Sie sind auf Seite 1von 40

4/15/2014

CHAPTER 5

SCHEDULING AND TRACKING WORK


IN CONSTRUCTION PROJECT
MANAGEMENT

Introduction

Planning & Scheduling


• Principles of planning and scheduling
• Techniques of planning and scheduling
• Work breakdown structure
• Gantt Chart & S-Curve
• Successor/ predecessor relationship
• Arrow Diagram Method and
Precedence Diagram Method
• Critical Path Method

1
4/15/2014

THE INTEGRATION OF TIME &


SUSTAINABLE CONSTRUCTION

Our focus!!

Traditional Project’s Critical Components (time, cost, & quality); in relation with
sustainable construction concept

Introduction
• Project planning
– Process of identifying all the activities necessary
to successfully complete the project.
– Provides map to guide where to go and focused
on how to get there
– Planned in early stage of Project life Cycle (owner)
or also before site activities start (contractor).

2
4/15/2014

Introduction
• Importance of planning
– Reduce mistake and rework
– Avoid wastage
– Minimize unnecessary in time and cost scheduling
– Better quality control
– Effective project progress control
– Effective usage resources

Introduction
• Project scheduling
– Process of determining the sequential order of the
planned activities, assigning realistic durations to
each activity and determining the start and finish
dates for each activities.
– It can be used to manage, coordinate, control and
report.
– Depending on the sophistication of the user, the
schedule can take different forms.

3
4/15/2014

Introduction
• Purpose of project scheduling
– Claim
– Project time and cost control
– Allocate project resources more efficiently
– As a monitoring tool
– Material delivery at site
– Storage
– Avoid delay of the work and activity.
– Minimize the cash flow – as min as possible such as order material
stage by stage depend on the work needed.
– Control human resources and machinery to improve the efficiency
of the operation through the efficient use of resources and cost
control.
• Project planning is prerequisite to project scheduling!

Desired results of planning and


scheduling
• Finish the project on time.
• Continuous (uninterrupted) flow of work (no delays)
• Reduce amount of rework (least amount of changes)
• Minimize confusion or misunderstandings.
• Increase knowledge of status of project by everyone.
• Meaningful and timely reports to management.
• You run the project instead the project running you.
• Knowledge of scheduled times of key parts of the project.
• Knowledge of the distributions of costs of the project
• Accountability of people, define responsibility/authority.
• Clear understanding of who does what, when & how much.
• Integration of all work to ensure a quality project for the owner.

4
4/15/2014

What are the differences?


• Planning is more difficult to accomplish than
scheduling - the ability to identify all work
required to complete the project.
• The term planning and scheduling are often
used synonymously – planning and scheduling
are performed interactively.
• Planning is the first step to project scheduling.
• Tools used for planning and scheduling are
different!

Principles of planning and scheduling


• Begin planning before starting work, rather than after starting
work.
• Involve people who will actually do the work in the planning
and scheduling process.
• Includes all aspects of the project: scope, budget, schedule &
quality.
• Build flexibility into the plan, include allowance for changes and
time for reviews and approvals.
• Remember the schedule is the plan for doing the work, and it
will never be precisely correct.
• Keep the plan simple, eliminate irrelevant details that prevent
the plans from being readable.
• Communicating the plan to all parties; any plan is worthless
unless it is known.

5
4/15/2014

COST

RESOURCES TIME

SCOPE QUALITY

The Collection of Project’s Critical Components (should be in equilibrium)

Planning must include and link the components of project: scope,


cost, quality, resources and time.

Steps in planning and scheduling


Time &
Resource
Management
Scope Activity
definition Sequencing

Schedule
development
Create WBS Activity Activity
resource Duration
planning Estimation

Cost Estimating Cost Budgeting


Scope
Management
Cost
Management

6
4/15/2014

Steps in planning and scheduling


1. Develop a work breakdown structure (WBS)
2. Prepare a drawing (network diagram)
3. Determine the time, cost and resources required
4. Compute the schedule to determine start, finish
and float times
5. Analyze costs and resources for the project
6. Communicate the results of the plan and
schedule

Work breakdown structure (WBS)


• Identifies the tasks and activities that must be
performed.
• It divides the project into identifiable parts that can be
managed.
• Concept of WBS: in order to manage the whole project,
one must manage and control each of its parts.
• It defines:
– The work to be performed
– The need of expertise
– Assist in selection of project team
– Establish a base of project scheduling and control

7
4/15/2014

Work breakdown structure (WBS)


• WBS is displayed as a graphical or outline
method that shows the division of work in a
multi-level system.
• In developing WBS, we should consider:
– Activities that require time
– Activities that require cost
– Activities that need to arrange
– Activities that need to monitor

Work Breakdown Structure (Graphical)


Level 1 Construction of one block office building

Level 2 Testing & Project


Start Project Preliminaries Block A
Commissioning complete

Performance
Earthwork
Level 3 bond

Establish and
removal of site Structure Work
office

Architecture
Work

Architecture
Work

M&E work

8
4/15/2014

Work Breakdown Structure (Outline)


• Construction of one – Testing and
block office building Commissioning
– Start Project – Project complete
– Preliminaries
• Performance bond
• Establish and removal
of site office
– Block A
• Earthwork
• Structure Work
• Architecture Work
• M&E work

Work breakdown structure (WBS)


• Importance of WBS
– Overall program can be explain in summary according to
each sub-element divided.
– Planning could execute.
– Cost and budget could be estimated more accurately.
– Time, Cost and Performance of each element could be
monitor from time to time.
– Objective could be relate directly with the available
resources in the company.
– Network diagram and control planning could be prepared
in early stages.
– Responsibilities for each parties involve in every element
could be identified and assigned.

9
4/15/2014

Work breakdown structure (WBS)


Exercise:
You are the Project Manager for a Construction of
“Cadangan Membina dan Menyiapkan Sebuah
Rumah Banglo 2 Tingkat Serta Kerja-kerja Berkaitan
Untuk Tetuan Dato’ Kamal Jaafar.” Develop a
preliminary graphical work breakdown structure (up
to level 4) for the project given. Your WBS should
complete with all works needs in completing a one
unit bungalow.

Exercise (Suggested Answer-Graphical Method)


Level Cadangan Membina dan Menyiapkan Sebuah Rumah Banglo 2 Tingkat Serta Kerja-
1 kerja Berkaitan Untuk Tetuan Dato’ Kamal Jaafar

Level Preliminary Building External


2 works works works

Level Performance
Structure Architecture M&E Sewerage
3 bond

Progress Road and


Foundation Wall/facade Wiring
Report drainage

Fittings
Ground level Floor Landscape
installation
Level
4
1st floor level Roof

2nd floor
Fittings
level

10
4/15/2014

Exercise (Suggested Answer-Outline Method)

11
4/15/2014

Techniques for scheduling


• Techniques used will vary depending on:
– Project size
– Complexity
– Duration
– Personnel
– Owner requirements
• Two general methods commonly used :
Bar chart (Gantt chart)
Critical path method (CPM/ network analysis
system)

Bar chart (Gantt Chart)


• Developed by Henry L. Gantt
• It is a graphical time-scale of the schedule;
length represent the duration of activity.

12
4/15/2014

Advantages Disadvantages

• Easy to interpret • Difficult to update


• Simplicity & ease of preparation and
understanding (Simple graphical). • Does not show
• No theory or complicated calculation
interdependences of activities
involved (Easy for general • Does not integrate costs or
comprehension). resources with the schedule
• Time-scaled (the length of the bar • Limited application for detail
representing certain activity is construction work
proportional to the duration of that • Difficult to use it for forecasting
activity.
the effects that changes in a
• Appeal to persons who do not have a
particular activity will have on
technical background
the overall schedule
• Wide spread used in industry
• Mostly used in small project
• Fairly broad planning and scheduling
tools, so they require less revision
and updating than more
sophisticated systems

Bar chart (Gantt Chart)


No. Description Month
1 2 3 4 5 6 7 8 9 10
100
1 Mobilization
2 Foundation Excavation
Original Schedule
3 Diversion Stage
Cumulative progress (%)

4 Foundation Grouting
5 Dam Concrete
6 Install Outlet Gates
7 Install Trash Racks
8 Prestress
Actual progress
9 Radial Gates
10 Spillway Bridge
11 Curtain Grout
12 Dismantle Plant, Clean Up
0

 Bar chart basically use x-axis only (to depict time).


 The y-axis is use to show individual activities, to represent a variable across time
(e.g.: man-hours, budget, % complete and so forth.
 The variables usually shown as a curve superimposed on the bar chart.

13
4/15/2014

Bar chart (Gantt Chart)


• Example 1:
A project consist of five activities that should be
done in a period of time. Try to create a bar chart
to ease the project planning and scheduling.
* consider 1 week as 7 days
Activity A : 1 week, starting from 1 Jun 2014
Activity B : 2 week, starting from 8 Jun 2014
Activity C : 3 week, starting from 15 Jun 2014
Activity D : 2 week, starting from 22 Jun 2014
Activity E : 2 week, starting from 29 Jun 2014

Bar chart (Gantt Chart)-Example 1


• Step 1: identify start date and finish date for
each activity
Activity A : 1 week, starting from 1 Jun 2014 (1/6-7/6)
Activity B : 2 week, starting from 8 Jun 2014 (8/6-21/6)
Activity C : 3 week, starting from 15 Jun 2014 (15/6-5/7)
Activity D : 2 week, starting from 22 Jun 2014 (22/6-5/7)
Activity E : 2 week, starting from 29 Jun 2014 (29/6-12/7)

14
4/15/2014

Bar chart (Gantt Chart)-Example 1


• Step 2: Draw outline of bar chart

Activity Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6


(week)
1/6 8/6 15/6 22/6 29/6 6/7

Act. A 1
Act. B 2
Act. C 3
Act. D 2
Act. E 2

Bar chart (Gantt Chart)-Example 1


Activity A : 1 week, starting from 1 Jun 2014
(1/6-7/6)

• Step 3: Draw the Activity B : 2 week, starting from 8 Jun 2014


(8/6-21/6)
Activity C : 3 week, starting from 15 Jun 2014
activity bars (15/6-5/7)
Activity D : 2 week, starting from 22 Jun 2014
(22/6-5/7)
Activity E : 2 week, starting from 29 Jun 2014
(29/6-12/7)
Activity Duration Week 1 Week 2 Week 3 Week 4 Week 5 Week 6
(week)
1/6 8/6 15/6 22/6 29/6 6/7

Act. A 1
Act. B 2
Act. C 3
Act. D 2
Act. E 2

15
4/15/2014

Bar chart (Gantt Chart)-Example 2


Num. Activity Duration Start Date Cost (RM) Resources
(days) (person)

1 Activity A 3 4/5/2014 1,400.00 2


2 Activity B 5 7/5/2014 2,700.00 3
3 Activity C 7 10/5/2014 3,500.00 2
4 Activity D 5 15/5/2014 6,000.00 4
5 Activity E 4 17/5/2014 4,700.00 4
6 Activity F 6 19/5/2014 12,600.00 5
30,900.00

Bar chart (Gantt Chart)-Example 2


• Step 1: identify start date and finish date for
each activity
Activity A : 3 days, starting from 4 May 2014 (4/5-6/5)
Activity B : 5 days, starting from 7 May 2014 (7/5-11/5)
Activity C : 7 days, starting from 10 May 2014 (10/5-16/5)
Activity D : 5 days, starting from 15 May 2014 (15/5-19/5)
Activity E : 4 days, starting from 17 May 2014 (17/5-20/5)
Activity F : 6 days, starting from 19 May 2014 (19/5-24/5)

16
4/15/2014

Bar chart (Gantt Chart)-Example 2


• Step 2: Draw outline of bar chart

Activity Duration

10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
4/5
5/5
6/5
7/5
8/5
9/5
(days)
Act. A 3
Act. B 5
Act. C 7
Act. D 5
Act. E 4
Act. F 6

Bar chart (Gantt Chart)-Example 2


Activity A : (4/5-6/5)

• Step 3: Draw the Activity B


Activity C
: (7/5-11/5)
: (10/5-16/5)
Activity D : (15/5-19/5)
activity bars Activity E : (17/5-20/5)
Activity F : (19/5-24/5)

Activity Duration
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
4/5
5/5
6/5
7/5
8/5
9/5

(days)
Act. A 3
Act. B 5
Act. C 7
Act. D 5
Act. E 4
Act. F 6

17
4/15/2014

S-Curve
• An S-curve is defined as:
"A display of cumulative costs, labor hours or
other quantities plotted against time. The name
derives from the S-like shape of the curve, flatter
at the beginning and end and steeper in the
middle, which is typical of most projects. The
beginning represents a slow, deliberate but
accelerating start, while the end represents a
deceleration as the work runs out."

S-Curve
• Type of S-Curve
– Physical S-Curve
– Financial S-Curve
• Both S-curve can be in Baseline (planned) or
actual S-curve

18
4/15/2014

S-Curve (Example)
Num. Activity Duration Start Date Cost (RM) Resources/
(days) day
(person)
1 Activity A 3 4/5/2014 1,400.00 2
2 Activity B 5 7/5/2014 2,700.00 3
3 Activity C 7 10/5/2014 3,500.00 2
4 Activity D 5 15/5/2014 6,000.00 4
5 Activity E 4 17/5/2014 4,700.00 4
6 Activity F 6 19/5/2014 12,600.00 5
30,900.00

Based on bar chart in Example 2, construct S-curve (daily basis) for this
project:
1. Financial S-Curve
2. Physical S-curve (resources vs time & work vs time)

Financial S-Curve
Activity Duration Cost Cost/da y
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
4/5
5/5
6/5
7/5
8/5
9/5

(days) (RM) (RM)


30900
Act. A 3 1,400
=1,400/3
467
25750
Act. B 5 2,700
=2,700/5
540
20600
Act. C 7 3,500
=3,500/7
500
15450
Act. D 5 6,000
=6,000/5
1200
10300
Act. E 4 4,700
=4,700/4
1175
5150
Act. F 6 12,600 =12,600/
2100
6
0
1040

2100
1040

1700
1700
2375
2375
4475
3275
2100
2100
2100

Cost/day
540
467
467
467
540

540

500
500
500

26701
10001
12376
14751
19226
22501
24601

28801
30901

Cumulative cost/day
2481
1041
1941

3021
4061
5101
5601
6101
6601
8301
467
934

19
4/15/2014

Physical S-Curve (resources VS time)


Activity Duration Resource/

10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
day

4/5
5/5
6/5
7/5
8/5
9/5
(days)
102
Act. A 3 2
85
Act. B 5 3
68
Act. C 7 2
51
Act. D 5 4
34
Act. E 4 4
17
Act. F 6 5
0
Resource/day

13
3
2
2
2

3
3
5
5
2
2
2
6
6
8
8

9
5
5
5
5
Cumulative resource/day

101
12
15
20
25
27
29
31
37
43
51
59
72
81
86
91
96
9
2
4
6

Physical S-Curve (work VS time)


Activity Duration
10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
4/5
5/5
6/5
7/5
8/5
9/5

(days)
30
Act. A 3
25
Act. B 5
20
Act. C 7
15
Act. D 5
10
Act. E 4
5
Act. F 6
0
Work/day
1
1
1
1

1
1
2
2
1
1
1
2
2
2
2
3
2
1
1
1
1

Cumulative work/day
10
11
12
13
15
17
19
21
24
26
27
28
29
30
4
1
2
3

5
6
8

20
4/15/2014

Planning VS Actual S-curve??


• Before this, we just create a planning bar
chart.
• What if, the real activities has started? How to
create actual S-curve?
• Actually, same process is involve. But it’s ok…
let’s take a look one example.

Planning VS Actual S-curve (Example 2)


Physical S-Curve (work vs time)
Num. Activity Duration Start Date Actual Actual Cost (RM) Resources
(days) Start Date Finish Date (person)

1 Activity A 3 4/5/2014 4/5/2014 6/5/2014 1,400.00 2


2 Activity B 5 7/5/2014 7/5/2014 12/5/2014 2,700.00 3
3 Activity C 7 10/5/2014 11/5/2014 17/5/2014 3,500.00 2
4 Activity D 5 15/5/2014 17/5/2014 21/5/2014 6,000.00 4
5 Activity E 4 17/5/2014 18/5/2014 22/5/2014 4,700.00 4
6 Activity F 6 19/5/2014 21/5/2014 26/5/2014 12,600.00 5
30,900.00

21
4/15/2014

Bar chart (Gantt Chart)-Example 2


Activity Duration Start Actual Actual

10/5
11/5
12/5
13/5
14/5
15/5
16/5
17/5
18/5
19/5
20/5
21/5
22/5
23/5
24/5
25/5
26/5
(days)

4/5
5/5
6/5
7/5
8/5
9/5
Date Start Finish
Date Date

Act. A 3 4/5/14 4/5/14 6/5/14

Act. B 5 7/5/14 7/5/14 12/5/14

Act. C 7 10/5/14 11/5/14 17/5/14

15/5/14
Act. D 5 17/5/14 21/5/14

Act. E 4 17/5/14 18/5/14 22/5/14

Act. F 6 19/5/14 21/5/14 26/5/14

Planning cumulative work / day 1 2 3 4 5 6 8 10 11 12 13 15 17 19 21 24 26 27 28 29 30


Actual cumulative work/ day 1 2 3 4 5 6 7 9 11 12 13 14 15 17 19 21 23 26 28 29 30 31 32

Network Diagram
• Activity on Arrow (AOA)/ Arrow Diagram
Method (ADM)
– In arrow diagram project task or activities are
represented by the arrow and connected by the
node to express their logical relationship

Activity A Activity B

Node Node Node

22
4/15/2014

Network Diagram
Diagram for construction of pad footing

Network Diagram
• Activity on Node (AON)/ Precedence Diagram
Method (PDM)
– activity is place on the node
– The arrow used to connect between project task
to show their logical relationship

Act. A Act. B

Node Node

23
4/15/2014

Network Diagram
Diagram for construction of pad footing

Arrow - Logical
Node - Activity
Logical – Show the relationship
between activities
- Sequences of interrelated
activity

Basic definition in network diagram


• Activity- the performance of a task required to
complete the project. An activity require time,
cost, or both.
• Network- a diagram to represent the
relationship of activities to complete a project.
The network may be drawn as ADM or PDM.
• Duration- the estimated time required to
perform an activity.

24
4/15/2014

Basic definition in network diagram


• Early start (ES)- the earliest time an activity can
be started.
• Early finish (EF)- the earliest time an activity can
be finished.
EF = ES + D
• Late finish (LF)- the latest time an activity can be
finished.
• Late start (LS)- the latest time an activity can be
started without delaying the completion date of
the project.
LS = LF - D

Basic definition in network diagram


• Total float (TF)- the amount of time an activity
may be delayed without delaying the completion
date of the project.
TF = LF – ES – D
• Free float (FF)- the amount of time an activity
may be delayed without delaying the early start
time of the immediately following activity.
FF(i) = ES(j) –EF(i) ;
i-preceding activity, j-following activity

25
4/15/2014

Basic definition in network diagram


2 E 5 7 G 10
3 3
10 8 13 11 4 14

ES (E) = 2 EF(E) = 5 LS(E) = 10 LF(E)= 13

Duration (E) Total Float = 8 days


= 3d
Free
Float =
2 days
ES(G) = 7

ES ACT EF
DUR
LS TF LF

Basic definition in network diagram


• Critical path – a series of interconnected activities
through the network diagram, with each activity
having zero total float time. The critical path
determines the minimum time to complete the
project.
• Dummy activity- an activity (represent by a
dotted line) that indicates any activity following
the dummy cannot be started until the
activity(ies) preceding the dummy are
completed. Does not require time.

26
4/15/2014

Activity Sequencing
• Understand the order of how the job to be
accomplished in the field.
• The planner must understand how various
activities of the project related to each other
in term of their logical sequence.
• Example preparing formwork before
reinforcement could be place & than pouring
concrete.

Activity Sequencing
• Predecessor
– A task whose start or finish date determines the
start or finish date of its successor task.
• Successor
– A task whose start or finish date is driven by its
predecessor task.

27
4/15/2014

Link (Relationship)
• Finish to Start (FS) Act. A
– Activity B cannot start until
Activity A finish Act. B

• Start to Start (SS) Akt. A


– Activity B cannot start until
Activity A start Akt. B

28
4/15/2014

Link (Relationship)
• Finish to Finish (FF) Act. A
– Activity B cannot finish until
Activity A finish. Act. B

• Start to Finish (SF)


– Activity B cannot finish until Act. A
Activity A start.
Act. B

Lead time & lag time


• Lead time Act. A
– Overlap between
dependent activity
– Eg : FS – 5d Act. B
5d
• Lag time
– Delay between Act. A
dependent activity
– Eg: FS + 2 d
Act. B
2d

29
4/15/2014

Critical Path Method (CPM)


• Calculates the total project duration based on
individual task durations and their
interdependencies.
• The sequence of tasks determining the
minimum time needed for the project is the
critical path.

Critical Path Method (CPM)


FORWARD PASS

Early Early
Start Finish

Late Late
Start Finish
BACKWARD PASS

30
4/15/2014

Example (ADM)
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 -
Act. C 3 A
Act. D 4 B
Act. E 3 C,D
Act. F 2 C,D
Act. G 4 E
Act. H 3 F

1. Develop an arrow diagram for the project.


2. Identify critical activity and critical path for the project.

Example (ADM) – Forward pass

2 5

2 10

7
1 4
14
0 7

6
3
9
3

Node Num. Activity Node Num

ES LS Duration EF LF

31
4/15/2014

Example (ADM)-Backward pass

2 5

2 4 10 10

7
1 4
14 14
0 0 7 7

6
3
9 11
3 3

Example (ADM)-Total Float


Activity Duration ES EF LS LF TF
(day)
Act. A 2 0 2 0 4 2
Act. B 3 0 3 0 3 0*
Act. C 3 2 7 4 7 2
Act. D 4 3 7 3 7 0*
Act. E 3 7 10 7 10 0*
Act. F 2 7 9 7 11 2
Act. G 4 10 14 10 14 0*
Act. H 3 9 14 11 14 2

* Critical Activity

32
4/15/2014

Example (ADM)-Critical Path

2 5

2 4 10 10

7
1 4
14 14
0 0 7 7

6
3
9 11
3 3

Critical path

Example (PDM)
Activity Duration (day) Predecessor (s)
Act. A 10 -
Act. B 11 A
Act. C 5 B
Act. D 4 B
Act. E 12 A
Act. F 3 C,D
Act. G 7 F
Act. H 11 E
Act. I 4 G,H
1. Develop a precedence diagram for the project.
2. Identify critical activity and critical path for the project.

33
4/15/2014

Example (PDM-forward pass)


21 C 26
5
10 B 21 26 F 29 29 G 36
11 3 7

21 D 25
4
A I
0 10 36 40
10 4

10 E 22 22 H 33
12 11

ES Act. EF
Dur
LS TF LF

Example (PDM-backward pass)


21 C 26
5
10 B 21 21 26 26 F 29 29 G 36
0
11 3 7
10 0 21 26 0 29 29 0 36

21 D 25
4
A 22 1 26 I
0 10 36 40
10 4
0 0 10 36 0 40

10 E 22 22 H 33
12 11
13 3 25 25 3 36

Critical path

34
4/15/2014

Example (PDM)
Activity Duration (week) Predecessor (s)
Act. A 2 -
Act. B 3 A (FS+2),
C (FF+1),
D(FF)
Act. C 2 A
Act. D 1 C (SS)

1. Develop a precedence diagram for the project.


2. Identify critical activity and critical path for the project.

Example (PDM-forward pass)

4 B 7
+2 3

0 A 2
2
2 C 4
2
+1

2 D 3
1
ES Act. EF
Dur
LS TF LF

35
4/15/2014

Example (PDM-backward pass)

4 B 7
+2 3
4 0 7

0 A 2
2
0 2 2 C 4
0 +1
2
4 0 6

2 D 3
1
6 1 7

Critical path

Exercise (ADM)
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 A
Act. C 5 A
Act. D 4 A
Act. E 2 B,C
Act. F 3 C
Act. G 4 C,D
Act. H 2 E,F,G

• Prepare a arrow diagram for the project.


• Identify critical path for the project.

36
4/15/2014

Exercise (ADM-Solution)

Act. B 4
3
7 9

1 Act. A 2 Act. C 3 Act. F 6 Act. H 7


0 0 2 2 2 5 7 7 3 11 11 2 13 13

Act. D 5
4 7 7
Critical path

Exercise (PDM)
Activity Duration (day) Predecessor (s)
Act. A 2 -
Act. B 3 A
Act. C 5 A
Act. D 4 A
Act. E 2 B,C
Act. F 3 C
Act. G 4 C,D
Act. H 2 E,F,G

• Prepare a precedence diagram for the project.


• Identify critical path for the project.

37
4/15/2014

Exercise (PDM-Solution)
2 B 5 7 E 9
3 2
6 4 9 9 2 11

0 A 2 2 C 7 7 F 10 11 H 13
2 5 3 2
0 0 2 2 0 7 8
1 11 11
0 13

2 D 6 7 G 11
4 4
3 1 7 7 0 11

BUT… WAIT!!
• Are there any other type of Scheduling
method??
• How if the Gantt Chart and CPM did not
actually work/represent well with the
nature/requirement of the particular
construction project??

• So, actually we have… LINEAR SCHEDULING


METHOD (LSM) / LINE OF BALANCE (LOB)

38
4/15/2014

LINEAR SCHEDULING METHOD (LSM)


/ LINE OF BALANCE (LOB)
• This method is actually appropriate for a
project that:
– Progress linearly (straight without major
fluctuation of activities),
– Highly repetitive works,
– Have fixed starting point and end,
– Such as; highways, airfields, pipelines, multiple
housing units, high-rise buildings, etc.

LINEAR SCHEDULING METHOD (LSM)


(cont.)
• Take for example; a highway construction
project:

39
4/15/2014

LINEAR SCHEDULING METHOD (LSM)


(cont.)
We have 5 linear
activities:
1. Clear & strip
2. Drainage
3. Subgrade
4. Base course
5. Pave
Kilometer (km)

Width of B:
At 40km, the subgrade
works will starts at week
4.4 until week 5.

Height of A:
At week 3, subgrade
works from 13km to
21km.

Distance of C:
It is a time lag / time
float for 10km; between
subgrade works and base
LSM Diagram for highway project (adopted from Nunnally, 2014) course works.
1.4 weeks to be exact.

QUIZ!!!

YOU’RE GIVEN 20 MINUTES TO


COMPLETE IT…
BEST OF LUCK!

40

Das könnte Ihnen auch gefallen