full diameter of tree truck. / each $250.00
20.3 20.3 Install Orange Construction Fencing surrounding tree and critical root structure / each $200.00
(generally the radius of tree branches). Include all staking for a four foot high
fence.

SECTION 21.0 CONCRETE WEIGHTS


21.0 Installation of concrete weights or mats on the new gas main due to water conditions
that may affect the depth of the new main. This price should include the pickup of
mats at National Grids Hicksille location, installation of two layers of mats and rock
shield around gas main.

21.1 21.1 Install concrete weights or mats on gas main / each $495.00

SECTION 22.0 CLEARING AND GRUBBING


22.0 Unit prices below cover out of scope requirements, as well as credits for deletions, NOT REQUIRED
for the clearing and removal of various size trees, bushes and debris. The contractor FOR THIS BID
is to provide all labor and equipment necessary for the complete removal and
disposal of all removed debris.

22.1 22.1 Clearing and grubbing of trees, stumps and bushes - up to 200 sq. yds. / square yard N/A
22.2 22.2 Clearing and grubbing of trees, stumps and bushes - greater than 200 sq. yds and / square yard N/A
less than 500 sq. yds.
22.3 22.3 Clearing and grubbing of trees, stumps and bushes - greater than 500 sq. yds and / square yard N/A
less than 1000 sq. yds.
22.4 22.4 Clearing and grubbing - > 1,000 sq. yds. / square yard N/A

SECTION 23.0 LEACHING BASINS


23.0 Installation of concrete leaching basins. Must include a minimum of 2 rings each at 4 NOT REQUIRED
feet in height and 8 feet in diameter, concrete cover and cast iron road grate, and a FOR THIS BID
minimum of 3 ft high brick chimney and 6" thick layer of blue stone around the
complete diameter of the rings.

23.1 23.1 Leaching Basins / each N/A

SECTION 24.0 DOLOMITE


24.0 Installation of 3/4" stone dolomite stone bedding.

24.1 Dolomite - minimum of 4" Thick with commercial weed barrier blanket / square yard $50.00
24.2 Dolomite - minimum of 4" Thick without commercial weed barrier blanket / square yard $43.00
24.3 Dolomite - minimum of 2" Thick without commercial weed barrier blanket / square yard $35.00

SECTION 25.0 LEAN CONCRETE BEDDING


25.0 Installation of a lean concrete bedding over gas facilities as directed by National Grid
personnel. Maximum rating of concrete not to exceed 500 psi.

25.1 25.1 Lean Concrete Bedding / cubic yard $750.00

SECTION 26.0 ELECTRICAL CONDUIT


26.0 Unit Price to install 2" conduit at a depth of 2 feet (24") for electrical supply and
telecommunictions. This price will include supplying of all conduit, fittings and
terminations. Do not include pavement restoration or removal, this item will be
covered under their respective unit price.

26.1 26.1.1 2" rigid galvanized conduit installation - machine excavation. / linear foot $14.00
26.1.2 2" rigid galvanized conduit installation - hand excavation. / linear foot $35.00
26.1.3 2" plastic conduit installation - machine excavation. / linear foot $18.00
26.1.4 2" plastic conduit installation - hand excavation. / linear foot $43.00

26.2 26.2.1 Directional Drilling - 2" rigid galvanized conduit / linear foot $100.00
26.2.1 Directional Drilling - 2" plastic conduit / linear foot $100.00

SECTION 27.0 CROSSING OF CAST IRON OR TRANSITE WATER MAINS


27.0 Unit Price to replace the cast iron or transite water main located within the trench
area of the designed gas main installation. This unit price to include all material,
labor and coordination to replace this main with Ductile Iron pipe, restrained joints,
class 56 within the limits of the trench excavation plus ten (10) feet on either side of
trench. Disposal of transite pipe to be included in price. This unit price to be for the
entire crossing (not by linear foot).

27.1 27.1.1 Replace 12" Cast Iron Water Main. each crossing $10,192.00
27.1.2 Replace 6 or 8" Cast Iron Water Main. each crossing $8,500.00

27.2 27.2.1 Replace 12" Transite Water Main. each crossing $10,192.00
27.2.2 Replace 6 or 8" Transite Water Main. each crossing $8,500.00