Date: August 23, 2018

Individual Contribution:
- I organized the meeting to make plan for the semester
- Set up the agenda for the meeting
- Set up the plan for the team this semester
Meeting Attendees: Huy, Jay, Beau, Alvin
Key Accomplishments:
- Getting started for the new semester
- Establish team plan for the semester
- Remind/ update team member on the progress of the project
Key Issues:
- Our team was not able to use the ICE network via browser.
Actions:
- Huy to contact the customer to set up monthly meeting (Target: August 25)
- Jay to contact Prof. Manzo to set up the meeting (Target: August 25)
- Alvin to finish assembling the first beacon (Target: September 7)

Date: August 27, 2018 – meeting with SME


Individual Contribution:
- Report on the beacon progress
- Report on the modulation/demodulation schemes for the beacon
Meeting Attendees: Huy, Jay, Beau, Alvin
Key Accomplishments:
- SME approved the plan the beacon
- Contacted the customer and agreed on the meeting dates
Key Issues:
- Still working on getting the connection from ICEPOD to the computer
Actions:
- Huy to work on the soldering certification (Target: September 7)
- Jay & Beau to contact ICE (Target: August 31)
- Alvin to finish assembling the first beacon (Target: September 7)

Date: August 28, 2018 – meeting with mentor


Individual Contribution:
- Report on the beacon progress
Meeting Attendees: Huy, Jay, Beau, Alvin
Key Accomplishments:
- Went over the semester kick off PowerPoint
- Contacted the customer and agreed on the meeting dates
Key Issues:
- Still working on getting the connection from ICEPOD to the computer
Actions:
- Huy to work on the soldering certification (Target: September 7)
- Jay & Beau to contact ICE (Target: August 31)
- Alvin to finish assembling the first beacon (Target: September 7)

Date: August 29, 2018 – team meeting


Individual Contribution:
- Update on the customer meeting
Meeting Attendees: Huy, Jay, Beau, Alvin
Key Accomplishments:
- Able to observe the radio signal using the ICEPOD
- Able to capture the signal and playback signal using the ICEPOD
- Able to download the signal to local drive to analyze
Key Issues:
- Cannot open the file from ICEPOD
Actions:
- Huy to work on the soldering certification (Target: September 7)
- Jay & Beau to contact ICE (Target: September 7)
- Alvin to finish assembling the first beacon (Target: September 7)

Date: September 5, 2018 – team meeting


Individual Contribution:
- Helped Jay + Beau on obtaining the file from the ICEPOD
- Contacted ICEPOD regarding the ICEPOD issue
- Obtained the soldering certification
Meeting Attendees: Huy, Jay, Beau
Key Accomplishments:
- Documented ICEPOD usage and troubleshooting
- Finished assembling one complete beacon
Key Issues:
- Cannot open the file from ICEPOD
Actions:
- Huy to work on modulation schemes (Target: September 21)
- Jay & Beau to contact ICE (Target: September 14)
- Alvin to finish assembling the second beacon (Target: September 21)

Date: September 10, 2018 – meeting with SME


Individual Contribution:
- Worked on the modulation with SME
- Transmitted and received the signal via the ICEPOD
Meeting Attendees: Huy, Jay, Alvin
Key Accomplishments:
- Documented ICEPOD usage and troubleshooting
- Finished assembling one complete beacon
Key Issues:
- Cannot open the file from ICEPOD
- ICE stops giving support to the project
Actions:
- Huy to work on modulation schemes (Target: October 5)
- Jay & Beau to contact Zeta to receive help (Target: September 21)
- Alvin to finish assembling the second beacon (Target: September 21)

Date: September 17, 2018 – meeting with SME


Individual Contribution:
- Reported on the problem with the ICEPOD
Meeting Attendees: Huy, Jay, Beau
Key Accomplishments:
- Contacted Zeta for supports
- Dr. Beex provided some alternative device to capture the signal
Key Issues:
- ICE stops giving support to the project
Actions:
- Huy, Jay & Beau to resolve the issue with the ICEPOD (Target: September 28)
- Alvin to finish assembling the second beacon, and transmit the GPS signal from the 1st
beacon (Target: September 21)

Date: September 19, 2018 – meeting with the customer


Individual Contribution:
- Reported on the progress of the project
- Reported on the problem with the ICEPOD
Meeting Attendees: Huy, Jay, Beau, Alvin
Key Accomplishments:
- Presented the reported to the customer
- Zeta is satisfied with the progress of the project
Key Issues:
- ICEPOD may be out of order
Actions:
- Huy, Jay & Beau to resolve the issue with the ICEPOD (Target: September 28)
- Alvin to finish assembling the second beacon, and transmit the GPS signal from the 1 st
beacon (Target: September 21)