Sie sind auf Seite 1von 6

Feature Report

Short-Cut Piping Costs


This method saves TABLE 1. STRAIGHT RUN PROCESS PIPING —
BASE COSTS AND BARE MODULE INSTALLED PRICES
precious time in Pipe type Sched- CP·a
ule
FM·a Pipe Field Equipment,
Base cost pipe, Material Racks, installa- engineering,
CBM·a
Total bare
FBM·a
Instal-

preparing estimates for flanges, and


preparation,
$/m
Factor $/m tion, $/m contractor’s
expenses,
$/m
module cost,
$/m
lation
factor

pre-design and other Polyvinylchloride (PVC) 80


5-cm nominal diameter — pressures up to 10 barg
3.63 0.3 14.77 9.89 15.74 44.03 3.4

approximated analyses Chlorinated polyvinyl-


chloride (CPVC)
80 9.35 0.7 14.77 9.89 15.74 49.75 3.9

Carbon Steel 40 12.83 1.0 11.05 11.24 16.25 51.36 4.0


Stainless 304L 10 19.92 1.6 11.95 11.24 17.99 61.10 4.8
Gael D. Ulrich and Stainless 316L 10 25.67 2.0 11.95 11.24 18.74 67.60 5.3
Palligarnai T. Vasudevan Lined carbon steel 40
• Rubber 29.20 2.3 19.41 14.05 22.20 84.86 6.6
University of New Hampshire
• Conventional plastic 61.68 4.8 20.91 14.05 26.98 123.62 9.6

E
• Fluorocarbon 126.07 9.8 19.41 14.05 31.94 191.48 14.9
ngineers often need to predict • Glass 127.42 9.9 22.36 14.05 34.14 197.98 15.4
the cost of piping and pipefitting Fiberglass-reinforced 63.33 4.9 19.41 14.05 26.23 123.02 9.6
associated with a process unit. plastic (FRP)
Alloy 20 10 112.13 8.7 12.41 11.58 27.73 163.84 12.8
Even though detailed prices are
Monel 10 140.42 11.0 12.11 11.24 29.98 193.75 15.1
available, finding and organizing them Hastelloy C-276 10 195.07 15.2 13.17 12.14 37.47 257.84 20.1
takes time and costs money. For those Titanium 10 127.81 10.0 14.08 13.04 32.22 187.16 14.6
needing a quick method of approxima- Zirconium 10 388.29 30.3 14.08 13.04 58.45 473.86 37.0
tion (such as for a pre-design estimate), 10-cm nominal dia. — pressures up to 10 barg
a short-cut piping cost method is pre- Polyvinylchloride (PVC) 80 9.41 0.4 14.77 12.59 17.99 54.76 2.1
Chlorinated polyvinyl- 80 26.62 1.0 14.77 12.59 19.48 73.47 2.8
sented in this article. For convenience chloride (CPVC)
and compactness, the relevant equa- Carbon Steel 40 25.85 1.0 11.49 14.61 20.69 72.64 2.8
tions and data lists are superimposed Stainless 304L 10 39.69 1.5 12.40 14.61 23.23 89.94 3.5
on the same diagram as the base cost Stainless 316L 10 49.63 1.9 12.41 14.61 23.98 100.63 3.9
curves (p. 48). The method of the chart’s Lined carbon steel 40
• Rubber 49.97 1.9 24.30 16.86 28.89 120.02 4.6
compilation and other background de-
• Conventional plastic 132.23 5.1 26.98 16.86 38.22 214.30 8.3
tails are described below. • Fluorocarbon 239.81 9.3 24.30 16.86 48.37 329.34 12.7
Lindley and Floyd [1] reported de- • Glass 215.41 8.3 30.35 16.86 48.32 310.95 12.0
tailed data for more than 30 types of Fiberglass-reinforced 91.43 3.5 24.30 16.86 33.72 166.31 6.4
piping in three diameters (2, 4 and 6 plastic (FRP)
Alloy 20 10 232.83 9.0 12.85 15.06 43.47 304.21 11.8
in., essentially equivalent to 5, 10 and
Monel 10 324.09 12.5 12.55 14.61 51.71 402.97 15.6
15 cm. nominal dia.) and two types of Hastelloy C-276 10 557.37 21.6 13.62 15.96 77.94 664.89 25.7
installation: Titanium 10 282.15 10.9 14.52 17.31 51.71 365.70 14.1
1. Simple straight runs such as those Zirconium 10 1017.76 39.4 14.52 17.31 125.15 1174.75 45.4
used to convey raw materials from 15-cm nominal dia. — pressures up to 10 barg
storage to a process module Polyvinylchloride (PVC) 80 16.84 0.4 17.94 14.39 21.73 70.90 1.7
Chlorinated polyvinyl- 80 51.55 1.2 17.94 14.39 25.48 109.36 2.6
2. Complex systems such as the chloride (CPVC)
plumbing associated with a distilla- Carbon Steel 40 42.40 1.0 12.37 17.09 25.79 97.65 2.3
tion column or heat exchanger Stainless 304L 10 63.51 1.5 13.28 17.09 28.48 122.36 2.9
That database is, no doubt, valued by Stainless 316L 10 80.90 1.9 13.28 17.09 29.98 141.24 3.3
many who prepare detailed definitive Lined carbon steel 40 0.0
• Rubber 58.15 1.4 30.06 19.67 33.98 141.86 3.3
cost estimates. We likewise found it
• Conventional plastic 215.34 5.1 35.22 19.67 51.71 321.94 7.6
useful to construct our short-cut chart, • Fluorocarbon 359.90 8.5 30.06 19.67 64.45 474.08 11.2
which is applicable to the same set of • Glass 373.16 8.8 37.77 19.67 69.13 499.72 11.8
piping sizes and materials. Fiberglass-reinforced 152.43 3.6 30.06 19.67 43.84 246.00 5.8
plastic (FRP)
Alloy 20 10 364.58 8.6 13.73 17.76 59.20 455.27 10.7
Simple, straight pipe runs
Monel 10 912.96 21.5 13.43 17.09 113.91 1057.39 24.9
Consider a simple system made of Hastelloy C-276 10 750.98 17.7 14.49 18.89 100.42 884.78 20.9
standard piping suitable for pressures Titanium 10 415.52 9.8 15.40 20.68 68.95 520.55 12.3
up to 10 barg at ambient tempera- Zirconium 10 1168.91 27.6 15.40 20.68 144.64 1349.64 31.8

44 CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2006


NOMENCLATURE
CBM·a Bare module price of piping material Dact Bare pipe actual outside diameter, cm Fp
Pressure factor, dimensionless
”a”, i.e., its total contribution to the FBM·a Bare module installation factor for L
Pipe length, m
capital cost of a process material “a“ (ratio of bare module p
Internal pipe pressure, barg (bars gage)
module, $/m installed cost to purchase price of car- S
Design stress of pipeline material,
CBM·Ins Bare module price of piping bon steel), dimensionless bara (bar absolute)
insulation, $/m of pipe length FM·a Material factor for material “a“ t Pipe wall thickness, cm
CP·a Base cost or purchase price of (quotient of base cost CP·a for piping topt Optimum insulation thickness, cm
piping material “a“ prepared for material divided by CP·cs the base cost ∆T Difference between pipe temperature
transport to an installation site, $/m of carbon steel pipe having the same and ambient, °C
D, Dnom Bare pipe nominal diameter, cm diameter), dimensionless

TABLE 2. COMPLEX PIPING SYSTEMS —


BASE COSTS AND BARE MODULE INSTALLED PRICES �������������

������������� �������
Pipe type Sched- CP·a FM·a Pipe Field Equipment, CBM·a FBM·a ��� �������
ule Base cost Material Racks, instal- engineering, Total bare Instal-
pipe, flanges, Factor $/m lation, contractor’s module lation


and prepara- $/m expenses, cost, $/m factor
tion, $/m $/m
5-cm nominal diameter — pressures up to 10 barg ������������
Polyvinylchloride (PVC) 80 18.42 0.4 7.62 23.27 29.11 78.42 1.7 ����������
Chlorinated polyvinyl- 80 26.09 0.6 7.62 23.27 30.43 87.40 1.9
chloride (CPVC) ��
Carbon Steel 40 46.67 1.0 19.56 23.44 50.79 140.45 3.0 � �� ���
Stainless 304L 10 71.96 1.5 19.88 23.44 53.13 168.41 3.6 ���������������������
Stainless 316L 10 83.62 1.8 19.88 23.44 52.83 179.77 3.9
Lined carbon steel 40 FIGURE 1. To obtain an installed price
• Rubber 80.31 1.7 25.88 25.85 40.48 172.53 3.7 for any either complex or straight-run pip-
• Conventional plastic 204.03 4.4 29.04 25.85 50.85 309.77 6.6 ing, simply multiply the appropriate value
• Fluorocarbon 329.87 7.1 25.88 25.85 60.38 441.99 9.5 from this figure by the installation factor,
• Glass 294.49 6.3 31.67 25.85 61.90 413.92 8.9 FBM·a, for that material
Fiberglass-reinforced 180.23 3.9 25.88 25.85 49.18 281.15 6.0
plastic (FRP)
ture.1 To prepare carbon steel pipe
Alloy 20 10 325.92 7.0 20.03 23.55 72.84 442.34 9.5
Monel 10 285.72 6.1 19.94 23.44 69.32 398.42 8.5
for straight runs, it is normally cut to
Hastelloy C-276 10 420.80 9.0 20.28 23.55 87.31 551.93 11.8 length (typically 6 or 12 m) in a shop
Titanium 10 356.52 7.6 20.62 23.66 86.78 487.58 10.4 where flanges are welded at each end.
Zirconium 10 763.40 16.4 20.62 23.66 120.88 928.56 19.9 These “thimbles” are sandblasted,
10-cm nominal dia. — pressures up to 10 barg painted and otherwise made ready for
Polyvinylchloride (PVC) 80 36.91 0.5 7.62 27.93 40.02 112.48 1.4
transport to the plant site.2 In 1993,
Chlorinated polyvinyl- 80 66.59 0.8 7.62 27.93 42.04 144.18 1.8
chloride (CPVC) Lindley and Floyd reported the price
Carbon Steel 40 80.62 1.0 30.48 28.19 75.16 214.45 2.7 for such preconditioned, Schedule 40,
Stainless 304L 10 139.64 1.7 30.79 28.19 79.89 278.50 3.5 5-cm (2 in.) nominal dia., carbon-steel
Stainless 316L 10 164.25 2.0 30.79 28.19 82.21 305.44 3.8 pipe to be $1,711 for a 500-ft long
Lined carbon steel 40
(152.4-m) section. This corresponds
• Rubber 111.29 1.4 45.12 32.60 61.34 250.35 3.1
• Conventional plastic 382.20 4.7 50.59 32.60 84.23 549.62 6.8
to a base price of $11.23/m in 1993
• Fluorocarbon 588.56 7.3 45.12 32.60 98.70 764.98 9.5 dollars. For this article, we escalated
• Glass 486.91 6.0 57.02 32.60 100.72 677.25 8.4 numbers to mid-2003 dollars by mul-
Fiberglass-reinforced 267.92 3.3 45.12 32.60 74.38 420.02 5.2 tiplying all 1993 data by 400 (the CE
plastic (FRP)
Plant Cost Index [CE PCI] for mid
Alloy 20 10 732.76 9.1 30.94 28.24 124.25 916.20 11.4
Monel 10 706.76 8.8 30.86 28.19 123.58 889.38 11.0
2003) and then dividing it by 350 (the
Hastelloy C-276 10 1072.30 13.3 31.19 28.36 165.55 1297.39 16.1 CE PCI for 1993). The resulting 5-cm
Titanium 10 765.74 9.5 31.53 28.52 145.87 971.67 12.1 carbon-steel base price in mid-2003
Zirconium 10 1852.97 23.0 31.53 28.52 238.46 2151.49 26.7 dollars is $12.83/m, the value shown
15-cm nominal dia. — pressures up to 10 barg in the third row of Table 1.
Polyvinylchloride (PVC) 80 65.26 0.5 10.46 32.17 49.01 156.90 1.3
To update data in this article to a
Chlorinated polyvinyl- 80 127.78 1.0 10.46 32.17 54.07 224.49 1.8
chloride (CPVC)
1. Ranges of suitable temperatures vary widely,
Carbon Steel 40 124.18 1.0 39.57 32.51 95.16 291.42 2.3 depending on type of pipe. Some conventional
Stainless 304L 10 262.43 2.1 39.47 32.51 104.02 438.42 3.5 plastic pipe is limited to 65°C (service tem-
Stainless 316L 10 313.44 2.5 39.47 32.51 108.67 494.08 4.0 peratures for specific polymers can be found in
Dennis [2] or in Perry [3], Tables 10-15, 10-16,
Lined carbon steel 40 10-17, and 28-22). Copper and aluminum tubing
• Rubber 137.44 1.1 58.20 39.34 73.46 308.45 2.5 are not normally recommended above 150°C.
• Conventional plastic 635.69 5.1 64.64 39.34 114.40 854.07 6.9 Carbon steel is suitable to 500°C if protected
from oxidation. Stainless steels and nickel al-
• Fluorocarbon 919.33 7.4 58.20 39.34 132.25 1149.12 9.3 loys serve up to 600°C under favorable circum-
• Glass 785.32 6.3 73.35 39.34 135.41 1033.42 8.3 stances. Limits for titanium and glass-lined
Fiberglass-reinforced 506.23 4.1 58.20 39.34 101.66 705.43 5.7 pipe are 315°C and 232°C respectively (Perry
plastic (FRP) [3], pages 10-96 and 10-99).
Alloy 20 10 1171.58 9.4 39.62 32.59 173.04 1416.83 11.4 2. Some of those preparation steps could be con-
sidered installation expenses rather than part
Monel 10 1610.63 13.0 39.53 32.51 216.73 1899.40 15.3 of base pipe cost. We included them in the base
Hastelloy C-276 10 1685.59 13.6 39.87 32.73 227.37 1985.57 16.0 cost to place all pipe on the same footing, because
Titanium 10 1368.80 11.0 40.21 32.96 209.80 1651.76 13.3 some types come from the factory as thimbles
already prepared for the field with no need for
Zirconium 10 2714.46 21.9 40.21 32.96 317.23 3104.85 25.0 cleaning, painting, or welding.

CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2006 45


Feature Report

year after 2003, multiply your result


TABLE 3. MATERIAL FACTORS FOR SELECTED CONSTRUCTION
by the overall CE PCI for the more
MATERIALS AND COMPONENTSe
recent time period and then divide by
Material Pipec Metal Process vessels, Pumpsa Heat exchang-
400 (the value for mid 2003). For ex- plated etc. a,b ers a,b
ample, per the final Dec. 2005 index Carbon steel 1.0 1.0 1.0 1.0 1.0
(the most up to date CE PCI as of this Aluminum 1.5
issue, p. 84) the ratio is approximately Copper/Brass 1.8 1.4
476/400 or 1.19. Rubber-lined steel 1.6 1.3 1.4
Meanwhile, installation includes Stainless, 304 1.7 1.7 2.8 1.7
Stainless, 316 2.0 2.0 2.9 1.8
transport to the site, pipe rack con-
Alloy 20 8.6 5 6.1 5.2
struction, pipe assembly, equipment Titanium 9.8 13-35 10.7 8.7
rental, labor and contractor fees. The Monel 12 20 9.0 3.3 7.3
sum of updated costs for these activities Hastelloy C-276 15 15 12.5 10.1
reported by Lindley and Floyd yields Zirconium 26 11 8.7
an installed bare-module value equal a. Holland and Wilkinson (Perry [3], page 9-74)
to $51.40/m for 5-cm dia., Schedule 40, b. Yau and Bird [6]
c. This study, average of all data in Tables 1 and 2
carbon steel pipe. Installed cost divided
d. McMaster-Carr [7] catalogue
by the base price ($51.40/m ÷ $12.80/ e. Because of labor, installation factors are not the same as material factors. The material factor for
m) yields a bare module (installation) titanium, for example, is about 10 times that of carbon steel. The ratio of installed costs, on the other
hand, is usually between 3 and 5 because much of the expense involves labor, which is basically the
factor FBM·cs of 4.0.3 Installation fac- same for both materials. Because of ambiguity in some data sources, some numbers in this list may
tors for 14 other types of piping were be ratios of installed costs rather than ratios of purchase prices (the definition of FM in this article)
computed via the same procedure and
are listed in Table 1. (Values quoted costs four times as much as the average ter (Figure 1).6 There are two lines: one
above for carbon steel can be found in fitting. Results are contained in Table for straight runs, the other for complex
the carbon steel row of the 5-cm-pipe 2. By way of explanation, consider each piping networks. This requires only six
sub-table.) Material factors, FBM·a column of that table briefly: data points from Tables 1 and 2; for
(where subscript “a” denotes material • Base costs, valves included, are straight-run and complex carbon-steel
of construction), are equal to the base listed in column three4 piping in three diameters.
cost, CP·a (again, where subscript “a” • FM·a material factors (ratios of CP·a
denotes material of construction), for to CP·cs), are listed in column four Different materials of
each type of piping divided by CP·cs, the • Pipe rack costs (unaffected by the construction and installation
base cost of carbon steel pipe having presence of valves) were drawn di- Two simple curves for carbon steel
the same diameter. rectly from Lindley and Floyd5 pipe in Figure 1 serve as the launch-
• Columns six and seven, Field installa- ing point from which installed costs
Complex piping systems tion, and Equipment engineering and of many types and sizes of pipes will
Complex piping systems were ana- contractor fees, were revised by as- be estimated. To obtain an installed
lyzed by an approach similar to that suming that reported differences be- price for any type of pipe, one simply
used for straight pipe runs. Lindley tween complex and straight-run pipe multiplies the appropriate value from
and Floyd assumed a layout averag- were due to fittings. These differences Figure 1 by the installation factor for
ing one fitting (elbow or tee) every 3 were increased by 40% to account for that material. For example, the in-
m and one valve every 7.5 m. They did valves and added back to original stallation factor from Table 2 aver-
not include purchase and installation straight-run prices for each pipe size ages about 3.5 for Type 304 stainless-
of valves in their tally, however, be- and type steel pipe in complex networks. This
cause they felt that valve prices vary • After these adjustments, total bare yields a mid-2003 cost for 8-cm dia.
too widely to be included in data in- module price CBM·a is simply the 304-stainless-steel piping associated
tended for definitive estimates. sum of the costs. Installation factors with process equipment of $240/m
Valves can be included in a pre- FBM·a were derived as the quotient (CP·cs of $68/m from Figure 1 for 8-cm
liminary estimate like the one in this of CBM·a and the base cost of carbon pipe in a complex network, multiplied
article, where limits of precision are steel CP·cs by 3.5). For a straight run, where the
broader. Bare module costs for complex In the preparation of a cost chart, CP·cs installation factor (Table 1) is 4.0,
pipe systems, valves included, were de- is plotted versus nominal pipe diame- the mid-2003 price in 304 stainless
termined by using Lindley and Floyd’s is $84/m (CP·cs of $21/m from Fig-
assumption of 2.5 fittings for every 4. Costs of pipe, flanges, and routine fittings were ure 1 for 8-cm dia., straight-run pipe
listed by Lindley and Floyd. To estimate the added
valve and our estimate that a valve effect of valves, prices for fittings were multiplied times 4.0). To predict costs for the
by 1.6 (0.4 valves per fitting at four times the same piping in a project planned for
price). Sandblasting and painting charges were
3. Based on Guthrie’s capital-cost estimation tech- not changed. Shop fabrication expenses were in- the future, one would multiply these
nique [4, 5], where installed cost of equipment in creased by 40% to allow for valves. These were
a bare process module is equal to purchase cost summed to give Base Cost, valves included.
multiplied by bare module factor. Subscript “cs” 6. The chart employs log-log coordinates, since
denotes material of construction (carbon steel in 5. Adjusted to mid 2003 prices and normalized capital costs usually follow the six-tenths rule,
this case). per meter of pipe length. producing a straight line when plotted.

46 CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2006


EXAMPLE– PIPELINE COST ESTIMATE

O
wners of a steam boiler are considering a plant expansion. pipe is calculated to be 4.9 from Equation (3). Thus, the mid-
No change is planned for the boiler module itself, but its 2003 bare-module cost of uninsulated pipe is 4.9  $11.50/m
fuel-oil storage tanks are to be relocated. This will require a = $56/m.
new fuel-feed pipeline, 65 m in length. Construction is expected to The pipe must be traced to maintain its temperature at 95°C.
occur in 2006. Estimate the cost of running the new line. From Equation (5), the optimum insulation thickness is found to
An operator pumps fuel from storage to the feed drum once every be 2.6 cm. With this value for topt and 4.8 cm for Dact, we find
shift for a period of 15 minutes, requiring a flow of 3.9 liter/s. an additional cost of $22/m for insulation. Thus, the total bare
Perry [3], page 6-14, suggests an optimum flow velocity in the module cost in 2003 dollars is $78/m or $5,100 for a 65-m
range of 1.8–2.4 m/s for this situation. Nominal-3.8-cm standard run. Based on a projected CE Plant Cost Index of 485, the 2006
pipe will suffice (1-1/2 in., Schedule 40, 4.1-cm actual inside di- predicted price is $5,100  485/400 = $6,200.
ameter, 4.8 cm OD).a, b Past experience with the old line suggests that we might save
A corrosion checkc confirms common experience that almost any in maintenance dollars and aggravation if we make the line of
of the metals covered by the short-cut chart (p. 48) will contain Schedule 10, Type 304 stainless steel. In this case, FM is 1.5,
the fuel without corroding. Carbon steel, the current metal, has leading to a value of 5.5 for FBM. Uninsulated pipe cost is 5.5 
served for many years, and maintenance people tell us that sur- $11.50/m = $63/m. With insulation at $22/m, the bare module
face conditions inside the pipe are like new. Otherwise, weather cost is $85/m or $5,525 in 2003 dollars; $6,700 in 2006. The
exposure on the outside has required periodic repainting and difference is slight enough to seriously consider stainless steel.
other maintenance. A more experienced engineer notes that even though Sched-
According to the short-cut chart (p. 48), the base cost CP·cs for ule-10 or light-wall pipe is adequate for the pressure and expo-
nominal 3.8 cm pipe (straight run) is $11.50/m. For carbon steel sure, it may not tolerate abused. A heavier wall stock would be
with material and pressure factors of unity, FBM•cs for straight-run safer. She suggests using 304 stainless steel, Schedule-40 pipe.
Since this is the wall thickness in alloy piping denoted for high
a. At 2.4 m/s, the calculated diameter is 4.5 cm. Optimum pipe diame- pressure service, we can estimate its price by using a pressure
ters/flow velocities from Perry [3] assume continuous pumping of fluid. A
rigorous analysis of batch transfers like this one will push the optimum factor of 1.6 in the equation for FBM. Doing so, we find FBM
to a slightly smaller diameter and a higher velocity for Schedule 40, 304-stainless-steel pipe is 6.5. Its 2006 bare
b. We must, of course, choose a diameter that is commercially available. module price is $7,600 for the 65 m line. ❒
Standard U.S. nominal pipe sizes are denoted by ticks on the horizontal
axis of the short-cut chart, p. 48.
d. A large fraction of industrial safety/pollution incidents is caused by
c. See, for example, Table 4-1a, Ulrich and Vasudevan [8] vehicles puncturing outdoor pipelines and storage tanks

results by the ratio of the future CE Table 3 lists material factors for vari- where FM values are those listed in
PCI to 400. In mid 2007, for instance, ous piping materials alongside values Columns 4 of Tables 1 and 2, and
current trends suggest a CE PCI of that have been published throughout Fp = 1.0 for pressures less than 10 barg
500. Thus, mid-2007 prices would be literature for other types of equip- Fp = 1.6 for 10 to 40 barg pressure
25% greater than those cited in this ment. Values for alloy plate, pumps,
example. heat exchangers, process vessels, and Insulation costs
To make things easier for spread- so on, are included. With the information assembled thus
sheet formulation, we gain generality far, one can quickly estimate installed
and consistency with a minor loss of High pressure service prices for simple and complex net-
precision by using equations to calcu- By an analysis similar to that just works from Figure 1 for fifteen differ-
late installation factors. For straight- described, pressure factors can be de- ent types of pipe between 5 and 15-cm
runs, Equation (1) yields factors for all rived to predict bare module prices of nominal dia. at pressures up to 40
three diameters that, on average, fall heavier pipe. Lindley and Floyd in- barg. The approach is even more use-
within ±5% of those listed in Table 17 cluded data for seven piping materials ful if it is extended to include the cost
FBM⋅a = 11.6 D −0.84 + 1.13 FM ⋅a rated for up to 40 barg pressure. These of insulation, which is necessary in
(1) higher pressure piping costs can be most chemical process applications.
The following equation does almost as predicted via Figure 1 if equations for Finding the optimum thickness of
well for complex networks in Table 2 FBM are revised by replacing FM in pipe insulation is discussed in Chap-
each case with the product FM·Fp. ter 7 of Ulrich and Vasudevan [8].
FBM⋅a = 2.0 − 0.024 D − 0.001D2 + 1.22 FM⋅a
Straight-run piping systems: Based on that analysis using 2003
−0.011D ⋅ FM⋅a − 0.015 D ⋅ ( FM⋅a )
−2
(2) energy prices, one finds the optimum
FBM⋅a = 11.6 D –0.84 + 1.13 FM ⋅a ⋅ Fp
With these equations, a list of mate- (3) insulation thickness to be10
rial factors, and two cost curves, one Complex piping networks: 0.20
topt = 0.85 Dnom ⋅ ∆T 0.65
can estimate bare module prices for 2
(5)
FBM⋅a = 2.0 – 0.024 D − 0.001D + 1.22 FM⋅a ⋅ Fp
straight-run and complex piping sys- where
( )
−2
tems in 15 materials and all diameters −0.011D ⋅ FM⋅a ⋅ Fp − 0.015 D FM⋅a ⋅ Fp topt = optimum insulation thickness,
between 5 and 15 cm.8, 9 For context, (4) cm
Dnom = bare pipe nominal diameter,
7. Two thirds of the calculations fall within plus eter. The act of smoothing data with a general cm
or minus 5%. None differs by more than 20% correlation like the one we are building might ∆T = the difference between pipe tem-
from original data. actually improve their reliability.
8. For a few materials in Tables 1 and 2, FM·a
perature and ambient, °C
9. Pipe made from premium metals, because of
varies erratically from one pipe size to another. greater strength and smaller corrosion allow- With thickness known, the 2003 cost
This stems from the data source where Hastel- ance, can be lighter than carbon steel. Thin-wall
loy C-276, for example, is reported to cost 70% (schedule 10) stainless steel and alloy piping 10. Steam-traced pipe based on energy costs of
more than Monel in 10-cm pipe but 15% less in serves at pressures up to 10 barg, for example, $3.80/GJ. For other energy prices, electrical trac-
15-cm pipe. Except for a few discrepancies like in service where schedule 40 would be required ing, and different circumstances, see Ulrich and
this, relative prices in Lindley and Floyd’s tables if made from carbon steel. Schedule 40 alloy pipe Vasudevan [8], Chapter 7 or Perry [3], Tables 11-
change only slightly and consistently with diam- can often be used at pressures up to 40 barg. 21 and 11-22.

CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2006 47


Feature Report

THE SHORT-CUT METHOD FOR PIPING COSTS

Using data from this chart (right) and the


�����������������������������
table (below), these equations can be used to ��������������������������������
quickly estimate costs for 15 different piping �����������������������������������
materials of 5–15-cm dia. at pressures up to ���
40 barg.
�������������

�������������� �������
�������
CBM = FBM ⋅ CP⋅cs + CBM⋅Ins

(
CBM⋅Ins = 1.13 ⋅ topt Dact + topt )
For straight-run piping systems:
������������
FBM⋅a = 11.6 D –0.84 + 1.13 FM ⋅a Fp ����������
���������
��������
For complex piping networks: �����
������
���� ���� �� ������ �� �� �� �� �� �� ��� ���
FBM⋅a = 2.0 – 0.024 D − 0.001D2 + 1.22 FM ⋅a ⋅ Fp ��
������ ������ ��� ���
( )
−2 � �� ���
−0.011D ⋅ FM ⋅a ⋅ Fp − 0.015 D FM ⋅a ⋅ Fp �����������������������������

MATERIAL FACTORS [FM]


Piping type Straight-run Complex Piping type Straight-run Complex
Polyvinyl chloride (PVC) 0.4 0.5 Fiberglass-reinforced plastic (FRP) 4.0 3.8
Chlorinated polyvinyl chloride (CPVC) 0.9 0.8 Alloy 20 8.8 8.5
Carbon steel 1.0 1.0 Titanium 10.2 9.4
Type 304 stainless steel 1.5 1.8 Monel 15.0 9.3
Type 316 stainless steel 1.9 2.1 Hastelloy C-276 18.2 12.0
Carbon-steel pipe lined with: Zirconium 32.4 20.4
-rubber 1.9 1.4
PRESSURE FACTORS Fp
-conventional plastic (cp) 5.0 4.7
-fluorocarbon plastic (fp) 9.2 7.3 Less than 10 barg 1.0
-glass 9.0 6.2 10 to 40 barg 1.6

of purchasing and installing insula- trapolated with confidence outside the p⋅ D (8)
t=
tion can be calculated from 5–15 cm range.) 2(0.9 S − 0.6 p)
First, one would expect the cost of With typical design-stress values S
(
CBM⋅Ins = 1.13 ⋅ topt Dact + topt ) pipe to be proportional to mass — a falling in the range of 1,000 bara and
(6) variation on π·D·t·L. Accordingly, for at pipe internal pressures of 40 barg
where Dact is actual bare-pipe outside pipes of different diameter made from or less, the second term in the denom-
diameter, cm the same material, their base cost inator’s parenthetical expression can
ratio would be be disregarded. Thus, wall thickness
The cost chart CP 1⋅a D1 ⋅ t1 is directly proportional to pressure
Finally, we have the information to = and diameter. For pipes of the same
CP 2⋅a D2 ⋅ t2
prepare a refined, comprehensive cost (7) material designed to handle the same
chart. In composing it, let us consider The relevant design expression that pressure, thickness ratio is, therefore,
basic capital cost concepts and revisit relates wall thickness to material equal to diameter ratio.
the lines in Figure 1. (With creative strength, pressure, and diameter is11: t1 D1 (9)
=
insight, these curves might be ex- 11. See Ulrich and Vasudevan [8], p. 95. t2 D2

References 2. Dennis, G., Picking the Best Thermoplastic


Lining, Chem. Eng., pp. 122-124, October,
Beach, California, 1974.
6. Yau, T. and K.W. Bird, Know which Reactive
1. Lindley, N.L. and J.C. Floyd, Piping Systems: 1998. and Refractory Metals Work for You, Chem.
How Installation Costs Stack Up, Chem. 3. Perry, J. H., D.W. Green, and J.O. Maloney, Eng. Prog., 88, pp. 65-69, February, 1992.
Eng., pp. 94-100, January, 1993. (This com- “Perry’s Chemical Engineers’ Handbook,”
prehensive study is more than 10 years old, 7. McMaster-Carr Catalogue 106, McMaster-
7th Ed., McGraw-Hill, New York, 1997. Carr Supply Company, New Brunswick, N.J.,
near the limit recommended for scaling with
inflation factors. No major technological or 4. Guthrie, K.M., Data and Techniques for Pre- 2000, www.mcmaster.com.
productivity changes have occurred with pip- liminary Capital Cost Estimation, Chem. 8. Ulrich, G.D. and P.T. Vasudevan, “Chemical
efitting in the interim, however, so escalated Eng., pp. 114-142, Mar. 24, 1969. Engineering Process Design and Economics,
numbers reported here are considered valid 5. Guthrie, K.M., “Process Plant Estimating, A Practical Guide,” 2nd Ed., Process Publish-
for today’s use.) Evaluation and Control,” Craftsman, Solano ing, 2004, ulrichvasudesign.com.

48 CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2006


Authors
Gael D. Ulrich (34R Pren-
tiss St., Cambridge, MA
Substituting Equation (9) into Equa- at small diameter and two at large 02140-2241; Email: gael.
tion (7) suggests that piping cost should diameter. ulrich@comcast.net) is pro-
fessor emeritus of chemical
be proportional to diameter squared: A closer look at Figure 1 revels that engineering at the University
2
the data points are actually represented of New Hampshire, where he
joined the faculty in 1970. He
CP 1⋅a D1 ⋅ t1  D1  much more accurately by a curved line worked at Atomics Interna-
= =
CP 2⋅a D2 ⋅ t2  D2  (10) than a straight one. In the final short- tional Div. of North American
aviation and Cabot Corp. prior
cut cost chart (p. 48), curves for both to entering teaching. He holds
a B.S.Ch.E. and an M.S.Ch.E. from the University
According to Equation (10), cost plot- simple and complex piping systems of Utah and an Sc.D. from the Massachusetts In-
ted against diameter on a log-log chart are drawn to pass through the center stitute of Technology. For the past thirty years, he
has consulted for a number of corporations and
should have a slope of two. of each data point and asymptotically presided over a small contract research firm for
A quick check of Figure 1, however, approach the limiting slopes zero and ten. Material in this article was extracted from
Reference [8] published with coauthor P. T. Va-
reveals a slope much closer to one. two. This graph, along with relevant sudevan in 2004.
This deviation from theoretical is data and equations summarized next Palligarnai T. Vasudevan
is professor of chemical en-
caused by other factors included in to it, are all that is needed to prepare a gineering at the University
base cost. Some of these (shop labor, quick estimate of piping costs12. of New Hampshire (Chemi-
cal Engineering Department,
etc.), vary less with diameter than For an illustrative example of how to Kingsbury Hall, Rm W301, 33
do materials alone. As diameter in- use the chart and equations to estimate College Road, Durham, NH
03824; Phone: 603-862-2298;
creases, however, the labor compo- piping costs, see the box, p. 47. ■ Email: vasu@unh.edu) where
nent should diminish, causing the Edited by Rebekkah Marshall he joined the faculty in 1988.
He worked for a large petro-
slope to drift toward two. As diameter chemical company for seven
years prior to entering teaching. For the past 15
decreases, on the other hand, labor 12. Cost data derived from the short-cut chart are years, he has worked in the areas of catalysis and
will become dominant and the slope compared with the data used to create it on pp. biocatalysis. He is currently collaborating with
355 and 356 of Reference [8]. Standard deviations researchers in Spain in the areas of hydrode-
will approach zero. This suggests that average less than ±15% in most cases. The largest sulfurization and enzyme catalysis. Vasudevan
the two lines in Figure 1 should be variances match anomalies in data mentioned ear- holds a B.S.Ch.E. from Madras, India, a M.S.Ch.
lier. Most errors are overestimates by the correla- E. from SUNY at Buffalo and a Ph.D. in chemical
curved, with slopes approaching zero tion, especially for the smallest diameter pipe. engineering from Clarkson University.

PRESSURE RELIEF FOR


ALMOST ANY APPLICATION
O
ver pressure conditions threaten productivity at the most
inopportune time. Late at night, the weekend, a holiday.
Your process needs safety protection and emergency service.
At Continental Disc Corporation, our professionals
are trained and on-call for situations like
these. They’ll ask the right questions and
proceed into emergency production and
shipping. You’ll get the protection you
need in your time of need. Call it
24/7/365 Emergency Service.
Let us be your pressure-relief partner.

• Rupture Discs • Pressure/Vacuum Relief Valves


• Flame/Detonation Arresters • Pilot Operated Valves
3160 West Heartland Drive
• Blanket Gas Regulators
Liberty, MO 64068-3385
(816) 792-1500 Come see us at ACHEMA, Booth N48-N50
www.contdisc.com
email: pressure@contdisc.com CERTIFICATIONS:

Emergency Service • Design/Sizing Services • Inventory Management • Training Seminars


Circle 25 on p. 72 or go to adlinks.che.com/5827-25
CHEMICAL ENGINEERING WWW.CHE.COM MARCH 2006 49

Das könnte Ihnen auch gefallen