Here are a few questions Future Value Questions

that deal with the future and Question One


present value of money. I You are the project manager of
recommend you try to solve the NHQ Project. This project
these by hand first, and then needs $456,786 to get started
you can review your and will last three years. What
is the future value of this
answers on the Formulas
investment considering the
page. You can also make up interest rate is 6 percent?
your own questions and test
your math agility.

Question Two

You are the project manager of


the XCV Project. This project
needs $876,000 to get started
and will last seven years. What
is the future value of this
investment considering the
interest rate is 6 percent?

Question Three

You are the project manager of


the UPD Project. This project
needs $549,007 to get started
and will last four years. What is
the future value of this
investment considering the
interest rate is 6 percent?
Present Value Questions
Question One
You are the project manager of
the AAX Project. You believe this
project will be worth $1,987,112
in three years. What is the
present value of this project's
promised return if the assumed
interest rate is 6 percent?

Question Two

You are the project manager of


the QSA Project. You believe this
project will be worth $10,980,000
in five years. What is the present
value of this project's promised
return if the assumed interest
rate is 6 percent?

Question Three

You are the project manager of


the QSA Project. You believe this
project will be worth $765,000 in
two years. What is the present
value of this project's promised
return if the assumed interest
rate is 6 percent?
Future Value Formula
FV = PV(1 + i)n
Fill in the value for your questions in the following cells.
PV is present value
i is the interest rate
n is the number of time periods

The following cells will be calculated for you based on the above entries.
Present value is
(1 + i) is
Time value is
Future value result is

Present Value Formula


PV = FV / (1 + i)n
Fill in the value for your questions in the following cells.
FV is future value
i is the interest rate
n is the number of time periods

The following cells will be calculated for you based on the above entries.
Future value is
(1 + i) is
Time value is
Present value result is
Future Value Formula

for your questions in the following cells.


$1,897,526
0.06
5

be calculated for you based on the above entries.


$1,897,526.00
1.06
1.3382255776
$2,539,317.83

Present Value Formula

for your questions in the following cells.


$789,456
0.06
3

be calculated for you based on the above entries.


$789,456.00
1.06
1.191016
$662,842.48