SITE PROGRESS ACTVITIES

CLUSTER E

EXCAVATION OF ANTITERMITE PROOFING OF ANTITERMITE PROOFING AND


10 M VILLA # LAYOUT FOOTING PCC FOOTING Watar Proofing Membrane Screed of Raft
FOOTING FOOOTING PCC OF RAFT

E144 100% 100% 100% 100% 100% 100% 100%

E143 100% 100% 100% 100% 100% 100% 100%

E142 100% 100% 100% 100% 100% 100% 100%

E141 100% 100% 100% 100% 100% 100% 100%

E140 100% 100% 100% 100% 100% 100%

E139 100% 100% 100% 100% 100% 100%

E138 100% 100% 100% 100% 100% 100%

E137 100% 100% 100% 100% 100% 100%

E136 100% 100% 100% 100% 100%

E135 100% 100% 100% 100% 100%

E134 100% 100% 100% 100% 100%

E133 100% 100% 100% 100% 100%

E132 100% 100% 100% 100% 100%

E131 100% 100% 100% 100% 100%

E130 100% 100% 100% 100%

E129 100% 100% 100% 100%

E128 100% 100% 100% 100%

E127 100% 100% 100% 100%

E126 100% 100% 100% 100%

E126A 100% 100% 100% 100%

E125 100% IN PROGRESS IN PROGRESS

E124 100% IN PROGRESS IN PROGRESS

E123 100% IN PROGRESS IN PROGRESS

E122 100% IN PROGRESS IN PROGRESS

CLUSTER B
Excavation of Villa # 21 of 4 K (A) and Villa# 08 of 8 k (A) is in progress.

Page 5