PROJECT REF NO: A1891-00073-2016

PROPOSED ERECTION OF 6 STOREY SINGLE USER DATA CENTRE WITH ANCILLARY


FACILITIES ON LOT 0869C PT MK06 AT SUNVIEW DRIVE SINGAPORE (BOON LAY
PLANNING AREA)

PARTICULARS AND CONTACTS OF OWNER/DEVELOPER, ARCHITECT/QP, CONTRACTOR AND


QECP

1. Developer/Owner

DBS TRUSTEE LIMITED


(AS TRUSTEE OF MAPLETREE INDUSTRIAL TRUST)
10 Pasir Panjang Road
#13-01 Mapletree Business City
Singapore 117438
Tel: 6377 6111 Fax: 6273 2753

2. Contractor

SHIMIZU CORPORATION
8 Kallang Avenue
#05-01, Aperia Tower 1
Singapore 339509
Tel: 6220 0406 Fax: 6224 9890
Email: Mutaguchi.Shojiro@shimz.biz

Contact Person Name: Mr. Mutaguchi Shojiro


Mobile No: 91890304

3. Architect/Qualified Person

XCUBE ARCHITECTS
8 Burn Road
#17-07, Trivex
Singapore 369977
Tel: 6634 2810

Architect Name: Ms. Chia Hui Teen

4. ECM Consultant

FIRST ENGINEERS CONSULTANTS PTE LTD


81 Ubi Avenue 4
#09-16, UB.One
Singapore 408830
Tel: 62848186 Fax: 6284 8187
Email: ngan@first-engineers.com

QECP Name: Mr Ngan See Pyng


QECP No: 0011
Mobile No: 98211255
First Engineers Consultants Pte Ltd
TEL: 62848186 FAX: 62848187

PROJECT:
PROPOSED ERECTION OF 6 STOREY SINGLE USER DATA CENTRE
WITH ANCILLARY FACILITIES ON LOT 0869C PT MK06 AT SUNVIEW
DRIVE SINGAPORE (BOON LAY PLANNING AREA)

JOB DESCRIPTION
STAGE 1 - INSTALLATION OF ULTIMATE LOAD TEST PILE AT PRE-
CONSTRUCTION STAGE

DESIGN CALCULATION
EARTH CONTROL MEASURES (ECM)

Document Number : FE/C/17-307-01/01

Date : 15-Mar-2017
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 2
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

A - ECM WRITE-UP
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 3
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

1 - Earth Control Measures (ECM)

This write-up proposes the erosion and sediment control as well as construction water control for
the installation of ultimate load test pile at pre-construction stage for proposed construction of 6-
storey single user data centre on lot 0869C PT MK06 at Sunview Drive.
The main objective of earth control measures is to contain muddy water and soiled construction
water within the construction area. This unclean / silty water is stored in an appropriate storage
area and then treated with ECM water treatment system to achieve the sediment yield of
discharge water less than 50ppm.

2 - Project Description

The project site is located at on Lot 0869C PT MK06 at Sunview Drive and the total site
occupied area (site area within boundary line of 9000 sq.m plus temporary site facilities area out
boundary line of 5950 sq.m) is about 14950 sq.m.
The scope of Stage 1 - ECM works is for installation of ultimate load test pile at pre-construction
stagefor proposed construction of 6-Storey Single User Data Centre.
The estimate duration for installation of ultimate load test pile is 22/03/2017 to 31/05/2017.

3 - Measures to Control Erosion, Sediment and Construction Water

Stage 1: Installation fo Ultimate Load Test Pile


1) Limit expose or bare surface area to be minimum as possible.
2) Maximum isolated open-up/exposed area is about 100 sq.m.
3) Provide silt fence along the perimeter of ultimate load test pile area.
4) Cover up all exposed area with erosion control blanket (ECB) as possible. Minimise earth
stockpile on site and cover up with ECB.
5) Provide enough size of storage pond and required capacity of treatment system. Regular
maintenance should be carried out to work effectively.
6) All collected silty water from at the storage pond to be pumped into water treatment system.
7) Treat all silty/construction water with water treatment system before discharging to public
drain. Provide adequate ECM system on site and prevent any discharge of silty water of
exceeding 50mg/l into public drain.

4 - Materials and Equipment Required for ECM

Stage 1: Installation fo Ultimate Load Test Pile


1) Silt fence and erosion control blankets.
3
2) Water treatment system: 1 unit of 3m /hr.
3) Sedimentation/ECM Storage water pond of 2.5m x 2.5m x 1m depth.
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 4
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

B - ECM DESIGN CALCULATION


Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 5
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

1 - Design Statement

This calculation presents the earth control measures (ECM) for installation of ultimate load test
pile at pre-construction stage.

The objective is to provide an effective earth control measure system to meet the PUB's
requirement by keeping sediment yield of discharge water to be less than 50ppm.

Proposed ECM concept of discharge of water

Stage 1: Installation fo Ultimate Load Test Pile


- Provide steel plate or hardcore material for the access of piling machine.
- Maximun exposed area for the test pile installation is 100 sq.m.
- Duration of installation of test pile is about 9 weeks.
- Provide silt fence along the perimeter of test pile area.
- Limit expose surface area to be minimum as possible and cover the exposed area with
erosion control blankets.
- The construction/silty water from the exposed area to be discharged to ECM water storage
pond of 2.5mx2.5mx1.m depth.
- The collected water at the sedimentation storage pond will then be treated with ECM
treatment system with minimum capacity of 3m3/hr to achieve sediment yeild of 50ppm.
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 6
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

2 - Earth Control Measures Plan

Refer to attached Appendix: 7.5


Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 7
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

3 - Soil Data and Calculation Formulae for Estimation of Soil Lost

Soil lost due to excavation works is calculated based on the following soil information &
formulae.

Design Rainfall Intensity


Storm event (using 5-year return period) (Refer to Appendix 7.2)
Duration of storm = 1.00 hr
Maximum rainfall intensity = 80.00 mm

Soil Information (Assumption)


Soil Type : Clayey SAND
Gravel : 25%
Sand : 40%
Clay & Silt : 35%
Soil structure : 3 (fine granular)
Permeability : 3 (moderate)
Organic matter : 0%

Calculate Sediment Yield


Modified USLE equation is used.
T = R x K x LS x C x P
T = sediment yield per storm event (tons)
0.56
R = Ψ2(V*Qp)
Ψ2 = 89.6 for SI units
3
V = Volume of runoff (m )
3
Qp = Peak flow (m /s)
K, LS, C and P are USLE parameters

To calculate K factor (Refer to Appendix: 7.3: Soil Erodibility Chart)


K = 0.03

To calculate LS factor
m S
LS = (λ/22.13) x (0.065 + 0.046S + 0.0065S )
λ = slope length (m)
S = slope in percent
m = 0.2 for S<1.0%
0.3 for 1%<S<3%
0.4 for 3%<S<5%
0.5 for 5%<S<12%
0.6 for S>12%

To calculate CP factor
Construction site (bareland) = 1.000
Lean concrete = 0.001
Asphalt pave surface = 0.003
Well compacted hardcore = 0.005
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 8
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

4 - Calculation of Maximum Soil Content

Stage 1: Proposed concept of ECM for Installation of Ultimate Load Test Pile

- Maximum occupied area for proposed works is 100 sq.m.

To calculate LS factor
λ = 5.00 m
S = 0.50 %
m = 0.20
m S
LS = (λ/22.13) x (0.065 + 0.046S + 0.0065S ) = 0.05

To calculate Runoff volume & Peak flow


2
Excavation area, A = 100 m
Volume of runoff, V = α x Rainfall intensity x A = 0.70*80*10^-3*A
3
= 5.60 m
3
Peak flow, Qp = Runoff volume/Duration = 0.002 m /s
0.56 0.56
R = Ψ2(V*Qp) = 89.6*(V*Qp)
= 6.29

To calculate Sediment Yield


Sediment yield, T = R x K x LS x C x P = 0.01 tonnes

To calculate Soil Content


Soil content = T/V = T*10^9/(V*10^3)
= 1748 mg/litre

Provide silt fence around the perimeter of isolated test pile area and cover the exposed area
with the erosion control blanket if possible.
Provide treatment system to treat the discharged water to achieve sediment yield of less than
50mg/L.
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 9
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

5 - Calculation of Capacity of Runoff Water and Treatment Time

Stage 1: Proposed concept of ECM for Installation of Test Pile

Check on Capacity of runoff water


Storm Event (using 5-year return period) (Refer to Appendix 7.2)
Duration of storm = 1.00 hr
Maximum rainfall intensity = 80 mm
2
Max. exposed area, A = 100 m
Total volume of runoff water = 0.70*80*10^-3*A
3
= 5.60 m
Water storage pond/tank to be provided = 1 Nos x 2.5m x 2.5m x 1m
3
= 6.25 m OK

Check on Capacity of Treatment System


Design treatment time = 10.00 hrs
Capacity of treatment system required = 0.6 m3/hr
Capacity of treatment system to be provided = 3.0 m3/hr
Volume of silty water treated within 10 hrs = 30.0 m3 OK
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 10
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

6 - Summary on Earth Control Measures

1) ECM to be carried out are as follows,


a. Provide silt fence along the perimeter of ultimate load test pile area.
b. Limit expose or bare surface area to be minimum as possible.
c. Provide sedimentation/ECM water storage pond with dimension of 2.5m(L) x 2.5m(W)
x 1m(Depth) and 1 unit treatment system with capacity of 3m3/hr.
d. Maintain sediment control once a week.
e. All exposed area to be covered with well-compacted hardcore or ECB.
f. Maintain the ECM system on site till the completion of the proposed works.

2) Best Management Practices to be carried out are as follows,


a. Engage full-time ECMO to carry out periodic inspection.
The frequency of inspection is as follows;
- Every Monday morning
b. Assign full-time workers to carry out maintenance of installed ECM.
c. ECMO to meet and update to QECP every month.
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE 11
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

7 - Appendix

7.1 - ECM Checklist

7.2 - Rainfall Intensity - Duration - Frequency Curves for Singapore

7.3 - Soil Erodibility Chart

7.4 - Treatment System Catalogue

7.5 - Earth Control Measures Plan Drawings

7.5.1 - Drawing No: FE/ECM/17-307-01/01


Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE A1
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

7.1 - ECM Checklist


INSPECTION OF EROSION CONTROL MEASURES
Date of Inspection: S/N BEST MANAGEMENT INSPECTION COMPLIANCE ACTIONS
PRACTICES
Name of Inspecting Officer: 1 Construction Clearing of construction areas carried Yes / No / NA
Sequence & out in phases?
Scheduling
Appointment 2 Stockpiles of Earth Stockpile location according to ECM Yes / No / NA
Materials plan?
Date & Time of Site Visit: 3 Stablization through Location according to ECM Yes / No / NA
laying of milled schedule?
Weather Condition: waste, lean concrete, Construction according to ECM Yes / No / NA
turfing …etc details?
Any signs of damage at lean Yes / No / NA
concrete areas?
Project Title: Any signs of damage at milled waste Yes / No / NA
areas?
Any signs of damage at turfed areas? Yes / No / NA
4 Stockpiles of Earth Stockpile location according to ECM Yes / No / NA
Location of Site : Materials plan?
Protected against erosion? Yes / No / NA
Protected against sedimentation? Yes / No / NA
Project Duration: 5 Silt Traps Installation of silt traps including Yes / No / NA
location according to ECM schedule?
Type of Present Construction Activity: Installation of silt traps according to Yes / No / NA
ECM plan including no.s & size?
Silt Traps damaged? Yes / No / NA
PUB Permit Number: 6 Sedimentation Installation of basins / ponds Yes / No / NA
Basins / Storage including location according to ECM
Ponds schedule?
Installation of basins / ponds Yes / No / NA
Owner / Developer: according to ECM plan including
no.s?
QP for Project: Concentration of TSS in effluent Yes / No / NA
(outlet of discharge) < 50mg/l?
Sediment filled to within 300mm of Yes / No / NA
QECP for ECM:
water discharge level of outflow
structure?
ECO: Sedimentation basins inlet / outlet Yes / No / NA
choked?
Owner / Developer's Representative on-site: Protected against sedimentation? Yes / No / NA
7 Treatment Units / Treatment unit(s) in operation? Yes / No / NA
Polymer Blocks Polymer blocks used / adequate? Yes / No / NA
8 Perimeter cut-off Installation of cut-off drains including Yes / No / NA
Date of ECM Plan: drains location according to ECM schedule?
Installation of cut-off drains according Yes / No / NA
to ECM plan including lengths?
Last Date of ECM Plan Review:
Cut-off drain lined? Yes / No / NA
Any signs of inadequate capacity? Yes / No / NA
(flooding)
ADDITIONAL INFORMATION Any obstruction / sediment? Yes / No / NA
Date & Time of Previous Site Visit: Any signs of damage? Yes / No / NA
9 Wheeled wash areas, Location according to ECM plan? Yes / No / NA
entry/exit points Construction according to details? Yes / No / NA
Date Of Last Inspection Report: Any signs of damage? Yes / No / NA
Run-off (from wheeled wash areas) Yes / No / NA
and overflow / discharge channeled
Issues Identified In Previous Site Visit: to suitable areas for proper
treatment?
Any signs of silty water from these Yes / No / NA
areas into public drains (drains /
roads / etc)?
10 Others Any areas without/inedequate ECM? Yes / No / NA
Public drains at discharge points Yes / No / NA
silted?
Public drains in vicinity of site silted / Yes / No / NA
obstructed?
Run-off from site not channeled Yes / No / NA
This site inspection has been certified by: through silt fences / cut-off drains /
QP / QECP: silt traps?
Any discharge of water into public Yes / No / NA
Signature: drains?
Date: Earth surfaces / slops adjacent to any Yes / No / NA
drain not turfed, paved or covered?
Contractor:
Any other observations / comments:
Signature:
Date:

Owner/Developer:
Signature:
Date:

Note:
Earth Control Measures is for the treatment of
silty water due to rain water. Construction
wastewater (slurry, bentonite..etc) due to
tunnelling, boring..etc shall be separately treated.
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE A2
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

7.2 - Rainfall Intensity - Duration - Frequency Curves for Singapore


Appendix 7.2
100
50
25
15
10
5
3
2
100
50
25
15
10
5
3
2
The IDF Curve has been revised to include till 2009 rainfall data.
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE A3
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

7.3 - Soil Erodibility Chart


Appendix 7.3
Soil Erodibility Chart [To be adopted]
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE A4
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

7.4 - Treatment System Catalogue


FP WATERHUB PTE LTD
ULTRA‐ECM SILT & SEDIMENT TREATMENT SYSTEM for Storm‐Water Management  
Earth Control Measure 
 

Our ULTRA-ECM Silt & Sediment Treatment Systems are


designed to treat silt & sediment/run-off water from earthwork
and construction sites. It is a robust, simple and cost effective
treatment system. Operation is automatic with little attendance
for long period of time. No operator experience is required as
the control panel is simple and safe.   

• Fully-automatic & 24-hr workhorse


• Submersible pump with float switch
• Low running cost
• Easy maintenance
• Single or Three Phases
  Model: FP‐WW‐40, Capacity: 40m3/hr  

 
 
 
 
 
 
 
 
 
 
 
 
   Model: FP‐WW‐05, Capacity: 5m3/hr  
 
 

Model Capacity Voltage Dimension


FP‐WW‐03  3 M3/HR  220V/1PH  1.2 (L) X 1.2 (W) X 2.0 (H) M 
FP‐WW‐05  5 M3/HR  220V/1PH  1.8 (L) X 1.2 (W) X 2.0 (H) M 
FP‐WW‐10  10 M3/HR  220V/1PH  2.4 (L) X 2.0 (W) X 2.0 (H) M 
FP‐WW‐20  20 M3/HR  415V/3PH  4.0 (L) X 2.0 (W) X 2.0 (H) M 
FP‐WW‐40  40 M3/HR  415V/3PH  6.0 (L) X 2.0 (W) X 2.3 (H) M 
FP‐WW‐60  60 M3/HR  415V/3PH  6.0 (L) X 2.0 (W) X 2.6 (H) M 
    Customized capacities also available upon request 

For more information, please contact: 
F P   W a t e r h u b   P t e   L t d 
No 1 Charlton Lane #01‐01 Charlton Corner Singapore 539631  
TEL: (65) 6858 1310  FAX: (65) 6858 1324 / 6281 7995 HP: (65) 9623 2813 EMAIL: fpwater@gmail.com 
Project Job Ref.
First Engineers PROPOSED ERECTION OF 6 STOREY SINGLE USER 17-307-01
Consultants Pte Ltd DATA CENTRE WITH ANCILLARY FACILITIES ON Sheet no./rev.
81 Ubi Ave 4 #09-16 UB.One LOT 0869C PT MK06 AT SUNVIEW DRIVE A5
Singapore 408830 Calc. by Date Chk'd. by Date App'd. by Date
tnm 15-Mar-17 nsp 15-Mar-17 nsp 15-Mar-17

7.5 - Earth Control Measures Plan Drawing

7.5.1 - Drawing No: FE/ECM/17-307-01/01