“Management & Care of Intercepted Irregular Immigrants Project Phase 2”

Construction Coordination Meeting

Minutes of Meeting
 
Date& Location of Meeting: 25 March 2013/ IOM office at Batam  
Agenda: 
1. Progress Report (General Progress) 
2. Review update of Last Meeting 
3. Safety Issues 
4. Contractual Issues 
5. Field/ Construction Issues 
6. Other Issues 
 
Participants: 
 
Contractor – Utomo Ladju  Consultant ‐ BITA  IOM 
 Didik S    Ries Munandar   Male Bobby  Rihidara 
 Johannes P   B. Cahya Erwanto   Roslinda Perangin‐angin  
 Tri Aji S   Zayadi 
 

General Progress 

General Progress 
Date  :   March 25, 2013  
Actual  :   2,388 %     
Plan  :   2,888  %  
    0,500 % delay 
   
Summary of Meeting Agreements & Discussions 
Review status of Last Meeting Issues
I. Field / Construction Issues 
1  Doing re‐layout of the archive building  Ongoing status: need to  PT. Utomo Ladju 
to be functioned as temporary office  installed AC and ceramics   
for IOM, Consultant, Contractor  layer for pantry 
started on 26/02/2013 
2  Installing the temporary fence and  ‐ Change position of the  PT. Utomo Ladju 
retaining wall started on 26/02/13.  temporary fence door to   
  west side  
‐ The temporary fence will 
be painted line on the 5th 
week 
3  Steel reinforcement, sand, gravel,  ‐ Contractor shall submit the  PT. Utomo Ladju 
cement  and concrete test and should  certificate at least one week 
be done with independent  institution  before material received 
such as PU    ‐ Steel reinforcement will be 
tested after material 
received 
4  Clarify the schedule of PLN with owner  ‐ IOM will coordinate with  IOM and BITA 
and consultant  Immigration Office for 
upgrading electricity power 
in archive building. Time 
estimation is 2 weeks 
 ‐ Need further discussion on 
monthly subscription fees of 
electricity usage in 
temporary office between 
Contractor and IOM  
‐ Contractor  ought to install 
separate electricity meter 
for construction work 
purpose 
5  Mock‐up  for  connection  and  bending  Ongoing status: contractor  PT. Utomo Ladju 
reinforcement  should  be  prepared  by  will provide it   
contractor 

6  ATB  pipe  inside  of  site  area  shall  be  ‐ Requested by contractor  IOM & BITA 
removed from site area.  ‐ Not urgent and has no 
impact to exavation. From 
the drawing, there is no 
building on that area 
7  Contractor  must  make  report  for  in‐ Ongoing status  Contractor 
out existing asbes material 
8  Planning  to  cut  Manggo  tree  near  the  ‐ Contractor will do survey  Contractor 
back wall  based on the drawing to 
decide if it’s needed to cut 
the mango tree or not  
‐ Contactor  shall provide 
the photo of tree before and 
after cutting for evidence to 
KLH 
9  Progress for STP & Clean water will be  ‐ Cancel the forward  IOM, PT. Utomo Ladju 
forwarded  in  the  beginning  of  April  schedule of STP 
2013  ‐ Incase STP is received early 
than the schedule, will store 
it in the place that protected 
from sunshine 
‐ Contractor requested the 
STP brochure 
II. Safety Issues 
1  Contractor  must  provide  the  trash  bin  Contractor will provide it on  PT. Utomo Ladju 
in site area to keep the site area clean  the 5th week 
and healthy 
III. Contractual Issues 
1  Employment  contract  with  the  The latest update from  IOM 
Contractor must be resolved. Once it’s  contractor, it will be 
completed,  the  insurance  (Jamsostek)  approved on the 5th week 
will be submitted by Contractor 

2  Contractor  must  use  IOM’s  template  Contractor already using the  PT. Utomo Ladju 


for  the  report  and  administration  form 
purposes 
IV.  Other Issues 
1  IOM requested Contractor and  Contractor will complete it  PT. Utomo Ladju 
consultant to submit names, photos,  ASAP 
specimen signatures, email addresses 
and mobile phone numbers 
       
V. Next Meeting Agenda 
  Will  be  held  on  Monday,  1st  April    BITA, PT. Utomo Ladju 
2013,  at  10.00  am  –  onwards  at 
Temporary Office, MCIIP II, Sekupang ‐ 
Batam   
 
 
Meeting Discussion
A. Field / Construction Issues 
1  Propose to have regular morning  It will be starting on the 5th  IOM, BITA, PT. Utomo 
briefing attended by IOM, Consultant  week  Ladju 
and Contractor prior to start working 
2  Some pile can not penetration follow  BITA  will seek advice from   BITA 
specification 3.5m depth mininum  PENTA to solve the problem 
3  Planning to undertake concrete test  BITA will check the testing  BITA 
K500 for concrete pile size  agency ( third party) 
250x250mm 
       
B. Contractual Issue 
1  Contractor must  submit the Progress  Ongoing status: IOM Batam  PT. Utomo Ladju 
Report of Demolition Works for  has received invoice and tax 
payment process  form from Utomo Ladju but 
no report attached 
2  Contractor must  prepare and submit  Ongoing status  PT. Utomo Ladju 
Monthly Report for compiling one       
month activities 
 

Signed and agreed by 

IOM         PT.BITA Consultant      PT. Utomo Ladju 