TWO-WEEKS LOOK-AHEAD

HOLIDAY INN HOTEL PROJECT, JUBAIL KSA


1st week 2nd Week
Dec-18
Zone Item Activity Location Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri
8/Dec 9/Dec 10/Dec 11/Dec 12/Dec 13/Dec 14/Dec 15/Dec 16/Dec 17/Dec 18/Dec 19/Dec 20/Dec 21/Dec
1 HVAC duct work and insulation Ground & 1st floor
ZONE 3

2 Firefighting work (pipe repainting, fire hose cabinet) 1st, 2nd, 3rd floor
3 Roof waterproofing (membrane+insulattion) Roof & Upper Roof Deck
4 External Plastering work (axis 3 & 1) 1st, 2nd, 3rd & Roof
1 HVAC duct work and insulation Ground & 1st floor
2 Firefighting work (pipe repainting, fire hose cabinet) 1st, 2nd, 3rd floor
ZONE 2

3 Electrical conduits installation First and Second


4 Roof waterproofing (membrane+insulattion) Roof & Upper Roof Deck
5 Internal Plastering work 2nd & 3rd floor
1 CMU block laying 3rd floor
2 Internal Plastering work 2nd & 3rd floor
ZONE 1

3 Roof waterproofing (membrane+insulattion) Roof & Upper Roof Deck


4 Plumbing work (sanitary pipe line) 1st, 2nd, 3rd floor
5 Firefighting work (main fire water line) 1st, 2nd, 3rd floor
1 Shuttering and rebars installation (SCECO, Guard House, Genset, Garbage rm)
External Work

2 Concrete pouring
3 Deshuttering
4 Sanitary piping
5 Backfilling, compaction, termite and rebars installation (grade slab)

Legend :
PLANNED