Sie sind auf Seite 1von 18

 

Santiago Solar 

 
LUMP SUM TURNKEY, ENGINEERING, PROCUREMENT AND CONSTRUCTION CONTRACT 

 
Contract No. _________ 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Annex 1 Appendix D  
 
Quality Assurance & Quality Control 
   
   25‐04‐2016 
  Rev. 15 
 
   

Annex 1 Appendix D Quality Assurance 2016 04 25 DRAFT Rev 15.docx   1 
 
Content: 

1  General ........................................................................................................................................... 4 
2  QA / QC System and Organization ................................................................................................. 4 
2.1  QA/QC System ........................................................................................................................... 4 
2.2  QA/QC Manager ........................................................................................................................ 4 
2.3  Inspection and Test Plan (ITP) / Owners inspection rights ....................................................... 4 
2.4  Non‐Conforming Items .............................................................................................................. 5 
2.5  Independent Expert .................................................................................................................. 5 
2.5.1  Contractor’s Independent Expert (CIE) ............................................................................ 5 
2.5.2  Owner’s Independent Expert (OIE) .................................................................................. 5 
3  Quality Assurance during Construction and Commissioning ......................................................... 5 
3.1  Main Completion Certificates during Construction .................................................................. 5 
3.1.1  Tracks and Hardstands Complete ..................................................................................... 5 
3.1.2  Foundation Complete (per power plant subsystem / inverter segment) ........................ 6 
3.1.3  Mechanical Completion (per power plant subsystem / inverter segment) ..................... 6 
3.1.4  Electrical Completion (per power plant subsystem / inverter segment) ......................... 6 
3.1.5  Control System completion (per power plant subsystem / inverter segment) ............... 6 
3.1.6  Function test Completion (per power plant subsystem / inverter segment) .................. 6 
3.1.7  Commissioning Completion (per power plant subsystem / inverter segment) ............... 6 
3.1.8  Performance testing of power plant ................................................................................ 7 
3.1.9  Acceptance testing and complete facility performance testing ...................................... 7 
4  Inspection and Testing of Components ......................................................................................... 7 
4.1  Inverter & switchgear ................................................................................................................ 7 
4.2  MV/HV Transformer and HV electrical equipment ................................................................... 7 
4.3  PV Modules Testing ................................................................................................................... 7 
4.3.1  Objective ........................................................................................................................... 7 
4.3.2  Application area ............................................................................................................... 7 
4.3.3  Reference documents ...................................................................................................... 7 
4.3.4  Role and responsibility ..................................................................................................... 8 
4.3.5  Module power control procedure .................................................................................... 8 
 
 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
Abbreviations / Definitions 
AC  Alternating Current 
AM  Air Mass 
AME  Andes Mining Energy 
DC  Direct Current 
EL  Electroluminescence 
EPC  Engineering Procurement and Construction  (the 
contractual scheme) 
FNTP  Full Notice to Proceed 
HSE  Health, Safety and Environment 
HV  High Voltage 
HV‐TL  High Voltage Transmission Line 
IE  (Contractor’s or Owner’s) Independent Expert 
IEC  International Electrotechnical Convention 
ITL  Independent Test Laboratory 
ITP   Inspection and Test Plan 
I‐V (curve)  Current‐voltage curve 
(k)(M)Wh  Kilo or mega watt.hour 
LID  Light Induced Degradation 
LNTP  Limited Notice to Proceed 
LV, MV, HV  Low, Medium, High Voltage 
ML  Manufacturer Laboratory 
OE   Owners Engineer 
PID  Potential Induced Degeneration 
PV  Photovoltaic 
QA  Quality Assurance 
QC  Quality Control 
STC  Standard Testing Conditions  
Defined as: 1000W/m2 at 25°C module 
temperature, Air Mass AM1,5 
UV  Ultra‐violet 
VDE  Electrotechnical Association of Germany 
 
   

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
1 GENERAL 

This document serves as Appendix D, part of “Annex 1 Technical Specification” to the EPC Contract 
and  therefore  constitutes  a  contractual  document.  It  describes  the  QA/QC  requirements  for  the 
execution of the EPC Contract for the construction of a fully functional PV plant, including substation 
and transmission lines (“Project”). 

2 QA / QC SYSTEM AND ORGANIZATION 

2.1 QA/QC System 

Contractor  shall  implement  a  state‐of‐the‐art  QA/QC  system,  where  all  equipment  and  works  are 
controlled and tested and properly documented. Contractor shall enforce the QA/QC at his suppliers 
and subcontractors, and shall make the existence of such system a pre‐requisite for his procurement. 
The QA/QC System shall include, among other items, the following: 
‐ Quality Assurance (QA) program, 
‐ Inspection  &  Test  Plan  for  manufactured  and  supplied  materials.  This  shall  include  all  major 
equipment such as for instance Modules, Inverters, Mounting Structures, HV and MV equipment, 
‐ Quality Control (QC) and Inspection plan for construction and commissioning, 
‐ Establishing and up‐to‐date keeping of all documentation at all phases of construction. 

2.2 QA/QC Manager 

Contractor  shall  appoint  a  designated  QA/QC  Manager  for  the  complete  Project  duration,  starting 
with Limited Notice To Proceed (LNTP) until final acceptance. The QA/QC‐Manager shall have more 
than 10 years of work experience and more than 5 years of experience in quality assurance and quality 
control for plants with similar complexity. Contractor shall present the QA/QC Manager to Owner for 
his approval. 
The QA/QC manager shall be responsible for all tasks related to the QA/QC of the project and shall be 
the counterpart for the Owners QA/QC representative. 

2.3 Inspection and Test Plan (ITP) / Owners inspection rights 

Contractor  shall  prepare  a  comprehensive  Inspection‐  and  Test‐Plan  for  the  complete  Project,  all 
subsystems, equipment and components. The ITP shall be submitted to owner after LNTP for approval. 
This shall include, but not be limited to the following: 
Workshop/Factory Inspection 
Owner has the right to inspect all manufacturing facilities and workshops for equipment related to 
the  Project.  EPC  Contractor’s  QA/QC  Manager  shall  arrange  all  access  and  visits  with  respective 
Supplier/Subcontractor. Owner will give a 1 (one) week notice to Contractor for his intended visit. 
Witness inspection 
Owner reserves the right to attend and witness all relevant inspection for equipment and material 
produced and procured for his project. Contractor shall provide a complete inspection plan at the start 
of the Project (with LNTP, to be updated with FNTP) for Owner’s review and comment. 
Contractor shall invite Owner with at least 2 weeks’ notice of any inspection event, even if dates as 
per original schedule are kept. 
Construction and Commissioning 
Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
Owner and his designated representatives shall have access to the complete construction site at all 
times.  Contractor  shall  provide  training  on  health,  safety  and  environment  (HSE)  regulations  as 
required. 
Documentation 
Contractor shall keep all files updated with a complete set in his site office. Owner has the right to 
review and check documentation without prior notice. 

2.4 Non‐Conforming Items 

The Contractor must maintain a record of all non‐conforming items throughout the duration of the 
Project. This should reflect evidence of notification of the non‐conformance to the relevant party and 
the suggested course of action or an instruction issued to rectify the situation where necessary. 
The Contractor will provide the Employer’s Representative with copies of all non‐conformance notices 
issued throughout the duration of the Project. An updated register with evidence of close out of the 
non‐conformance where appropriate will be presented for review at the monthly progress meeting. 

2.5 Independent Expert 

2.5.1 Contractor’s Independent Expert (CIE) 

CIE  conducts  the  necessary  tests  and  inspections  as  required  by  the  EPC  Contract  (and  described 
below) at his own costs. 

2.5.2 Owner’s Independent Expert (OIE) 

Owner shall have the right to select one or several OIE at his own expense to verify the work of the 
Contractor if he desires to do so. Contractor shall provide access to all tests, documentation etc to OIE 
or to Owner directly. 
The Owner will appoint a specific OIE within the frame of the Modules QC described below in 4.3. This 
Modules QC and the associated testing and inspection will be at Owner’s costs. 

3 QUALITY ASSURANCE DURING CONSTRUCTION AND COMMISSIONING 

Contractor shall prepare a detailed construction and commissioning plan and prepare checklists and 
certificates for each of the construction phases as listed below. 
Certificates shall be provided with original signatures from the supervisor responsible for the specific 
part of the work, from the Contractor’s QA/QC manager and Owner’s witnesses prior to hand‐over of 
system  to  next  construction  phase.  All  certificates  shall  be  kept  and  form  part  of  final  project 
documentation. 
All  certificates,  procedures  and  inspection  check‐lists  shall  be  prepared  by  the  Contractor  and 
submitted for approval to Owner prior to start of construction work. 

3.1 Main Completion Certificates during Construction 

3.1.1 Tracks and Hardstands Complete 

For each power plant segment, the Contractor shall prove that acceptable quality and CBR values are 
reached  in  order  to  ensure  proper  and  safe  traffic  and  stability.  Based  on  the  technical  solution 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
selected and the materials used, the Contractor will carry out load bearing capacity tests with static 
plates and/or deflectometry tests (depending on the construction technique used).  
Minimum CBR shall be 10. 
At  least  one  test  per  500  linear  meters  of  track  and  one  test  per  hardstand/crane  pad  shall  be 
performed. 

3.1.2 Foundation Complete (per power plant subsystem / inverter segment) 

For each power plant segment, prior to start of mechanical erection, the foundations shall be checked 
and  certified  to  be  in  accordance  with  drawings  and  design  requirements  in  terms  of  location, 
alignment, quality of work and quality of provided materials (e.g.  samples of concrete shall be made 
and laboratory tested). 

3.1.3 Mechanical Completion (per power plant subsystem / inverter segment) 

For each power plant segment, mechanical completion shall be checked and certified prior to start of 
electrical works. Mechanical completion shall include the complete assembly of mounting structures 
and modules. Checks shall verify accordance with construction drawings and manuals, workmanship, 
alignment, no damages on materials, etc.  

3.1.4 Electrical Completion (per power plant subsystem / inverter segment) 

For each power plant segment, electrical completion shall be checked and certified prior to testing of 
systems.  Checks  shall  verify  accordance  with  construction  drawings,  proper  routing,  bending  and 
fixing of cables (UV protection, bending protection, etc.), certify the correct connection of each cable, 
testing of cable, labeling, etc. 

3.1.5 Control System completion (per power plant subsystem / inverter segment) 

For  each  power  plant  segment,  completion  of  control  system  and  all  connected  components  and 
measurements  shall  be  checked  and  certified  prior  to  testing  of  systems.  Checks  shall  verify 
accordance with construction drawings, proper routing, bending and fixing of cables (UV protection, 
bending protection, etc.), certify the correct connection of each cable, testing of cable, labeling, etc. 

3.1.6 Function test Completion (per power plant subsystem / inverter segment)  

For each power plant segment, function tests shall be conducted according to a specific test plan to 
avoid any damage to equipments due to improper sequence or accidental operation. 

3.1.7 Commissioning Completion (per power plant subsystem / inverter segment)  

For  each  power  plant  segment,  commissioning  shall  be  conducted  according  to  a  specific 
commissioning  procedure  to  avoid  any  damage  to  equipments  due  to  improper  sequence  or 
accidental operation.  
The commissioning procedure shall be provided to the Owner for approval 3 Months prior to start of 
Commissioning activities. 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
3.1.8 Performance testing of power plant  

The completed system shall be performance tested based on specific performance test procedures, 
as may be provided within the EPC Contract or be approved by Owner prior to start of construction. 
Such  performance  test  will  be  a  mandatory precondition  for  the Acceptance Test of  the complete 
power plant for Substantial Completion. 

3.1.9 Acceptance testing and complete facility performance testing 

Details are provided in the EPC Contract, Appendix A and Appendix D 

4 INSPECTION AND TESTING OF COMPONENTS 

4.1 Inverter & switchgear 

In addition to all standard QA procedures and good practices, thermographic measurements of all 
inverters  and  switch  gears  during  nominal  load  to  identify  processing  defects  or  improper 
connections. 

4.2 MV/HV Transformer and HV electrical equipment 

In  addition  to  all  standard  QA  procedures  and  good  practices,  all  sleeve  interconnections  and 
connections have to be documented with inspection sheets. 

4.3 PV Modules Testing 

The majority of the tests described in this section will be done in the power plant site (installed module 
or in onsite test laboratory). The onsite Test Laboratory will be of recognized prestige and must be 
acceptable by all the involved parties: Owner, Contractor and PV Modules Manufacturer. 
Owner will execute samples when modules are delivered on site. In case samples show no compliance 
with the agreed module specification according to Annex 1 Technical Specification, owner will execute 
a  module  testing  process  as  described  below.  If  any  of  the  selected  parts  do  not  satisfy  the 
requirements as described in this document then contractor shall fulfill the condition as described in 
the clause “Testing of Sample Products” of the agreement.  

4.3.1 Objective 

The objective is to define a QA procedure to evaluate the performance and quality of photovoltaic 
modules. 

4.3.2 Application area 

This process can be used to evaluate the nominal power and general quality of photovoltaic modules 
coming from approved or under approval suppliers of Owner. 

4.3.3 Reference documents  

Proposed tests are based on the following international standards: 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
‐ IEC 61215 Crystalline silicon terrestrial photovoltaic (PV) modules – Design qualification and type 
approval. 
‐ International Standards in testing of PV modules. 
The tests will be performed by Owner or Owner’s Representative / OIE and supervised by Contractor 
or Contractor’s Representative / CIE based on IEC 61215 standards. 

4.3.4 Role and responsibility 

The execution of the tests and inspections by the Owner. All test equipment must comply with latest 
applicable norms and standards considering industry practice for TIR1 supplier.  
- The Contractor (via Module Manufacturer) must provide: 
o The modules 
o The tolerance ranges 
o The module « Flash list » data  
o The electroluminescence images 
 
- Owner / OIE must: 
o Define the sampling method 
o Execute test as listed below 
o Provide a report on visual inspection of photovoltaic modules 
o Provide  results  on  measured  characteristics  current‐voltage  at  STC  conditions  for 
each module sample 
o Provide results on LID (Light Induced Degradation) for the sample 
o Provide results of Electroluminescence –EL images and defects classifications 
o Provide a detailed report on measurement results 
o Provide raw data of the done measurements. 
 

4.3.5 Module power control procedure 

4.3.5.1 Sampling method 

Module samples must be randomly selected from a lot or a sub batch of produced modules (included 
in a « flash list »). 
Sampling method should be agreed with the Contractor according with the International Standard ISO 
2859. 
Sampled quantity is detailed in below as agreed by both Parties. The modules must be produced in 
the same conditions and using the same manufacturing process as usual. These modules must have 
undertaken first an inspection and a quality control as defined by the module manufacturer. 
The  module  sampling  to  test  must  be  selected  according  to  a  statistic  method  in  function  of  the 
nominal  power  at  STC  conditions,  the  manufacturing  date  and  the  confidence  level  of  the 
manufacturer.  This  statistic  method  allows  a  representative  sample  to  be  chosen  from  the  whole 
production lot or sub‐batch. 
The percentages of modules to be tested will be based in the International Standard ISO 2859: 
- The  quantities  for  testing  and  accordingly  for  rejection  considers  a  Batch  Size  of  11440 
Modules 
- Special Inspection Level according to below table 
- Acceptable Quality Level according to below table depending on the test 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
 
Visual Inspection. 
Modules Electrical Characteristics 
Images with Electroluminescence (EL) camera. 
EVA cross linking degree. 
Thermography 
UV resistance 32 
Peel Test 
Leakage test 
Potential Induced Degradation (PID) 
 
In case of one or more of the previous type of tests fail, Elecnor reserves the right (at its cost) 
to retest with presence of OIE the PV modules. In case the test of Client is confirmed (number 
of failed modules above acceptable number of failed modules) the relevant batch / sub batch 
shall be rejected. 
Contractor might test with presence of OIE at his own costs sub batches considering a sample 
size  based  on  the  same  inspection  level  and  based  on  the  same  quality  requirements  as 
defined below. In case number of failed modules in the retest are within the required quality 
level, these sub batches can be used for the power plant. 
The  test  quantities  in  the  table  below  are  defined  for  one  Batch  of  11440  Modules  (or  20 
container); in case one batch is divided in sub batches upon request of contractor, the number 
of tested modules to justify a rejection has to be adapted considering the norm ISO 2859 with 
the respective Inspection level as defined for each test in the below table. In case contractor 
is requesting such division in sub batches, the additional testing is at contractor costs. 
 
   

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 

 
Table 1: Summary of Sample Selection and Fail Criteria for Module Testing 

Number of
Modules for
Test Inspection each batch with
Item Acceptance Criteria Fail Consequence / Comment
Description Level approximately
11440 modules
(20 container)
AQL = 1 for critical defects as Fail: Rejection of Batch
defined below
Failed Module allowed = 3
AQL = 1 for major defects based
on IEC 61215 definition
Visual
4.3.5.2 G-1 125 Failed Module allowed = 3
Inspection.
AQL = 2.5 for minor defects based
on IEC 61215 definition
Failed Module allowed = 7

Fail:
Compensation of reduced output
with additional installed capacity
or
Modules Economical compensation if no
Electrical AQL = 2.5 additional power can be installed
4.3.5.3 G-1 125
Characteristics: Failed Module allowed = 7 based on site restrictions or
Power/I-V/LID approval restrictions
(please refer to detail below)
or
rejection of batch (Contractor
decision)
Fail: Reject of Batch
Images with
Electroluminesce AQL = 1.5
4.3.5.4 G-1 125
nce (EL) Failed Module allowed = 5
camera.
Destructive Testing
Failed Module rejection of both
EVA crosslinking 1 module for 2 No AQL Level batches
4.3.5.5
degree. batches Failed Module allowed = 0 Same Modules will be used both
for EVA Cross Linking Test and
Peel Test
In case of failure additional
4.3.5.6 Thermography 10% Failed modules to be replaced measurements to be agreed
between parties
Destructive Testing
Failed Module rejection of both
1 module for 2 No AQL Level batches
4.3.5.8 Peel Test
batches Failed Module allowed = 0 Same Modules will be used both
for EVA Cross Linking Test and
Peel Test
2 per batch but Fail: Reject of Batch
no less than 1 No AQL Level
4.3.5.9 Leakage test
per MW in Failed Module allowed = 0
average
Potential 2 per batch but
Induced no less than 1 No AQL Level Fail: Reject of Batch
4.3.5.10
Degradation per MW in Failed Module allowed = 0
(PID) average
 
 

4.3.5.2 Visual inspection 

i. Test description 

This test objective is to detect any visual defect on the modules. The Laboratory must inspect carefully 
all the modules of the sample with a light intensity superior or equal to 1 000 lux in order to check the 
following defects according to Supplier’s visual inspection criteria:  

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
10 
 
‐ Cracked, bent, misaligned or torn external surfaces; 
‐ Broken cells; 
‐ Cracked cells; 
‐ Faulty interconnections or joints; 
‐ Cells touching one another or the frame; 
‐ Failure of adhesive bonds; 
‐ Bubbles or delamination forming a continuous path between a cell and the edge of the module; 
‐ Tacky surfaces of plastic materials; 
‐ Faulty terminations, exposed live electrical part; 
‐ Any other conditions which may affect performance. 
Make note of and/or photograph the nature and position of any cracks, bubbles or delamination, etc. 
which may worsen and adversely affect the module performance in subsequent tests. 
 
 

ii. Acceptation criteria 

A module design and aspect shall be judged to have passed the visual qualification tests, if each test 
sample meets the following criteria: 
‐ No broken, no cracked and no torn external surfaces, including superstrates, substrates, frames 
and junction boxes; 
‐ Both  of  horizontal  and  vertical  dislocation  of  cell  strings  (maximum  exposure  of  cell  bus  bar 
metallization) ≤ 2mm with offset length;  
‐ The junction box should be parallel to the backsheet or frame.  
‐ No  bent  and  no  misaligned  external  surfaces,  including  superstrates,  substrates,  frames  and 
junction  boxes  to  the  extent  that  the  installation  and/or  operation  of  the  module  would  be 
impaired. 
‐ No crack in a cell the propagation of which could remove more than 10% of that cell’s area from 
the electrical circuit of the module; 
‐ No bubbles and no delamination forming a continuous path between any part of the electrical 
circuit and the edge of the module; 
Loss of mechanical integrity, to the extent that the installation and/or operation of the module would 
be impaired. 
 

Test execution:       Test  to  be  done  before  installation  of  module  in  the  onsite 
        laboratory.  Time  between  arrivals  of  relevant  container  to
        site to fail report maximum 20 calendar days 
 
Quantity to be tested:  According to ISO 2859: Inspection Level G1 normal 
inspection. 

 
AQL‐Level:        1 for all critical defects as listed above (3 failures allowed) 

          For additional major defects according to IEC 61215 AQL = 1 
          (3 failures allowed).For additional minor defects according to 
          IEC 61215 AQL = 2.5 (7 failures allowed) 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
11 
 
 

4.3.5.3 Modules electrical characteristic 

i. Test description 

The current‐voltage characteristic I‐(V) and the STC power from each module is determined according 
to the IEC standard IEC 61215. 
The test must be conducted with a class AAA sun simulator according to IEC 60904. 
The calibration must be traceable to SI‐standards. The reference device must have an uncertainty of 
<1% for Isc. 
The STC power is the power at Standard Test Conditions: 1000 W/m2, at 25°C  
The measurement uncertainty must be as low as possible but up to the agreed third party testing lab 
ability for silicon technology. A measurement of spectral response is done for one reference module. 
For each module, the laboratory will do 3 consecutive I‐V measurements. 
 
For  C‐Si  modules,  the  Light‐Induced‐Degradation  (LID)  is  measured  on  sampling  modules  with  the 
following conditions;  
‐ Exposure to 20kWh of natural sunlight  
‐ During exposure, modules are kept close to MPP. 
 
Quantity to be tested:      According to ISO 2859 Inspection Level  G‐1  
 

ii. Acceptance criteria 

Each test samples need to meet the following criteria: 
1. The  module  individual  power  at  STC  should  be  in  the  positive  tolerance  range  and 
comparable to the Nominal Power agreed by both parties. 
2. The average STC‐power must be equal or above nameplate power. 
3. All  modules  I‐V  curves  have  a  smooth  behavior  according  characteristics  in  the  range  of 
values given by the manufacturer 
4. LID measurement must be in the range of values given by the manufacturer 
 
Quantity to be tested:   According to ISO 2859: Inspection Level G1 normal 
inspection 

AQL‐Level:        2.5 (applicable only for criteria 1, 3 and 4) 

Test criteria 2 average STC‐power must be equal or above nominal power of the module. If the 
average STC‐power is below the nominal power of the module the test failed 

Consequence in case of test failure 

In case of failure the measured values of the test are used as supporting values for a new simulation 
and the substandard performance is determined by way of calculation. In such case additional 
modules must be installed in order to satisfy the Power Guaranty, if possible pursuant to the 
applicable permits and space constraints. If additional modules can’t be implemented in the existing 
Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
12 
 
plant based on space and permit constraints, reduced installed capacity has to be compensated with 
a price reduction of the facility equivalent to Liquidated Damages for underperformance as defined 
in Appendix D of the contract. This means for each percent reduced installed capacity of the plant 
(and fractions of this), contractor will i) reduce the full turnkey EPC price 1.5 % or ii) increase 
guarantee PR in the same proportion.  

If contractor pays compensation for reduced installed capacity based on electrical testing, the 
reduced installed capacity shall be considered in the performance calculation according to Appendix 
D of the contract. In the same way, if contractor compensates the reduced installed capacity with an 
increase of PR, this new PR shall be considered in the performance calculation according to 
Appendix D of the contract. 

If criteria 2 average STC‐power if more than 2 % below nominal output of the Module the batch shall 
be rejected and replaced with new modules. 

 Test execution:   Test to be done before installation of module in the onsite    
    laboratory. Time between arrivals of relevant container to    
    site to fail report maximum 20 calendar days for all electrical    
    testing (except LID measurement). Time between for fail   
    report LID measurement as quick as possible. 
 

4.3.5.4 Images with Electroluminescence (EL) camera 

i. Test description 

The objective is to control the number and type of cell defects (micro‐cracks, broken fingers…). 
For each module, EL measurements are done in injecting current with the same value as module short 
circuit condition. 
For each module, the laboratory summarizes the following defects: 
‐ Estimated module defective active area  
‐ Maximum cell defective area 
‐ Presence of cell defective area caused by crack 
‐ Presence of cell with multiple cracks 
‐ Number of cracks and micro‐cracks in module classified in the following categories 
 Cross cracks 
 Perpendicular to busbars 
 Parallel to busbars 
 45° oriented 
 Dendritic cracks 
 Cracks with other directions 
‐ Presence of grid finger defects 
‐ Presence of inactive cells 
‐ Existing evident EL contrast among cell 
‐ Presence of contact molding defect 
‐ Presence of soldering defects 
‐ Evidence of slope breakage in I(V) curve 
 
Quantity to be tested:      According to ISO 2859 Inspection Level G‐1 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
13 
 
 

ii. Acceptance criteria 

The tested modules must comply with micro‐cracks specifications attached below: 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
14 
 
Table 2: Definition of fulfilment of micro‐cracks specification 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
15 
 
‐ AQL‐Level:       1.5 (failed modules allowed = 5 modules 

 
Test execution:       Test  to  be  done  before  installation  of  module  in  the  onsite 
          laboratory.  Time  between  arrivals  of  relevant  container  to 
          site to fail report maximum 20 calendar days 

4.3.5.5 EVA crosslinking degree 

The determination of the EVA crosslinking degree gives an indication of the production quality (oven 
temperature, homogeneity, duration). A poor crosslinking degree has an adverse effect on the service 
life of the module. The data sheet information of the EVA supplier is deemed as the pass criterion. 
The test method is wet‐chemical, i.e it is not an exact physical measuring method and afflicted with a 
high degree of uncertainty. This fact is taken into account in the pass criteria. 
 
Quantity to be tested:      1 module for 2 batches 

Test Characteristic      Destructive Testing 

Method of testing:      Soxleth extraction in Xylene. 

Pass Criteria:        Minimum 65% (measurement tolerance considered) 

If the module fails, both batches rejected 

Test execution:       Test  to  be  done  before  installation  of  module  in  the  onsite 
          laboratory.  Time  between  arrivals  of  relevant  container  to 
          site to fail report maximum 30 calendar days 

4.3.5.6 Thermography 

Quantity to be tested:      10 % 

Test / Pass Criteria: 

‐ Temperature difference between the substrings within a module is less than 5 K.  
‐ Temperature difference between single cells within a module is less than 10K.  
‐ Less than 5 cells within a module have a temperature deviation from average greater than 5 K . 
If not, then the performance deviation shall be less than 10% of the value in the SF flash report. 

Note: Adaptation of the limits after joint measurement onsite and, where appropriate, verification 
in the laboratory.  

Consequence: 

‐ Failing modules to be replaced; in case of significant number of failure increase of test quantity 
to be mutually agreed 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
16 
 
Test execution:       Test to be done after module installation on structure 

4.3.5.7 Peel test 

This test is used to check as to whether the EVA/backsheet adhesion complies with the manufacturer's 
specification.  This  measurement  is  not  possible  in  all  cases  because  the  backsheet  may  adhere  so 
strongly that, instead of allowing for peeling off, it tends to tear inherently. 
Quantity to be tested:      1 module for 2 batches 

Test Characteristic      Destructive Testing 

Pass Criteria:        60 N/cm EVA vs glass, 20 N/cm for EVA backsheet   
If the module fails, both batches rejected 

Test execution:       Test  to  be  done  before  installation  of  module  in  the  onsite 
          laboratory.  Time  between  arrivals  of  relevant  container  to 
          site to fail report maximum 30 calendar days 

4.3.5.8 Leakage test 
Wet leakage test according to IEC 61215. Power is applied to the short‐circuited module in the water 
bath and the leakage current is measured. This test is used to determine the insulation resistance. It 
is a safety test. 
Quantity:        2 modules per batch but no less than 1 per MW in average. 
Test Criteria:         

Pass criteria        40 MOh/m² considering IEC 61215   

If the 1 module fails, the batch is rejected 

 
Test execution:       Test  to  be  done  before  installation  of  module  in  the  onsite 
          laboratory. Time between arrivals of relevant container to site 
          to fail report maximum 20 calendar days 
 

4.3.5.1 Potential Induced Degradation (PID) 
The PID test shall identify the Potential‐Induced Degradation resulting from voltage influence on the 
module. It is a degradation resulting in lower output, which can occur on one side of a string. The test 
procedure  is  not  yet  standardized,  but  a  procedure  recommended  from  several  Module 
manufacturers. During the PID test, a negative potential of ‐1000V is induced between cell and module 
frame. The glass cover shall have contact with the frame via aluminum foil (IEC 62804 TS, Methode B). 
Before  and  after  the  test,  EL  measurements  and  STC  output  measurements  will  be  carried  out  to 
determine  the  effect  on  the  modules.  Additionally,  the  isolating  resistivity  of  the  modules  will  be 
measured after the test. 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
17 
 
 
Quantity:        2 modules per batch but no less than 1 per MW in average. 
Test Criteria:  STC measurement before and after exposure to bias. Max. 
Power loss < 5%. Exposure 168h at 25°C ‐1000V at inner 
circuit, front glass covered with grounded aluminum foil. 

If the 1 module fails, the batch is rejected 

Test execution:  Test to be done in the onsite laboratory. Time between 
arrivals of container on site to fail report to be minimized 
according to applicable test sequence. 

Annex 1 Technical Specification Appendix D 

QUALITY ASSURANCE & QUALITY CONTROL 
18 

Das könnte Ihnen auch gefallen