 MOBILISATION PLAN

Sl no Activity Name Original Duration Start Finish

MOBILISATION 60 1‐Dec‐17 30‐Jan‐18

1‐Dec‐17 21‐Dec‐17
Site Infrastructure Development 20

1 Preparation of roads to office and site vehicular movement 10 1‐Dec‐17 11‐Dec‐17

Preparation of site boundary barrication with GI Sheets or compund  8 6‐Dec‐17 14‐Dec‐17


2 wall /Gates for vehicular movement
Preparation of Ground for site office/store room/material stack 
10 9‐Dec‐17 19‐Dec‐17
3 room 

4 Vehicle Parking area Development 7 14‐Dec‐17 21‐Dec‐17

5 Drainage and water supply system for labours/Staff 5 11‐Dec‐17 16‐Dec‐17

14‐Dec‐17 13‐Jan‐18
ORGANISATION & DESIGN 30
Submission & Approval of contractor execution plan, quality  30 14‐Dec‐17 13‐Jan‐18
1 plan,HSE Plan & Baseline Prog.

2 Mobilization of key personnel  8 14‐Dec‐17 22‐Dec‐17

3 Submission & approval of Design report 15 17‐Dec‐17 1‐Jan‐18


 MOBILISATION PLAN
Sl no Activity Name Original Duration Start Finish

Site office /Engineers Office Development 45 16‐Dec‐17 30‐Jan‐18

1 Set up of portcabin installation 25 16‐Dec‐17 10‐Jan‐18


2 All plumbing & Electrical fit‐out works 10 23‐Dec‐17 2‐Jan‐18
3 office furniture facility set‐out 10 30‐Dec‐17 9‐Jan‐18
4 Installation of all Electrionic equipments(PC,AC etc.) 6 9‐Jan‐18 15‐Jan‐18
5 Arrangement for supply of power & water  8 15‐Jan‐18 23‐Jan‐18
6 development of staff/labourers toilet facility 15 23‐Dec‐17 7‐Jan‐18
7 Medical/first Aid facility room development 15 7‐Jan‐18 22‐Jan‐18
8 Construction of store room 10 12‐Jan‐18 22‐Jan‐18
9 Construction of materials stacking yard 10 7‐Jan‐18 17‐Jan‐18
10 Construction of security cabin  10 20‐Jan‐18 30‐Jan‐18
11 Development of hard scape around the site office 10 20‐Jan‐18 30‐Jan‐18