M/s Shapoorji Pallonji Real Estate M/s Shapoorji Pallonji Engineering & Construction

JOY VILLE TOWER 6


Name of Work : ELECTRICAL WORKS
PROJECT

Location : Joy Ville - Virar West.

6th FLOOR

Contractor : M/S ELECTROM ENGINEERING (I) PVT.LTD.

Site Conditions:
SITE

Normal Day Rainy Day

WORK ACTIVITY Qty TODAY


LOCATION UOM
PROGRESS DESCRIPTION T C B PLANNED

Back Box Fixing Nos. 14 14 0 0


Vertical Conduiting Nos. 25 25 0 0
1 2 BHK ( L) Apt -1
Slab Conduiting Pts 28 0 28 28
Rope Pulling 4rd FLOOR Pts 28 28 0 0
Back Box Fixing Nos. 12 12 0 0
Vertical Conduiting Nos. 22 22 0 0
2 2 BHK ( S) Apt -2
Slab Conduiting Pts 26 0 26 26
Rope Pulling 4rd FLOOR Pts 26 26 0 0
Back Box Fixing Nos. 12 12 0 0
Vertical Conduiting Nos. 22 22 0 0
3 2 BHK ( S) Apt -3
Slab Conduiting Pts 26 0 26 26
Rope Pulling 4rd FLOOR Pts 26 26 0 0
Back Box Fixing Nos. 14 14 0 0
Vertical Conduiting Nos. 25 25 0 0
4 2 BHK ( L) Apt -4
Slab Conduiting Pts 28 0 28 28
Rope Pulling 4rd FLOOR Pts 28 28 0 0
Back Box Fixing Nos. 14 14 0 0
Vertical Conduiting Nos. 25 25 0 0
5 2 BHK ( L) Apt -5
Slab Conduiting Pts 28 0 28 28
Rope Pulling 4rd FLOOR Pts 28 28 0 0
Back Box Fixing Nos. 12 12 0 0

6 2 BHK ( S) Apt -6
Vertical Conduiting Nos. 22 22 0 0
6 2 BHK ( S) Apt -6
Slab Conduiting Pts 26 0 26 26
Rope Pulling 4rd FLOOR Pts 26 26 0 0
Back Box Fixing Nos. 12 12 0 0
Vertical Conduiting Nos. 22 22 0 0
7 2 BHK ( S) Apt -7
Slab Conduiting Pts 26 0 26 26
Rope Pulling 4rd FLOOR Pts 26 26 0 0
Back Box Fixing Nos. 14 14 0 0
Vertical Conduiting Nos. 25 25 0 0
8 2 BHK ( L) Apt -8
Slab Conduiting Pts 28 0 28 28
Rope Pulling 4rd FLOOR Pts 28 28 0 0
DESCRIPTION Unit Received Consumed Balance
1 25 mm Black Conduit Mtr 6900 4115 2785

2 25 mm Grey Conduit Mtr 900 0 900

3 20 mm Black Conduit Mtr 10800 7560 3240

4 20 mm Grey Conduit Mtr 4500 2324 2176

5 32 mm Black Conduit Mtr 2000 1406 594

6 2 M GI BACK BOX Nos 500 330 170

7 3 M GI BACK BOX Nos 250 128 122

8 4 M GI BACK BOX Nos 70 24 46

9 6M GI BACK BOX Nos 150 140 10

10 8M GI BACK BOX Nos 170 116 54

11 12 M GI Back BOX Nos 30 0 30

Note : - Site Related Issue to be written with justifications for Prepared by:
improvements w.r.t Agency.
Miss.Priyanka
CONSTRAINTS

___________________

Date:
DAILY PROGRESS REPORT
DATE:- 10/7/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date 16th April 2018

Contract Completion _As per W_

ons: Slushy Dry

TODAY TOTAL MANPOWER


TOMORROW
TILL
PLANNED
ACHIEVED ACHIEVED PLANNED ACHIEVED 8M 6M 4M

14 0% 100% 3 2 1

25 0% 100%

0 100% 0%

28 0% 100%

12 0% 100% 1 3

22 0% 100%

0 100% 0%

26 0% 100%

12 0% 100% 1 3

22 0% 100%

0 100% 0%

26 0% 100%

14 0% 100%

25 0% 100%

0 100% 0%

28 0% 100%
3 3
14 0% 100%

25 0% 100%

0 100% 0%

28 0% 100%

12 0% 100%
22 0% 100%

0 100% 0%

26 0% 100%

12 0% 100%

22 0% 100%

0 100% 0%

26 0% 100%

14 0% 100%

25 0% 100%

0 100% 0%

28 0% 100%

Note :-

1. All the Work Permits are prepared before sign off

2.Tool Box Talk is Conducted on Daily Basis & submitted

3.Head Count is taken before signing off this DPR.

4.Everyday evening the activity for the next day is planned 5 o clock

with Spcl & team for co-ordination.

5. Workfronts are discussed and forecasted to optimize labour


resources
6.Any shortage of Materials will be informed in advance atleast 3 - 4
Weeks

2 weeks before based on the available Data.

Checked by Approved by

Mr.Benadict Joshua Mr.Sagar A L

___________________ ___________________

Date: Date:
3M 1&2M

2 6

2 5

3 5
M/s Shapoorji Pallonji Engineering & DAIL
M/s Shapoorji Pallonji Real Estate
Construction DATE:-

JOY VILLE TOWER 7 FORMAT NO

Name of Work : ELECTRICAL WORKS


PROJECT

Location : Joy Ville - Virar West.

9th FLOOR

Contractor : M/S ELECTROM ENGINEERING (I) PVT.LTD.

Site Conditions:
SITE

Normal Day Rainy Day

WORK ACTIVITY Qty TODAY


PROGRESS LOCATION UOM
DESCRIPTION T C B PLANNED ACHIEVED

Back Box Fixing Nos. 12 12 0 0 12


Vertical Conduiting Nos. 24 24 0 0 24
1 3 BHK Apt -1
Slab Conduiting Pts 29 29 0 0 29
Rope Pulling 7th FLOOR Pts 29 29 0 0 29
Back Box Fixing Nos. 12 12 0 0 12
Vertical Conduiting Nos. 22 22 0 0 22
2 2 BHK ( S) Apt -2
Slab Conduiting Pts 26 26 0 0 26
Rope Pulling 7th FLOOR Pts 26 0 26 26 0
Back Box Fixing Nos. 14 14 0 0 14
Vertical Conduiting Nos. 25 25 0 0 25
3 2 BHK ( L) Apt -3
Slab Conduiting Pts 28 28 0 0 28
Rope Pulling 7th FLOOR Pts 28 0 28 28 0
Back Box Fixing Nos. 14 14 0 0 14
Vertical Conduiting Nos. 25 25 0 0 25
4 2 BHK ( L) Apt -4
Slab Conduiting Pts 28 28 0 0 28
Rope Pulling 7th FLOOR Pts 28 0 28 28 0
Back Box Fixing Nos. 12 12 0 0 12
Vertical Conduiting Nos. 22 22 0 0 22
5 2 BHK ( S) Apt -5
Slab Conduiting Pts 26 26 0 0 26
5 2 BHK ( S) Apt -5

Rope Pulling 7th FLOOR Pts 26 0 26 26 0


Back Box Fixing Nos. 12 12 0 0 12
Vertical Conduiting Nos. 24 24 0 0 24
6 3 BHK Apt -6
Slab Conduiting Pts 29 29 0 0 29
Rope Pulling 7th FLOOR Pts 29 29 0 0 29
DESCRIPTION Unit Received Consumed Balance
1 25 mm Black Conduit Mtr 6900 4115 2785

2 25 mm Grey Conduit Mtr 900 0 900 Note :-

3 20 mm Black Conduit Mtr 1080 7560 -6480

4 20 mm Grey Conduit Mtr 4500 2324 2176 1. All the Work Perm

5 32 mm Black Conduit Mtr 2000 1406 594 2.Tool Box Talk is C

6 2 M GI BACK BOX Nos 500 330 170 3.Head Count is tak

7 3 M GI BACK BOX Nos 280 128 152 4.Everyday evening

8 4 M GI BACK BOX Nos 70 24 46 with Spcl & team fo

5. Workfronts are d
9 6M GI BACK BOX Nos 150 140 10 resources
6.Any shortage of M
10 8M GI BACK BOX Nos 170 116 54 Weeks

11 12 M GI Back BOX Nos 30 0 30 2 weeks before bas

Note : - Site Related Issue to be written with justifications for


improvements w.r.t Agency.
Prepared by: Checked

Miss.Priyanka Mr.Benadict J
CONSTRAINTS

___________________ ____________

Date: Date:
DAILY PROGRESS REPORT
DATE:- 10/7/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date 16th April 2018

Contract Completion _As per W_

Slushy Dry

TOTAL MANPOWER
TOMORROW
TILL
PLANNED
ACHIEVED PLANNED ACHIEVED 8M 6M 4M 3M

1 3 3
0% 100%

0% 100%

0% 100%

0% 100%
1 3 2
0% 100%

0% 100%

0% 100%

100% 0%
1 3 3
0% 100%

0% 100%

0% 100%

100% 0%
6 6
0% 100%

0% 100%

0% 100%

100% 0%

0% 100%

0% 100%

0% 100%
100% 0%

0% 100%

0% 100%

0% 100%

0% 100%

:-

the Work Permits are prepared before sign off

ol Box Talk is Conducted on Daily Basis & submitted

ad Count is taken before signing off this DPR.

eryday evening the activity for the next day is planned 5 o clock

Spcl & team for co-ordination.

orkfronts are discussed and forecasted to optimize labour


urces
y shortage of Materials will be informed in advance atleast 3 - 4
ks

eks before based on the available Data.

Checked by Approved by

Mr.Benadict Joshua Mr.Sagar A L

_________________ ___________________

e: Date: