ID Task Task Name Duration Start Finish Predecessors May 6, '18 May 13, '18
Mode S M T W T F S S M
1 Initial Phase 90 hrs Mon 5/7/18 Tue 5/22/18 6%
2 Task A 8 hrs Mon 5/7/18 Mon 5/7/18 100%
3 Task B 14 hrs Tue 5/8/18 Wed 5/9/18 2 0%
4 Task C 68 hrs Wed 5/9/18 Tue 5/22/18 3 0%
5 Task D 36 hrs Wed 5/9/18 Wed 5/16/183
6 Analyze The Data 64 hrs Tue 5/22/18 Fri 6/1/18 1
7 Task E 16 hrs Tue 5/22/18 Thu 5/24/18 5
8 Task F 48 hrs Thu 5/24/18 Fri 6/1/18 7
9 UI Design 12 hrs Fri 6/1/18 Mon 6/4/18 6
10 Task G 4 hrs Fri 6/1/18 Fri 6/1/18 8
11 Task H 4 hrs Fri 6/1/18 Mon 6/4/18 10
12 Task I 4 hrs Mon 6/4/18 Mon 6/4/18 11