Sie sind auf Seite 1von 51

SALEM CITY MUNICIPAL CORPORATION

Name of Work: Construction of First Floor Shopping Complex and Renavation of Bus Bays and
Shop Building Ground Floor at Dr.M.G.R Central Bus Stand in Division No: 24 , Zone-I, Salem
City Municipal Corporation
Estimate Amount: Rs. 590.00 Lakhs

DETAILED ESTIMATE

S Description Nos L B D Content Qty


No
1 Dismatling the Existing Damaged Brick work in cement mortar including
all cost and conveyance etc.,complete
For Bus Stand Shop Complex
For NBS Parapet Wall Allround 1 x 1 148.67 0.23 0.90 30.77
For Staircase room 1 x 2 14.23 0.23 2.15 14.07
1 x 2 14.23 0.23 2.15 14.07
2 x 2 7.23 0.23 2.15 14.30
Add Cable Wall 2 x 2 7.23 0.23 0.45 2.99
D/F Door 1 x 2 -1.00 0.23 2.15 -0.99
Staircase Room 1 x 2 4.80 0.23 2.15 4.75
1 x 2 4.80 0.23 2.15 4.75
1 x 2 7.23 0.23 2.15 7.15
1 x 2 7.23 0.23 2.15 7.15
D/F Door 1 x 2 -1.00 0.23 2.15 -0.99
For Parapet Wall 1 x 2 11.00 0.23 0.90 4.55
1 x 2 22.50 0.23 0.90 9.32
Sundries 2.11
Total 114.00 114.00 m3
2 Dismatling the Existing Damaged One Course of Pressed Tile Roof finish
in cement mortar including all cost and conveyance etc.,complete
For Bus Stand Shop Complex
For NBS Parapet Wall Allround 1 x 1 127.54 18.25 2327.61
D/F Staircase Room 1 x 2 -14.69 7.69 -225.93
D/F Staircase Room 1 x 2 -5.26 7.69 -80.90
For Bus Stand Bays
West Side Bus Bay 1 x 1 19.10 10.75 205.33
1 x 1 134.95 4.75 641.01
Centre Bay 1 x 1 19.10 21.75 415.43
1 x 1 134.95 9.70 1309.02
East Side Bus Bay 1 x 1 19.10 10.75 205.33
1 x 1 134.95 4.75 641.01
Sundries 2.09
S Description Nos L B D Content Qty
No
Total 5440.00 5440.00 m2
3 Dismatling the Existing Damaged AC Sheet Roof with out Roof Timbers
including all cost and conveyance etc.,complete
For Bus Stand Shop Complex
For West Side Staircase Room 1 x 1 5.26 6.74 35.45
For Centre Staircase Room 1 x 2 5.26 6.74 70.90
1 x 2 5.26 6.74 70.90
For East Side Staircase Room 1 x 2 5.26 6.74 70.90
For Bus Stand Bays
West Side Bus Bay 1 x 1 135.20 8.00 1081.60
1 x 1 135.20 1.00 135.20
Centr Side Bus Bay 1 x 2 135.20 8.00 2163.20
1 x 2 135.20 1.00 270.40
East Side Bus Bay 1 x 1 135.20 8.00 1081.60
1 x 1 135.20 1.00 135.20
Sundries 2.80
Total 4870.00 4870.00 m2
4 Dismatling the Existing Damaged Cement concrete including all cost and
conveyance etc.,complete
For Bus Stand Shop Complex
For Dummy Column 4 x 30 0.60 0.30 1.20 25.92
For Passage Flooring West Side 1 x 1 13.88 11.63 0.10 16.14
1 x 1 6.28 4.20 0.10 2.64
For Passage Flooring East Side 1 x 1 13.88 11.63 0.10 16.14
1 x 1 6.28 4.20 0.10 2.64
For Centre Passage 1 x 1 14.00 6.30 0.10 8.82
1 x 1 14.00 5.56 0.10 7.78
D/F Column 2 x 4 -0.60 0.30 0.10 -0.14
1 x 1 14.00 6.28 0.10 8.79
For Shop between Passage 1 x 2 21.27 5.10 0.10 21.70
1 x 2 21.27 5.10 0.10 21.70
For Bus Stand Bays
West Side Bus Bay 1 x 1 19.10 10.75 0.10 20.53
1 x 1 134.95 4.75 0.10 64.10
Sundries 13.24
Total 230.00 230.00 m2
5 Earth work excavation for foundation in ordinary soil, light black cotton
sandy loam and dry silt including shoring, strutting, baling or pumping
out water wherever necessary and refilling the sides of foundation with
excavated earth in layers of 15cm thick and depositing the surplus earth
at places as directed by the departmental officers with initial lead and lift
S Description Nos L B D Content Qty
No
For Bus Stand Shop Complex
For Front Side Drain 1 x 1 150.00 1.80 0.80 216.00
For Culvert 1 x 1 10.00 2.20 1.20 26.40
Sundries 7.60
Total 250.00 250.00 m3
6 Supplying and filling with approved quality of dry river sand to filling in
foundation and basement and filling the site in layers of not more than
15cm thick etc., complete. Complying with standard specifications and
drawings and has directed by departmental Engineers

For Bus Stand Shop Complex


For Passage Flooring West Side 1 x 1 13.88 11.63 0.10 16.14
1 x 1 6.28 4.20 0.10 2.64
For Passage Flooring East Side 1 x 1 13.88 11.63 0.10 16.14
1 x 1 6.28 4.20 0.10 2.64
For Centre Passage 1 x 1 14.00 6.30 0.10 8.82
1 x 1 14.00 5.56 0.10 7.78
D/F Column 2 x 4 -0.60 0.30 0.10 -0.14
1 x 1 14.00 6.28 0.10 8.79
For Shop between Passage 1 x 2 21.27 5.10 0.10 21.70
1 x 2 21.27 5.10 0.10 21.70
For Bus Stand Bays
West Side Bus Bay 1 x 1 19.10 10.75 0.10 20.53
1 x 1 134.95 4.75 0.10 64.10
Sundries 9.16
Total 200.00 200.00 m3
7 Cement concrete of mix 1:4:8 (one cement – four sand – eight broken
stone) using Hard broken granite stone jelly of 40 mm gauge for
foundation leveling course, standard specifications and drawings and has
directed by departmental Engineers. Including cost and conveyance of all
materials to working site, laying concrete and curing etc.

For Bus Stand Shop Complex


For Passage Flooring West Side 1 x 1 13.88 11.63 0.10 16.14
1 x 1 6.28 4.20 0.10 2.64
For Passage Flooring East Side 1 x 1 13.88 11.63 0.10 16.14
1 x 1 6.28 4.20 0.10 2.64
For Centre Passage 1 x 1 14.00 6.30 0.10 8.82
1 x 1 14.00 5.56 0.10 7.78
D/F Column 2 x 4 -0.60 0.30 0.10 -0.14
1 x 1 14.00 6.28 0.10 8.79
For Shop between Passage 1 x 2 21.27 5.10 0.10 21.70
1 x 2 21.27 5.10 0.10 21.70
S Description Nos L B D Content Qty
No
Front Side Passage 1 x 1 130.00 2.70 0.10 35.10
For Bus Stand Bays
West Side Bus Bay 1 x 1 19.10 10.75 0.10 20.53
1 x 1 134.95 4.75 0.10 64.10
For Front Side Drain 1 x 1 150.00 1.80 0.10 27.00
For Culvert 1 x 1 10.00 2.20 0.15 3.30
Sundries 13.76
Total 270.00 270.00 m3
8 Supplying and erecting in the position of MS sheets including necessary
supports for plane surfaces using MS Sheets of size 90cm x 60cm and or
suitable shifted with welded mild steel angles of size 25mm x 25mm x
3mm for boarding laid over silver oak (country wood) joints of size 10cm
x 6.5cm, complete complying with standard specification below Ground
level.

a). Square Columns & Sunshade


For Bus Stand Shop Complex
Columns 4 x 30 1.80 3.30 712.80
4 x 30 1.80 0.90 194.40
Sundries 22.80
Total 930.00 930.00 m2
c) Lintel, Beam & Roof Slab
For Bus Stand Shop Complex
Bank Office Window 2 x 4 2.44 0.23 4.49
Server Room 1 x 1 6.43 0.23 1.48
Dining Door 1 x 1 3.00 0.23 0.69
Toilet Door 1 x 2 1.00 0.23 0.46
Ventilator Bottom 1 x 2 0.75 0.23 0.35
Dinning Window 1 x 1 2.44 0.23 0.56
Locker Room Door 1 x 1 1.50 0.23 0.35
Passage Open 1 x 1 5.65 0.23 1.30
Main Shutter 1 x 1 3.00 0.23 0.69
ATM Door 1 x 1 3.00 0.23 0.69
Lift Door 1 x 1 1.00 0.23 0.23
Shop No : 3 Main Door 1 x 2 3.00 0.23 1.38
Window Bottom 2 x 3 2.45 0.23 3.38
1 x 1 2.45 0.23 0.56
Toilet Door 1 x 2 1.00 0.23 0.46
Ventilator Bottom 1 x 2 0.75 0.23 0.35
Shop No : 2 Main Door 1 x 2 3.00 0.23 1.38
Window Bottom 2 x 3 2.45 0.23 3.38
1 x 1 2.45 0.23 0.56
Toilet Door 1 x 2 1.00 0.23 0.46
S Description Nos L B D Content Qty
No
Ventilator Bottom 1 x 2 0.75 0.23 0.35
ATM Door 1 x 1 3.00 0.23 0.69
Lift Door 1 x 1 1.00 0.23 0.23
Shop No : 2 Main Door 1 x 2 3.00 0.23 1.38
Window Bottom 2 x 4 2.45 0.23 4.51
1 x 2 2.45 0.23 1.13
Toilet Door 1 x 2 1.00 0.23 0.46
Ventilator Bottom 1 x 2 0.75 0.23 0.35
Long Side Beam 2 x 4 128.49 0.45 462.56
Cross Side Beam 2 x 30 18.87 0.45 509.49
Locker Room Roof 1 x 1 5.67 8.55 48.48
Dining Roof 1 x 1 5.85 5.98 34.98
Toilet Roof 1 x 1 6.43 4.25 27.33
Server Room 1 x 1 6.43 2.34 15.05
Passage 1 x 1 5.85 2.60 15.21
Bank Office 1 x 1 18.41 17.50 322.18
ATM Roof 1 x 1 3.00 4.27 12.81
Lobby 1 x 1 8.51 4.27 36.34
1 x 1 15.58 4.43 69.02
Shop No : 3 Roof 1 x 1 18.41 15.80 290.88
1 x 1 13.39 5.39 72.17
Toilet Block 1 x 1 4.79 4.25 20.36
Centre Lobby 1 x 1 18.41 14.20 261.42
D/F 1 x 1 -5.14 4.37 -22.46
D/F Staircase 1 x 4 -4.94 2.44 -48.21
1 x 4 -4.00 2.44 -39.04
Shop No : 2 1 x 1 18.41 17.75 326.78
1 x 1 13.61 3.44 46.82
Toilet Block 1 x 1 4.57 3.21 14.67
Toilet Block 1 x 1 3.20 4.23 13.54
Passage 1 x 1 2.70 4.23 11.42
1 x 1 5.49 8.73 47.93
1 x 1 6.66 4.47 29.77
Shop No : 1 1 x 1 18.41 18.85 347.03
1 x 1 13.30 7.52 100.02
Toilet Block 1 x 1 4.88 7.52 36.70
Front Side Passage 1 x 2 128.49 2.44 627.03
For Locker Room Wall 1 x 1 28.44 3.30 93.85
1 x 1 30.28 3.30 99.92
D/F Door 1 x 2 -1.50 2.15 -6.45
1 x 1 299.60 0.15 44.94
For Shunshade 1 x 2 128.49 1.23 316.09
S Description Nos L B D Content Qty
No
2 x 2 128.49 0.15 77.09
D/F Stair Case 1 x 4 4.80 1.80 34.56
D/F 1 x 4 4.00 1.80 28.80
D/F Stair Case 1 x 2 6.43 1.80 23.15
D/F 1 x 2 2.24 1.80 8.06
For Side 1 x 6 15.00 0.15 13.50
Sundries 57.42
Total 4513.51 4513.51 m2
d) Centering without strutting below 1m height
For Front Side Drain 1 x 3 150.00 0.85 382.50
1 x 1 80.00 0.85 68.00
Sundries 9.50
Total 460.00 460.00 m2
e)Centering without strutting above 1m height
For Culvert 2 x 2 10.00 1.10 44.00
Sundries 1.00
Total 45.00 45.00 m2
9 Supplying, fabricating and placing in position mild steel or tar steel bars
for all reinforced cement concrete items of work including cost of steel
transporting, straightening, cutting, bending, cranking, blinding, welding
etc. including cost of MS or RTS rod and binding wire, all labour and
materials complete Complying with standard specifications and drawings
and has directed by departmental Engineers.

Steel Reinforcement 1 x 1 715.00 120.00 85800.00


Sundries 200.00
Total 86000.00 86000.00 kg
10 Providing and laying reinforced cement concrete of mix 1:11.5:3 (one
cement, one point five sand and three metal) using machine crushed hard
broken granite stone jelly 20mm ISS gauge for RCC works but including
curing etc. and including fixing fan clamps or hooks,. complete
Complying with standard specifications and drawings and has directed by
departmental Engineers.
Basement
For Culvert 1 x 1 10.00 1.80 0.25 4.50
Sundries 0.50
Total 5.00 5.00 m3
First Floor
For Bus Stand Shop Complex
For Column 4 x 30 0.60 0.30 3.30 71.28
4 x 30 0.60 0.30 0.90 19.44
For Lintel 1 x 2 128.49 0.23 0.23 13.59
S Description Nos L B D Content Qty
No
1 x 9 18.87 0.23 0.23 8.98
Roof Level Beam 1 x 30 18.41 0.23 0.45 57.16
1 x 4 128.49 0.23 0.45 53.19
1 x 1 128.49 2.44 0.15 47.03
Roof Level Slab 1 x 1 128.00 21.31 0.15 409.15
Locker Room Wall 1 x 1 29.36 0.23 3.30 22.28
D/F Door 1 x 1 -1.50 0.23 2.15 -0.74
D/F Stair Case 1 x 4 -4.80 1.80 0.15 -5.18
D/F 1 x 4 -4.00 1.80 0.15 -4.32
D/F Stair Case 1 x 2 -6.43 1.80 0.15 -3.47
D/F 1 x 2 -2.24 1.80 0.15 -1.21
Open to Sky 1 x 2 -5.14 4.37 0.15 -6.74
D/F Stair Case 1 x 4 4.80 1.80 0.15 5.18
D/F 1 x 4 4.00 1.80 0.15 4.32
D/F Stair Case 1 x 2 6.43 1.80 0.15 3.47
D/F 1 x 2 2.24 1.80 0.15 1.21
Sundries 15.38
Total 710.00 710.00 m3
11 Plain cement concrete 1:2:4 mix (One cement two sand and four
aggregate) using 20mm size ISS gauge HBBG metal including mixing,
laying, consolidating, curing, cost and conveyance of all materials to site
and all labour charges etc., complete as per standard specification

For Drain Wall 1 x 1 150.00 0.30 0.85 38.25


1 x 1 150.00 0.20 0.85 25.50
For Drain Wall 1 x 1 10.00 0.45 1.10 4.95
1 x 1 10.00 0.45 1.10 4.95
Front side Passage 1 x 1 130.00 2.70 0.10 35.10
Sundries 6.25
Total 115.00 115.00 m3
12 Brick work in cement mortar 1:5 (one cement five sand) using best
quality country bricks including cost and conveyance of all materials to
working site in super sector curing etc. complete. Complying with
standard specifications and has directed by departmental Engineers.
Including cost and conveyance of all materials to working site etc.

First Floor
For Bus Stand Shop Complex
Walls allaround 1 x 1 293.80 0.23 3.30 222.99
For Column 2 x 4 -0.23 0.23 3.30 -1.40
2 x 28 -0.23 0.23 3.30 -9.78
Cross Wall 1 x 7 18.41 0.23 3.30 97.81
Locker Room Wall 1 x 1 -29.36 0.23 3.30 -22.28
S Description Nos L B D Content Qty
No
Toilet Wall 1 x 1 6.41 0.23 3.30 4.87
1 x 1 4.25 0.23 3.30 3.23
1 x 2 3.09 0.11 2.15 1.46
1 x 2 1.22 0.11 2.15 0.58
Dining Wall 1 x 1 5.85 0.23 3.30 4.44
Open 1 x 1 -3.00 0.23 2.15 -1.48
Server Room 1 x 1 2.34 0.23 3.30 1.78
Stair Wall 1 x 1 4.24 0.23 3.30 3.22
Atm Wall 1 x 1 8.70 0.23 3.30 6.60
ATM Door 1 x 1 -3.00 0.23 2.15 -1.48
Cross Wall 1 x 1 3.00 0.23 3.30 2.28
Lift Wall 1 x 1 2.60 0.23 3.30 1.97
1 x 1 1.90 0.23 3.30 1.44
Lift Door 1 x 1 -1.00 0.23 3.30 -0.76
Toilet Block 1 x 1 4.25 0.23 3.30 3.23
1 x 1 5.39 0.23 3.30 4.09
1 x 3 2.52 0.11 2.15 1.79
1 x 2 1.22 0.11 2.15 0.58
D/F Door 1 x 3 -0.90 0.23 2.15 -1.34
D/F Door 2 x 2 -0.75 0.11 2.15 -0.71
Wall Allround OTS 1 x 1 19.94 0.23 0.90 4.13
Toilet Block 1 x 1 4.57 0.23 3.30 3.47
1 x 1 3.21 0.23 3.30 2.44
1 x 1 3.21 0.11 2.15 0.76
1 x 1 1.22 0.11 2.15 0.29
D/F Door 1 x 2 -0.90 0.23 2.15 -0.89
D/F Door 1 x 2 -0.75 0.11 2.15 -0.35
1 x 2 4.27 0.23 3.30 6.48
1 x 1 6.26 0.23 3.30 4.75
ATM Wall 1 x 1 4.23 0.23 3.30 3.21
1 x 1 3.20 0.23 3.30 2.43
1 x 1 2.60 0.23 3.30 1.97
D/F Door 1 x 1 -1.00 0.23 3.30 -0.76
1 x 1 -1.20 0.23 3.30 -0.91
1 x 2 -0.75 0.23 3.30 -1.14
Stair Wall 1 x 1 4.80 0.23 3.30 3.64
Toilet Block 1 x 1 7.52 0.23 3.30 5.71
1 x 2 4.88 0.23 3.30 7.41
1 x 1 3.53 0.23 3.30 2.68
1 x 2 3.53 0.11 2.15 1.67
D/F Door 1 x 3 -1.00 0.23 2.15 -1.48
D/F Door 2 x 2 -0.75 0.11 2.15 -0.71
S Description Nos L B D Content Qty
No
Sundries 22.07
Total 390.00 390.00 m2
Second Floor
For Bus Stand Shop Complex
Parapet Walls allaround 1 x 1 293.80 0.23 0.90 60.82
D/F Column 4 x 2 -0.23 0.23 0.90 -0.38
2 x 28 -0.23 0.23 0.90 -2.67
Wall Allround OTS 1 x 1 19.94 0.23 0.90 4.13
For Stair Case Room 6 x 2 4.80 0.23 2.10 27.82
6 x 2 4.80 0.23 0.15 1.99
6 x 2 6.30 0.23 3.00 52.16
6 x 2 6.30 0.23 2.70 46.95
D/F Door 1 x 6 -1.00 0.23 2.10 -2.90
Sundries 12.08
Total 200.00 200.00 m3
13 Providing Gravel filling including cost and conveyance of Gravel from
approved quarry to work site and stacking to departmental gauge for pre
measurement including labour for spreading complete

1 x 1 128.49 2.10 0.35 94.44


Sundries 5.56
Total 100.00 100.00 m3
14 Supplying and fixing MS grill to doors windows and ventilators etc.
using 20mm x 6mm as directed by the departmental officers inclusive of
cost of MS grill and labour charges including one coat of red oxide and
fixing in position etc. complete (as per schedule of rates) as per standard
specification
For Bus Stand Shop Complex
1 x 1 5000.00
Sundries 200.00
Total 5200.00 5200.00 kg
15 Supplying & fixing door shutters for Medium Density Fiber Board of
exterior grade 35mm thick, single leaf conforming to IS:12406/1989 with
35x12 mm T.W.Lipping on all edges with necessary adhesives and CP
screws complying with standard specification. The rate is inclusive of
three coats of best quality varnish but including cost of furniture fittings.
such as 125mm x 30mm Hinges 3 Nos, 300mm tower bolt 2nos, 200mm
tower bolt I no. 300mm Aldrop 1 No. Alu handle ornamental type 2 Nos,
and 1 No. Door stopper etc complete. consider a door shutters of size
1.2x2.1m

For Bus Stand Shop Complex


Toilet Door 2 x 2 0.75 1.80 5.40
S Description Nos L B D Content Qty
No
Toilet Door 2 x 2 0.75 1.80 5.40
Toilet Door 2 x 2 0.75 1.80 5.40
Toilet Door 2 x 2 0.75 1.80 5.40
Sundries 3.40
Total 25.00 25.00 m2
16 Supplying, fabricating and fixing in position of Alumi.Anod.natural
colour matt finish door with fully PLB board 12 mm thick using
rectangular Alu.Box section of following sizes for frame and shutter with
necessary accessories such as Al. Clips, Best double action floor springs,
Aluminium Handles on both sides,floor stopper,Tower bolt, Locks and
glass including all materials, Labour, power consemption charges
required for fabrication if necessary chipping, dismantling making
necessary holes in RCC Coloums, Beams or Masonry wherever necessary
with power drill to the extent required and made good to the original
conditions after fixing etc.,complete. The Alumi. surface must be
anodised with matt finish under electrically controlled condition in
accordance with IS specification 1868 / 1962 of Anodic filthickness of
not less than 15 Microns (Fifteen) for all sections.All the materials
should be got approved by the Engineer - In -charge before fixing as
directed.

For Bus Stand Shop Complex


Toilet Main Door 1 x 3 1.00 2.15 6.45
Toilet Main Door 1 x 3 1.00 2.15 6.45
Toilet Main Door 1 x 3 1.00 2.15 6.45
Toilet Main Door 1 x 3 1.00 2.15 6.45
Sundries 2.20
Total 28.00 28.00 m2
17 Supplying and Erecting Pull and Push Type Rolling Shutter with ISI
make of approved size and section using 18 GI sheet. The shutter shall be
painted with one coat of red oxide primer and the rate is inclusive of hood
covers, transportation charges etc

For Bus Stand Shop Complex


Bank Sapce Main Door 1 x 1 3.00 3.00 9.00
ATM Door 1 x 1 3.00 3.00 9.00
For Shop No : 3 1 x 2 3.00 3.00 18.00
For Shop No : 2 1 x 2 3.00 3.00 18.00
ATM Door 1 x 1 3.00 3.00 9.00
For Shop No : 1 1 x 1 3.00 3.00 9.00
Sundries 8.00
Total 80.00 80.00 m2
S Description Nos L B D Content Qty
No
18 Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride)
Windows of casement type (open) from the profile the size of outer frame
60mm x 58mm and shutter profile are reinforcement with GI/1mm
125GSM and 100% corrosion free, the profiles are multi chambered
sections with wall thick of 2mm. The EPDM rubber (black colour)
covered with over all the edges of frame and shutter the shutter will be
provided with Espag multi power point locks and also it operates as
handle. The corners and joints should be welded and cleaned. Radiations
free pin headed plain or brown
colour glass 4mm thick should be provided to the shutter and it should
not allow leakage of water even at most ranging storms and should have
key lockable action, security protective hinges, strong locking systems
and as per size for arresting noise and energy loss. The connecting
mechanism
between sash and outer frame that enables opening of the window. The
window should be fixed to the wall with 100% packing with screws and
silicon packing all round the frames.The window should be got approved
from the ExecutiveEngineer before use on work

For Bus Stand Shop Complex


Bank Sapce Window 2 x 4 2.44 1.35 26.35
1 x 1 2.44 1.35 3.29
For Shop No : 3 2 x 2 4.50 3.00 54.00
1 x 1 4.50 3.00 13.50
For Shop No : 2 2 x 3 4.50 3.00 81.00
1 x 1 4.50 3.00 13.50
For Shop No : 1 2 x 4 2.44 1.35 26.35
1 x 2 2.44 1.35 6.59
Sundries 15.42
Total 240.00 240.00 m2
19 Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride)
Louvered Ventilators of from the profile the size of outer frame 60mm x
58mm and shutter profile size of 60 x 78mmboth profiles are reinforced
with GI/1mm 125GSM and 100% corrosion free, the profile are multi
chambered sections with wall thick of 2mm. The EPDM rubber (black
colour) covered with all over the edges of frame and shutter.The corners
and joints should be welded and cleaned. Radiations pin headed glass
4mm thick should be provided in the louvers. The window should be
fixed to the wall with 100% packing with screws and silicon packing all
round the frames. The ventilator should be got approved from the
Executive Engineer before use on work

For Bus Stand Shop Complex


Ventilator 4 x 4 0.75 0.45 5.40
Sundries 0.60
S Description Nos L B D Content Qty
No
Total 6.00 6.00 m2
20 Plastering with cement mortar 1:3 mix, 20mm thick including cost and
conveyance of all materials to site, loading and unloading charges and
labour charges for mixing, laying and curing etc. complete . complying
with std. specifications

For Drin Sill 1 x 1 150.00 1.00 150.00


Sundries 1.00
Total 151.00 151.00 m2
21 Special Ceiling Plastering for RCC slabs and beams with cement mortar
1:3 mix 10mm thick including cost and conveyance of all materials to
site, loading and unloading charges and labour charges for mixing, laying
and curing etc. complete . complying with std. specifications

For Bus Stand Shop Complex


Locker Room Roof 1 x 1 5.67 8.55 48.48
Dining Roof 1 x 1 5.85 5.98 34.98
Toilet Roof 1 x 1 6.43 4.25 27.33
Server Room 1 x 1 6.43 2.34 15.05
Passage 1 x 1 5.85 2.60 15.21
Bank Office 1 x 1 18.41 17.50 322.18
ATM Roof 1 x 1 3.00 4.27 12.81
Lobby 1 x 1 8.51 4.27 36.34
1 x 1 15.58 4.43 69.02
Shop No : 3 Roof 1 x 1 18.41 15.80 290.88
1 x 1 13.39 5.39 72.17
Toilet Block 1 x 1 4.79 4.25 20.36
Centre Lobby 1 x 1 18.41 14.20 261.42
D/F 1 x 1 -5.14 4.37 -22.46
D/F Staircase 1 x 4 -4.94 2.44 -48.21
1 x 4 -4.00 2.44 -39.04
Shop No : 2 1 x 1 18.41 17.75 326.78
1 x 1 13.61 3.44 46.82
Toilet Block 1 x 1 4.57 3.21 14.67
Toilet Block 1 x 1 3.20 4.23 13.54
Passage 1 x 1 2.70 4.23 11.42
1 x 1 5.49 8.73 47.93
1 x 1 6.66 4.47 29.77
Shop No : 1 1 x 1 18.41 18.85 347.03
1 x 1 13.30 7.52 100.02
Toilet Block 1 x 1 4.88 7.52 36.70
Front Side Passage 1 x 2 128.49 2.44 627.03
Sundries 81.77
S Description Nos L B D Content Qty
No
Total 2800.00 2800.00 m2
22 Plastering with cement mortar 1:5 mix, 12mm thick including cost and
conveyance of all materials to site, loading and unloading charges and
labour charges for mixing, laying and curing etc. complete . complying
with std. specifications

For Bus Stand Shop Complex


Locker Room 1 x 1 28.44 3.30 93.85
Dining Roof 1 x 1 23.66 3.30 78.08
Toilet 1 x 1 14.68 3.30 48.44
1 x 3 3.10 3.30 30.69
1 x 2 1.22 3.30 8.05
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Server Room 1 x 1 17.54 3.30 57.88
Passage 1 x 1 16.90 3.30 55.77
Bank Office 1 x 1 71.82 3.30 237.01
D/F Locker Room Door 1 x 2 -1.50 2.15 -6.45
D/F Window 1 x 2 -2.44 1.35 -6.59
D/F Open 1 x 2 -3.00 2.15 -12.90
D/F Server Door 1 x 2 -3.00 2.15 -12.90
D/F Window 2 x 8 -2.44 1.35 -52.70
D/F Main Door 1 x 2 -3.00 3.00 -18.00
ATM Roof 1 x 1 14.54 3.30 47.98
Lobby 1 x 1 34.42 3.30 113.59
D/F ATM Door 1 x 1 -3.00 3.00 -9.00
Lift 1 x 1 9.00 3.30 29.70
D/F Door 1 x 2 -1.20 2.15 -5.16
Shop No : 3 1 x 1 79.20 3.30 261.36
D/F Main Door 2 x 2 -3.00 3.00 -36.00
D/F Window 2 x 7 -4.50 3.00 -189.00
Toilet Block 1 x 2 4.79 3.30 31.61
1 x 2 4.79 3.30 31.61
3 x 2 2.52 2.15 32.51
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Centre Lobby 1 x 1 65.22 3.30 215.23
1 x 2 19.94 0.90 35.89
D/F 2 x 2 -2.44 1.35 -13.18
Shop No : 2 1 x 1 79.20 3.30 261.36
D/F Window 2 x 7 -4.50 3.00 -189.00
Toilet Block 2 x 2 3.21 3.30 42.37
Toilet Block 1 x 2 3.21 2.15 13.80
S Description Nos L B D Content Qty
No
1 x 1 1.22 2.15 2.62
D/F Main Door 2 x 2 -1.00 2.15 -8.60
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
1 x 1 14.94 3.30 49.30
1 x 2 3.20 2.15 13.76
1 x 2 1.22 2.15 5.25
D/F Main Door 1 x 2 -1.00 2.15 -4.30
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Lobby 1 x 1 47.46 3.30 156.62
Lift Door 1 x 2 -1.20 2.15 -5.16
D/F ATM Door 1 x 2 -3.00 3.00 -18.00
D/F Open 1 x 2 -2.44 1.35 -6.59
ATM Centre 1 x 1 14.86 3.30 49.04
1 x 1 9.60 3.30 31.68
Shop No : 1 1 x 1 90.56 3.30 298.85
D/F Window 2 x 10 -2.45 1.35 -66.15
Toilet Block 2 x 2 4.88 3.30 64.42
2 x 3 3.53 3.30 69.89
2 x 2 3.53 2.15 30.36
2 x 2 1.22 2.15 10.50
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 4 -0.75 2.15 -12.90
Outer Side Alround 1 x 1 128.49 4.32 555.08
Inner Side Parapet 1 x 1 128.49 0.90 115.64
For Stair Case Room 6 x 4 4.80 2.10 241.92
6 x 4 4.80 0.15 17.28
6 x 4 6.30 3.00 453.60
6 x 4 6.30 2.70 408.24
D/F Door 2 x 6 -1.00 2.10 -25.20
Sundries 111.45
Total 3650.00 3650.00 m2
23 Flooring with ceramic tiles of approved Colour and quality of size
305mm x 305mm x 6mm laid first quality design of all colours in cement
mortar 1:3 mix, 20mm thick and pointing with the same mortar etc.,
completely and finish very neatly

For Bus Stand Shop Complex


For Toilet Blocks 1 x 1 3.09 4.25 13.13
1 x 1 3.09 1.22 3.77
1 x 1 3.09 2.92 9.02
Toilet Block 1 x 1 2.52 4.25 10.71
1 x 1 2.52 3.16 7.96
S Description Nos L B D Content Qty
No
1 x 1 2.52 1.22 3.07
Toilet Block 1 x 1 2.48 3.21 7.96
1 x 1 2.48 1.22 3.03
1 x 1 3.20 4.27 13.66
Toilet Block 1 x 1 3.53 4.88 17.23
1 x 1 3.53 3.13 11.05
1 x 1 3.53 1.22 4.31
Sundries 5.10
Total 110.00 110.00 m2
24 Dadooing walls with Ceramic tiles of size 20cm x 20cm x 6mm first
quality design tiles of all colours laid in cement mortar 1:2 mix, 10mm
thick and pointing with white cement using 0.40 kg/1m2 including
finishing the joint and pointing flush with tile surface etc., complete

For Bus Stand Shop Complex


For Toilet Blocks 1 x 1 14.68 3.30 48.44
1 x 1 12.02 3.30 39.67
2 x 2 3.09 2.15 26.57
2 x 2 1.22 2.15 10.49
1 x 1 8.62 3.30 28.45
D/F Door 2 x 2 -0.75 2.15 -6.45
2 x 2 -1.00 2.15 -8.60
D/F Toilet Door 1 x 2 -1.00 2.15 -4.30
For Toilet Blocks 1 x 1 13.54 3.30 44.68
1 x 1 11.34 3.30 37.42
1 x 1 7.48 3.30 24.68
2 x 2 2.52 2.15 21.67
2 x 2 1.22 2.15 10.49
1 x 2 2.52 3.30 16.63
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Door 2 x 2 -0.75 2.15 -6.45
Toilet Block 1 x 1 11.38 3.30 37.55
1 x 1 7.40 3.30 24.42
1 x 1 14.94 3.30 49.30
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Door 2 x 2 -0.75 2.15 -6.45
Toilet Block 1 x 1 16.82 3.30 55.51
1 x 1 13.32 3.30 43.96
1 x 1 8.70 3.30 28.71
2 x 2 3.13 2.15 26.92
2 x 2 1.22 2.15 10.49
D/F Main Door 2 x 3 -1.00 2.15 -12.90
S Description Nos L B D Content Qty
No
D/F Door 2 x 2 -0.75 2.15 -6.45
Sundries 11.35
Total 520.00 520.00 m2
25 Paving the floor with best approved quality fine polished Rajesthan kotta
stone slab of size 20mm with machine cut edges of size below 2'0" x 2'0"
laid over a cement mortar 1:3 mix, fixing the slab in true tight angles with
minimum possible width of joints and polishing the joints with cement
mortar 1:3 mix and polishing with floor polisher to a high degree to finish
and curing etc. complete as directed by depat. officers.

For Bus Stand Shop Complex


For Passage Flooring West Side 1 x 1 13.88 11.63 161.42
1 x 1 6.28 4.20 26.38
For Passage Flooring East Side 1 x 1 13.88 11.63 161.42
1 x 1 6.28 4.20 26.38
For Centre Passage 1 x 1 14.00 6.30 88.20
1 x 1 14.00 5.56 77.84
D/F Column 2 x 4 -0.60 0.30 -1.44
1 x 1 14.00 6.28 87.92
For Shop between Passage 1 x 2 21.27 5.10 216.95
1 x 2 21.27 5.10 216.95
For West Passage 1 x 1 14.80 7.70 113.96
1 x 1 4.20 6.30 26.46
Centre Passage 1 x 1 14.00 18.25 255.50
D/F Stair 1 x 2 -4.50 1.80 -16.20
1 x 2 -2.00 1.80 -7.20
D/F Stair 1 x 2 -4.50 1.80 -16.20
1 x 2 -2.00 1.80 -7.20
For Bus Stand Bays 0.00
West Side Bus Bay 1 x 1 19.10 10.75 205.33
1 x 1 134.95 4.75 641.01
Sundries 42.52
Total 2300.00 2300.00 m2
26 Flooring with Eurocon grip tiles of size 30 x 30 x 1cm of approved colour
and quality (Endura industrial tiles) in cement mortar 1:3 mix and
pointing with the same mortar etc. complete and finish very neatly

For Bus Stand Shop Complex


Front Side Passage 1 x 1 130.00 2.40 312.00
1 x 1 20.00 2.40 48.00
Front Side Passage 1 x 1 128.49 2.44 313.52
Sundries 26.48
S Description Nos L B D Content Qty
No
Total 700.00 700.00 m2
S Description Nos L B D Content Qty
No
27 Flooring with Vetrified flooring tiles of size 600 x 600 x 8mm of
approved colour and quality of required size laid in cement mortar 1:3
mix 20mm thick and pointing with the same mortar complete and finish
very neatly etc complete

For Bus Stand Shop Complex 1 x 1


Locker Room 1 x 1 5.67 8.55 48.48
Dining 1 x 1 5.85 5.98 34.98
Server Room 1 x 1 6.43 2.34 15.05
Passage 1 x 1 5.85 2.60 15.21
Bank Office 1 x 1 18.41 17.50 322.18
ATM 1 x 1 3.00 4.27 12.81
Lobby 1 x 1 8.51 4.27 36.34
1 x 1 15.58 4.43 69.02
Shop No : 3 1 x 1 18.41 15.80 290.88
1 x 1 13.39 5.39 72.17
Centre Lobby 1 x 1 18.41 14.20 261.42
D/F 1 x 1 -5.14 4.37 -22.46
D/F Staircase 1 x 4 -4.94 2.44 -48.21
1 x 4 -4.00 2.44 -39.04
Shop No : 2 1 x 1 18.41 17.75 326.78
1 x 1 13.61 3.44 46.82
Passage 1 x 1 2.70 4.23 11.42
1 x 1 5.49 8.73 47.93
1 x 1 6.66 4.47 29.77
Shop No : 1 1 x 1 18.41 18.85 347.03
1 x 1 13.30 7.52 100.02
Sundries 21.40
Total 2000.00 2000.00 m2
28 Dadooing the walls with Vetrified tiles of size 600 x 600 x 8mm thick laid
in cement mortar 1:2 mix 10mm thick and pointing with white cement
using 0.40 kg./cm2 including finishing the joint and pointing flush with
tile surface etc.

For Bus Stand Shop Complex


For Ground Floor Passage 1 x 2 13.88 2.50 69.40
D/F Window 1 x 2 -1.80 1.25 -4.50
D?F Open 1 x 1 3.00 2.15 6.45
1 x 1 11.63 2.50 29.08
1 x 1 6.53 2.50 16.33
1 x 1 7.80 2.50 19.50
For Passage 1 x 2 5.50 2.50 27.50
Centre Passage 1 x 2 6.30 2.50 31.50
S Description Nos L B D Content Qty
No
1 x 2 6.30 2.50 31.50
East Side Passage 1 x 2 13.88 2.50 69.40
D/F Window 1 x 2 -1.80 1.25 -4.50
D?F Open 1 x 1 3.00 2.15 6.45
1 x 1 11.63 2.50 29.08
1 x 1 6.53 2.50 16.33
1 x 1 7.80 2.50 19.50
For First Floor Passage 1 x 1 42.86 2.50 107.15
D/F Door 1 x 2 -3.00 2.10 -12.60
1 x 1 64.50 2.50 161.25
D/F Door 1 x 2 -3.00 2.50 -15.00
D/F Window 1 x 2 -2.00 2.30 -9.20
East Side Passage 1 x 1 42.86 2.50 107.15
D/F Door 1 x 3 -3.00 2.10 -18.90
1 x 1 -1.50 2.10 -3.15
Sundries 20.28
Total 700.00 700.00 m2
29 Paving the floor with best approved quality fine polished Granite
Slabstone slab of size 20mm with machine cut edges of size below 2'0" x
2'0" laid over a cement mortar 1:3 mix, fixing the slab in true tight angles
with minimum possible width of joints and polishing the joints with
cement mortar 1:3 mix and polishing with floor polisher to a high degree
to finish and curing etc. complete as directed by depat. officers.

For Staircase 4 x 25 1.80 0.30 54.00


4 x 25 1.80 0.15 27.00
1 x 4 1.80 1.80 12.96
2 x 25 1.80 0.30 27.00
2 x 25 1.80 0.15 13.50
2 x 2 1.80 1.80 12.96
Sundries 12.58
Total 160.00 160.00 m2
30 Wall Finishing with Putty Powder Three Coats using Putty powder Water
Primer Including all cost in all Floors etc.,complete.

For Bus Stand Shop Complex


Locker Room Roof 1 x 1 5.67 8.55 48.48
Dining Roof 1 x 1 5.85 5.98 34.98
Toilet Roof 1 x 1 6.43 4.25 27.33
Server Room 1 x 1 6.43 2.34 15.05
Passage 1 x 1 5.85 2.60 15.21
Bank Office 1 x 1 18.41 17.50 322.18
ATM Roof 1 x 1 3.00 4.27 12.81
S Description Nos L B D Content Qty
No
Lobby 1 x 1 8.51 4.27 36.34
1 x 1 15.58 4.43 69.02
Shop No : 3 Roof 1 x 1 18.41 15.80 290.88
1 x 1 13.39 5.39 72.17
Toilet Block 1 x 1 4.79 4.25 20.36
Centre Lobby 1 x 1 18.41 14.20 261.42
D/F 1 x 1 -5.14 4.37 -22.46
D/F Staircase 1 x 4 -4.94 2.44 -48.21
1 x 4 -4.00 2.44 -39.04
Shop No : 2 1 x 1 18.41 17.75 326.78
1 x 1 13.61 3.44 46.82
Toilet Block 1 x 1 4.57 3.21 14.67
Toilet Block 1 x 1 3.20 4.23 13.54
Passage 1 x 1 2.70 4.23 11.42
1 x 1 5.49 8.73 47.93
1 x 1 6.66 4.47 29.77
Shop No : 1 1 x 1 18.41 18.85 347.03
1 x 1 13.30 7.52 100.02
Toilet Block 1 x 1 4.88 7.52 36.70
Front Side Passage 1 x 2 128.49 2.44 627.03
Locker Room 1 x 1 28.44 3.30 93.85
Dining Roof 1 x 1 23.66 3.30 78.08
Toilet 1 x 1 14.68 3.30 48.44
1 x 3 3.10 3.30 30.69
1 x 2 1.22 3.30 8.05
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Server Room 1 x 1 17.54 3.30 57.88
Passage 1 x 1 16.90 3.30 55.77
Bank Office 1 x 1 71.82 3.30 237.01
D/F Locker Room Door 1 x 2 -1.50 2.15 -6.45
D/F Window 1 x 2 -2.44 1.35 -6.59
D/F Open 1 x 2 -3.00 2.15 -12.90
D/F Server Door 1 x 2 -3.00 2.15 -12.90
D/F Window 2 x 8 -2.44 1.35 -52.70
D/F Main Door 1 x 2 -3.00 3.00 -18.00
ATM Roof 1 x 1 14.54 3.30 47.98
Lobby 1 x 1 34.42 3.30 113.59
D/F ATM Door 1 x 1 -3.00 3.00 -9.00
Lift 1 x 1 9.00 3.30 29.70
D/F Door 1 x 2 -1.20 2.15 -5.16
Shop No : 3 1 x 1 79.20 3.30 261.36
S Description Nos L B D Content Qty
No
D/F Main Door 2 x 2 -3.00 3.00 -36.00
D/F Window 2 x 7 -4.50 3.00 -189.00
Toilet Block 1 x 2 4.79 3.30 31.61
1 x 2 4.79 3.30 31.61
3 x 2 2.52 2.15 32.51
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Centre Lobby 1 x 1 65.22 3.30 215.23
1 x 2 19.94 0.90 35.89
D/F 2 x 2 -2.44 1.35 -13.18
Shop No : 2 1 x 1 79.20 3.30 261.36
D/F Window 2 x 7 -4.50 3.00 -189.00
Toilet Block 2 x 2 3.21 3.30 42.37
Toilet Block 1 x 2 3.21 2.15 13.80
1 x 1 1.22 2.15 2.62
D/F Main Door 2 x 2 -1.00 2.15 -8.60
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
1 x 1 14.94 3.30 49.30
1 x 2 3.20 2.15 13.76
1 x 2 1.22 2.15 5.25
D/F Main Door 1 x 2 -1.00 2.15 -4.30
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Lobby 1 x 1 47.46 3.30 156.62
Lift Door 1 x 2 -1.20 2.15 -5.16
D/F ATM Door 1 x 2 -3.00 3.00 -18.00
D/F Open 1 x 2 -2.44 1.35 -6.59
ATM Centre 1 x 1 14.86 3.30 49.04
1 x 1 9.60 3.30 31.68
Shop No : 1 1 x 1 90.56 3.30 298.85
D/F Window 2 x 10 -2.45 1.35 -66.15
Toilet Block 2 x 2 4.88 3.30 64.42
2 x 3 3.53 3.30 69.89
2 x 2 3.53 2.15 30.36
2 x 2 1.22 2.15 10.50
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 4 -0.75 2.15 -12.90
Outer Side Alround 1 x 1 128.49 7.50 963.68
Inner Side Parapet 1 x 1 128.49 0.90 115.64
For Stair Case Room 6 x 4 4.80 2.10 241.92
6 x 4 4.80 0.15 17.28
6 x 4 6.30 3.00 453.60
6 x 4 6.30 2.70 408.24
S Description Nos L B D Content Qty
No
D/F Door 2 x 6 -1.00 2.10 -25.20
Sundries 134.62
Total 6800.00 6800.00 m2
31 Supply and fixing in position of European water closet with 'S' (or) 'P'
trap of approved color and quality with dauble flapped rigid PVC sheet
cover the CP brass hinges etc., complete complying with standard
specification including supply and fixing in position of 10litre capacity
glazed porcelain low level flushing tank on wall including 2 Nos of
15mm & brass nipple, 15mm dia PVC brass connection, 15mm dia GI
wheel value, 15mm dia Nylon connection and giving necessary water
supply connection etc., complete complying with standard specification

For Bus Stand Shop Complex 4 x 4 16.00


Total 16.00 16.00 Each
32 Supplying and fixing in position best quality approved make white glazed
earthen ware wash hand basin size 550mm x 400mm with a pair of cast
iron brackets including cost of 15mm Φ brass chromium plated pillar
tap, 32mm Φ C.P. waste, 32mm Φ PVC waste pipe with rubber plugs
and chain, 15mm Φ G.M. Wheel valve 15mm Φ brass nipple, 15mm Φ
Nylon connections etc. Including fixing the wash hand basin in the wall
in position with a pair of C.I. Brackets with teak wood plugs and screws
and giving necessary water supply connection and painting the brackets
with two coats of paint over a priming coat of anticorrosive paint
including testing for leakage etc. complete as per standard
specifications.

4 x 2 8.00
Total 8.00 8.00 Each
33 Supply & fixing in position of Indian make white glazed earthernware
lipped mouth porceliain flat back urinal with all accessories such as
32mm dia bell mouth PVC connection, 15mm dia GM wheel valve,
fixing the urinal to the wall in position with necessary TW plugs, clamps,
screws, shellac etc including dismantling brick masonry if necessary and
making good of the disturbed portion to original condition, fixing 15mm
GI pipe connection and wheel valve, painting the pipe with two coats of
approved paint over one coat of primer and check without any leakage
etc. complete complying with std. specifications and as directed by dept.
officers. (the Urinal should got approved by the Exe. Engineer before use
on works)

For Bus Stand Shop Complex 4 x 4 16.00


Total 16.00 16.00 Each
S Description Nos L B D Content Qty
No
34 Weathering Course with broken brick jelly 20mm size pure slacked lime
over R.C.C. roof slab the preparation of 32:12.5 for required depth and
slope etc. complete.
For Bus Stand Shop Complex
1 x 1 128.49 20.85 0.10 267.90
D/F Stair Case 1 x 2 -4.80 4.80 0.10 -4.61
D/F 1 x 4 -4.80 4.80 0.10 -9.22
D/F OTS 1 x 1 -5.14 4.37 0.10 -2.25
For Bus Stand Bays
West Side Bus Bay 1 x 1 19.10 10.75 0.10 20.53
1 x 1 134.95 4.75 0.10 64.10
Centre Bay 1 x 1 19.10 21.75 0.10 41.54
1 x 1 134.95 9.70 0.10 130.90
East Side Bus Bay 1 x 1 19.10 10.75 0.10 20.53
1 x 1 134.95 4.75 0.10 64.10
16.48
Total 610.00 610.00 m3
35 Finishing the top of roof with one course of machine pressed tiles 20 C.m
x 20 C.m x 2 C.m size using cement mortor 1:3 mix mixed with 2% by
weight of Crude Oil and pointing with Cement Mortor 1:3 mix Cost of all
materials and labour charges

For Bus Stand Shop Complex


1 x 1 128.49 20.85 2679.02
D/F Stair Case 1 x 2 -4.80 4.80 -46.08
D/F 1 x 4 -4.80 4.80 -92.16
D/F OTS 1 x 1 -5.14 4.37 -22.46
For Bus Stand Bays
West Side Bus Bay 1 x 1 19.10 10.75 205.33
1 x 1 134.95 4.75 641.01
Centre Bay 1 x 1 19.10 21.75 415.43
1 x 1 134.95 9.70 1309.02
East Side Bus Bay 1 x 1 19.10 10.75 205.33
1 x 1 134.95 4.75 641.01
Sundries 64.56
Total 6000.00 6000.00 m2
S Description Nos L B D Content Qty
No
36 Wiring with 2 x 1.5 sqmm (22 / 0.3) PVC insulated SC unsheathedCu.
Conductor of 1100V grade in suitable PVC rigid pipe concealed in wall
and ceiling with PVC accessories in flush with wall with 3mm thick
hylum sheet cover with TW switch box and 5A F.T switch with
continuous earth wire connection of 14 SWG TC wire for making good
of the concealed portion with suitable colour for PVC concealed light
point / Fan point (For electronic regulator). (SD-23)

For Bus Stand Shop Complex


1 x 132 132.00
1 x 132 132.00
Sundries 18.00
Total 282.00 282.00 Each
37 Supply and Fixing of 5A 3Pin and Combined flush type wall socket with
5A flush type switch condealed in suitable MS Box in flush with wall and
concealed with 3mm thick hylem sheet. (SD-135)
For Bus Stand Shop Complex
1 x 200 200.00
Sundries
Total 200.00 200.00 Each
38 Supply and Fixing of 5A / 15A 3Pin and Combined flush type wall socket
with 15A flush type switch condealed in suitable MS Box in flush with
wall and concealed with 3mm thick hylem sheet. (SD-135)

For Bus Stand Shop Complex


1 x 90 90.00
Sundries 6.00
Total 96.00 96.00 Each
39 Supply and fixing of single box type 4'40 W flu fitting complete with
copper choke and condensor with TW round blocks on wall or ceiling
with flu tube with PVC unsheathed Copper leads from terminals to the
fitting. (SD-88)
For Bus Stand Shop Complex
1 x 132 132.00
Sundries 16.00
Total 148.00 148.00 Each
40 Supply and fixing of 1200 mm (48") AC ceiling fan complete with
stepped electronic 300W regulator with 1meter down rod on the existing
clamp. (SD-107)

For Bus Stand Shop Complex


1 x 132 132.00
Sundries 12.00
S Description Nos L B D Content Qty
No
Total 144.00 144.00
41 Painting two coats with ready mixed plastic emulsion paint of 1st class
quality and of approved color over a priming coat including through
scraping clean removal of dirt etc., complete and including necessary
plaster of paris putty wherever required

For Bus Stand Shop Complex


Locker Room Roof 1 x 1 5.67 8.55 48.48
Dining Roof 1 x 1 5.85 5.98 34.98
Toilet Roof 1 x 1 6.43 4.25 27.33
Server Room 1 x 1 6.43 2.34 15.05
Passage 1 x 1 5.85 2.60 15.21
Bank Office 1 x 1 18.41 17.50 322.18
ATM Roof 1 x 1 3.00 4.27 12.81
Lobby 1 x 1 8.51 4.27 36.34
1 x 1 15.58 4.43 69.02
Shop No : 3 Roof 1 x 1 18.41 15.80 290.88
1 x 1 13.39 5.39 72.17
Toilet Block 1 x 1 4.79 4.25 20.36
Centre Lobby 1 x 1 18.41 14.20 261.42
D/F 1 x 1 -5.14 4.37 -22.46
D/F Staircase 1 x 4 -4.94 2.44 -48.21
1 x 4 -4.00 2.44 -39.04
Shop No : 2 1 x 1 18.41 17.75 326.78
1 x 1 13.61 3.44 46.82
Toilet Block 1 x 1 4.57 3.21 14.67
Toilet Block 1 x 1 3.20 4.23 13.54
Passage 1 x 1 2.70 4.23 11.42
1 x 1 5.49 8.73 47.93
1 x 1 6.66 4.47 29.77
Shop No : 1 1 x 1 18.41 18.85 347.03
1 x 1 13.30 7.52 100.02
Toilet Block 1 x 1 4.88 7.52 36.70
Front Side Passage 1 x 2 128.49 2.44 627.03
Locker Room 1 x 1 28.44 3.30 93.85
Dining Roof 1 x 1 23.66 3.30 78.08
Toilet 1 x 1 14.68 3.30 48.44
1 x 3 3.10 3.30 30.69
1 x 2 1.22 3.30 8.05
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Server Room 1 x 1 17.54 3.30 57.88
S Description Nos L B D Content Qty
No
Passage 1 x 1 16.90 3.30 55.77
Bank Office 1 x 1 71.82 3.30 237.01
D/F Locker Room Door 1 x 2 -1.50 2.15 -6.45
D/F Window 1 x 2 -2.44 1.35 -6.59
D/F Open 1 x 2 -3.00 2.15 -12.90
D/F Server Door 1 x 2 -3.00 2.15 -12.90
D/F Window 2 x 8 -2.44 1.35 -52.70
D/F Main Door 1 x 2 -3.00 3.00 -18.00
ATM Roof 1 x 1 14.54 3.30 47.98
Lobby 1 x 1 34.42 3.30 113.59
D/F ATM Door 1 x 1 -3.00 3.00 -9.00
Lift 1 x 1 9.00 3.30 29.70
D/F Door 1 x 2 -1.20 2.15 -5.16
Shop No : 3 1 x 1 79.20 3.30 261.36
D/F Main Door 2 x 2 -3.00 3.00 -36.00
D/F Window 2 x 7 -4.50 3.00 -189.00
Toilet Block 1 x 2 4.79 3.30 31.61
1 x 2 4.79 3.30 31.61
3 x 2 2.52 2.15 32.51
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Centre Lobby 1 x 1 65.22 3.30 215.23
1 x 2 19.94 0.90 35.89
D/F 2 x 2 -2.44 1.35 -13.18
Shop No : 2 1 x 1 79.20 3.30 261.36
D/F Window 2 x 7 -4.50 3.00 -189.00
Toilet Block 2 x 2 3.21 3.30 42.37
Toilet Block 1 x 2 3.21 2.15 13.80
1 x 1 1.22 2.15 2.62
D/F Main Door 2 x 2 -1.00 2.15 -8.60
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
1 x 1 14.94 3.30 49.30
1 x 2 3.20 2.15 13.76
1 x 2 1.22 2.15 5.25
D/F Main Door 1 x 2 -1.00 2.15 -4.30
D/F Toilet Door 2 x 2 -0.75 2.15 -6.45
Lobby 1 x 1 47.46 3.30 156.62
Lift Door 1 x 2 -1.20 2.15 -5.16
D/F ATM Door 1 x 2 -3.00 3.00 -18.00
D/F Open 1 x 2 -2.44 1.35 -6.59
ATM Centre 1 x 1 14.86 3.30 49.04
1 x 1 9.60 3.30 31.68
S Description Nos L B D Content Qty
No
Shop No : 1 1 x 1 90.56 3.30 298.85
D/F Window 2 x 10 -2.45 1.35 -66.15
Toilet Block 2 x 2 4.88 3.30 64.42
2 x 3 3.53 3.30 69.89
2 x 2 3.53 2.15 30.36
2 x 2 1.22 2.15 10.50
D/F Main Door 2 x 3 -1.00 2.15 -12.90
D/F Toilet Door 2 x 4 -0.75 2.15 -12.90
Outer Side Alround 1 x 1 128.49 7.50 963.68
Inner Side Parapet 1 x 1 128.49 0.90 115.64
For Stair Case Room 6 x 4 4.80 2.10 241.92
6 x 4 4.80 0.15 17.28
6 x 4 6.30 3.00 453.60
S Description Nos L B D Content Qty
No
6 x 4 6.30 2.70 408.24
D/F Door 2 x 6 -1.00 2.10 -25.20
Sundries 134.62
Total 6800.00 6800.00 m2
42 Fabricating, Supplying and fixing of Pre painted galvanised iron sheets
with the following specification, the materials should be of PPGL tile
profile with a red colour or any other approved design 0.47mm thick 24
guage having width 1050mm. The sheet should be GI base pre painted
hot dipped galvanised iron sheet and to be fixed with shelf tapping
screws, plastic washer. The washer and screws to be fixed by using
minute power machine drilled without damaging the sheets paint coating
to be regular modified polyster coat with zinc coating of Z 120 GSM
paint thickness the finish should be terra cotta finish like malabar
mangalore tiles frinish optional matt finish. The sheet to be fixed with
making suitable corrugated, cutting the sheet into the required size and
making ornamental designs as per the site condition and as directed by
the departmental officers.

For Bus Stand Bays


West Side Bus Bay 1 x 1 135.20 8.00 1081.60
1 x 1 135.20 1.00 135.20
Centr Side Bus Bay 1 x 2 135.20 8.00 2163.20
1 x 2 135.20 1.00 270.40
East Side Bus Bay 1 x 1 135.20 8.00 1081.60
1 x 1 135.20 1.00 135.20
Sundries 22.80
Total 4890.00 4890.00 m2
43 Manufacturing, Supplying and Fixing of Stainless Steel Hand rails for
staircase using 50mm dia 304L Grade Stainless Steel pipe of 1.60mm
thick at required locations to a height of900mm from finished floor level
welded to 38mm dia Stainless Steel pipe post of 1.00mm thick as vertical
at 900mm centre with 2 Nos. of 25mm dia intermediate horizontal
stainless steel pipe of 1.60mm thick in between.The vertical pipe has to
be welded to the 100 X 100 X 6mm MS base plate encased in the base
concrete. The rate is inclusive of the charges for cutting, bending,
welding,grinding, polishing, conveyance, electrical charges, etc.complete

For Bus Stand Shop Complex


For Stair Hand Rail 2 x 2 4.80 0.75 14.40
2 x 2 2.10 0.75 6.30
2 x 2 1.80 0.75 5.40
Centre Stair Case 2 x 4 4.80 0.75 28.80
S Description Nos L B D Content Qty
No
2 x 4 2.50 0.75 15.00
For Front Passage 1 x 1 128.49 0.75 96.37
Sundries 13.73
Total 180.00 180.00 m2
44 Supply and laying of 31/2 x 25 sqmm pvc armoured LTUG Cable in a
treanch to be excavated at a depth of 0.75m putting 0.150 layer of sand
and covering the cable completely (SD-204)
UG Cable 1 x 1 1200.00 1200.00
Sundries
Total 1200.00 1200.00 Rm
45 Supply and fixng of TNEB Moter Board suitable for 3 Phases 200A
service connection made up of suitable angle iron frame work of size 3
feet x 2 feet using angle iron of size 1 1/2" x 1 1/2" x 1/4" rigidly fixed on
wall covered with hylem sheet of size 3 feet x 2 feet of 12mm thickness
with necessary bolts and nuts supports and supply and fixing of 3 Nos
200A fuse units (500V) 1 No. Neutral link, copper earth flat of size 1" x
1/4" with inter connection of EB meter to fuse units by 19/16 PVC
insulated copper wire with earth connection complete - SD 131

2 x 10 20.00
Sundries
Total 20.00 20.00 Each
46 Geological investigation charges preparation of geological survey report
etc., complete
1 x 1 1.00
Sundries
Total 1.00 1.00 Each
47 Drilling of 150mm Dia bore well in hard rack area in including labour
charges for drilling and development charges for erection of caching pipe
in over burden soils all cost and conveyance etc., complete

a). Drilling of 150mm Dia Bore


wells in overburden soil including
labour charges for insertion of
casing pipes.
1 x 1 30.00 30.00
Sundries
Total 30.00 30.00 Rm
b). Drilling of 150mm Dia Bore
wells in hard rock areas including
transportation to the work site in
hard rock areas and developing the
bore wells
S Description Nos L B D Content Qty
No
1 x 1 300.00 300.00
Sundries
Total 300.00 300.00 Rm
48 Supplying of best approved quality of PVC casing pipe of 160mm dia
for bore well with socket end to suit bore well of required depth -6kg/cm2
best approved quality with ISI mark with necessary PVC coupling etc.,

1 x 1 30.00 30.00
Sundries
Total 30.00 30.00 Rm
49 Supply and delivery of 10 HP Three phase Submersible Motor pumpset
as per IS 8034 with ISI tandard specification, the Duty Condition are 125
LPM x 225m head etc. complete including all cost and conveyanve etc.
complete

1 x 1 1.00
Sundries
Total 1.00 1.00 Each
50 Supply and Delivery of Three Phase Panel board Star Delta with Two
Level Guard and Auto Start upto 10 HP submersible motor pumpset as
per standard specification

1 x 1 1.00
Sundries
Total 1.00 1.00 Each
51 Supply and Fixing of the Following Pipes and Specials etc., Complete.
110mm Dia PVC Pipe 3 x 1 15.00 45.00
25 x 2 6.00 300.00
345.00 345.00 Rm
110mm Dia PVC Tee 1 x 25 25.00 25.00

110mm Dia PVC Elbow 1 x 25 25.00 25.00

32 mm G.I. Pipe 1 x 1 145.00 145.00 145.00


32 mm Coupling 1 x 20 20.00 20.00
32mm GI Elbow 1 x 25 25.00 25.00
32mm Gate valve 1 x 4 4.00 4.00
32mm GI Bend 1 x 8 8.00 8.00
32mm GI Union 1 x 10 10.00 10.00
32mm GI B Nipple 6" 1 x 10 10.00 10.00
32mm Dia Hex Nipple 1 x 12 12.00 12.00
1" Dia GI Pipe 1 x 1 55.00 55.00 55.00
1" Dia GI Elbow 1 x 15 15.00 15.00
S Description Nos L B D Content Qty
No
1" Dia Union 1 x 4 4.00 4.00
1" Dia Gate Valve 1 x 5 5.00 5.00
1" x 3/4" GI Reducer 1 x 10 10.00 10.00
3/4" Dia GI Pipe 1 x 1 55.00 55.00 55.00
3/4" Dia GI Elbow 1 x 10 10.00 10.00
3/4" Dia GI Tee 1 x 10 10.00 10.00
3/4" Dia Union 1 x 6 6.00 6.00
3/4" Dia Gate Valve 1 x 5 5.00 5.00
3/4" x 1/2" GI Reducer 1 x 25 25.00 25.00
CP Tap 1 x 25 25.00 25.00
Angle Valve 1 x 4 4.00 4.00
50mm Dia GI Pipe 'B' Class 1 x 1 600.00 600.00 600.00 rm
50mm Dia GI Coupling 1 x 120 120.00 120.00 E
50mm Dia GI Bend 1 x 12 12.00 12.00 E
50mm Dia GI Elbow 1 x 30 30.00 30.00 E
50mm Dia GI Tee 1 x 12 12.00 12.00 E
50mm Dia GI Union 1 x 12 12.00 12.00 E
50mm Dia Non-Return Valve 1 x 2 2.00 2.00 E
50mm Dia GM Gate Valve 1 x 12 12.00 12.00 E
Bore Clampset 1 x 2 2.00 2.00 E
Bore Cover 1 x 1 1.00 1.00 E
50mm Dia GI 'Hex' Nipple 1 x 12 12.00 12.00 E
50mm Dia GI End Cup 1 x 6 6.00 6.00 E
50mm Dia GI Barrel Nipple- 12" E
1 x 24 24.00 24.00
Long
50mm Dia GI Barrel Nipple- 9" E
1 x 12 12.00 12.00
Long
50mm Dia GI Barrel Nipple- 6" E
1 x 12 12.00 12.00
Long

52 Supply and delivery Of 3 Core copper conductor Flat Cable (4Sq.mm)


confirming to IS 694/1990 with ISI marking sutiable for Submersible
Pumpset etc., Complete

Flat Cable 1 x 1 1500.00 1500.00


Sundries
Total 1500.00 1500.00 Rm
53 Supply and delivery of 1000Liter Capacity HDPE tank as per IS 12701 /
1996 including loading, unloading, transportation and labour charges for
fixing of the GI pipes and specials for pipe including cutting, threading
and fixingconnection works charges etc.,

3 x 2 6.00 6.00
S Description Nos L B D Content Qty
No

54 Provisions for GST 12% LS LS


55 Provisions for Centage Charge 2.5 % LS LS
56 Provisions for Lift arrangements etc,complete LS LS
57 Provisions for Elevation Ornamental Works etc., Complete. LS LS
58 Provision for Fire Fighting arrangements etc.,complete LS LS
59 Provision for Park Arranagements etc.complete LS LS
60 Provisions for Manual Workers Genaral Welfare Fund LS LS
61 Contengencies and other Unforseen items only LS LS

Assistant engineer Assistant Executive engineer


SALEM CITY MUNICIPAL CORPORATION

Name of Work: Construction of First Floor Shopping Complex and Renavation of Bus Bays and Shop
Building Ground Floor at Dr.M.G.R Central Bus Stand in Division No: 24 , Zone-I, Salem City Municipal
Corporation
Estimate Amount: Rs. 590.00 Lakhs

ABSTRACT OF ESTIMATE

S Qty Description of Item Rate Per Amount Remarks


No
Dismatling the Existing Damaged Brick work in
1 cement mortar including all cost and conveyance
etc.,complete
114.00 154.14 m3 17572.00
Dismatling the Existing Damaged One Course of
2 Pressed Tile Roof finish in cement mortar
5440.00 including all cost and conveyance etc.,complete 13.30 m2 72352.00
Dismatling the Existing Damaged AC Sheet Roof
3 with out Roof Timbers including all cost and
conveyance etc.,complete
4870.00 9.77 m2 47580.00
Dismatling the Existing Damaged Cement
4 concrete including all cost and conveyance
etc.,complete
230.00 252.00 m3 57960.00
Earth work excavation for foundation in ordinary
soil, light black cotton sandy loam and dry silt
including shoring, strutting, baling or pumping
out water wherever necessary and refilling the
5 sides of foundation with excavated earth in layers
of 15cm thick and depositing the surplus earth at
places as directed by the departmental officers
with initial lead and lift
250.00 90.00 m3 22500.00
Supplying and filling with approved quality of
dry river sand to filling in foundation and
basement and filling the site in layers of not more
6 than 15cm thick etc., complete. Complying with
standard specifications and drawings and has
directed by departmental Engineers
200.00 831.00 m3 166200.00
Cement concrete of mix 1:4:8 (one cement – four
sand – eight broken stone) using Hard broken
granite stone jelly of 40 mm gauge for foundation
leveling course, standard specifications and
7 drawings and has directed by departmental
Engineers. Including cost and conveyance of all
materials to working site, laying concrete and
curing etc.
270.00 3444.00 m3 929880.00
S Qty Description of Item Rate Per Amount Remarks
No
Supplying and erecting in the position of MS
sheets including necessary supports for plane
surfaces using MS Sheets of size 90cm x 60cm
and or suitable shifted with welded mild steel
8 angles of size 25mm x 25mm x 3mm for
boarding laid over silver oak (country wood)
joints of size 10cm x 6.5cm, complete complying
with standard specification below Ground level.

930.00 a). Square Columns & Sunshade 713.30 m2 663369.00


4513.51 c) Lintel, Beam & Roof Slab 594.42 m2 2682921.00
460.00 d) Centering without strutting below 1m height 258.85 m2 119071.00
45.00 e)Centering without strutting above 1m height 517.70 m2 23297.00
Supplying, fabricating and placing in position
mild steel or tar steel bars for all reinforced
cement concrete items of work including cost of
steel transporting, straightening, cutting, bending,
cranking, blinding, welding etc. including cost of
9 MS or RTS rod and binding wire, all labour and
materials complete Complying with standard
specifications and drawings and has directed by
departmental Engineers.
86000.00 62.74 Kg 5395640.00
Providing and laying reinforced cement concrete
of mix 1:11.5:3 (one cement, one point five sand
and three metal) using machine crushed hard
broken granite stone jelly 20mm ISS gauge for
10 RCC works but including curing etc. and
including fixing fan clamps or hooks,. complete
Complying with standard specifications and
drawings and has directed by departmental
Engineers.

5.00 Basement 6161.10 m3 30806.00


710.00 First Floor 6338.00 m3 4499980.00
Plain cement concrete 1:2:4 mix (One cement
two sand and four aggregate) using 20mm size
ISS gauge HBBG metal including mixing,
11 laying, consolidating, curing, cost and
conveyance of all materials to site and all labour
charges etc., complete as per standard
115.00 specification 4418.08 m3 508079.00
Brick work in cement mortar 1:5 (one cement
five sand) using best quality country bricks
including cost and conveyance of all materials to
working site in super sector curing etc. complete.
12 Complying with standard specifications and has
directed by departmental Engineers. Including
cost and conveyance of all materials to working
site etc.
S Qty Description of Item Rate Per Amount Remarks
No
390.00 First Floor 5097.30 m3 1987947.00
200.00 Second Floor 5176.20 m3 1035240.00
Providing Gravel filling including cost and
conveyance of Gravel from approved quarry to
work site and stacking to departmental gauge for
13
pre measurement including labour for spreading
complete
100.00 242.00 m3 24200.00
Supplying and fixing MS grill to doors windows
and ventilators etc. using 20mm x 6mm as
directed by the departmental officers inclusive of
cost of MS grill and labour charges including one
14 coat of red oxide and fixing in position etc.
complete (as per schedule of rates) as per
standard specification
5200.00 71.80 Kg 373360.00
Supplying & fixing door shutters for Medium
Density Fiber Board of exterior grade 35mm
thick, single leaf conforming to IS:12406/1989
with 35x12 mm T.W.Lipping on all edges with
necessary adhesives and CP screws complying
with standard specification. The rate is inclusive
of three coats of best quality varnish but
15 including cost of furniture fittings. such as
125mm x 30mm Hinges 3 Nos, 300mm tower
bolt 2nos, 200mm tower bolt I no. 300mm
Aldrop 1 No. Alu handle ornamental type 2 Nos,
and 1 No. Door stopper etc complete. consider a
door shutters of size 1.2x2.1m

25.00 2652.00 m2 66300.00


S Qty Description of Item Rate Per Amount Remarks
No
Supplying, fabricating and fixing in position of
Alumi.Anod.natural colour matt finish door with
fully PLB board 12 mm thick using rectangular
Alu.Box section of following sizes for frame and
shutter with necessary accessories such as Al.
Clips, Best double action floor springs,
Aluminium Handles on both sides,floor
stopper,Tower bolt, Locks and glass including all
materials, Labour, power consemption charges
required for fabrication if necessary chipping,
dismantling making necessary holes in RCC
Coloums, Beams or Masonry wherever necessary
16 with power drill to the extent required and
made good to the original conditions after
fixing etc.,complete. The Alumi. surface must be
anodised with matt finish under electrically
controlled condition in accordance with IS
specification 1868 / 1962 of Anodic filthickness
of not less than 15 Microns (Fifteen) for all
sections.All the materials should be got
approved by the Engineer - In -charge before
fixing as directed.

28.00 6431.00 m2 180068.00


Supplying and Erecting Pull and Push Type
Rolling Shutter with ISI make of approved size
and section using 18 GI sheet. The shutter shall
17 be painted with one coat of red oxide primer and
the rate is inclusive of hood covers,
transportation charges etc
80.00 2010.00 m2 160800.00
Supplying and fixing UPVC (Un-Plasticized
Polyvinyl Chloride) Windows of casement type
(open) from the profile the size of outer frame
60mm x 58mm and shutter profile are
reinforcement with GI/1mm 125GSM and 100%
corrosion free, the profiles are multi chambered
sections with wall thick of 2mm. The EPDM
18 rubber (black colour) covered with over all the
edges of frame and shutter the shutter will be
provided with Espag multi power point locks and
also it operates as handle. The corners and joints
should be welded and cleaned. Radiations free
pin headed plain or brown
colour glass 4mm thick should be provided to the
shutter and it should not allow leakage of water
240.00 even at most ranging storms and should have key 6000.00 m2 1440000.00
lockable action, security protective hinges, strong
locking systems and as per size for arresting
noise and energy loss. The connecting
mechanism
between sash and outer frame that enables
opening of the window. The window should be
fixed to the wall with 100% packing with screws
and silicon packing all round the frames.The
window should be got approved from the
S Qty Description of Item Rate Per Amount Remarks
No
Supplying and fixing UPVC (Un-Plasticized
Polyvinyl Chloride) Louvered Ventilators of from
the profile the size of outer frame 60mm x 58mm
and shutter profile size of 60 x 78mmboth
profiles are reinforced with GI/1mm 125GSM
and 100% corrosion free, the profile are multi
chambered sections with wall thick of 2mm. The
EPDM rubber (black colour) covered with all
over the edges of frame and shutter.The corners
19 and joints should be welded and cleaned.
Radiations pin headed glass 4mm thick should be
provided in the louvers. The window should be
fixed to the wall with 100% packing with screws
and silicon packing all round the frames. The
ventilator should be got approved from the
Executive Engineer before use on work

6.00 6500.00 m2 39000.00


Plastering with cement mortar 1:3 mix, 20mm
thick including cost and conveyance of all
20 materials to site, loading and unloading charges
and labour charges for mixing, laying and curing
etc. complete . complying with std. specifications
151.00 335.00 m3 50585.00
Special Ceiling Plastering for RCC slabs and
beams with cement mortar 1:3 mix 10mm thick
including cost and conveyance of all materials to
21 site, loading and unloading charges and labour
charges for mixing, laying and curing etc.
complete . complying with std. specifications
2800.00 179.00 m2 501200.00
Plastering with cement mortar 1:5 mix, 12mm
thick including cost and conveyance of all
materials to site, loading and unloading charges
22
and labour charges for mixing, laying and curing
etc. complete . complying with std. specifications
3650.00 156.00 m2 569400.00
Flooring with ceramic tiles of approved Colour
and quality of size 305mm x 305mm x 6mm laid
23 first quality design of all colours in cement
mortar 1:3 mix, 20mm thick and pointing with
the same mortar etc., completely and finish very
110.00 neatly 992.00 m2 109120.00
Dadooing walls with Ceramic tiles of size 20cm
x 20cm x 6mm first quality design tiles of all
colours laid in cement mortar 1:2 mix, 10mm
24 thick and pointing with white cement using 0.40
kg/1m2 including finishing the joint and pointing
flush with tile surface etc., complete
520.00 1048.00 m2 544960.00
S Qty Description of Item Rate Per Amount Remarks
No
Paving the floor with best approved quality fine
polished Rajesthan kotta stone slab of size 20mm
with machine cut edges of size below 2'0" x 2'0"
laid over a cement mortar 1:3 mix, fixing the slab
in true tight angles with minimum possible width
25 of joints and polishing the joints with cement
mortar 1:3 mix and polishing with floor polisher
to a high degree to finish and curing etc.
complete as directed by depat. officers.
2300.00 1223.00 m2 2812900.00
Flooring with Eurocon grip tiles of size 30 x 30 x
1cm of approved colour and quality (Endura
industrial tiles) in cement mortar 1:3 mix and
26 pointing with the same mortar etc. complete and
finish very neatly
700.00 1114.72 m2 780304.00
Flooring with Vetrified flooring tiles of size 600 x
600 x 8mm of approved colour and quality of
required size laid in cement mortar 1:3 mix
27
20mm thick and pointing with the same mortar
complete and finish very neatly etc complete
2000.00 1405.00 m2 2810000.00
Dadooing the walls with Vetrified tiles of size
600 x 600 x 8mm thick laid in cement mortar 1:2
mix 10mm thick and pointing with white cement
28
using 0.40 kg./cm2 including finishing the joint
and pointing flush with tile surface etc.
700.00 1453.00 m2 1017100.00
Paving the floor with best approved quality fine
polished Granite Slabstone slab of size 20mm
with machine cut edges of size below 2'0" x 2'0"
laid over a cement mortar 1:3 mix, fixing the slab
in true tight angles with minimum possible width
29 of joints and polishing the joints with cement
mortar 1:3 mix and polishing with floor polisher
to a high degree to finish and curing etc.
complete as directed by depat. officers.

160.00 3250.00 m2 520000.00


Wall Finishing with Putty Powder Three Coats
30 using Putty powder Water Primer Including all
cost in all Floors etc.,complete.
6800.00 150.00 m3 1020000.00
S Qty Description of Item Rate Per Amount Remarks
No
Supply and fixing in position of European water
closet with 'S' (or) 'P' trap of approved color and
quality with dauble flapped rigid PVC sheet
cover the CP brass hinges etc., complete
complying with standard specification including
supply and fixing in position of 10litre capacity
glazed porcelain low level flushing tank on wall
31 including 2 Nos of 15mm & brass nipple, 15mm
dia PVC brass connection, 15mm dia GI wheel
value, 15mm dia Nylon connection and giving
necessary water supply connection etc., complete
complying with standard specification

16.00 5544.00 E 88704.00


Supplying and fixing in position best quality
approved make white glazed earthen ware wash
hand basin size 550mm x 400mm with a pair of
cast iron brackets including cost of 15mm Φ
brass chromium plated pillar tap, 32mm Φ C.P.
waste, 32mm Φ PVC waste pipe with rubber
plugs and chain, 15mm Φ G.M. Wheel valve
15mm Φ brass nipple, 15mm Φ Nylon
connections etc. Including fixing the wash hand
32 basin in the wall in position with a pair of C.I.
Brackets with teak wood plugs and screws and
giving necessary water supply connection and
painting the brackets with two coats of paint
over a priming coat of anticorrosive paint
including testing for leakage etc. complete as per
standard specifications.

8.00 2993.00 23944.00


Supply & fixing in position of Indian make white
glazed earthernware lipped mouth porceliain flat
back urinal with all accessories such as 32mm dia
bell mouth PVC connection, 15mm dia GM
wheel valve, fixing the urinal to the wall in
position with necessary TW plugs, clamps,
screws, shellac etc including dismantling brick
masonry if necessary and making good of the
33 disturbed portion to original condition, fixing
15mm GI pipe connection and wheel valve,
painting the pipe with two coats of approved
paint over one coat of primer and check without
any leakage etc. complete complying with std.
specifications and as directed by dept. officers.
(the Urinal should got approved by the Exe.
Engineer before use on works)
16.00 1818.00 m2 29088.00
S Qty Description of Item Rate Per Amount Remarks
No
Weathering Course with broken brick jelly 20mm
size pure slacked lime over R.C.C. roof slab the
34 preparation of 32:12.5 for required depth and
slope etc. complete.
610.00 3013.00 m3 1837930.00
Finishing the top of roof with one course of
machine pressed tiles 20 C.m x 20 C.m x 2 C.m
size using cement mortor 1:3 mix mixed with 2%
35 by weight of Crude Oil and pointing with Cement
Mortor 1:3 mix Cost of all materials and labour
charges
6000.00 794.00 m2 4764004.00
Wiring with 2 x 1.5 sqmm (22 / 0.3) PVC
insulated SC unsheathedCu. Conductor of 1100V
grade in suitable PVC rigid pipe concealed in
wall and ceiling with PVC accessories in flush
with wall with 3mm thick hylum sheet cover with
36 TW switch box and 5A F.T switch with
continuous earth wire connection of 14 SWG TC
wire for making good of the concealed portion
with suitable colour for PVC concealed light
point / Fan point (For electronic regulator). (SD-
23)
282.00 1808.00 E 509856.00
Supply and Fixing of 5A 3Pin and Combined
flush type wall socket with 5A flush type switch
37 condealed in suitable MS Box in flush with wall
and concealed with 3mm thick hylem sheet. (SD-
135)
200.00 295.00 E 59000.00
Supply and Fixing of 5A / 15A 3Pin and
Combined flush type wall socket with 15A flush
38 type switch condealed in suitable MS Box in
flush with wall and concealed with 3mm thick
hylem sheet. (SD-135)
96.00 357.00 E 34272.00
Supply and fixing of single box type 4'40 W flu
fitting complete with copper choke and
condensor with TW round blocks on wall or
39
ceiling with flu tube with PVC unsheathed
Copper leads from terminals to the fitting. (SD-
148.00 88) 630.00 E 93240.00
Supply and fixing of 1200 mm (48") AC ceiling
fan complete with stepped electronic 300W
40 regulator with 1meter down rod on the existing
144.00 clamp. (SD-107) 1624.00 E 233856.00
Painting two coats with ready mixed plastic
emulsion paint of 1st class quality and of
approved color over a priming coat including
41 through scraping clean removal of dirt etc.,
complete and including necessary plaster of paris
putty wherever required
6800.00 157.00 m2 1067600.00
S Qty Description of Item Rate Per Amount Remarks
No
Fabricating, Supplying and fixing of Pre painted
galvanised iron sheets with the following
specification, the materials should be of PPGL
tile profile with a red colour or any other
approved design 0.47mm thick 24 guage having
width 1050mm. The sheet should be GI base pre
painted hot dipped galvanised iron sheet and to
be fixed with shelf tapping screws, plastic
washer. The washer and screws to be fixed by
using minute power machine drilled without
damaging the sheets paint coating to be regular
42 modified polyster coat with zinc coating of Z 120
GSM paint thickness the finish should be terra
cotta finish like malabar mangalore tiles frinish
optional matt finish. The sheet to be fixed with
making suitable corrugated, cutting the sheet into
the required size and making ornamental designs
as per the site condition and as directed by the
departmental officers.

4890.00 672.00 m2 3286080.00


Manufacturing, Supplying and Fixing of
Stainless Steel Hand rails for staircase using
50mm dia 304L Grade Stainless Steel pipe of
1.60mm thick at required locations to a height
of900mm from finished floor level welded to
38mm dia Stainless Steel pipe post of 1.00mm
thick as vertical at 900mm centre with 2 Nos. of
25mm dia intermediate horizontal stainless steel
43 pipe of 1.60mm thick in between.The vertical
pipe has to be welded to the 100 X 100 X 6mm
MS base plate encased in the base concrete. The
rate is inclusive of the charges for cutting,
bending, welding,grinding, polishing,
conveyance, electrical charges, etc.complete

180.00 5120.00 m2 921600.00


Supply and laying of 31/2 x 25 sqmm pvc
armoured LTUG Cable in a treanch to be
excavated at a depth of 0.75m putting 0.150 layer
44
of sand and covering the cable completely (SD-
204)
1200.00 378.00 Rm 453600.00
S Qty Description of Item Rate Per Amount Remarks
No
Supply and fixng of TNEB Moter Board suitable
for 3 Phases 200A service connection made up of
suitable angle iron frame work of size 3 feet x 2
feet using angle iron of size 1 1/2" x 1 1/2" x 1/4"
rigidly fixed on wall covered with hylem sheet of
size 3 feet x 2 feet of 12mm thickness with
necessary bolts and nuts supports and supply and
45
fixing of 3 Nos 200A fuse units (500V) 1 No.
Neutral link, copper earth flat of size 1" x 1/4"
with inter connection of EB meter to fuse units
by 19/16 PVC insulated copper wire with earth
connection complete - SD 131

20.00 5938.00 Each 118760.00


Geological investigation charges preparation of
46 geological survey report etc., complete
1.00 2000.00 Each 2000.00
Drilling of 150mm Dia bore well in hard rack
area in including labour charges for drilling and
47 development charges for erection of caching pipe
in over burden soils all cost and conveyance etc.,
complete

a). Drilling of 150mm Dia Bore wells in


overburden soil including labour charges for
insertion of casing pipes.
30.00 275.00 Rm 8250.00
b). Drilling of 150mm Dia Bore wells in hard
rock areas including transportation to the work
300.00 site in hard rock areas and developing the bore 295.00 Rm 88500.00
wells
Supplying of best approved quality of PVC
casing pipe of 160mm dia for bore well with
48 socket end to suit bore well of required depth
-6kg/cm2 best approved quality with ISI mark
with necessary PVC coupling etc.,
30.00 599.00 Rm 17970.00
Supply and delivery of 10 HP Three phase
Submersible Motor pumpset as per IS 8034 with
49 ISI tandard specification, the Duty Condition are
125 LPM x 225m head etc. complete including
all cost and conveyanve etc. complete
1.00 68478.00 Each 68478.00
Supply and Delivery of Three Phase Panel board
Star Delta with Two Level Guard and Auto Start
50 upto 10 HP submersible motor pumpset as per
standard specification
1.00 18006.00 Each 18006.00
S Qty Description of Item Rate Per Amount Remarks
No
Supply and Fixing of the Following Pipes and
51 Specials etc., Complete.
345.00 110mm Dia PVC Pipe 254.60 Rm 87837.00
25.00 110mm Dia PVC Tee 139.10 Each 3478.00
25.00 110mm Dia PVC Elbow 84.80 Each 2120.00
145.00 32 mm G.I. Pipe 219.00 Rm 31755.00
20.00 32 mm Coupling 49.00 Each 980.00
25.00 32mm GI Elbow 74.00 Each 1850.00
4.00 32mm Gate valve 798.00 Each 3192.00
8.00 32mm GI Bend 66.00 Each 528.00
10.00 32mm GI Union 147.00 Each 1470.00
10.00 32mm GI B Nipple 6" 65.00 Each 650.00
12.00 32mm Dia Hex Nipple 55.00 Each 660.00
55.00 1" Dia GI Pipe 174.00 Rm 9570.00
15.00 1" Dia GI Elbow 45.00 Each 675.00
4.00 1" Dia Union 104.00 Each 416.00
5.00 1" Dia Gate Valve 601.00 Each 3005.00
10.00 1" x 3/4" GI Reducer 35.00 Each 350.00
55.00 3/4" Dia GI Pipe 120.00 Rm 6600.00
10.00 3/4" Dia GI Elbow 29.00 Each 290.00
10.00 3/4" Dia GI Tee 41.00 Each 410.00
6.00 3/4" Dia Union 62.00 Each 372.00
5.00 3/4" Dia Gate Valve 448.00 Each 2240.00
25.00 3/4" x 1/2" GI Reducer 22.00 Each 550.00
25.00 CP Tap 150.00 Each 3750.00
4.00 Angle Valve 250.00 Each 1000.00
600.00 50mm Dia GI Pipe 'B' Class 347.00 Rm 208200.00
120.00 50mm Dia GI Coupling 109.00 E 13080.00
12.00 50mm Dia GI Bend 129.00 E 1548.00
30.00 50mm Dia GI Elbow 141.00 E 4230.00
12.00 50mm Dia GI Tee 208.00 E 2496.00
12.00 50mm Dia GI Union 265.00 E 3180.00
2.00 50mm Dia Non-Return Valve 1731.00 E 3462.00
12.00 50mm Dia GM Gate Valve 1731.00 E 20772.00
2.00 Bore Clampset 500.00 E 1000.00
1.00 Bore Cover 300.00 E 300.00
12.00 50mm Dia GI 'Hex' Nipple 95.00 E 1140.00
S Qty Description of Item Rate Per Amount Remarks
No
6.00 50mm Dia GI End Cup 33.00 E 198.00
24.00 50mm Dia GI Barrel Nipple- 12" Long 120.00 E 2880.00
12.00 50mm Dia GI Barrel Nipple- 9" Long 90.00 E 1080.00
12.00 50mm Dia GI Barrel Nipple- 6" Long 75.00 E 900.00

Supply and delivery Of 3 Core copper conductor


Flat Cable (4Sq.mm) confirming to IS 694/1990
52 with ISI marking sutiable for Submersible
Pumpset etc., Complete
1500.00 153.00 Rm 229500.00
Supply and delivery of 1000Liter Capacity
HDPE tank as per IS 12701 / 1996 including
loading, unloading, transportation and labour
53 charges for fixing of the GI pipes and specials for
pipe including cutting, threading and
fixingconnection works charges etc.,
6.00 7186.00 E 43116.00
sub Total 45097864.00
54 LS Provisions for GST 12% 5411743.68
55 LS Provisions for Centage Charge 2.5 % 1127446.60
56 LS Provisions for Lift arrangements etc,complete LS LS 1000000.00
Provisions for Elevation Ornamental Works etc.,
57
LS Complete. LS LS 1500000.00
Provision for Fire Fighting arrangements
58 etc.,complete LS LS 1500000.00
59 Provision for Park Arranagements etc.complete LS LS 1000000.00
Provisions for Manual Workers Genaral Welfare
60
LS Fund LS LS 590000.00
61 LS Contengencies and other Unforseen items only LS LS 1772945.72
Total 59000000.00

Assistant Engineer Assistant Executive Engineer Executive Engineer


REPORT TO ACCOMPANY THE ESTIMATE

Name of Work: Construction of First Floor Shopping Complex and Renavation of Bus Bays and Shop
Building Ground Floor at Dr.M.G.R Central Bus Stand in Division No: 24 , Zone-I, Salem City
Municipal Corporation

Estimate Amount: Rs. 590.00 Lakhs

As per Instruction were given by the Commissioner and Exe. Engineer the Above Estimate was
Prepared and Submitted for the Following Provisions.

1 Dismatling the Existing Damaged Brick work in cement mortar including all cost and conveyance
2 etc.,complete
Dismatling the Existing Damaged One Course of Pressed Tile Roof finish in cement mortar including
all cost and conveyance etc.,complete
3 Dismatling the Existing Damaged AC Sheet Roof with out Roof Timbers including all cost and
conveyance etc.,complete
4 Dismatling the Existing Damaged Cement concrete including all cost and conveyance etc.,complete
5 Earth work excavation for foundation in ordinary soil, light black cotton sandy loam and dry silt
including shoring, strutting, baling or pumping out water wherever necessary and refilling the sides of
foundation with excavated earth in layers of 15cm thick and depositing the surplus earth at places as
directed by the departmental officers with initial lead and lift

6 Supplying and filling with approved quality of dry river sand to filling in foundation and basement and
filling the site in layers of not more than 15cm thick etc., complete. Complying with standard
specifications and drawings and has directed by departmental Engineers

7 Cement concrete of mix 1:4:8 (one cement – four sand – eight broken stone) using Hard broken granite
stone jelly of 40 mm gauge for foundation leveling course, standard specifications and drawings and
has directed by departmental Engineers. Including cost and conveyance of all materials to working site,
laying concrete and curing etc.
8 Supplying and erecting in the position of MS sheets including necessary supports for plane surfaces
using MS Sheets of size 90cm x 60cm and or suitable shifted with welded mild steel angles of size
25mm x 25mm x 3mm for boarding laid over silver oak (country wood) joints of size 10cm x 6.5cm,
complete complying with standard specification below Ground level.

a). Square Columns & Sunshade

c) Lintel, Beam & Roof Slab

d) Centering without strutting below 1m height


9 Supplying, fabricating and placing in position mild steel or tar steel bars for all reinforced cement
concrete items of work including cost of steel transporting, straightening, cutting, bending, cranking,
blinding, welding etc. including cost of MS or RTS rod and binding wire, all labour and materials
complete Complying with standard specifications and drawings and has directed by departmental
Engineers.

10 Providing and laying reinforced cement concrete of mix 1:11.5:3 (one cement, one point five sand and
three metal) using machine crushed hard broken granite stone jelly 20mm ISS gauge for RCC works
but including curing etc. and including fixing fan clamps or hooks,. complete Complying with standard
specifications and drawings and has directed by departmental Engineers.

11 Plain cement concrete 1:2:4 mix (One cement two sand and four aggregate) using 20mm size ISS
gauge HBBG metal including mixing, laying, consolidating, curing, cost and conveyance of all
materials to site and all labour charges etc., complete as per standard specification
12 Brick work in cement mortar 1:5 (one cement five sand) using best quality country bricks including
cost and conveyance of all materials to working site in super sector curing etc. complete. Complying
with standard specifications and has directed by departmental Engineers. Including cost and
conveyance of all materials to working site etc.

13 Providing Gravel filling including cost and conveyance of Gravel from approved quarry to work site
and stacking to departmental gauge for pre measurement including labour for spreading complete
14 Supplying and fixing MS grill to doors windows and ventilators etc. using 20mm x 6mm as directed by
the departmental officers inclusive of cost of MS grill and labour charges including one coat of red
oxide and fixing in position etc. complete (as per schedule of rates) as per standard specification

15 Supplying & fixing door shutters for Medium Density Fiber Board of exterior grade 35mm thick,
single leaf conforming to IS:12406/1989 with 35x12 mm T.W.Lipping on all edges with necessary
adhesives and CP screws complying with standard specification. The rate is inclusive of three coats of
best quality varnish but including cost of furniture fittings. such as 125mm x 30mm Hinges 3 Nos,
300mm tower bolt 2nos, 200mm tower bolt I no. 300mm Aldrop 1 No. Alu handle ornamental type 2
16 Supplying, fabricating
Nos, and 1 No. and fixing
Door stopper in position
etc complete. of Alumi.Anod.natural
consider a door shutters ofcolour matt finish door with fully
size 1.2x2.1m
PLB board 12 mm thick using rectangular Alu.Box section of following sizes for frame and shutter
with necessary accessories such as Al. Clips, Best double action floor springs, Aluminium Handles on
both sides,floor stopper,Tower bolt, Locks and glass including all materials, Labour, power
consemption charges required for fabrication if necessary chipping, dismantling making necessary
holes in RCC Coloums, Beams or Masonry wherever necessary with power drill to the extent
required and made good to the original conditions after fixing etc.,complete. The Alumi. surface
must be anodised with matt finish under electrically controlled condition in accordance with IS
specification 1868 / 1962 of Anodic filthickness of not less than 15 Microns (Fifteen) for all
sections.All the materials should be got approved by the Engineer - In -charge before fixing as
directed.

17 Supplying and Erecting Pull and Push Type Rolling Shutter with ISI make of approved size and section
using 18 GI sheet. The shutter shall be painted with one coat of red oxide primer and the rate is
inclusive of hood covers, transportation charges etc
18 Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride) Windows of casement type (open)
from the profile the size of outer frame 60mm x 58mm and shutter profile are reinforcement with
GI/1mm 125GSM and 100% corrosion free, the profiles are multi chambered sections with wall thick
of 2mm. The EPDM rubber (black colour) covered with over all the edges of frame and shutter the
shutter will be provided with Espag multi power point locks and also it operates as handle. The corners
and joints should be welded and cleaned. Radiations free pin headed plain or brown
colour glass 4mm thick should be provided to the shutter and it should not allow leakage of water even
at most ranging storms and should have key lockable action, security protective hinges, strong locking
systems and as per size for arresting noise and energy loss. The connecting mechanism
between sash and outer frame that enables opening of the window. The window should be fixed to the
wall with 100% packing with screws and silicon packing all round the frames.The window should be
got approved from the ExecutiveEngineer before use on work

19 Supplying and fixing UPVC (Un-Plasticized Polyvinyl Chloride) Louvered Ventilators of from the
profile the size of outer frame 60mm x 58mm and shutter profile size of 60 x 78mmboth profiles are
reinforced with GI/1mm 125GSM and 100% corrosion free, the profile are multi chambered sections
with wall thick of 2mm. The EPDM rubber (black colour) covered with all over the edges of frame and
shutter.The corners and joints should be welded and cleaned. Radiations pin headed glass 4mm thick
should be provided in the louvers. The window should be fixed to the wall with 100% packing with
screws and silicon packing all round the frames. The ventilator should be got approved from the
Executive Engineer before use on work

20 Plastering with cement mortar 1:3 mix, 20mm thick including cost and conveyance of all materials to
site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete .
complying with std. specifications

21 Special Ceiling Plastering for RCC slabs and beams with cement mortar 1:3 mix 10mm thick including
cost and conveyance of all materials to site, loading and unloading charges and labour charges for
mixing, laying and curing etc. complete . complying with std. specifications

22 Plastering with cement mortar 1:5 mix, 12mm thick including cost and conveyance of all materials to
site, loading and unloading charges and labour charges for mixing, laying and curing etc. complete .
complying with std. specifications
23 Flooring with ceramic tiles of approved Colour and quality of size 305mm x 305mm x 6mm laid first
quality design of all colours in cement mortar 1:3 mix, 20mm thick and pointing with the same mortar
etc., completely and finish very neatly

24 Dadooing walls with Ceramic tiles of size 20cm x 20cm x 6mm first quality design tiles of all colours
laid in cement mortar 1:2 mix, 10mm thick and pointing with white cement using 0.40 kg/1m2
including finishing the joint and pointing flush with tile surface etc., complete

25 Paving the floor with best approved quality fine polished Rajesthan kotta stone slab of size 20mm with
machine cut edges of size below 2'0" x 2'0" laid over a cement mortar 1:3 mix, fixing the slab in true
tight angles with minimum possible width of joints and polishing the joints with cement mortar 1:3
mix and polishing with floor polisher to a high degree to finish and curing etc. complete as directed by
depat. officers.

26 Flooring with Eurocon grip tiles of size 30 x 30 x 1cm of approved colour and quality (Endura
industrial tiles) in cement mortar 1:3 mix and pointing with the same mortar etc. complete and finish
very neatly
27 Flooring with Vetrified flooring tiles of size 600 x 600 x 8mm of approved colour and quality of
required size laid in cement mortar 1:3 mix 20mm thick and pointing with the same mortar complete
and finish very neatly etc complete

28 Dadooing the walls with Vetrified tiles of size 600 x 600 x 8mm thick laid in cement mortar 1:2 mix
10mm thick and pointing with white cement using 0.40 kg./cm2 including finishing the joint and
pointing flush with tile surface etc.

29 Paving the floor with best approved quality fine polished Granite Slabstone slab of size 20mm with
machine cut edges of size below 2'0" x 2'0" laid over a cement mortar 1:3 mix, fixing the slab in true
tight angles with minimum possible width of joints and polishing the joints with cement mortar 1:3
mix and polishing with floor polisher to a high degree to finish and curing etc. complete as directed by
depat. officers.

30 Wall Finishing with Putty Powder Three Coats using Putty powder Water Primer Including all cost in
all Floors etc.,complete.
31 Supply and fixing in position of European water closet with 'S' (or) 'P' trap of approved color and
quality with dauble flapped rigid PVC sheet cover the CP brass hinges etc., complete complying with
standard specification including supply and fixing in position of 10litre capacity glazed porcelain low
level flushing tank on wall including 2 Nos of 15mm & brass nipple, 15mm dia PVC brass connection,
15mm dia GI wheel value, 15mm dia Nylon connection and giving necessary water supply connection
etc., complete complying with standard specification

32 Supplying and fixing in position best quality approved make white glazed earthen ware wash hand
basin size 550mm x 400mm with a pair of cast iron brackets including cost of 15mm Φ brass
chromium plated pillar tap, 32mm Φ C.P. waste, 32mm Φ PVC waste pipe with rubber plugs and
chain, 15mm Φ G.M. Wheel valve 15mm Φ brass nipple, 15mm Φ Nylon connections etc. Including
fixing the wash hand basin in the wall in position with a pair of C.I. Brackets with teak wood plugs and
screws and giving necessary water supply connection and painting the brackets with two coats of paint
over a priming coat of anticorrosive paint including testing for leakage etc. complete as per standard
specifications.

33 Supply & fixing in position of Indian make white glazed earthernware lipped mouth porceliain flat
back urinal with all accessories such as 32mm dia bell mouth PVC connection, 15mm dia GM wheel
valve, fixing the urinal to the wall in position with necessary TW plugs, clamps, screws, shellac etc
including dismantling brick masonry if necessary and making good of the disturbed portion to original
condition, fixing 15mm GI pipe connection and wheel valve, painting the pipe with two coats of
approved paint over one coat of primer and check without any leakage etc. complete complying with
std. specifications and as directed by dept. officers. (the Urinal should got approved by the Exe.
Engineer before use on works)

34 Weathering Course with broken brick jelly 20mm size pure slacked lime over R.C.C. roof slab the
preparation of 32:12.5 for required depth and slope etc. complete.
35 Finishing the top of roof with one course of machine pressed tiles 20 C.m x 20 C.m x 2 C.m size using
cement mortor 1:3 mix mixed with 2% by weight of Crude Oil and pointing with Cement Mortor 1:3
mix Cost of all materials and labour charges
36 Wiring with 2 x 1.5 sqmm (22 / 0.3) PVC insulated SC unsheathedCu. Conductor of 1100V grade in
suitable PVC rigid pipe concealed in wall and ceiling with PVC accessories in flush with wall with
3mm thick hylum sheet cover with TW switch box and 5A F.T switch with continuous earth wire
connection of 14 SWG TC wire for making good of the concealed portion with suitable colour for
PVC concealed light point / Fan point (For electronic regulator). (SD-23)

37 Supply and Fixing of 5A 3Pin and Combined flush type wall socket with 5A flush type switch
condealed in suitable MS Box in flush with wall and concealed with 3mm thick hylem sheet. (SD-135)
38 Supply and Fixing of 5A / 15A 3Pin and Combined flush type wall socket with 15A flush type switch
condealed in suitable MS Box in flush with wall and concealed with 3mm thick hylem sheet. (SD-135)

39 Supply and fixing of single box type 4'40 W flu fitting complete with copper choke and condensor
with TW round blocks on wall or ceiling with flu tube with PVC unsheathed Copper leads from
terminals to the fitting. (SD-88)

40 Supply and fixing of 1200 mm (48") AC ceiling fan complete with stepped electronic 300W regulator
with 1meter down rod on the existing clamp. (SD-107)

41 Painting two coats with ready mixed plastic emulsion paint of 1st class quality and of approved color
over a priming coat including through scraping clean removal of dirt etc., complete and including
necessary plaster of paris putty wherever required
42 Fabricating, Supplying and fixing of Pre painted galvanised iron sheets with the following
specification, the materials should be of PPGL tile profile with a red colour or any other approved
design 0.47mm thick 24 guage having width 1050mm. The sheet should be GI base pre painted hot
dipped galvanised iron sheet and to be fixed with shelf tapping screws, plastic washer. The washer and
screws to be fixed by using minute power machine drilled without damaging the sheets paint coating to
be regular modified polyster coat with zinc coating of Z 120 GSM paint thickness the finish should be
terra cotta finish like malabar mangalore tiles frinish optional matt finish. The sheet to be fixed with
making suitable corrugated, cutting the sheet into the required size and making ornamental designs as
per the site condition and as directed by the departmental officers.

43 Manufacturing, Supplying and Fixing of Stainless Steel Hand rails for staircase using 50mm dia 304L
Grade Stainless Steel pipe of 1.60mm thick at required locations to a height of900mm from finished
floor level welded to 38mm dia Stainless Steel pipe post of 1.00mm thick as vertical at 900mm centre
with 2 Nos. of 25mm dia intermediate horizontal stainless steel pipe of 1.60mm thick in between.The
vertical pipe has to be welded to the 100 X 100 X 6mm MS base plate encased in the base concrete.
The rate is inclusive of the charges for cutting, bending, welding,grinding, polishing, conveyance,
electrical charges, etc.complete

44 Supply and laying of 31/2 x 25 sqmm pvc armoured LTUG Cable in a treanch to be excavated at a
depth of 0.75m putting 0.150 layer of sand and covering the cable completely (SD-204)
45 Supply and fixng of TNEB Moter Board suitable for 3 Phases 200A service connection made up of
suitable angle iron frame work of size 3 feet x 2 feet using angle iron of size 1 1/2" x 1 1/2" x 1/4"
rigidly fixed on wall covered with hylem sheet of size 3 feet x 2 feet of 12mm thickness with necessary
bolts and nuts supports and supply and fixing of 3 Nos 200A fuse units (500V) 1 No. Neutral link,
copper earth flat of size 1" x 1/4" with inter connection of EB meter to fuse units by 19/16 PVC
insulated copper wire with earth connection complete - SD 131

46 Geological investigation charges preparation of geological survey report etc., complete


47 Drilling of 150mm Dia bore well in hard rack area in including labour charges for drilling and
development charges for erection of caching pipe in over burden soils all cost and conveyance etc.,
complete
a). Drilling of 150mm Dia Bore wells in overburden soil including labour charges for insertion of
casing pipes.
b). Drilling of 150mm Dia Bore wells in hard rock areas including transportation to the work site in
hard rock areas and developing the bore wells
48 Supplying of best approved quality of PVC casing pipe of 160mm dia for bore well with socket end
to suit bore well of required depth -6kg/cm2 best approved quality with ISI mark with necessary PVC
coupling etc.,

49 Supply and delivery of 10 HP Three phase Submersible Motor pumpset as per IS 8034 with ISI
tandard specification, the Duty Condition are 125 LPM x 225m head etc. complete including all cost
and conveyanve etc. complete
50 Supply and Delivery of Three Phase Panel board Star Delta with Two Level Guard and Auto Start upto
10 HP submersible motor pumpset as per standard specification
51 Supply and Fixing of the Following Pipes and Specials etc., Complete.
110mm Dia PVC Pipe
110mm Dia PVC Tee
110mm Dia PVC Elbow
32 mm G.I. Pipe
32 mm Coupling
32mm GI Elbow
32mm Gate valve
32mm GI Bend
32mm GI Union
32mm GI B Nipple 6"
32mm Dia Hex Nipple
1" Dia GI Pipe
1" Dia GI Elbow
1" Dia Union
1" Dia Gate Valve
1" x 3/4" GI Reducer
3/4" Dia GI Pipe
3/4" Dia GI Elbow
3/4" Dia GI Tee
3/4" Dia Union
3/4" Dia Gate Valve
3/4" x 1/2" GI Reducer
CP Tap
Angle Valve
50mm Dia GI Pipe 'B' Class
50mm Dia GI Coupling
50mm Dia GI Bend
50mm Dia GI Elbow

52 Supply and delivery Of 3 Core copper conductor Flat Cable (4Sq.mm) confirming to IS 694/1990
with ISI marking sutiable for Submersible Pumpset etc., Complete

53 Supply and delivery of 1000Liter Capacity HDPE tank as per IS 12701 / 1996 including loading,
unloading, transportation and labour charges for fixing of the GI pipes and specials for pipe including
cutting, threading and fixingconnection works charges etc.,

54 Provisions for GST 12%

55 Provisions for Centage Charge 2.5 %

56 Provisions for Lift arrangements etc,complete

57 Provisions for Elevation Ornamental Works etc., Complete.

58 Provision for Fire Fighting arrangements etc.,complete

59 Provision for Park Arranagements etc.complete

60 Provisions for Manual Workers Genaral Welfare Fund

61 Contengencies and other Unforseen items only

This Estimate has been prepared as per Current Schedule of Rates Year-2017-2018

Assistant engineer Assistant Executive engineer Executive engineer