SINEWAVE BIOMASS POWER PVT. LTD.

SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

ASSESSMENT REPORT

10 MW SINEWAVE BIOMASS POWER PVT. LTD.


TUNG VILLAGE ,

SANGLI, MAHARASTRA

PREPARED BY

DAKSH POWER COMPANY


KOLKATA (INDIA)

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

OBJECTIVES
TO CARRY OUT THE ASSESSMENT OF PROJECT & WORK OUT THE PLAN TO COMPLETE & COMMISSION
THE PLANT

INDEX
1. SYNOPSIS

2. STATUS OF DRAWINGS , PENDING SUPPLIES etc.

3. QUICK MEASURES SUGGESTED FOR SAVING THE CAPEX

4. STATUS OF PROJECT EXECUTION

5. CONTRACTOR STATUS

6. ORGANISATION TO COMPLETE THE PROJECT

7. ORGANISATION TO OPERATE & MAINTAIN THE POWER PLANT

8. INFRASTRUCTURE REQUIRED BEFORE COMMISSIONING OF THE PLANT

9. TENTATIVE SCHEDULE

10. STATUTORY CLEARANCES REQUIRED BEFORE COMMISSIONING

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

01. SYNOPSIS

i. The Power Project was being executed by an EPC company.


ii. There are some issues & EPC company is not delivering the services & goods.
iii. This has delayed the project beyond speculated time.
iv. & the site has been left unmanned by the EPC company.
v. The store was inspected , the material stored was not proper & its list is not available for
assessment.

02. STATUS OF DRAWINGS , PENDING SUPPLIES etc.


i. The Basic Design & Detailed design information not available at site
ii. The related drawings are not available at site.
iii. The pending supplies material list available but it is not authentic & is incomplete. The
complete list is very important for working out the procurement actions.

03. IMMEDIATE ACTIONS


1. Deployment of experienced Engineers (as per organisation chart)
2. Assessment of the drawings / documents & coordination with the EPC contractor , Consulting
engineers to work out mitigation plans.
3. Preparation of Area –wise plug list for material procurement / job completion.
4. Water Treatment lab to be set up immediately & DM Plant to be commissioned before Alkali
Boil out of Boiler.

AFTER DEPLOYMENT
i. Our engineers will work out the list drawings / documents status in 2-3 weeks (will the
prioritized) for immediate actions.
ii. Will prepare area wise plug list in 2-3 weeks time (will the prioritized) for immediate actions.
iii. Will submit the list of equipments for water treatment plant in 3-4 days
iv. Will submit list of tools / tackles etc in 3-4 days.
v. Actions for integration of Fuel Handling system shall be taken up (Separate design agency
needed to be engaged for designing the system)

BUDGETARY COST : For working out the budgetary cost we will be requiring design inputs / authentic
list of balance materials.

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

03. QUICK MEASURES SUGGESTED FOR SAVING THE CAPEX


CONTROL ROOM AIR CONDITIONING

GENERAL PRACTICE : Centralised Air Conditioning System.

Disadvantages
i. Capex is high
ii. Power consumption is high
iii. In case of failure of the system the Power Plant operation will be disrupted

SUGGESTED : In place of centralized AC we should install 10x 2 Tonnes (of Refrigration) split air
conditioners.

Advantages
i. Capex is very low just 20 – 30% of the Centralised AC
ii. Power consumption is lower , because during nights & summers only few ACs need to be
operated.
iii. In case of failure of 1or 2 units , Power Plant operation is not hampered.

NUTRALISING PIT
i. The present neutralizing pit is too big in size & the quality of job done is too bad (gunny
bags are left at RCC joints) this will cause leakage.
ii. The water proofing & further lining with Acid proof bricks will be requiring good investment.

Solution
We need to construct another neutralizing pit & size will be approximately 1/4th of the existing one
, this will be requiring lesser investment in construction as well as acid proof tiling.

USAGE OF PRESENT CEMENT STORAGE FOR FUEL STORAGE


i. The existing cement storage shed can be used for fuel storage & a separate feeding line can
be designed & integrated with the existing feed point to avoid manual handling.
ii. This will save capex on Building bigger size of Fuel storage shed.

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

START UP POWER

Present plan :
Initially to start with 11 KV later on switch over to 132 KV

Our suggestion :
i. Planning for 11 KV will be requiring power feeding arrangement this will attract
capex.
ii. We should straight way apply for 132KV start up Power & the evacuation system can
be used for drawing the strat up power.

Emergency Power
DG Set to be decided immediately – lead time 3 approx. months + integration with the
system 45 days.

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

04. STAUTS OF THE PROJECT EXECUTION

10 MW - SINEWAVE BIOMASS POWER PLANT


ASSESSMENT REPORT
ACTION TO BE
SNO AREA / DESCRIPTION STATUS AGENCY / RESONSIBILITY TAKEN REMARKS
PLANT – LAYOUT
DECISION BASED
ON WATER
WATER ANALYSIS REPORT SCHEME
100% EXCEPT SOFTNER BY SINE WAVE + PRESENT DECISION TO BE
1 LAYOUT TO BE FINALISED WATER P&I TAKEN
PRESENT
CEMENT
STORAGE SPACE THE SUGGESTED
TO BE USED & FUEL STORAGE YARD
CONVEYOR CAN TO BE MATCHED
BE INSTALLED WITH THE
FOR ALTERNATE USE OF
CONNECTING PRESENT CEMENT
2 LAYOUT - FUEL SHED NO ACTION TAKEN SINEWAVE / CVPL FEEDING POINT STORAGE
THIS IS IMPORTANT
ACTIVITY AS THE
SYSTEM NEEDS TO BE
CRUSHER HOUSE DESIGNED ,
WOOD CHIPPER + COAL + SCHEME TO BE INTEGRATED &
3 CRUSHER NO ACTION TAKEN SINEWAVE / CVPL ADDED EXECUTED
CIVIL
POWER HOUSE
BUILDING
ALMOST COMPLETED ,
SOME AREAS FLLORING
1a 00 FLOOR IS IN PROGRESS SINEWAVE / CVPL
CABLE TRENCH
WORK IS BAD AS THE
FLOOR OF TRENCH IS
SINKING , WALLAS
ARE CRACKING &
GETTING WIDE
APART. SLOPE HAS
NOT BEEN
MAINTAINED & WILL
BE SUBJECTED TO
B CABLE TRENCES COMPLETED SINEWAVE / CVPL RAIN WATER ENTRY.
PROPER
REINFORCEMENT TO
C FLOORING IN PROGRESS SINEWAVE / CVPL BE DONE

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

WATER
PROOFING TO BE
DONE + SUMP
D CEP PIT COMPLETED SINEWAVE / CVPL PIT TO BE MADE
E 3.5 MTR FLOOR MAX WORK COMPLETED
OPTION KOTA
STONE / RCC RCC WITH IRON
WITH IRON TOPPING WILL BE
F 8.0 MTRS FLOORING SINEWAVE / CVPL TOPPING ECONOMICAL

FALSE ROOFING -
CLEARANCE
GIVEN FOR
SEMIFINSHED STARING THE
G CONTROL ROOM CONDITION SINEWAVE / CVPL WORK
TO BE STARTED
H FALSE FLOOING PENDING SINEWAVE / CVPL IMMEDIATELY
ARCHITECTURAL DRAWING TO BE NO DRAWINGS WERE
I DRAWING WORK JUST STARTED SINEWAVE / CVPL REVIEWED AVAILABLE AT SITE

CIVIL - FOUNDATIONS
WORK TO BE
1 ASH HANDLING PENDING DRAWINGS AVAILABLE STARTED
DM PLANT
2 CIVIL WORKS FLOORING PENDING SINEWAVE / CVPL
ACID TILING SINEWAVE / CVPL
DARIN ACID PROOF
TILING SINEWAVE / CVPL
INCOMPLETE - SIZE TOO IT CAN BE USED
BIG , NOT TO BE USED FOR SOME
3 NEUTRALISING PIT FOR NP SINEWAVE / CVPL OTHER PURPOSE
SUMP
WATERPROOFIN
G TO BE DONE &
RETURN SUMP
WATER
PROOFING TO BE
TAKEN UP
4 COOLING TOWER ALMOST COMPLETED SINEWAVE / CVPL IMMEDIATELY
AREAS NEAR COOLING
5 TOWER FLOORING PENDING SINEWAVE / CVPL TO BE TAKEN UP
EXCEPT CRUSHER
HOUSE + CHIPPER TO
6 FUEL HANDLING SYSTEM CIVIL COMPLETED SINEWAVE / CVPL BE ADDED
THIS WILL BE
REQUIRED FOR
TO BE STARTED QUICK & SAFE
7 PLANT ROAD NO ACTION SINEWAVE IMMEDIATELY COMMISSIONING &

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

OPERATION OF THE
PLANT

TURBINE
BEARINGS & EXCITOR
ARE IN OPEN
CONDITION THIS
MAY LEAD TO
DAMAGE OF
1 TG PLACED ON FOUDATION SINEWAVE / CVPL BERAINGS / EXCITOR
OIL PIPE WAS IN
PROGRESS NOW
2 TG OIL PIPING STOPPED SINEWAVE / CVPL
BOTTOM FLANGES
ARE CUT BY GAS ,
THIS IS A BAD
3 CONDENSER PLACED ON FOUDATION SINEWAVE / CVPL PRACTICE
SOLE PLATE TO BE
CONDENSER INSTALLED SINEWAVE / CVPL
BELLOW TO BE
CONDENSER CONNECTED SINEWAVE / CVPL
CONDENSER GROUTING TO BE DONE SINEWAVE / CVPL
4 CONDESATE PIPING TO BE STARTED SINEWAVE / CVPL
SWPL
INFORMED THAT
ALL PIPES DRAWINGS WERE
TURBINE AUX STEAM APPROVED BY NOT AVAILABLE AT
5 PIPING TO BE STARTED SINEWAVE / CVPL IBR SITE
SWPL
INFORMED THAT
ALL PIPES DRAWINGS WERE
OTHER STEAM & IBR APPROVED BY NOT AVAILABLE AT
6 PIPING IN PROGRESS SINEWAVE / CVPL IBR SITE
CVPL TO SUBMIT THE
DOCUMENTS – ENGG
QA FOR STEAM & IBR CONSULATANT TO
7 PIPING NOT KNOWN REVIEW & APPROVE TO BE CHECKED

BOP

SS BOLTS 2000 NOS TO


BE INSTERED FOR FIXING TO BE STATED
1 COOLING TOWER SPLASH BAR SINEWAVE / CVPL IMMEDIATELY
PVC FILLS TO BE
INSTALLED + DECK TO BE STATED
NOZZLES SINEWAVE / CVPL IMMEDIATELY
PUMPS PLACED ON
2 PUMPS FOUNDATION SINEWAVE / CVPL

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

THE PIPE ARE LAID


WITHOUT SADDLE
SUPPORTS , THIS IS
CAUSING THE PIPE
TO OVERHUNG.
THERE IS ELEVATION
,MISMATCH
BETWEEN PIPE &
DISCHARGE FLANGE
OF MCW PUMPS. IF
DONE IN THIS WAY
MAIN COOLING WATER THERE WILL BE
PIPING WORK IS IN ENARMOUS STRESS
3 LP PIPING PROGRESS SINEWAVE / CVPL ON PUMPS
BOILER
THE PUNCH LIST TO
ALMOST COMPLETE – BE PREPARED FOR
PATCH –UP ITEMS TO BE CARRYING OUT
1 BOILER ERECTION LISTED OUT SINEWAVE / CVPL PATCH UPS
THE PUNCH LIST TO
BE PREPARED FOR
CARRYING OUT
2 DUCTINGS COMPLETE SINEWAVE / CVPL PATCH UPS
THIS WILL TAKE
APPROX 3MONTHS ,
SO TO BE STARTED
3 INSULATION TO BE STARTED SINEWAVE / CVPL IMMEDIATELY
BOILER - AUXILIARIES
PLACED ON
1 HP DOSING FOUNDATION SINEWAVE / CVPL
PIPING TO BE DONE SINEWAVE / CVPL
LOCATION DECIDED
NEAR BOILER FEED
2 LP DOISING PUMPS SINEWAVE / CVPL
PIPING TO BE DONE SINEWAVE / CVPL
PLACED ON
3 ID FANS FOUNDATION SINEWAVE / CVPL
PLACED ON
4 MOTORS FOUNDATION SINEWAVE / CVPL
PLACED ON
5 PA & SA FANS FOUNDATION SINEWAVE / CVPL
PLACED ON
6 PA & SA FANS MOTORS FOUNDATION SINEWAVE / CVPL

MISC
HOPPER GATES BOILER
1 & ESP NOT ERECTED SINEWAVE / CVPL
2 PIPE SUPPORTS NOT ERECTED SINEWAVE / CVPL

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

3 STEAM PIPING INCOMPLETE SINEWAVE / CVPL


4 BOILER FEED PIPING INCOMPLETE SINEWAVE / CVPL
5 BFW SUCTION PIPING IN COMPLETE SINEWAVE / CVPL
FOUNDATION TO BE
6 ESP DUCTING SUPPORTS GROUTED SINEWAVE / CVPL

ASH HANDLING
ERECTED MINOR JOBS SINEWAVE / CVPL or
1 SILO PENDING CVPL’S SUB VENDOR
SINEWAVE / CVPL’S SUB
2 ASH VESSELS NOT RECD VENDOR
SINEWAVE / CVPL’S SUB
3 CONVEYING PIPING NOT RECD VENDOR
SINEWAVE / CVPL’S SUB
4 DOME VALVES NOT RECD VENDOR
5 COMPRESSOR STATUS NOT KNOWN SINEWAVE / CVPL

FUEL HANDING
FINAL PLUG LIST
TO BE PREPARED
AFTER
DEPUTING
1 CONVEYOR GALLERY ALMOST COMPLETED SINEWAVE / CVPL ENGRS
SPECS TO BE FROZEN
IMMEDIATELY &
PROCUREMENT
ACTION TO BE
2 CUTTERS NO ACTION TAKEN SINEWAVE / CVPL INITIATED
DRAWINGS TO BE
FROZEN
NO ACTION TAKEN - IMMEDIATELY &
LIST IS AVAILABLE – PROCUREMENT
DRAWINGS ARE NOT ACTION TO BE
3 PULLEYS AVAILABLE SINEWAVE / CVPL INITIATED
DRAWINGS TO BE
FROZEN
NO ACTION TAKEN - IMMEDIATELY &
LIST IS AVAILABLE – PROCUREMENT
PULLEY DRAWINGS ARE NOT ACTION TO BE
4 FRAMES/CARRIERS AVAILABLE SINEWAVE / CVPL INITIATED
DRAWINGS TO BE
FROZEN
IMMEDIATELY &
PROCUREMENT
ACTION TO BE
5 WEIGHYERS NO ACTION TAKEN SINEWAVE / CVPL INITIATED

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

COAL FEEDING CIRCUIT


FINAL PLUG LIST
TO BE PREPARED
AFTER
DEPUTING
1 CONVEYOR GALLERY ALMOST COMPLETED SINEWAVE / CVPL ENGRS
SPECS TO BE FROZEN
IMMEDIATELY &
CRUSHERS & CRUSHING PROCUREMENT
SYSTEM INTEGRATION ACTION TO BE
2 WITH THE MAIN STREAM NO ACTION TAKEN SINEWAVE INITIATED
SCHEME TO BE
FROZEN
IMMEDIATELY ,
ENGINEERING TO BE
DONE & EXECUTION
CRUSHER HOUSE NO ACTION TAKEN SINEWAVE TO BE STARTED
ACTION FOR
SCREENS / GRIZZLEY SCREEN/ GRIZZLEY IS STARTING THE JOB
3 FEEDERS LYING SINEWAVE / CVPL TO BE TAKEN
SPECS TO BE FROZEN
IMMEDIATELY &
PROCUREMENT
ACTION TO BE
4 PULLEYS NOT AVAILABLE SINEWAVE / CVPL INITIATED
SPECS TO BE FROZEN
IMMEDIATELY &
PROCUREMENT
PULLEY ACTION TO BE
5 FRAMES/CARRIERS NOT AVAILABLE SINEWAVE / CVPL INITIATED
SPECS TO BE FROZEN
IMMEDIATELY &
PROCUREMENT
ACTION TO BE
6 WEIGHYERS NOT AVAILABLE SINEWAVE / CVPL INITIATED
WEAR PLATES TO BE
7 RCC HOPPERS GROUND INSATLLED SINEWAVE / CVPL
8 MAGNETIC PICK UP STATUS NOT KNOWN SINEWAVE / CVPL
GROUND HOPPER TO
TAKE OFF GALLERY
STRUCTURE SUPPORT
9 FOOTINGS NOT DONE SINEWAVE / CVPL
GROUND HOPPER TO BE TAKEN
10 WATER PROOFING IMMEDIATELY SINEWAVE / CVPL
SEPARATE CKT. FOR COAL TO BE TAKEN
11 CRUSHER IMMEDIATELY SINEWAVE
MODIFICATION/LOCATIO TO BE TAKEN
12 N OF WOOD CHIPPER IMMEDIATELY SINEWAVE

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

UTILIZATION OF OLD TO BE TAKEN DESIGNER TO BE


13 SHED FOR FUEL STORAGE IMMEDIATELY SINEWAVE ENGAGED FOR
COAL CRUSHER TO BE INTEGRATING
ADDED INTO THE TO BE TAKEN THE EXISTING
14 CIRCUIT IMMEDIATELY SINEWAVE SYSTEM
SPECS TO BE FROZEN
IMMEDIATELY &
PROCUREMENT
NOT AVAILABLE , NO ACTION TO BE
15 CONVEYOR BELTS SPECS AVAILABLE SINEWAVE / CVPL INITIATED
WATER TREATMENT
PLANT
RECD IN BAD
CONDITION , SOME
RUBBER LINING TO BE
1 VESSELS TAKEN UP SINEWAVE / CVPL
PART RECD , APPROX
2 MSRL PIPING 20% ERECTED SINEWAVE / CVPL
PLACED ON
3 RO SKID FOUNDATIONS SINEWAVE / CVPL
TOTAL SCHEME TO
BE REVIEWED &
WATER BALANCE TO
4 SOFETNER STATUS NOT KNOWN SINEWAVE / CVPL BE DONE
5 SIDE STREAM FILTER INSTALLED
TO BE SET UP
IMMEDIATELY
FOR
COMMSSIONING
6 WATER TREATMENT LAB DM PLAT
ELECTRICAL &
INSTRUMENTATION
1 MCC PANELS RECD
2 HT PANELS RECD
BOM AVAILABLE PO TO
3 HT CABLES BE PLACED
SOME RECD - BALANCE
4 LT CABLES TO BE PROCURED
INSTRUMENTATION SOME RECD - BALANCE
5 CABLES TO BE PROCURED
MAX RECD , WE CAN
PROCURE ADDITIONAL
BASED ON THE
6 CABLE TRAY REQUIREMENT
SOME RECD , BoM & P&I
7 BoP INSTRUMENTS NOT AVAILABLE

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

8 TRANSFORMERS
PLACED ON
a AUX TRANSFORMER FOUNDATION
b GT READY FOR DISPATCH
SWITCH YARD
TOTAL TIME TO
OUT OF 4 THREE ARE COMPLETE
1 TOWERS CLEAR FOR ERECTION 2MONTHS GOOD PROGRESS
2 FOUNDATIONS DONE
TOWER ASSEMBLY TO
BE STARTED
3 SWITCH YARD
a TOWERS ERECTED
INSPECTION BY MSDCL
b INSULATORS COMPLETD
c CT / PT etc AVAILABLE AT SITE
EASILY AVAILABEL WILL
d ENERGY METER BE PROCURED LATER
EASILY AVAILABEL WILL
e BARE CONDUCTORS BE PROCURED LATER
2.5 MONTHS ,
TIME REQUIRED TO INCLUDING CEIG
f COMPLETE THE JOB APPROVAL
INFRASTRUCTURE
REQUIRED
AS THE AREA IS
PRONED TO
FLOODING , STORM
DRAINS & ARTERIAL
DRAINS ARE
REQUIRED TO BE
COMPLETED BEFORE
1 STROM WATER DRAINS RAINS
2 PLANT DRAINS AS ABOVE
REQUIRED FOR
SMOOTH & SAFE
PHERIPHERAL PLANT OPERATION OF THE
3 ROAD PLANT

ADVISE FOR
IMPROVEMENT
THIS WILL SAVE THE
10X 2TONNES SPLIT AIR CAPEX BY 90% +
CONTROL ROOM AIR CONDITIONERS IN PLACE PART OPERATION
1 CONDITIONING OF SPLIT AC WILL SAVE ENERGY

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

WATER PROOFING TO
BE DONE + DRAIN PIT
2 CEP PIT FOR PUMPING OUT
THE PRESENT NP
SIZE IS TOO BIG , SHALL WILL BE USED FOR
BE USED FOR SOME SOME BETTER
3 NEUTRALISING PIT OTHER PURPOSE PURPOSE
THE SCHEME WAS NOT
AVAILABLE TO BE
REVIEWED & IF REQD THIS SCHEME IS VERY
WATER TREATMENT SCHEME CHANGES WILL IMPORTANT TO BE
4 SCHEME BE DONE REVIEWED

SUGGESTED TO GO
FOR 132KV ONLY , AS
THIS IS RELIABLE &
OPTIONS 11 KV & 132 THE SAME CIRCIUT
6 START UP POWER KV CAN BACK FEED

TO BE MODIFIED AS PER 500 KVA DECISION


7 FUEL FEEDING CIRCUIT ABOVE TO BE TAKEN
IMMEDIATE ACTION
8 EMERGENCY DG SET IN SCOPE OF CVPL TO BE TAKEN

ASSESSORIES FOR
SYNCHRONISING WITH
9 TG & EMERGENCY DG IN SCOPE OF CVPL

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

05. CONTRACTOR STATUS


ACTION TO BE
SNO AREA / DESCRIPTION STATUS AGENCY / RESONSIBILITY TAKEN REMARKS

AT PRESENT THERE ARE


1 MAIN EPC CONTRACTOR ISSUES TO BE RESOLVED SWPL
TEAM NEED TO
STRENGTHENED
FOR CARRYING BAD ERECTION
OF MECH & PRACTICES , TO BE
SOBHAN ENGG. – UNDER CONTROL OF ELECTRICAL JOBS CORRECTED
2 TURBINE MOBILISED CVPL PARALLELY IMMEDIATELY

C MOHAMMAD
DEMOLISED , TOOLS & UNDER CONTROL OF PLUG LIST JOBS
3 BOILER TACKLES ARE AT SITE CVPL TO ATTENEDED
NEEDED TO BE
MOBILSED
IMMEDIATELY
CONTRCATOR UNDER CONTROL OF FOR STARTING
4 COOLING TOWER DEMOBILISED CVPL THE JOB
BAD QUALITY OF
WORK , PROPER PIPE
SUPPORTING NO
DONE, MISMATCH
BETWEEN THE PIPE &
SOBHAN ENGG. – UNDER CONTROL OF PUMP FLANGE
5 PIPING ACW & MCW MOBILISED CVPL ELEVATION
NEEDED TO BE
MOBILSED
IMMEDIATELY
BD ENTERPISES – FOR STARTING BAD QULAITY OF
6 DM PLANT DEMOBILISED THE JOB WORK
NEEDED TO BE
RK & RKUMAR MOBILSED
DEMOBILSED , WILL IMMEDIATELY
REACH SITE ONCE WE FOR STARTING
7 ELECTRICALS & INSTT GIVE CLEARNCE THE JOB
CONTRACTOR
NEEDED TO
FINALISED IMPORTANT
IMMEDIATELY ACITIVITY TO BE
FOR STARTING COMPLETED BEFORE
8 INSULATION TO BE TAKEN UP THE JOB TRAILS START
CONTRACTOR IMPORTANT
9 ILLUMINATION TO BE TAKEN UP NEEDED TO BE BECAUSE

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

FINALISED ILLUMINATION IS
MUST FOR STARTING
THE TRAILS
LOCAL SMALL
TIME TO BE
ENGAGED TO
CARRY OUT THE UNIT RATE CAN BE
PETTY JOBS LEFT DECIDED & OPEN
PETTY MECH BY OTHER CONTRACT CAN BE
10 CONTRACTOR PARTIES AWARDED
TARGET TIME TO
THE PRESENT COMPLETE THE JOB
CONTRACTOR IS WITH CEIG
SWITCH YARD & COMPLETING THE JOB APPROVALS – 2.5 TO
11 TRANSMISSION LINE EFFICIENTLY 3.0 MONTHS

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

06. ORGANISATION TO COMPLETE THE PROJECT


(AS PER ANNEURE – 01)

07. ORGANISATION TO OPERATE & MAINTAIN THE POWER PLANT


(AS PER ANNEURE – 02)

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

08. INFRASTRUCTURE REQUIRED BEFORE COMMISSIONING OF THE PLANT

S.No FACILITIES TO BE CREATED ON PRIORITY REMARKS


NO GOOD HOTEL / RESTAURANT IS AVAILABLE NEARBY
1 CANTEEN FACILITIES THIS IS VERY IMPORTANT TO SAVE TIME
BOLERO (INITIALLY 1NO & BEFORE
2 COMMISSIONING - 2NOS) REQUIRED FOR COMMUTING
3 TOILETS FOR WORKMEN BASIC NEED
4 REST ROOMS FOR 5-6 PERSONS DURING COMMISSIONS & OPERATIONS
FOR TRIAL & COMMISSIONING OF THE SYSTEMS &
5 WALKIE TALKIE PLANT
FOR TRIAL & COMMISSIONING OF THE SYSTEMS &
6 PA SYSTEM PLANT
GUEST HOUSE FOR 50 PERSONNEL
(COMPRISING OF 3HoD + 25 ENGINEERS & THIS WILL BE REQUIRED BEFORE DEPUTATION OF O&M
7 BALANCE TECHNICIANS) PERSONNEL
8 POTABLE WATER SYSTEM FOR DRINKING

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

09. TENTATIVE SCHEDULE

i. Completion of the project : 14 – 16 weeks


ii. Trials of indivisual equipments : 8-10 weeks
iii. Pre Commissioning : 08 – 10 weeks

Total : 22- 26 weeks

We will plan parallel activities based on the site movement & will try to squeeze the time for putting the
plant into operation.

Subjective Conditions :
i. Availability of documents / drawings / design inputs
ii. Material flow as per requirement
iii. Contractor engagement as per requirement
iv. Manpower deputation as per requirement

DAKSH POWER CO. A 15 MILLENIUM APARTMENTS , 23 KALIBARI LANE JADAVPUR,


KOLKATA - 70032
SINEWAVE BIOMASS POWER PVT. LTD.
SITE ASSESSMENT REPORT – 10 MW BIO MASS POWER PLANT

11.STATUTORY CLEARANCES REQUIRED BEFORE COMMISSIONING

GENERAL
APPLICATION TO SPCB FOR CFO (CONSENT TO OPERATE)

BOILER
IBR APPROVALS (THIS CAN BE INITIATED ONLY AFTER COMPLETION OF ALL IBR JOBS)

ELECTRICAL
CEIG APPROVALS FOR

1. COMPLETE HT SYSTEM
2. COMPLETE LT SYSTEM
3. SWITCH YARD
4. TRANSMISSION LINE
5. ISSUANCE OF SAFETY CERTIFICATE

Line – tie permission for synchronizing the plant with grid as well as power drawl from grid for starting
the plant.

Power Sanction for start up : To be in place before starting up the trails.

Power Purchase Agreement : to be signed immediately

AVIATION :
Since the site is not near any airport (as per the information sought from site people) , aviation
clearance is not mandatory , but fixing of aviation lamps on Chimney is mandatory.

Site Visit dates : 21st & 22nd Dec 2012


DAKSH Executives visited :
Mr Shashi Chaurasia (CEO) & Mr Shailesh (Vice President Thermal Power)

Report prepared & submitted by

DAKSH POWER CO.


Dated 28th Dec 2012