M/s Shapoorji Pallonji Engineering & DAILY P

M/s Shapoorji Pallonji Real Estate


Construction DATE:-

JOY VILLE TOWER 6 FORMAT NO. SPC

Name of Work : ELECTRICAL WORKS


PROJECT

Location : Joy Ville - Virar West.

Contractor : M/S ELECTROM ENGINEERING (I) PVT.LTD.

Site Conditions:
SITE

Normal Day Rainy Day

WORK ACTIVITY Qty TODAY


LOCATION UOM
PROGRESS DESCRIPTION T C B PLANNED ACHIEVED

Back Box Fixing Nos. 14 14 0 0 14


1
Vertical Conduiting
2 BHK ( L) Apt -1 Nos. 25 0 25 25 0
Slab Conduiting Pts 28 25 3 3 25
Rope Pulling Pts 28 0 28 28 0
Back Box Fixing Nos. 12 12 0 0 12
Vertical Conduiting Nos. 22 18 4 4 18
2 2 BHK ( S) Apt -2
Slab Conduiting Pts 26 18 8 8 18
Rope Pulling Pts 26 0 26 26 0
Back Box Fixing Nos. 12 12 0 0 12
Vertical Conduiting Nos. 22 20 2 2 20
3 2 BHK ( S) Apt -3
Slab Conduiting Pts 26 20 6 6 20
Rope Pulling Pts 26 0 26 26 0
Back Box Fixing Nos. 14 14 0 0 14
Vertical Conduiting Nos. 25 25 0 0 25
4 2 BHK ( L) Apt -4
Slab Conduiting Pts 28 28 0 0 28
Rope Pulling Pts 28 0 28 28 0
Back Box Fixing Nos. 14 14 0 0 14
Vertical Conduiting Nos. 25 24 1 1 24
5 2 BHK ( L) Apt -5
Slab Conduiting Pts 28 27 1 1 27
Rope Pulling Pts 28 0 28 28 0
Back Box Fixing Nos. 12 12 0 0 12
6
Vertical Conduiting
2 BHK ( S) Apt -6 Nos. 22 20 2 2 20
Slab Conduiting Pts 26 20 6 6 20
Rope Pulling Pts 26 0 26 26 0
Back Box Fixing Nos. 12 12 0 0 12
7
Vertical Conduiting
2 BHK ( S) Apt -7 Nos. 22 0 22 22 0
Slab Conduiting Pts 26 0 26 26 0
Rope Pulling Pts 26 0 26 26 0
Back Box Fixing Nos. 14 14 0 0 14
8
Vertical Conduiting
2 BHK ( L) Apt -8 Nos. 25 0 25 25 0
Slab Conduiting Pts 28 0 28 28 0
Rope Pulling Pts 28 0 28 28 0
DESCRIPTION Unit Received Consumed Balance
1 25 mm Black Conduit Mtr 2400 1170 1230

2 25 mm Grey Conduit Mtr 900 0 900 Note :-

3 20 mm Black Conduit Mtr 4800 1050 3750

4 20 mm Grey Conduit Mtr 1500 600 900 1. All the Work Permits a

5 32 mm Black Conduit Mtr 2000 200 1800 2.Tool Box Talk is Condu

6 2 M GI BACK BOX Nos 500 72 428 3.Head Count is taken b

7 3 M GI BACK BOX Nos 280 41 239 4.Everyday evening the

8 4 M GI BACK BOX Nos 30 4 26 with Spcl & team for co-o

5. Workfronts are discus


9 6M GI BACK BOX Nos 150 38 112 resources
6.Any shortage of Mater
10 8M GI BACK BOX Nos 70 22 48 Weeks

11 12 M GI Back BOX Nos 30 0 30 2 weeks before based o

Note : - Site Related Issue to be written with justifications for Approved by Prepared by:
improvements w.r.t Agency.
Mr.Sagar A L Mr.Henry
CONSTRAINTS

___________________ ________________

Date: Date:
DAILY PROGRESS REPORT
DATE:- 7/19/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date 16th April 2018

Contract Completion _As per W_

Slushy Dry

TOTAL MANPOWER
TOMORROW
TILL
PLANNED
ACHIEVED PLANNED ACHIEVED 8M 6M 4M 3M
0% 100% 3 2 1 2
100% 0%
11% 89%
100% 0%
0% 100% 1 3 2
18% 82%
31% 69%
100% 0%
0% 100% 1 3 3
9% 91%
23% 77%
100% 0%
0% 100%
0% 100%
0% 100%
100% 0% 3 3
0% 100%
4% 96%
4% 96%
100% 0%
0% 100%
9% 91%
23% 77%
100% 0%
0% 100%
100% 0%
100% 0%
100% 0%
0% 100%
100% 0%
100% 0%
100% 0%
:-

the Work Permits are prepared before sign off

ol Box Talk is Conducted on Daily Basis & submitted

ad Count is taken before signing off this DPR.

eryday evening the activity for the next day is planned 5 o clock

Spcl & team for co-ordination.

orkfronts are discussed and forecasted to optimize labour


urces
y shortage of Materials will be informed in advance atleast 3 - 4
ks

eks before based on the available Data.

Prepared by: Checked by

Mr.Henry Mr.Benadict Joshua

_________________ ___________________

e: Date:
1&2M
6

5
M/s Shapoorji Pallonji Engineering & DAILY P
M/s Shapoorji Pallonji Real Estate
Construction DATE:-

JOY VILLE TOWER 7 FORMAT NO. SPC

Name of Work : ELECTRICAL WORKS


PROJECT

Location : Joy Ville - Virar West.

Contractor : M/S ELECTROM ENGINEERING (I) PVT.LTD.

Site Conditions:
SITE

Normal Day Rainy Day

WORK ACTIVITY Qty TODAY


LOCATION UOM
PROGRESS DESCRIPTION T C B PLANNED ACHIEVED

Back Box Fixing Nos. 12 12 0 0 12


1
Vertical Conduiting
3 BHK Apt -1 Nos. 24 24 0 0 24
Slab Conduiting Pts 29 29 0 0 29
Rope Pulling Pts 29 0 29 29 0
Back Box Fixing Nos. 12 12 0 0 12
Vertical Conduiting Nos. 22 22 0 0 22
2 2 BHK ( S) Apt -2
Slab Conduiting Pts 26 26 0 0 26
Rope Pulling Pts 26 0 26 26 0
Back Box Fixing Nos. 14 14 0 0 14
Vertical Conduiting Nos. 25 25 0 0 25
3 2 BHK ( L) Apt -3
Slab Conduiting Pts 28 28 0 0 28
Rope Pulling Pts 28 0 28 28 0
Back Box Fixing Nos. 14 14 0 0 14
Vertical Conduiting Nos. 25 24 1 1 24
4 2 BHK ( L) Apt -4
Slab Conduiting Pts 28 28 0 0 28
Rope Pulling Pts 28 0 28 28 0
Back Box Fixing Nos. 12 12 0 0 12
Vertical Conduiting Nos. 22 22 0 0 22
5 2 BHK ( S) Apt -5
Slab Conduiting Pts 26 26 0 0 26
Rope Pulling Pts 26 0 26 26 0
Back Box Fixing Nos. 12 12 0 0 12
6
Vertical Conduiting
3 BHK Apt -6 Nos. 24 24 0 0 24
Slab Conduiting Pts 29 29 0 0 29
Rope Pulling Pts 29 0 29 29 0
DESCRIPTION Unit Received Consumed Balance
1 25 mm Black Conduit Mtr 2400 1170 1230

2 25 mm Grey Conduit Mtr 900 0 900 Note :-

3 20 mm Black Conduit Mtr 4800 1050 3750

4 20 mm Grey Conduit Mtr 1500 600 900 1. All the Work Permits a
5 32 mm Black Conduit Mtr 2000 200 1800 2.Tool Box Talk is Condu

6 2 M GI BACK BOX Nos 500 72 428 3.Head Count is taken b

7 3 M GI BACK BOX Nos 280 41 239 4.Everyday evening the

8 4 M GI BACK BOX Nos 30 4 26 with Spcl & team for co-o

5. Workfronts are discus


9 6M GI BACK BOX Nos 150 38 112 resources
6.Any shortage of Mater
10 8M GI BACK BOX Nos 70 22 48 Weeks

11 12 M GI Back BOX Nos 30 0 30 2 weeks before based o

Note : - Site Related Issue to be written with justifications for Approved by Prepared by:
improvements w.r.t Agency.
Mr.Sagar A L Mr.Henry
CONSTRAINTS

___________________ ________________

Date: Date:
DAILY PROGRESS REPORT
DATE:- 7/19/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date 16th April 2018

Contract Completion _As per W_

Slushy Dry

TOTAL MANPOWER
TOMORROW
TILL
PLANNED
ACHIEVED PLANNED ACHIEVED 8M 6M 4M 3M
0% 100% 1 3 3
0% 100%
0% 100%
100% 0%
0% 100% 1 3 2
0% 100%
0% 100%
100% 0%
0% 100% 1 3 3
0% 100%
0% 100%
100% 0%
2 2
0% 100%
4% 96%
0% 100%
100% 0%
0% 100%
0% 100%
0% 100%
100% 0%
0% 100%
0% 100%
0% 100%
100% 0%

:-

the Work Permits are prepared before sign off


ol Box Talk is Conducted on Daily Basis & submitted

ad Count is taken before signing off this DPR.

eryday evening the activity for the next day is planned 5 o clock

Spcl & team for co-ordination.

orkfronts are discussed and forecasted to optimize labour


urces
y shortage of Materials will be informed in advance atleast 3 - 4
ks

eks before based on the available Data.

Prepared by: Checked by

Mr.Henry Mr.Benadict Joshua

_________________ ___________________

e: Date:
1&2M
5

5
M/s Shapoorji Pallonji Engineering &
M/s Shapoorji Pallonji Real Estate
Construction

JOY VILLE TOWER 6


Name of Work : MECHANICAL WORKS
PROJECT

Location : Joy Ville - Virar West.

Contractor :

Site Conditions:
SITE

Normal Day Rainy Day

WORK Qty TODAY


PROGRESS ACTIVITY DESCRIPTION LOCATION UOM
T C B PLANNED

Groove marking & fabrication Set 1 1 0 0


Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 0 5 5
F3 90 mm sleeve in beam Nos. 1 0 1 1
S2 125 mm sleeve in slab Nos. 2 0 2 2
S3 63 mm sleeve in slab Nos. 2 0 2 2
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
1 2 BHK (L) Apt -1
S5 125 mm sleeve in beam Nos. 4 0 4 4
S6 63 mm sleeve in beam Nos. 1 0 1 1
S7 25 mm sleeve in Mivan Wall Nos. 9 0 9 9
H1 110 mm sleeve in beam Nos. 2 0 2 2
H2 110 mm sleeve in beam Nos. 6 0 6 6
H3 110 mm sleeve in beam Nos. 1 0 1 1
H4 50 mm sleeve in slab Nos. 1 0 1 1
Groove marking & fabrication Set 1 1 0 0
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 0 5 5
F2 50 mm sleeve in beam Nos. 2 0 2 2
F3 90 mm sleeve in beam Nos. 1 0 1 1
S2 125 mm sleeve in slab Nos. 2 0 2 2
2 S3 63 mm sleeve in slab 2 BHK (S) Apt -2 Nos. 2 0 2 2
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
S5 125 mm sleeve in beam Nos. 2 0 2 2
S7 25 mm sleeve in Mivan Wall Nos. 8 0 8 8
H1 110 mm sleeve in beam Nos. 1 0 1 1
H2 110 mm sleeve in beam Nos. 4 0 4 4
H4 50 mm sleeve in slab Nos. 1 0 1 1
Groove marking & fabrication Set 1 1 0 0
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 5 0 0
F2 50 mm sleeve in beam Nos. 2 2 0 0
F3 90 mm sleeve in beam Nos. 1 1 0 0
S2 125 mm sleeve in slab Nos. 2 2 0 0
3 S3 63 mm sleeve in slab 2 BHK (S) Apt -3 Nos. 2 2 0 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
3 2 BHK (S) Apt -3

S5 125 mm sleeve in beam Nos. 2 2 0 0


S7 25 mm sleeve in Mivan Wall Nos. 8 0 8 8
H1 110 mm sleeve in beam Nos. 1 1 0 0
H2 110 mm sleeve in beam Nos. 4 4 0 0
H4 50 mm sleeve in slab Nos. 1 0 1 1
Groove marking & fabrication Set 1 1 0 0
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 5 0 0
F3 90 mm sleeve in beam Nos. 1 1 0 0
S2 125 mm sleeve in slab Nos. 2 2 0 0
S3 63 mm sleeve in slab Nos. 2 2 0 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
4 2 BHK (L) Apt -4
S5 125 mm sleeve in beam Nos. 4 4 0 0
S6 63 mm sleeve in beam Nos. 1 1 0 0
S7 25 mm sleeve in Mivan Wall Nos. 9 0 9 9
H1 110 mm sleeve in beam Nos. 2 2 0 0
H2 110 mm sleeve in beam Nos. 6 6 0 0
H3 110 mm sleeve in beam Nos. 1 1 0 0
H4 50 mm sleeve in slab Nos. 1 0 1 1
Groove marking & fabrication Set 1 1 0 0
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 5 0 0
F3 90 mm sleeve in beam Nos. 1 1 0 0
S2 125 mm sleeve in slab Nos. 2 2 0 0
S3 63 mm sleeve in slab Nos. 2 2 0 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
5 2 BHK (L) Apt -5
S5 125 mm sleeve in beam Nos. 4 2 2 2
S6 63 mm sleeve in beam Nos. 1 1 0 0
S7 25 mm sleeve in Mivan Wall Nos. 9 0 9 9
H1 110 mm sleeve in beam Nos. 2 2 0 0
H2 110 mm sleeve in beam Nos. 6 6 0 0
H3 110 mm sleeve in beam Nos. 1 1 0 0
H4 50 mm sleeve in slab Nos. 1 0 1 1
Groove marking & fabrication Set 1 1 0 0
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 5 0 0
F2 50 mm sleeve in beam Nos. 2 2 0 0
F3 90 mm sleeve in beam Nos. 1 1 0 0
S2 125 mm sleeve in slab Nos. 2 2 0 0
6 S3 63 mm sleeve in slab 2 BHK (S) Apt -6 Nos. 2 2 0 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
S5 125 mm sleeve in beam Nos. 2 2 0 0
S7 25 mm sleeve in Mivan Wall Nos. 8 0 8 8
H1 110 mm sleeve in beam Nos. 1 1 0 0
H2 110 mm sleeve in beam Nos. 4 4 0 0
H4 50 mm sleeve in slab Nos. 1 0 1 1
Groove marking & fabrication Set 1 1 0 0
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 0 5 5
F2 50 mm sleeve in beam Nos. 2 0 2 2
F3 90 mm sleeve in beam Nos. 1 0 1 1
S2 125 mm sleeve in slab Nos. 2 0 2 2
7 S3 63 mm sleeve in slab 2 BHK (S) Apt -7 Nos. 2 0 2 2
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
S5 125 mm sleeve in beam Nos. 2 0 2 2
S7 25 mm sleeve in Mivan Wall Nos. 8 0 8 8
H1 110 mm sleeve in beam Nos. 1 0 1 1
H2 110 mm sleeve in beam Nos. 4 0 4 4
H4 50 mm sleeve in slab Nos. 1 0 1 1
Groove marking & fabrication Set 1 1 0 0
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 0 5 5
F3 90 mm sleeve in beam Nos. 1 0 1 1
S2 125 mm sleeve in slab Nos. 2 0 2 2
S3 63 mm sleeve in slab Nos. 2 0 2 2
S4 160 mm sleeve in Mivan Wall Nos. 2 0 2 2
8 2 BHK (L) Apt -8
S5 125 mm sleeve in beam Nos. 4 0 4 4
S6 63 mm sleeve in beam Nos. 1 0 1 1
S7 25 mm sleeve in Mivan Wall Nos. 9 0 9 9
H1 110 mm sleeve in beam Nos. 2 0 2 2
H2 110 mm sleeve in beam Nos. 6 0 6 6
H3 110 mm sleeve in beam Nos. 1 0 1 1
H4 50 mm sleeve in slab Nos. 1 0 1 1
DESCRIPTION Unit Received Consumed Balance
1 25 mm pvc pipe x 6 mtr length Mtr 30 0 30

2 40 mm pvc pipe x 6 mtr length Mtr 90 8.85 81.15

3 50 mm pvc pipe x 6 mtr length Mtr 30 1.65 28.35

4 63 mm pvc pipe x 6 mtr length Mtr 60 7.48 52.52

5 90 mm pvc pipe x 6 mtr length Mtr 90 5.67 84.33

6 110 mm pvc pipe x 6 mtr length Mtr 144 7.1 136.9

7 125 mm pvc pipe x 6 mtr length Mtr 126 14.08 111.92

8 160 mm pvc pipe x 6 mtr length Mtr 60 5.68 54.32

Note : - Site Related Issue to be written with justifications for improvements w.r.t Approved by
Agency.
AINTS
Note : - Site Related Issue to be written with justifications for improvements w.r.t
Agency.

CONSTRAINTS Mr.Sagar A L

___________________

Date:
DAILY PROGRESS REPORT
DATE:- 7/19/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date :

Contract Completion :

ditions: Slushy Dry

TODAY TOTAL MANPOWER


TOMORROW
TILL
PLANNED
ACHIEVED ACHIEVED PLANNED ACHIEVED

1 0% 100%

100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
1 0% 100%

100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
100% 0%
1 0% 100%

5 0% 100%
2 0% 100%
1 0% 100%
2 0% 100%
2 0% 100%
0 100% 0%
2 0% 100%
0 100% 0%
1 0% 100%
4 0% 100%
0 100% 0%
1 0% 100%

5 0% 100%
1 0% 100%
2 0% 100%
2 0% 100%
0 100% 0%
4 0% 100%
1 0% 100%
0 100% 0%
2 0% 100%
6 0% 100%
1 0% 100%
0 100% 0%
2 2
1 0% 100%

5 0% 100%
1 0% 100%
2 0% 100%
2 0% 100%
0 100% 0%
2 50% 50%
1 0% 100%
0 100% 0%
2 0% 100%
6 0% 100%
1 0% 100%
0 100% 0%
1 0% 100%

5 0% 100%
2 0% 100%
1 0% 100%
2 0% 100%
2 0% 100%
0 100% 0%
2 0% 100%
0 100% 0%
1 0% 100%
4 0% 100%
0 100% 0%
1 0% 100%

0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
1 0% 100%

0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%
0 100% 0%

Prepared by: Checked by


Mr.Sateesh Kumar

___________________ ___________________

Date: Date:
M/s Shapoorji Pallonji Real Estate M/s Shapoorji Pallonji Engineering & Constructio

JOY VILLE TOWER 7


Name of Work : MECHANICAL WORKS
PROJECT

Location : Joy Ville - Virar West.

Contractor :
SITE Normal Day Rainy Day Site Conditions
WORK Qty
PROGRESS ACTIVITY DESCRIPTION LOCATION UOM
T C
Groove marking & fabrication Set 1 1
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 6 0
F2 50 mm sleeve in beam Nos. 1 0
F3 90 mm sleeve in beam Nos. 1 0
S1 160 mm sleeve in slab Nos. 1 0
S2 125 mm sleeve in slab Nos. 2 0
1 3BHK Apt -1
S3 63 mm sleeve in slab Nos. 2 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0
S5 125 mm sleeve in beam Nos. 2 0
S7 25 mm sleeve in Mivan Wall Nos. 7 0
H1 110 mm sleeve in beam Nos. 2 0
H2 110 mm sleeve in beam Nos. 4 0
H4 50 mm sleeve in slab Nos. 2 0
Groove marking & fabrication Set 1 1
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 0
F2 50 mm sleeve in beam Nos. 2 0
F3 90 mm sleeve in beam Nos. 1 0
S2 125 mm sleeve in slab Nos. 2 0
2 S3 63 mm sleeve in slab 2BHK (S) Apt -2 Nos. 2 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0
S5 125 mm sleeve in beam Nos. 2 0
S7 25 mm sleeve in Mivan Wall Nos. 8 0
H1 110 mm sleeve in beam Nos. 1 0
H2 110 mm sleeve in beam Nos. 4 0
H4 50 mm sleeve in slab Nos. 1 0
Groove marking & fabrication Set 1 1
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 5
F3 90 mm sleeve in beam Nos. 1 1
S2 125 mm sleeve in slab Nos. 2 0
S3 63 mm sleeve in slab Nos. 2 0

3 2BHK(L) Apt -3
S4 160 mm sleeve in Mivan Wall Nos. 2 2
3 2BHK(L) Apt -3
S5 125 mm sleeve in beam Nos. 4 0
S6 63 mm sleeve in beam Nos. 1 0
S7 25 mm sleeve in Mivan Wall Nos. 9 0
H1 110 mm sleeve in beam Nos. 2 2
H2 110 mm sleeve in beam Nos. 6 4
H3 110 mm sleeve in beam Nos. 1 1
H4 50 mm sleeve in slab Nos. 1 0
Groove marking & fabrication Set 1 1
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 5
F3 90 mm sleeve in beam Nos. 1 1
S2 125 mm sleeve in slab Nos. 2 0
S3 63 mm sleeve in slab Nos. 2 0
S4 160 mm sleeve in Mivan Wall Nos. 2 2
4 2BHK(L) Apt -4
S5 125 mm sleeve in beam Nos. 4 0
S6 63 mm sleeve in beam Nos. 1 0
S7 25 mm sleeve in Mivan Wall Nos. 9 0
H1 110 mm sleeve in beam Nos. 2 2
H2 110 mm sleeve in beam Nos. 6 4
H3 110 mm sleeve in beam Nos. 1 1
H4 50 mm sleeve in slab Nos. 1 0
Groove marking & fabrication Set 1 1
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 5 0
F2 50 mm sleeve in beam Nos. 2 0
F3 90 mm sleeve in beam Nos. 1 0
S2 125 mm sleeve in slab Nos. 2 0
5 S3 63 mm sleeve in slab 2 BHK(S) Apt -5 Nos. 2 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0
S5 125 mm sleeve in beam Nos. 2 0
S7 25 mm sleeve in Mivan Wall Nos. 8 0
H1 110 mm sleeve in beam Nos. 1 0
H2 110 mm sleeve in beam Nos. 4 0
H4 50 mm sleeve in slab Nos. 1 0
Groove marking & fabrication Set 1 1
Installation of Sleeve
F1 40 mm sleeve in beam Nos. 6 0
F2 50 mm sleeve in beam Nos. 1 0
F3 90 mm sleeve in beam Nos. 1 0
S1 160 mm sleeve in slab Nos. 1 0
S2 125 mm sleeve in slab Nos. 2 0
6 3BHK Apt -6
S3 63 mm sleeve in slab Nos. 2 0
S4 160 mm sleeve in Mivan Wall Nos. 2 0
S5 125 mm sleeve in beam Nos. 2 0
S7 25 mm sleeve in Mivan Wall Nos. 7 0
H1 110 mm sleeve in beam Nos. 2 0
H2 110 mm sleeve in beam Nos. 4 0
H4 50 mm sleeve in slab Nos. 2 0
DESCRIPTION Unit Received Consumed
1 25 mm pvc pipe x 6 mtr length Mtr 30 0
2 40 mm pvc pipe x 6 mtr length Mtr 90 8.85
3 50 mm pvc pipe x 6 mtr length Mtr 30 1.65
4 63 mm pvc pipe x 6 mtr length Mtr 60 7.48
5 90 mm pvc pipe x 6 mtr length Mtr 90 5.67
6 110 mm pvc pipe x 6 mtr length Mtr 144 7.1
7 125 mm pvc pipe x 6 mtr length Mtr 126 14.08
8 160 mm pvc pipe x 6 mtr length Mtr 60 5.68

Note : - Site Related Issue to be written with justifications for improvements w.r.t Approved by
Agency.
Mr.Sagar A L
CONSTRAINTS

___________________

Date:
ngineering & Construction
DAILY PROGRESS REPORT
DATE:- 7/19/2018
FORMAT NO. SPCL/001/E/JV/06 REV NO.00

Contract Start Date

Contract Completion

Site Conditions: Slushy Dry


TOTAL
Qty TODAY TOMORROW TILL MANPOWER

B PLANNED ACHIEVED PLANNED ACHIEVE PLANNED ACHIEVED


D
0 0 1 0% 100%

6 6 0 100% 0%
1 1 0 100% 0%
1 1 0 100% 0%
1 1 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
7 7 0 100% 0%
2 2 0 100% 0%
4 4 0 100% 0%
2 2 0 100% 0%
0 0 1 0% 100%

5 5 0 100% 0%
2 2 0 100% 0%
1 1 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
8 8 0 100% 0%
1 1 0 100% 0%
4 4 0 100% 0%
1 1 0 100% 0%
0 0 1 0% 100%

0 0 5 0% 100%
0 0 1 0% 100%
2 2 0 100% 0%
2 2 0 100% 0%
0 0 2 0% 100%
4 4 0 100% 0%
1 1 0 100% 0%
9 9 0 100% 0%
0 0 2 0% 100%
2 2 4 33% 67%
0 0 1 0% 100%
1 1 0 100% 0%
2 2
0 0 1 0% 100%

0 0 5 0% 100%
0 0 1 0% 100%
2 2 0 100% 0%
2 2 0 100% 0%
0 0 2 0% 100%
4 4 0 100% 0%
1 1 0 100% 0%
9 9 0 100% 0%
0 0 2 0% 100%
2 2 4 33% 67%
0 0 1 0% 100%
1 1 0 100% 0%
0 0 1 0% 100%

5 5 0 100% 0%
2 2 0 100% 0%
1 1 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
8 8 0 100% 0%
1 1 0 100% 0%
4 4 0 100% 0%
1 1 0 100% 0%
0 0 1 0% 100%

6 6 0 100% 0%
1 1 0 100% 0%
1 1 0 100% 0%
1 1 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
2 2 0 100% 0%
7 7 0 100% 0%
2 2 0 100% 0%
4 4 0 100% 0%
2 2 0 100% 0%
Consumed Balance
0 30
8.85 81.15
1.65 28.35
7.48 52.52
5.67 84.33
7.1 136.9
14.08 111.92
5.68 54.32

Approved by Prepared by: Checked by

Mr.Sagar A L Mr.Sateesh Kumar

___________________ ___________________ ___________________

Date: Date: