Beruflich Dokumente
Kultur Dokumente
E
• Fluorocarbon 126.07 9.8 19.41 14.05 31.94 191.48 14.9
ngineers often need to predict • Glass 127.42 9.9 22.36 14.05 34.14 197.98 15.4
the cost of piping and pipefitting Fiberglass-reinforced 63.33 4.9 19.41 14.05 26.23 123.02 9.6
associated with a process unit. plastic (FRP)
Alloy 20 10 112.13 8.7 12.41 11.58 27.73 163.84 12.8
Even though detailed prices are
Monel 10 140.42 11.0 12.11 11.24 29.98 193.75 15.1
available, finding and organizing them Hastelloy C-276 10 195.07 15.2 13.17 12.14 37.47 257.84 20.1
takes time and costs money. For those Titanium 10 127.81 10.0 14.08 13.04 32.22 187.16 14.6
needing a quick method of approxima- Zirconium 10 388.29 30.3 14.08 13.04 58.45 473.86 37.0
tion (such as for a pre-design estimate), 10-cm nominal dia. — pressures up to 10 barg
a short-cut piping cost method is pre- Polyvinylchloride (PVC) 80 9.41 0.4 14.77 12.59 17.99 54.76 2.1
Chlorinated polyvinyl- 80 26.62 1.0 14.77 12.59 19.48 73.47 2.8
sented in this article. For convenience chloride (CPVC)
and compactness, the relevant equa- Carbon Steel 40 25.85 1.0 11.49 14.61 20.69 72.64 2.8
tions and data lists are superimposed Stainless 304L 10 39.69 1.5 12.40 14.61 23.23 89.94 3.5
on the same diagram as the base cost Stainless 316L 10 49.63 1.9 12.41 14.61 23.98 100.63 3.9
curves (p. 48). The method of the chart’s Lined carbon steel 40
• Rubber 49.97 1.9 24.30 16.86 28.89 120.02 4.6
compilation and other background de-
• Conventional plastic 132.23 5.1 26.98 16.86 38.22 214.30 8.3
tails are described below. • Fluorocarbon 239.81 9.3 24.30 16.86 48.37 329.34 12.7
Lindley and Floyd [1] reported de- • Glass 215.41 8.3 30.35 16.86 48.32 310.95 12.0
tailed data for more than 30 types of Fiberglass-reinforced 91.43 3.5 24.30 16.86 33.72 166.31 6.4
piping in three diameters (2, 4 and 6 plastic (FRP)
Alloy 20 10 232.83 9.0 12.85 15.06 43.47 304.21 11.8
in., essentially equivalent to 5, 10 and
Monel 10 324.09 12.5 12.55 14.61 51.71 402.97 15.6
15 cm. nominal dia.) and two types of Hastelloy C-276 10 557.37 21.6 13.62 15.96 77.94 664.89 25.7
installation: Titanium 10 282.15 10.9 14.52 17.31 51.71 365.70 14.1
1. Simple straight runs such as those Zirconium 10 1017.76 39.4 14.52 17.31 125.15 1174.75 45.4
used to convey raw materials from 15-cm nominal dia. — pressures up to 10 barg
storage to a process module Polyvinylchloride (PVC) 80 16.84 0.4 17.94 14.39 21.73 70.90 1.7
Chlorinated polyvinyl- 80 51.55 1.2 17.94 14.39 25.48 109.36 2.6
2. Complex systems such as the chloride (CPVC)
plumbing associated with a distilla- Carbon Steel 40 42.40 1.0 12.37 17.09 25.79 97.65 2.3
tion column or heat exchanger Stainless 304L 10 63.51 1.5 13.28 17.09 28.48 122.36 2.9
That database is, no doubt, valued by Stainless 316L 10 80.90 1.9 13.28 17.09 29.98 141.24 3.3
many who prepare detailed definitive Lined carbon steel 40 0.0
• Rubber 58.15 1.4 30.06 19.67 33.98 141.86 3.3
cost estimates. We likewise found it
• Conventional plastic 215.34 5.1 35.22 19.67 51.71 321.94 7.6
useful to construct our short-cut chart, • Fluorocarbon 359.90 8.5 30.06 19.67 64.45 474.08 11.2
which is applicable to the same set of • Glass 373.16 8.8 37.77 19.67 69.13 499.72 11.8
piping sizes and materials. Fiberglass-reinforced 152.43 3.6 30.06 19.67 43.84 246.00 5.8
plastic (FRP)
Alloy 20 10 364.58 8.6 13.73 17.76 59.20 455.27 10.7
Simple, straight pipe runs
Monel 10 912.96 21.5 13.43 17.09 113.91 1057.39 24.9
Consider a simple system made of Hastelloy C-276 10 750.98 17.7 14.49 18.89 100.42 884.78 20.9
standard piping suitable for pressures Titanium 10 415.52 9.8 15.40 20.68 68.95 520.55 12.3
up to 10 barg at ambient tempera- Zirconium 10 1168.91 27.6 15.40 20.68 144.64 1349.64 31.8
������������� �������
Pipe type Sched- CP·a FM·a Pipe Field Equipment, CBM·a FBM·a ��� �������
ule Base cost Material Racks, instal- engineering, Total bare Instal-
pipe, flanges, Factor $/m lation, contractor’s module lation
�
and prepara- $/m expenses, cost, $/m factor
tion, $/m $/m
5-cm nominal diameter — pressures up to 10 barg ������������
Polyvinylchloride (PVC) 80 18.42 0.4 7.62 23.27 29.11 78.42 1.7 ����������
Chlorinated polyvinyl- 80 26.09 0.6 7.62 23.27 30.43 87.40 1.9
chloride (CPVC) ��
Carbon Steel 40 46.67 1.0 19.56 23.44 50.79 140.45 3.0 � �� ���
Stainless 304L 10 71.96 1.5 19.88 23.44 53.13 168.41 3.6 ���������������������
Stainless 316L 10 83.62 1.8 19.88 23.44 52.83 179.77 3.9
Lined carbon steel 40 FIGURE 1. To obtain an installed price
• Rubber 80.31 1.7 25.88 25.85 40.48 172.53 3.7 for any either complex or straight-run pip-
• Conventional plastic 204.03 4.4 29.04 25.85 50.85 309.77 6.6 ing, simply multiply the appropriate value
• Fluorocarbon 329.87 7.1 25.88 25.85 60.38 441.99 9.5 from this figure by the installation factor,
• Glass 294.49 6.3 31.67 25.85 61.90 413.92 8.9 FBM·a, for that material
Fiberglass-reinforced 180.23 3.9 25.88 25.85 49.18 281.15 6.0
plastic (FRP)
ture.1 To prepare carbon steel pipe
Alloy 20 10 325.92 7.0 20.03 23.55 72.84 442.34 9.5
Monel 10 285.72 6.1 19.94 23.44 69.32 398.42 8.5
for straight runs, it is normally cut to
Hastelloy C-276 10 420.80 9.0 20.28 23.55 87.31 551.93 11.8 length (typically 6 or 12 m) in a shop
Titanium 10 356.52 7.6 20.62 23.66 86.78 487.58 10.4 where flanges are welded at each end.
Zirconium 10 763.40 16.4 20.62 23.66 120.88 928.56 19.9 These “thimbles” are sandblasted,
10-cm nominal dia. — pressures up to 10 barg painted and otherwise made ready for
Polyvinylchloride (PVC) 80 36.91 0.5 7.62 27.93 40.02 112.48 1.4
transport to the plant site.2 In 1993,
Chlorinated polyvinyl- 80 66.59 0.8 7.62 27.93 42.04 144.18 1.8
chloride (CPVC) Lindley and Floyd reported the price
Carbon Steel 40 80.62 1.0 30.48 28.19 75.16 214.45 2.7 for such preconditioned, Schedule 40,
Stainless 304L 10 139.64 1.7 30.79 28.19 79.89 278.50 3.5 5-cm (2 in.) nominal dia., carbon-steel
Stainless 316L 10 164.25 2.0 30.79 28.19 82.21 305.44 3.8 pipe to be $1,711 for a 500-ft long
Lined carbon steel 40
(152.4-m) section. This corresponds
• Rubber 111.29 1.4 45.12 32.60 61.34 250.35 3.1
• Conventional plastic 382.20 4.7 50.59 32.60 84.23 549.62 6.8
to a base price of $11.23/m in 1993
• Fluorocarbon 588.56 7.3 45.12 32.60 98.70 764.98 9.5 dollars. For this article, we escalated
• Glass 486.91 6.0 57.02 32.60 100.72 677.25 8.4 numbers to mid-2003 dollars by mul-
Fiberglass-reinforced 267.92 3.3 45.12 32.60 74.38 420.02 5.2 tiplying all 1993 data by 400 (the CE
plastic (FRP)
Plant Cost Index [CE PCI] for mid
Alloy 20 10 732.76 9.1 30.94 28.24 124.25 916.20 11.4
Monel 10 706.76 8.8 30.86 28.19 123.58 889.38 11.0
2003) and then dividing it by 350 (the
Hastelloy C-276 10 1072.30 13.3 31.19 28.36 165.55 1297.39 16.1 CE PCI for 1993). The resulting 5-cm
Titanium 10 765.74 9.5 31.53 28.52 145.87 971.67 12.1 carbon-steel base price in mid-2003
Zirconium 10 1852.97 23.0 31.53 28.52 238.46 2151.49 26.7 dollars is $12.83/m, the value shown
15-cm nominal dia. — pressures up to 10 barg in the third row of Table 1.
Polyvinylchloride (PVC) 80 65.26 0.5 10.46 32.17 49.01 156.90 1.3
To update data in this article to a
Chlorinated polyvinyl- 80 127.78 1.0 10.46 32.17 54.07 224.49 1.8
chloride (CPVC)
1. Ranges of suitable temperatures vary widely,
Carbon Steel 40 124.18 1.0 39.57 32.51 95.16 291.42 2.3 depending on type of pipe. Some conventional
Stainless 304L 10 262.43 2.1 39.47 32.51 104.02 438.42 3.5 plastic pipe is limited to 65°C (service tem-
Stainless 316L 10 313.44 2.5 39.47 32.51 108.67 494.08 4.0 peratures for specific polymers can be found in
Dennis [2] or in Perry [3], Tables 10-15, 10-16,
Lined carbon steel 40 10-17, and 28-22). Copper and aluminum tubing
• Rubber 137.44 1.1 58.20 39.34 73.46 308.45 2.5 are not normally recommended above 150°C.
• Conventional plastic 635.69 5.1 64.64 39.34 114.40 854.07 6.9 Carbon steel is suitable to 500°C if protected
from oxidation. Stainless steels and nickel al-
• Fluorocarbon 919.33 7.4 58.20 39.34 132.25 1149.12 9.3 loys serve up to 600°C under favorable circum-
• Glass 785.32 6.3 73.35 39.34 135.41 1033.42 8.3 stances. Limits for titanium and glass-lined
Fiberglass-reinforced 506.23 4.1 58.20 39.34 101.66 705.43 5.7 pipe are 315°C and 232°C respectively (Perry
plastic (FRP) [3], pages 10-96 and 10-99).
Alloy 20 10 1171.58 9.4 39.62 32.59 173.04 1416.83 11.4 2. Some of those preparation steps could be con-
sidered installation expenses rather than part
Monel 10 1610.63 13.0 39.53 32.51 216.73 1899.40 15.3 of base pipe cost. We included them in the base
Hastelloy C-276 10 1685.59 13.6 39.87 32.73 227.37 1985.57 16.0 cost to place all pipe on the same footing, because
Titanium 10 1368.80 11.0 40.21 32.96 209.80 1651.76 13.3 some types come from the factory as thimbles
already prepared for the field with no need for
Zirconium 10 2714.46 21.9 40.21 32.96 317.23 3104.85 25.0 cleaning, painting, or welding.
O
wners of a steam boiler are considering a plant expansion. pipe is calculated to be 4.9 from Equation (3). Thus, the mid-
No change is planned for the boiler module itself, but its 2003 bare-module cost of uninsulated pipe is 4.9 $11.50/m
fuel-oil storage tanks are to be relocated. This will require a = $56/m.
new fuel-feed pipeline, 65 m in length. Construction is expected to The pipe must be traced to maintain its temperature at 95°C.
occur in 2006. Estimate the cost of running the new line. From Equation (5), the optimum insulation thickness is found to
An operator pumps fuel from storage to the feed drum once every be 2.6 cm. With this value for topt and 4.8 cm for Dact, we find
shift for a period of 15 minutes, requiring a flow of 3.9 liter/s. an additional cost of $22/m for insulation. Thus, the total bare
Perry [3], page 6-14, suggests an optimum flow velocity in the module cost in 2003 dollars is $78/m or $5,100 for a 65-m
range of 1.8–2.4 m/s for this situation. Nominal-3.8-cm standard run. Based on a projected CE Plant Cost Index of 485, the 2006
pipe will suffice (1-1/2 in., Schedule 40, 4.1-cm actual inside di- predicted price is $5,100 485/400 = $6,200.
ameter, 4.8 cm OD).a, b Past experience with the old line suggests that we might save
A corrosion checkc confirms common experience that almost any in maintenance dollars and aggravation if we make the line of
of the metals covered by the short-cut chart (p. 48) will contain Schedule 10, Type 304 stainless steel. In this case, FM is 1.5,
the fuel without corroding. Carbon steel, the current metal, has leading to a value of 5.5 for FBM. Uninsulated pipe cost is 5.5
served for many years, and maintenance people tell us that sur- $11.50/m = $63/m. With insulation at $22/m, the bare module
face conditions inside the pipe are like new. Otherwise, weather cost is $85/m or $5,525 in 2003 dollars; $6,700 in 2006. The
exposure on the outside has required periodic repainting and difference is slight enough to seriously consider stainless steel.
other maintenance. A more experienced engineer notes that even though Sched-
According to the short-cut chart (p. 48), the base cost CP·cs for ule-10 or light-wall pipe is adequate for the pressure and expo-
nominal 3.8 cm pipe (straight run) is $11.50/m. For carbon steel sure, it may not tolerate abused. A heavier wall stock would be
with material and pressure factors of unity, FBM•cs for straight-run safer. She suggests using 304 stainless steel, Schedule-40 pipe.
Since this is the wall thickness in alloy piping denoted for high
a. At 2.4 m/s, the calculated diameter is 4.5 cm. Optimum pipe diame- pressure service, we can estimate its price by using a pressure
ters/flow velocities from Perry [3] assume continuous pumping of fluid. A
rigorous analysis of batch transfers like this one will push the optimum factor of 1.6 in the equation for FBM. Doing so, we find FBM
to a slightly smaller diameter and a higher velocity for Schedule 40, 304-stainless-steel pipe is 6.5. Its 2006 bare
b. We must, of course, choose a diameter that is commercially available. module price is $7,600 for the 65 m line. ❒
Standard U.S. nominal pipe sizes are denoted by ticks on the horizontal
axis of the short-cut chart, p. 48.
d. A large fraction of industrial safety/pollution incidents is caused by
c. See, for example, Table 4-1a, Ulrich and Vasudevan [8] vehicles puncturing outdoor pipelines and storage tanks
results by the ratio of the future CE Table 3 lists material factors for vari- where FM values are those listed in
PCI to 400. In mid 2007, for instance, ous piping materials alongside values Columns 4 of Tables 1 and 2, and
current trends suggest a CE PCI of that have been published throughout Fp = 1.0 for pressures less than 10 barg
500. Thus, mid-2007 prices would be literature for other types of equip- Fp = 1.6 for 10 to 40 barg pressure
25% greater than those cited in this ment. Values for alloy plate, pumps,
example. heat exchangers, process vessels, and Insulation costs
To make things easier for spread- so on, are included. With the information assembled thus
sheet formulation, we gain generality far, one can quickly estimate installed
and consistency with a minor loss of High pressure service prices for simple and complex net-
precision by using equations to calcu- By an analysis similar to that just works from Figure 1 for fifteen differ-
late installation factors. For straight- described, pressure factors can be de- ent types of pipe between 5 and 15-cm
runs, Equation (1) yields factors for all rived to predict bare module prices of nominal dia. at pressures up to 40
three diameters that, on average, fall heavier pipe. Lindley and Floyd in- barg. The approach is even more use-
within ±5% of those listed in Table 17 cluded data for seven piping materials ful if it is extended to include the cost
FBM⋅a = 11.6 D −0.84 + 1.13 FM ⋅a rated for up to 40 barg pressure. These of insulation, which is necessary in
(1) higher pressure piping costs can be most chemical process applications.
The following equation does almost as predicted via Figure 1 if equations for Finding the optimum thickness of
well for complex networks in Table 2 FBM are revised by replacing FM in pipe insulation is discussed in Chap-
each case with the product FM·Fp. ter 7 of Ulrich and Vasudevan [8].
FBM⋅a = 2.0 − 0.024 D − 0.001D2 + 1.22 FM⋅a
Straight-run piping systems: Based on that analysis using 2003
−0.011D ⋅ FM⋅a − 0.015 D ⋅ ( FM⋅a )
−2
(2) energy prices, one finds the optimum
FBM⋅a = 11.6 D –0.84 + 1.13 FM ⋅a ⋅ Fp
With these equations, a list of mate- (3) insulation thickness to be10
rial factors, and two cost curves, one Complex piping networks: 0.20
topt = 0.85 Dnom ⋅ ∆T 0.65
can estimate bare module prices for 2
(5)
FBM⋅a = 2.0 – 0.024 D − 0.001D + 1.22 FM⋅a ⋅ Fp
straight-run and complex piping sys- where
( )
−2
tems in 15 materials and all diameters −0.011D ⋅ FM⋅a ⋅ Fp − 0.015 D FM⋅a ⋅ Fp topt = optimum insulation thickness,
between 5 and 15 cm.8, 9 For context, (4) cm
Dnom = bare pipe nominal diameter,
7. Two thirds of the calculations fall within plus eter. The act of smoothing data with a general cm
or minus 5%. None differs by more than 20% correlation like the one we are building might ∆T = the difference between pipe tem-
from original data. actually improve their reliability.
8. For a few materials in Tables 1 and 2, FM·a
perature and ambient, °C
9. Pipe made from premium metals, because of
varies erratically from one pipe size to another. greater strength and smaller corrosion allow- With thickness known, the 2003 cost
This stems from the data source where Hastel- ance, can be lighter than carbon steel. Thin-wall
loy C-276, for example, is reported to cost 70% (schedule 10) stainless steel and alloy piping 10. Steam-traced pipe based on energy costs of
more than Monel in 10-cm pipe but 15% less in serves at pressures up to 10 barg, for example, $3.80/GJ. For other energy prices, electrical trac-
15-cm pipe. Except for a few discrepancies like in service where schedule 40 would be required ing, and different circumstances, see Ulrich and
this, relative prices in Lindley and Floyd’s tables if made from carbon steel. Schedule 40 alloy pipe Vasudevan [8], Chapter 7 or Perry [3], Tables 11-
change only slightly and consistently with diam- can often be used at pressures up to 40 barg. 21 and 11-22.
�������������� �������
�������
CBM = FBM ⋅ CP⋅cs + CBM⋅Ins
(
CBM⋅Ins = 1.13 ⋅ topt Dact + topt )
For straight-run piping systems:
������������
FBM⋅a = 11.6 D –0.84 + 1.13 FM ⋅a Fp ����������
���������
��������
For complex piping networks: �����
������
���� ���� �� ������ �� �� �� �� �� �� ��� ���
FBM⋅a = 2.0 – 0.024 D − 0.001D2 + 1.22 FM ⋅a ⋅ Fp ��
������ ������ ��� ���
( )
−2 � �� ���
−0.011D ⋅ FM ⋅a ⋅ Fp − 0.015 D FM ⋅a ⋅ Fp �����������������������������
of purchasing and installing insula- trapolated with confidence outside the p⋅ D (8)
t=
tion can be calculated from 5–15 cm range.) 2(0.9 S − 0.6 p)
First, one would expect the cost of With typical design-stress values S
(
CBM⋅Ins = 1.13 ⋅ topt Dact + topt ) pipe to be proportional to mass — a falling in the range of 1,000 bara and
(6) variation on π·D·t·L. Accordingly, for at pipe internal pressures of 40 barg
where Dact is actual bare-pipe outside pipes of different diameter made from or less, the second term in the denom-
diameter, cm the same material, their base cost inator’s parenthetical expression can
ratio would be be disregarded. Thus, wall thickness
The cost chart CP 1⋅a D1 ⋅ t1 is directly proportional to pressure
Finally, we have the information to = and diameter. For pipes of the same
CP 2⋅a D2 ⋅ t2
prepare a refined, comprehensive cost (7) material designed to handle the same
chart. In composing it, let us consider The relevant design expression that pressure, thickness ratio is, therefore,
basic capital cost concepts and revisit relates wall thickness to material equal to diameter ratio.
the lines in Figure 1. (With creative strength, pressure, and diameter is11: t1 D1 (9)
=
insight, these curves might be ex- 11. See Ulrich and Vasudevan [8], p. 95. t2 D2