Beruflich Dokumente
Kultur Dokumente
Processing Facility
Failure Modes Effects Analysis (FMEA) for Critical
Infrastructure
8 March 2017
Sydney Melbourne
Arriscar Pty Limited Level 26 Level 2 Riverside Quay
ACN 162 867 763 44 Market Street 1 Southbank Boulevard
www.arriscar.com.au Sydney NSW 2000 Southbank VIC 3006
T: +61 2 9089 8804 T: +61 3 9982 4535
Plastics to Liquid Fuel: Critical Infrastructure FMEA
Distribution List
From To
Name Organisation
(Issue) (Issue)
John Sneddon FOY Group Limited - A
Project Master File Arriscar Pty Limited Draft A
Arriscar Pty Limited, and its respective officers, employees or agents are individually and collectively referred to in this
clause as 'Arriscar'. Arriscar assumes no responsibility, and shall not be liable to any person, for any loss, damage or
expense caused by reliance on the information or advice in this document or howsoever provided, unless that person has
signed a contract with Arriscar for the provision of this information or advice and in that case any responsibility or liability
is exclusively on the terms and conditions set out in that contract.
© Arriscar Pty Ltd.
Plastics to Liquid Fuel: Critical Infrastructure FMEA
Contents
Distribution List ........................................................................................................................................ 2
Document History and Authorisation........................................................................................................ 2
Notation .................................................................................................................................................. 5
1 Introduction ................................................................................................................................... 6
1.1 Background .................................................................................................................................... 6
1.2 Objectives ...................................................................................................................................... 6
1.3 Scope ............................................................................................................................................. 6
1.3.1 Scope of Analysis ........................................................................................................................... 6
1.3.2 Scope of Facilities and Operations ................................................................................................ 7
2 Methodology .................................................................................................................................. 8
2.1 FMEA Methodology ....................................................................................................................... 8
2.2 Generic Failure Modes ................................................................................................................ 10
3 Facility Description ....................................................................................................................... 12
3.1 Site Location ................................................................................................................................ 12
3.2 Facility Overview ......................................................................................................................... 12
3.3 Plastic Storage Area and Extruder ............................................................................................... 15
3.4 Processing Area ........................................................................................................................... 15
3.5 Tank Farm .................................................................................................................................... 17
3.6 Tanker Loading Area .................................................................................................................... 18
3.7 Staffing......................................................................................................................................... 18
3.8 Security ........................................................................................................................................ 18
3.9 Proposed Prevention and Mitigation Control Measures ............................................................. 19
3.9.1 Spill Prevention and Mitigation ................................................................................................... 19
3.9.2 Stormwater system ..................................................................................................................... 19
3.9.3 Fire Prevention, Detection and Mitigation .................................................................................. 20
3.9.4 Safety Management System ........................................................................................................ 20
7 References .................................................................................................................................... 30
Appendix A FMEA Worksheets...................................................................................................... 32
List of Figures
Figure 1 Overview of FMEA Process ........................................................................................................... 9
Figure 2 Location of Proposed Facility ..................................................................................................... 12
Figure 3 Site Layout .................................................................................................................................. 14
Figure 4 Process Flow Diagram ................................................................................................................ 17
List of Tables
Table 1: Systems and Equipment for Control of Emissions and Stormwater .................................................. 21
Notation
Abbreviation Description
ACT Australian Capital Territory
Arriscar Arriscar Pty Limited
DG Dangerous Good
DP&E NSW Department of Planning and Environment
EPA ACT Environment Protection Authority
FMEA Failure Modes and Effects Analysis
FMECA Failure Modes and Effects Criticality Analysis
FOY FOY Group Limited
FSS Fire Safety Study
HAZID Hazard Identification
HAZOP Hazard and Operability
HIPAP Hazardous Industry Planning Advisory Paper
HIWD Hazard Identification Word Diagram
LPG Liquefied Petroleum Gas
NSW New South Wales
PHA Preliminary Hazard Analysis
PPE Personal Protective Equipment
QRA Quantitative Risk Assessment
SIL Safety Integrity Level
SMS Safety Management System
t tonne
tpa tonnes per annum
tpd tonnes per day
1 INTRODUCTION
Arriscar Pty Limited was engaged by FOY Group Limited (FOY) as an independent consultant to
undertake an assessment of critical infrastructure failure for their plastics to liquid fuel facility in the
Australian Capital Territory (ACT).
The intention of the study was to evaluate related systems with regard to potential failure modes
and their effects on safety, operability of the equipment, and the environment. Hence, the main
objective was to identify and describe any aspects of the design that need to be clarified and / or
resolved or need extra focus during operation.
1.1 Background
FOY proposes to construct a 200 tonne/day waste plastic to fuel facility. Construction and operation
of the facility will occur in 4 stages:
Stage 1
• Construction of site infra-structure and services (power, water, etc.).
• Construction of office, feedstock storage, tank farm and processing buildings.
• Installation of the first 50 tonne/day processing module.
Stage 2
• Installation of the 2nd 50 tonne/day module.
Stage 3
• Installation of the 3rd 50 tonne/day module.
• Expansion of the tank farm.
Stage 4
• Installation of the 4th 50 tonne/day module.
• Expansion of the workshop facility to accommodate module construction for overseas
parties.
1.2 Objectives
The principal objective of the study was to perform an independent assessment of critical
infrastructure failure for the FOY Plastics to liquid fuel facility. For this assessment, critical
infrastructure is considered to include equipment provided for control of emissions and control
measures for protection against abnormal events that may involve a loss of containment, fire or
explosion.
1.3 Scope
2 METHODOLOGY
The following approaches where adopted for this study:
- Undertake a Failure Modes and Effects Analysis (FMEA) for plant and equipment at the
facility for which a failure would lead to an undesired outcome, such as an emission of
hydrocarbon gas or liquid to the air or stormwater (Also refer to Section1.3.1).
- Undertake a review of the Preliminary Hazard Analysis (PHA) [Ref 1] to identify and assess
the hazardous effects of a hydrocarbon release from vessels and plant, and to review the
prevention, detection and mitigation control measures in the design.
The FMEA technique is used for qualitative and semi-quantitative analysis of engineering systems.
It often provides the starting point for reliability analyses, and enables the analyst to gain an insight
into possible critical failures of the system being analysed. Furthermore, the obtained information
may be used as a benchmark input to further develop the system and to enhance its overall
reliability.
The main goals of the FMEA are:
1. Identify failure modes for the component and the resulting effects on each subsystem at a
local level and the total system as a whole. Particular attention is paid to common mode
failures that can eliminate the system redundancy due to failed items or components.
2. Identify how the failure modes are or can be detected, and devise provisions and safeguards
that prevent the system from failing. If none is feasible or attainable, the analysis provides
a way to alert designers if hazards are present when the system fails.
The FMEA was undertaken as a desktop exercise reviewing project documentation, primarily the
Critical Infrastructure Failure Report [Ref 6] and the EIS [Ref 7], in consultation with FOY engineers
as required. THE FMEA worksheets are given in Appendix A.
3 FACILITY DESCRIPTION
3.1 Site Location
The proposed development site is at 36 Couranga Crescent (Block 11, Section 21) (Refer to Figure
2), approximately 11 km South of Canberra’s central business district and approximately 4 km West
of Lake Jerrabombera and the Lake Jerrabombera township.
Figure 2 Location of Proposed Facility
• An office, including amenities, will be in the Eastern part of the site (excluding the
driveway area). A car park will be located adjacent to the office area.
• A hardstand area containing the first flush system will be in the northeast corner of the
site. The first flush system has been designed to contain the first 15mm of rain of all hard
stand areas excluding areas covered by impervious roofing.
• The fire protection system will be in the south-east corner of the site. The fire protection
system has been designed to provide a deluge of 20 minutes for the main processing
area.
• A workshop facility for general site equipment maintenance and spares storage
requirements will be in the northeast of the main processing area.
The proposed site will be accessed using Couranga Crescent, as shown on the site plan (Refer to
Figure 3).
The site surface will consist of sealed concrete in the vehicle and processing areas, gravel in areas
between processing and vehicle access, and an area to the west of the site which will be reserved
as a grassed area.
hydrocarbons are separated. Reflux diesel (diesel that has been previously fractioned) is
pumped from the small tank at the bottom of the fractionation column to the packed column
scrubber through a flow control system.
5. Impurity Extraction System. The diesel phase passes to the impurity extraction system where
it is contacted in a counter flow liquid/liquid extraction column. This system removes such
impurities as Polyaromatic hydrocarbons, Sulphur compounds, colour compounds and
oxygenates.
6. Vacuum drying column. The diesel fraction that has had impurities removed may still contain
trace water. Water is removed by passing the diesel fraction through the vacuum drying tower.
The diesel fraction falls through tower packing while exposed to a high vacuum at a
temperature of approximately 110 degrees C, causing the water to boil off and be directed to
the primary condenser. The produced diesel is piped to the above ground diesel storage tanks.
7. Primary condenser. The lighter-end vapours flow from the fractionation tower to the primary
condenser, where petrol and water are condensed from the vapour stream. The petrol is a
finished product and is piped to the aboveground petrol storage tanks. Reflux petrol from the
storage tanks is pumped through a flow control mechanism to the top of the fractionation
column tower to assist in the fractionation process. The water fraction is directed to the
reboiler where it is reheated to remove trace petrol. Post this step it is pumped to the
wastewater treatment facility where it is treated before reuse as process water in the cooling
tower. In the unlikely event that there is an excess of water, FOY will discharge the excess water
to the sewer in accordance with the requirements of the trade waste permit.
8. Chilled vent condenser and compressor. Gas vapours (primarily LPG), which do not condense
in the primary condenser are ducted to the chilled vent condenser which is chilled utilising an
industry-standard cold glycol water system. Petrol is condensed from the vapours and piped to
the petrol storage tank. Non-condensable gases from the chilled vent condenser are
compressed and piped to the aboveground LPG storage vessel. Gases that do not condense in
the compression process are drawn off and piped to the cyclone combustor for use as fuel.
9. Cyclone combustor. The cyclone combustor produces the hot gases and heat required for the
depolymerisation process. The combustor uses LPG for start-up after which a mixture of LPG
and non-condensable gases provides fuel for the burner. Hot combustion gases flowing from
the cyclone combustor at over 1,100 oC for over 2 seconds are mixed with recycled flue gas and
enter the interstitial spaces between the catalytic reactor and outer cylinder at 900oC.
10. Heat recovery unit. Flue gases flowing from the interstitial spaces between the outer cylinder
and catalytic reactor pass through a heat recovery unit where heat energy is recovered to
reduce the plants fuel consumption lowering emissions to atmosphere. A small amount of the
flue gases are vented to atmosphere via a stack with a real-time monitoring module for air
pollutants.
11. Pyrolysis residue recovery system. Residual non-converted material (pyrolysis residue) exits
the catalytic reactor via vapour locks to a sealed metal cooling vessel where it cools naturally.
During cooling the vessel is subjected to a slight negative pressure by the fugitive vapour
collection system to ensure any remaining vapours are captured and thermally oxidised in the
cyclone combustor. The content of the non-converted material comprises filler materials (from
the plastic feedstock), char and admix.
Vacuum dryer
Diesel
The dimensions of tank farm bund are: 33.0 m x 10.0 m x 1.2 m. This equates to total retention
capacity of approximately 396 kilolitres. The Australian Standard AS1940–2004: The Storage and
Handling of Flammable and Combustible Liquids requires a bund capable of retaining at least 110%
of the volume of the largest container. The proposed bund can contain approximately 136% of the
largest tank (one of the 290 kilolitre diesel tanks) inside the bunded area and therefore complies
with AS1940-2004 and may contain some firefighting water / foam in the event of a fire.
3.7 Staffing
The workforce at full plant capacity will include:
• One facility manager;
• Fourteen facility operators;
• One logistics manager;
• One plant engineer;
• Three logistics operators;
• One fitter;
• One engineer;
• Three maintenance staff;
• One lab supervisor;
• One lab technician;
• One admin assistant; and
• One accounts clerk.
3.8 Security
The site security system will include:
• Physical Barriers – The site will be fenced with a 1.8 m high chain mesh (cyclone) security
fence with triple barbed wire along the top;
• Signage;
• Shift security checks;
• Emergency action plans; and
• Background checks on employees prior to employment.
# System Equipment
1 Catalytic Reactor Slide Gate
Plug Screw
Packed gland seals
2 Fugitive Emission Control Collection Fan
System
System Ducting
Cyclone Burner
3 Catalytic Reactor Pressure Pressure Transmitter
Control System
Pressure Controller
Gas Compressor (including VSD)
4 Hydrocarbon Condensing Cooling Water Pump
System
Cooling Tower
Chilled Vent Condenser
5 Gas Destruction System Cyclone Combustor
Module Diverter Valve
Flare Diverter Valve
6 Emergency Flare System Flare Pilot
7 Spill Containment Spill Containment Bunds
8 First Flush System First Flush Hydrocarbon Recovery Tank
First Flush Diverter
Surface Drains
is also the heat source for the catalytic reactor, tail gas formation will be rapidly reduced on a
module shutdown.
The following failure modes were identified for the cyclone burner:
• Burner Flame Out – Full failure of a single cyclone combustor;
• Loss of control of fuel to air mixture ratio - Partial failure of a single cyclone combustor;
and
• Loss of power - Full failure of all cyclone combustor.
The design provides for automatic detection of the above failure cases with associated actions
undertaken by the PLC to control or shutdown as required.
A full failure of a single cyclone combustor will result in an immediate shutdown of the module with
the diversion of the gas to the remaining operating cyclone combustors. A partial failure of a single
cyclone combustor will first attempt to bring the fuel air ratio back within the operating limit. If the
fuel to air ratio is not brought back within the operating limits within 1 minute of the excursion a
shutdown of the module will be initiated with the diversion of the gas to the remaining operating
cyclone combustors.
In the event of a total power loss the plant is shutdown and flow of gas to all cyclone burners is
diverted to the Emergency Flare.
The diverter valves were also reviewed in the FMEA, as detailed in Appendix A, as a failure of the
diverter valve to actuate and divert the flow away from a cyclone combustor on demand will result
in a release of un-combusted gas via the module stack to the atmosphere.
It is recommended that a SIL assessment be undertaken to assess the reliability of the cyclone
combustor burner management system interfaces with the plant PLC and the diverter valve
functionality to ensure the risk is adequately reduced.
All ground surfaces at the facility where hydrocarbons are handled and stored are designed to
ensure that any potential spillage of liquid hydrocarbon will not leave the site either directly or via
the stormwater system.
The following is provided at the site:
• Bunding and spill containment is provided for the following areas on the site:
- Plastic Storage and Densification Area;
- Tank Farm; and
- Process Modules.
• Runoff generated in potentially contaminated areas of the site, such as the main process
areas, will be contained onsite in bunded areas and processed through the waste water
treatment plant (WWTP). The transfer of accumulated water within these potentially
contaminated portions of the site to the WWTP is a manual operation.
• The main process area is covered by a roof minimising the potential for accumulation of
stormwater within the area.
• The tanker loading area is located on a hardstand with the rain water runoff reporting to
skim pits in the main processing area. The fuel residue from the pits is recovered and sent
to the rework tank for further processing.
• All traffic areas on the site are sealed concrete and stormwater reports to the first flush
system.
• The first flush system separates contaminants from the stormwater before discharge into
the municipal storm water system. The first flush system is described in detail in Section
3.9.2.
The FMEA, as detailed in Appendix A, identified two main failure cases which could lead to
contaminated runoff from the site:
• Failure of the spill containment areas (i.e. bund failure); and
• Failure of the first flush system.
A failure of the water treatment plant was not carried forward for assessment as the transfer of
contaminated stormwater from the bunded areas for treatment is a batch operation. Transfer to
the WWTP will not proceed if the WWTP is unable to treat the contaminated water.
The integrity of the spill containment provisions at the site is managed through routine inspections
and preventative maintenance.
6.2 Recommendations
The following recommendations have been made:
1. A Safety Integrity Level (SIL) assessment be undertaken to assess the reliability of the Fugitive
Emission Control protective functions.
2. A SIL assessment be undertaken to assess the reliability of the cyclone combustor burner
management system interfaces with the plant PLC and the diverter valve functionality to
ensure the risk is adequately reduced.
3. The final design of the pilot gas supply system was not available at this stage of the project;
however, it is recommended that the pilot gas supply be suitably independent of the process
to ensure a loss of pilot gas will not result from any plant upset or emergency condition. This
may include redundancy via an LPG cylinder backup supply on loss of pilot gas.
4. The checks associated with the first flush system are critical; therefore, FOY should consider
adopting a formalised ‘Check Sheet’ with appropriate levels of sign off to ensure the first flush
system is being adequately monitored.
5. A Fire Safety Study should be undertaken to assess the adequacy of the fire prevention,
detection and mitigation provisions for the facility once the design has further developed.
6. Ensure a Hazard and Operability (HAZOP) Study is undertaken once the detailed design has
been developed.
7. Consider undertaken a full FMECA for the operation at the facility once the detailed design
has been developed.
7 REFERENCES
1. Arriscar Pty Limited, November 2016, Non-Recyclable Plastic to Liquid Fuel Processing
Facility Preliminary Hazard Analysis.
2. Department of Planning and Environment, January 2011, Hazardous Industry Planning
Advisory Paper (HIPAP) No. 4: Risk Criteria for Land Use Safety Planning.
3. Department of Planning and Environment, January 2011, Hazardous Industry Planning
Advisory Paper (HIPAP) No. 6: Hazard Analysis.
4. Department of Planning and Environment, January 2011, Hazardous Industry Planning
Advisory Paper (HIPAP) No. 2: Fire Safety Study Guidelines.
5. Australian Standard AS1940–2004: The Storage and Handling of Flammable and
Combustible Liquids
6. Btola, November 2016, Critical Infrastructure Failure Report, Report Number 2620.10753-
SO2.
7. FOY Group Limited, July 2016, Non-Recyclable Plastic to Liquid Fuel Processing Facility
Environmental Impact Statement.
Appendices
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
1 Catalytic Reactor Slide Gate Provides a seal Failure to seal Failure of Potential for Potential for a 1) RAMs fails closed
between the plug hydraulic air ingress into flammable 2) 2 Slide Gates
screw and the system the kiln mixture within operating in series
depolymerisation the kiln resulting 3) Plug screw seal
module preventing a in a confined
hydrocarbon release explosion
or air ingress via the
Connection Failure of link Potential for Potential for a 1) Solenoid valves are fail
feedstock conveyer
Failure between the hydrocarbon release of closed and will close in
ram and the gas release flammable the event of PLC
slide from kiln material and a communications loss
fire if ignited 2) Plug screw seal
Configuration Incorrectly Potential for Potential for a 1) Solenoid valves are fail
failure configured PLC hydrocarbon release of closed and will close in
gas release flammable the event of PLC
from kiln material and a communications loss
fire if ignited 2) PLC configuration
checks
3) Access to PLC logic and
configurations is
password protected
4) Plug screw seal
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
2 Catalytic Reactor Plug Screw Seal Provides a seal for Failure to seal Plug screw Potential for Potential for a Loss of current on 1) Slide Gates in series
the drive failure air ingress into flammable Plug Screw dive 2) Kiln under slight
depolymerisation the kiln mixture within raises and alarm, negative pressure
module preventing a the kiln resulting with operator
hydrocarbon release in a confined intervention
or air ingress via the explosion
feedstock conveyer
Failure to seal Plug screw flap Potential for Potential for a - 1) Slide Gates in series
failure hydrocarbon release of 2) Kiln under slight
gas release flammable negative pressure
from kiln material and a
fire if ignited
- No feedstock Potential for Potential for a Feed hopper level 1) Slide Gates in series
hydrocarbon release of alarm 2) Kiln under slight
gas release flammable negative pressure
from kiln material and a
fire if ignited
3 Packed Gland Provide a seal Failure to seal Wearing Small leaks at NA Visual Inspection 1) Material select for the
Seals rotating equipment the gland seal during shift duty
2) Preventative
Maintenance
Failure to seal Loss of stuffing Small leaks at NA Visual Inspection 1) Material select for the
box gland the gland seal during shift duty
2) Preventative
Maintenance
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
4 Fugitive emission Collection Fan Provides suction for Fan Failure Fan stops/fails Potential Potential to 1) Pressure 1) Controlled plant
collection system the fugitive emission fugitive exceed monitoring of the shutdown initiated on
system emission to allowable fugitive emission loss of vacuum in fugitive
atmosphere at fugitive system via PLC emission system
fume hood emissions levels 2) Alarm on loss of
locations Fugitive Emissions Fan
5 System ducting Provides pathway for Ducting failure 1) Mechanical Excess Air Reduction in 1) Pressure 1) Controlled plant
collection of fugitive impact ingress into fugitive monitoring of the shutdown initiated on
emissions 2) corrosion fugitive emissions fugitive emission loss of vacuum in fugitive
emissions system system via PLC emission system
system performance 2) Alarm on loss of
Fugitive Emissions Fan
6 Cyclone burner Vapour from fugitive Cyclone burner Cyclone burner Fugitive Fugitive Module Status 1) If cyclone burner has
emissions system is not operating trip emission emission Alarm tripped there is no heat
feed to the cyclone system flow hydrocarbon gas input into the reactor
burn continues into released from and hence no vapour
Cyclone burner the module generation
stack
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
7 Catalytic Reactor Pressure Maintain a slight Fails to sense Loss of Signal Potential for Increased Independent Module Shutdown on
pressure control Transmitter (on vacuum within the pressure (reads low) pressure pressure in Pressure loss of vacuum for more
discharge of catalytic reactor increase in system may Transmitter than 1 minute
Glycol Heat system result in a
Exchanger) release of
vapour from the
catalytic reactor
feed/ash
removal points
Fails to sense Loss of Signal Potential to Air ingress into Independent 1) 2 Slide Gates
pressure (reads high) create the catalytic Pressure operating in series
excessive reactor causing Transmitter 2) Plug screw seal
vacuum combustion
within the
reactor and
higher levels of
ash formation
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
9 Catalytic Reactor Gas Compressor Compressors gas to Under Speed Compressor Potential for Increased Pressure Module Shutdown on
pressure control (including VSD) the desired pressure VSD failure pressure pressure in Transmitter on loss of vacuum for more
increase in system may system than 1 minute
system result in a
release of
vapour from the
catalytic reactor
feed/ash
removal points
Drive failure Compressor Potential for Increased 1) Fault Alarm on 1) Module Shutdown on
VSD failure pressure pressure in Loss of current to loss of vacuum for more
(trip) increase in system may compressor drive than 1 minute
system result in a 2) Pressure 2) Gas flow diverted to
release of Transmitter (PT emergency flare
vapour from the XXX) on system
catalytic reactor
feed/ash
removal points
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
9 Catalytic Reactor Gas Compressor Compressors gas to Mechanical Compressor Potential for Increased 1) Fault Alarm on 1) Module Shutdown on
pressure control (including VSD) the desired pressure failure VSD failure pressure pressure in Excessive current to loss of vacuum for more
(seize etc.) increase in system may compressor drive than 1 minute
system result in a 2) Pressure 2) Gas flow diverted to
release of Transmitter) on emergency flare
vapour from the system
catalytic reactor
feed/ash
removal points
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
9 Catalytic Reactor Gas Compressor Compressors gas to - Loss of Power Potential for Increased 1) Fault Alarm on 1) Module Shutdown on
pressure control (including VSD) the desired pressure pressure pressure in Loss of current to loss of vacuum for more
increase in system may compressor drive than 1 minute
system result in a 2) Pressure 2) Gas flow diverted to
release of Transmitter on emergency flare
vapour from the system
catalytic reactor
feed/ash
removal points
10 Hydrocarbon Cooling water Provides flow of Pump Pump Loss of cooling Increased 1) Flow Transmitter 1) PALL initiates Back-up
condensing system pump (PU1601) cooling water mechanical mechanical water to hydrocarbon with Alarm on PLC diesel cooling water
damage damage condensers build up in [FAL] pump
vapour phase 2) Pressure 2) Back-up diesel cooling
Transmitter with water pump 'Available' is
Alarm on PLC [PAH] a plant permissive in the
PLC. Plant will not run if
the back-up diesel
cooling water pump is
not 'Available'
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
10 Hydrocarbon Cooling water Provides flow of Pump failure Pump failure Loss of cooling Increased 1) Flow Transmitter 1) PALL initiates Back-up
condensing system pump (PU1601) cooling water (drive stops) (drive stops) water to hydrocarbon with Alarm on PLC diesel cooling water
condensers build up in [FAL] pump
vapour phase 2) Pressure 2) Back-up diesel cooling
Transmitter with water pump 'Available' is
Alarm on PLC [PAL] a plant permissive in the
PLC. Plant will not run if
the back-up diesel
cooling water pump is
not 'Available'
- Loss of Power Loss of cooling Increased 1) Flow Transmitter 1) PALL initiates Back-up
water to hydrocarbon with Alarm on PLC diesel cooling water
condensers build up in [FAL] pump
vapour phase 2) Pressure 2) Back-up diesel cooling
Transmitter with water pump 'Available' is
Alarm on PLC [PAL] a plant permissive in the
PLC. Plant will not run if
the back-up diesel
cooling water pump is
not 'Available'
11 Cooling Tower Provides cooling Inadequate Fouling within Reduced Inadequate Routine Cooling 1) Cooling water
water to a given cooling cooling tower thermal condensation of tower inspections condition monitoring
temperature to efficiency hydrocarbon 2) Chemical dosing of
ensure adequate within cooling within the cooling water
cooling in the tower condensers
condenser
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
11 Hydrocarbon Cooling Tower Provides cooling Inadequate Cooling tower Reduced Inadequate Cooling tower fan Operator Intervention on
condensing system water to a given cooling fan fails thermal condensation of stop alarm on PLC alarm
temperature to efficiency hydrocarbon
ensure adequate within cooling within the
cooling in the tower condensers
condenser
High ambient Reduced Inadequate - The cooling tower has
temperature thermal condensation of been designed for the
efficiency hydrocarbon expected weather
within cooling within the conditions at the site
tower condensers
12 Chilled Vent Provides chilled Pump Stops Glycol Pump Reduction in No adverse Temperature -
Condenser cooling water to a failure volatile effect - this will Transmitter on
given temperature to component not lead to an Chilled Vent
ensure adequate yield emission form Condenser coolant
cooling in the the plant inlet
condenser
System Failure Chiller failure Reduction in No adverse Temperature -
volatile effect - this will Transmitter on
component not lead to an Chilled Vent
yield emission form Condenser coolant
the plant inlet
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
13 Gas Destruction Cyclone To destroy any Burner Flame Burner Flame Potentially Potential for a 1) Flame Scanners 1) Cyclone combustor
Combustor excess vapours Out Out hazardous release of within burner unit flame out will initiate a
before release to material not hazardous shutdown of the module
atmosphere destroyed material to the 2) Gases from the
atmosphere module will be diverted
to an operating module
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
13 Gas Destruction Cyclone To destroy any High or low Fuel air Possible flame Potential for a Flue Gas Oxygen 1) PLC control fuel air
Combustor excess vapours oxygen in flue mixture ratio out or release of Sensors mixture ratio
before release to gas control failure Inadequate hazardous 2) Module shutdown if
atmosphere temperature material to the combustion conditions
reached for atmosphere not restored
noxious 3) Gas diverted to the
chemical emergency flare
destruction 4) Emission monitoring
of Module Final Stack
for: NOX, CO, Particles
(total), Total organic
compounds, SO2.
5) Continues monitoring
of Module Final Stack
for: Combustion
chamber temperature,
O2 Concentration, Stack
temperature, and water
vapour.
Total Loss Loss of Power Possible flame Potential for a Alarm on the PLC 1)PLC will initiate full
out or release of plant shutdown on loss
Inadequate hazardous of power
noxious material to the 2) PLC provided with UPS
chemical atmosphere backup
destruction 3) Flow diverted to the
Emergency Flare
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
14 Gas Destruction Module Diverter Diverts the flow Valve stuck Valve fails to Gas not Un-combusted Position switches -
Valve away from the change diverted to the hydrocarbon gas on the diverter
offline cyclone position other cyclone released from valve with position
combustor to the combustors the module proving alarm on
online cyclone stack the PLC
combustors
15 Flare Diverter Diverts the flow Valve stuck Valve fails to Gas not Un-combusted Position switches -
Valve away from the change diverted to the hydrocarbon gas on the diverter
cyclone combustor position Emergency released from valve with position
to the Emergency Flare the module proving alarm on
Flare stack the PLC
16 Emergency Flare Flare Pilot Maintain an ignited Loss of pilot gas Loss of supply Flare pilot light Unable to ignite 1)Flame detectors 1)PLC monitors flare
pilot light to ignite a extinguished full flare flow in on flare tip 2) Loss of flare pilot light
flow of hydrocarbons the event of a will result in a module
in the event plant upset shutdown
hydrocarbons are
diverted to the
emergency flare
Loss of spark Ignition failure Unable to Unable to ignite 1)Flame detectors 1)PLC monitors flare
ignite pilot full flare flow in on flare tip 2) Loss of flare pilot light
light the event of a 2) Igniter system will result in a module
plant upset failure alarm shutdown
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
17 Spill Containment Spill Provides Loss of integrity Crack in the Bund unable to Potential for a 1)Operator 1) Periodic Inspection of
Containment containment of a bund wall perform its release of Surveillance bunds
Bund hydrocarbon spill in intended hazardous 2) Preventative
the event of an function material to the Maintenance
unwanted release site 3) All drains outside of
the bunded areas report
to the first flush system
Loss of integrity Degraded bund Bund unable to Potential for a 1)Operator 1) Periodic Inspection of
surface perform its release of Surveillance bunds
intended hazardous 2) Preventative
function material to the Maintenance
site 3) All drains outside of
the bunded areas report
to the first flush system
Loss of integrity Penetration Bund unable to Potential for a 1)Operator 1) Periodic Inspection of
failure perform its release of Surveillance bunds
intended hazardous 2) Preventative
function material to the Maintenance
site 3) All drains outside of
the bunded areas report
to the first flush system
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
18 First Flush First Flush Tanks To collect the Human Error Operator fails First 15mm of Potential for any 1) Stormwater
surface runoff for to empty tank the current surface management policy to
the first 15mm of after previous rain event not contaminants to empty system after each
rain for any rain rain event collected flow into the rain event
event municipal 2) Operator training
stormwater 3) Weekly inspections
4) General housekeeping
to minimise potential for
contaminants
Functional
No. System Equipment Failure Mode Failure Cause Local Effects Global Effects Detection Method Provisions & Safeguards
Description
First Flush Diverter Diverts the flow to Diverts to early Diverter stuck Portion of the Potential for any 1) Preventative
municipal first 15mm of surface maintenance of system
stormwater after runoff enters contaminants to 2) Weekly inspections
15mm of rain the municipal flow into the 3) General housekeeping
collected. stormwater municipal to minimise potential for
stormwater contaminants
4) Diverter valve design
Drain The drain is the Drain blockage Build-up of Runoff Potential for Visual Inspections 1) Housekeeping
collection point material accumulates runoff to spill 2) Weekly inspections in
which directs runoff on the surface beyond the site 3) Drain layout and
into the first flush and is not able surface gradient
system to be treated designed to keep runoff
onsite
Processes: 5. General
Nodes: 1. Sabotage
Prevention Mitigation
Scenario Causes Consequence Recommendations Responsibility
Control Control
1.Intentional Miss 1.Incompatibly material 1.Potential for fire or 1. CCTV 3.Consider suitable FOY
use/Terrorism brought on site (i.e. explosion checks of people and
2. Motion sensors
fertiliser) vehicles before
on the
granting access to the
perimeter
site
3. perimeter fence
with cyclone
barbwire
4. perimeter
lighting
5. Police Checks
for all staff
6. Car parking is
offsite
7. Contractor
management