PIPING
PRE-COMMISSIONING
Document No. Pekerjaan Engineering, Procurement & Rev. : 0
LREF-00-VDR-BBB-PR-00- Construction (EPC) Proyek Pembangunan Sheet No.
0015-A4 Terminal LPG Refrigerated 1 of 11
REVISION SHEET
GENERAL PROCEDURE FOR
PIPING
PRE-COMMISSIONING
Document No. Pekerjaan Engineering, Procurement & Rev. : 0
LREF-00-VDR-BBB-PR-00- Construction (EPC) Proyek Pembangunan Sheet No.
0015-A4 Terminal LPG Refrigerated 2 of 11
TABLE OF CONTENT
1. PURPOSE.............................................................................................................................4
2. SCOPE................................................................................................................................ 4
3. REFERENCES.................................................................................................................... 4
4. SEQUENCE OF PIPING PRE-COMMISSIONING..............................................................4
5. APPENDIX .......................................................................................................................... 10
GENERAL PROCEDURE FOR
PIPING
PRE-COMMISSIONING
Document No. Pekerjaan Engineering, Procurement & Rev. : 0
LREF-00-VDR-BBB-PR-00- Construction (EPC) Proyek Pembangunan Sheet No.
0015-A4 Terminal LPG Refrigerated 4 of 11
1. PURPOSES
This document describes the process adopted by PT Bangun Bejana Baja (BBB) to
successfully carry out piping pre-commissioning activities.
This procedure describes the requirement to be met during piping pre-commissioning
phase starting from preparation, execution, and acceptance.
2. SCOPE
This procedure applies to piping pre-commissioning activities performed by BBB in
accordance with Company in the scope of contract of LPG REFRIGERATED TERMINAL
DEVELOPMENT PROJECT.
3. REFERENCES
- ASME Sec. B31.3 Ed. 2014 : Process Piping
- ASME Sec. B16.5 B16.20 B16.21 : Spec Gasket
B16.47 & API 6A
- ANSI B1.1 : Spec Bolting
- ANSi B16.5 & API 6A : Pipe Flange & Flanged Fittings
- ASTM E 432 : Standard Guide for the Selection of a
Leak Testing
- ASTM E 479 : Standard Guide
for Preparation of a
Leak Testing Specification
- ASME Sec. V Ed. 2015 : Non Destructive
Examination
- LREF-00-LST-10-0001-A4 : Process Line List
- LREF-Piping & Instrumentasi Diagram Drawing
- LREF-Isometric Drawing
TP-NN-XXX-nnn
Where :
TP = Test pack identification
NN = System number
XX = Fluid service code
nnn = Test pack number of subsystem
GENERAL PROCEDURE FOR
PIPING
PRE-COMMISSIONING
Document No. Pekerjaan Engineering, Procurement & Rev. : 0
LREF-00-VDR-BBB-PR-00- Construction (EPC) Proyek Pembangunan Sheet No.
0015-A4 Terminal LPG Refrigerated 5 of 11
All test packs are grouped and summarized to confirm that the installed piping
spools have been already included on each test pack. The test pack summary list
shall be arranged together by Engineering Department and Pre-Commissioning
Team. It is issued as referencec in coordination with all depatments involved i.e.
Production Engineering Department, Quality Control (QC) Department, Fabrication
Department, and Pre-Commissioning Team, which responsible for all document
issued and execution of Pre-Commissioning activities
Piping Pre-Commissioning is to be performed by several steps. Specific procedures
completed with job risk assessments attached are issued by Production Engineering
to present detail information regarding safety obligation, preparation, requirement,
execution, acceptance criteria, and documentation of that respective step. The
sequential piping Pre-Commissioning activities described here are considered and
stated as ”hold point” or ”witnessed”. ”Hold Point” is indicating that there shall be no
activities continued before previous sequence is cleared and formally accepted by
QC Inspector in charge and Company Authorized Representatice :
Non destructive Hold Point
examination (NDE)
clearance
Line conformity check Hold Point
Piping lines flushing Hold Point
Piping lines pressure test Hold Point
(hydrostatic or pneumatic)
Drying Hold Point
Reinstatement Hold Point
Gross leak test lines Hold Point
pressurized with air and/or
nitrogen at 7.0 barg
Line check
Test report (Flushing, Pneumatic/Hydrotest, Blowing
Bar Chart
Punch List
Reinstatement
QC Department upon receipt of the test pack shall perform the ”line conformity
check” to ensure that all spool are already installed in accordance with P&ID, key
plan, piping layout plan, isometric drawing which describing orientation, dimension,
correct flanges, gaskets, valves, rating and insulation, inspection of weld, and piping
painting and color coding. If any outstanding item identified, QC Inspector shall
issue a ”puch list” to cover all the outstanding items. Gasket status to be recorded.
Its status to be classified as permanent or temporary. Company Authorized
Representative shall accept any permanent gasket installed as per specification.
During line conformity checks it shall also be notified whre the location of permanent
support hangers or supplementary supports required withstanding stress due to
flushing or hydrostatic load especially for gas and copper-nickel lines.
(See: Pipework Line Check Punch List” and ”Gasket Status & Acceptance Sheet)
In this step each outstanding item in punch list is categorized as ”priority A”, ”priority
B” and ”priority C. ”Priority A means that the outstanding item shall be cleared before
pressure test. ”Priority B” means that it may be cleared after pressure test, and
”Priority C” means that it can be performed after RFC like Painting touch up,
insulation and fire protection and same other activities.
After all inspection have been cleared by QC Department, subsequent inspection for
test pack sequence shall be carried out together with company Authorized
Representative to confirm that all requirements had been fulfilled out and
accordingly the Acceptance Report can be signed.
At the same time upon receipt of the test pack, QC Department shall trace the
completion of NDE requirement based on latest-revision isometric drawings involved
when all NDE has been cleared, QC Department shall submit the traceability report
to Company Authorized Representative for review whether all NDE requirements
were performed and NDE clearance sheet is signed at test pack index.
(See: ). Also, QC Department shall trace the material traceability. Summary of
material certificate must be include to the test pack.
At least three days in advance, it shall be approved prior to testing the piping
system.
Flushing shall be witnessed and approved by QC Inspector and Client Authorized
Representative. Flushing record is signed afterward.
Refer to specific procedure : LREF-70-PR-70-0001-A4 Rev. 1 APP Flushing Blowing
for Process Piping
GENERAL PROCEDURE FOR
PIPING
PRE-COMMISSIONING
Document No. Pekerjaan Engineering, Procurement & Rev. : 0
LREF-00-VDR-BBB-PR-00- Construction (EPC) Proyek Pembangunan Sheet No.
0015-A4 Terminal LPG Refrigerated 7 of 11
”Flushing Procedure for Piping System With NPS Larger Than 4 Inches” when
flushed by air is using quick decompression method with rupture disk.
”Flushing Procedure for Piping System With NPS 4 Inches and Smaller” when
flushed by air is using quick opening valve method.
Pressure test performed after flushing shall refer to ”Hydrotest and Leak Test
Procedure for Piping System” LREF-00-PR-00-0034-A4 Rev. 2. After completion of
pressure test, pre-commissioning test sheet of pressure test record and also record
chart (graphic) shall be signed together by QC Inspector and Company Authorized
Representative.
After a hydrostatic test, piping system shall be dried by air blowing using air supplied
from compressor. The air distribution is provided with filter to avoid any water, oil,
and dust entering the lines. Drying is not required when the piping line is tested by
using air and/or nitrogen. Partial drying when required may be applicable. After a
successful drying, a test sheet shall be signed by both QC Inspector and Company
Authorized Representative.
Reinstatement shall be performed after completion of piping pressure test and
drying to confirm that all components are installed in accordance with engineering
design as described on P&ID, Isometric, and key plan. During reinstatement any
temporary gasket shall be replaced by permanent one. Gasket Status & Acceptance
Sheet is then to be updated accordingly for final gasket acceptance. When it is all
gaskets for a test pack is considered accepted. Inspection shall be carried out with
Company Authorized Representative. And both QC Inspector and Company
Authorized Representave shall signe reinstatement record.
Refer to specific procedure : LREF-70-PR-70-0004-A4 Rev. 1 APP Air Gross Leak
Test
During reinstatement and before Company acceptance, all temporary drains and
vents shall be seal-welded. This items should be specifiy on the Punch List as
“Priority B”. And both QC Inspector and Company Authorized Representative shall
sign pre-com sequence for test pack than continued to pre-com sequence by
subsystem
Gross leak test shall be performed to examine the bolt tightness. The medium is
pressurized air at 7.0 bar. This leak test is to be recorded. Then QC Inspector and
Company Authorized Representative shall sign a test sheet for an accepted gross
leak test. (See form) by subsystem.
Refer to specific procedure : LREF-70-PR-70-0004-A4 Rev. 1 APP Air Gross Leak
Test
GENERAL PROCEDURE FOR
PIPING
PRE-COMMISSIONING
Document No. Pekerjaan Engineering, Procurement & Rev. : 0
LREF-00-VDR-BBB-PR-00- Construction (EPC) Proyek Pembangunan Sheet No.
0015-A4 Terminal LPG Refrigerated 8 of 11
All report shall be compiled from all the test packs in a subsystem. It shall become a
part of pre-commissioning dossier containing these following reports :
RFC Punch list
Updated status index
Marked-up P&ID, isometric drawing, flushing and pressure test layout, and pipe
support drawing
Check lists
Test sheets
Pressure test and gross leak test record charts
Gasket status and acceptance sheet
As-built drawings
GENERAL PROCEDURE FOR
PIPING
PRE-COMMISSIONING
Document No. Pekerjaan Engineering, Procurement & Rev. : 0
LREF-00-VDR-BBB-PR-00- Construction (EPC) Proyek Pembangunan Sheet No.
0015-A4 Terminal LPG Refrigerated 9 of 11
5. APPENDIX
A. Piping Precommissioning Procedure Flowchart
START
BY PRECOMM. CORD
FLUSHING
NO
ACCEPTED?
PUNCH LIST
NO PRIORITY 1
FOUND?
YES
APPROVED?
YES
REPAIR
PRESSURE TEST WORK PERMIT
DEPRESSURIZED
DEPRESSURIZED NO
ACCEPTED?
REINSTATEMENT
REINST.
ACCEPTED?
NO
N2 PURGING NO
ACCEPTED?