Beruflich Dokumente
Kultur Dokumente
DAVID ANDREWS'
CHRISTOPHER DICKS'
Professor of Naval Architecture. 2 Research Assistant.
Naval Architecture Research Group, Dept. of Mechanical Engineering, University College London.
Abstract
The paper describes the application of the _Building Block design methodology to the
preliminary design of a naval escort vessel for both a conventional monohull solution and the more
innovative configuration of a trimaran hull form. From the overall justification of an architecturally
centred initial ship syntlieSTS, the paper outlines the basis of the Building Block approach which
essentially takes the functional elements required of a new design in discrete elements or building
blocks and places them as desired by the designer. The paper concludes with a discussion of the
Building Block approach compared to the previous sequential sizing - parametric investigation -
arrangement approach for a monohull frigate and the comparison of the Building Block approach
for monohull and trimaran configurations. Finally the way ahead in developing the methodology is
outlined
1. Introduction
A recent paper by the first author [1] has placed the methodology of ship design in the wider
context of the design of physically large complex systems. In doing so, whilst due regard is given to
the importance of management oriented design procedures, that paper focuses on the ship design
process as a paradigm for the design of complex systems. Further emphasis is placed on the initial
phases of design as the most critical stage in determining the overall configuration. This is
reinforced by the current interest Concurrent Engineering [2]. For naval ships in particularthis is
combined with an ever more stringent financial environment demanding increased assurance before
any irntial commitmentis made to a new procurement programme [3]. Such assurances are linked to
a wider exploration at the preliminary design stage of all possible alternatives, comparing their
potential effectiveness' and costs through such mechanisms as the USA's COEA (Cost and
Operational Effectiveness Analysis [4]) and the UK's COEIA (Combined Operational Effectiveness
and Investment Appraisal [5]). All this reinforces the need _for __a methodology_based on an
architecturally centred synthesis which is the subjectof this paper.
The paper commences by placing this methodology in the context of previous approaches to
initial ship design which can be considered to be of an essentially sequential nature. From this the \
evolution of the architecturally centred synthesis approach to the new Building Block methodology
is outlined. This methodology whilst dependant on modern computer graphics facilities also
requires a more functionally orientated description of the ship if it is to provide the more open
exploration of options required of current naval ship design.
The remainder of the paper is taken up with a description of the application of the Building
Block approach to the preliminary design of a typical frigate. Both to demonstrate the flexibility of
the methodology and to meet the remit for open exploration, two distinct solutions to this postulated
frigate requirement are presented. Namely the ubiquitous monohull and a trimaran option. The latter
demonstrates the application of the methodology to a configurationally novel option, which UCL's
Naval Architecture Research Group has pioneered in recent years [6],[7].
The Building Block Design Methodology Applied to Advanced Naval Ship Design 2
The paper concludes by firstly discussing the advantages presented to the ship designer by
this design methodology with the potential of being both more information rich and fostering a
more exploratory design approach. Secondly the focus of current research in ship design using a
Building Block based design approach is outlined.
Figure 2 shows how this personal stamp of the designer influences all three of the above
sequential sub processes, essentially through the designer's interlinked personal schema (visual,
linguistic and practising system) [13] and the use of a key generator [14]. The later finding came
from interviews with architects and is consistent with the recorded views of prominent naval ship
designers [15].
Daley's Overlaps
A Visual Schema
B Linguistic Schema
Wider C Value Schema
Design
D 'Conscious' Propositional Knowledge -
Environment strongly influenced by Design Constraints
c Designer's `idiosyncratic'Influence
I
Task Current Current Current
Style of Crude Subsequent Integrative
Owner's Directed Output Output Process Output of
Emerging Generative Form Accumulative
Initiation Ship Design Input Process of Initial Selection rather than
of Form Comprehensive Architectural
Synthesis Analysis and
Engineering Synthesis
1
of configuration into the design is the ability to analyse more of the critical design aspects whilst the
design description is still fluid.
The decomposition of the design to greater levels of detail has proven to be a useful facility.
It allows the designer to go into more detail in critical areas in the earliest phases of the design,
without resorting to a general compartment level description and the consequential design
complexity. The use of a Master Building Block to contain the overall summation of the ship
description, and data which cannot be assigned to any one function, provides sufficient ship
definition for use in the auditing and analysis routines. Other advantages the methodology provides
include:-
• An 'open' or 'Glass Box' approach to the design allowing the designer to incorporate his
experience and judgement in the process, rather than having to rely on a 'Black Box' system
which has usually been produced by someone else.
• The methodology and resulting computer based systems are 'soft', so that the structure and
processes used can be readily updated and improved algorithms or even different modelling
features can be readily incorporated.
• Allowances for design margins and specifically access can be made as part of the particular
design evolution, rather than using default values based on possibly inappropriate historic data
values which may not reflect the actual configuration being designed [19].
Andrews et al. [18] described the development of the Building Block methodology along
with the demonstration of a submarine design produced using the Building Block methodology. The
Building Block approach utilised in that student design study was comparatively simple with
essentially four levels of detail. The number of Building Blocks expanded from 10 to 140 as the
design progressed, having commenced with a broad investigation of the contents of the pressure
hull and concluded with a three dimensional model of the internal and external features of the
Weapons
Tankage
BALLAST
1
REQUIREMENT
Trim Polygons Functiona 'Technology
ficiency Changes
GENERAL
G ecnnetric Definition
ARRANGEMENT
External Technology
Structures(
Changes
Materials
DETAILED
Pressure Space/ LAYOUT
Hull W eight Resistance Dynamic
S Eructates/ Algorithms and
Materials Propulsion Rccove
' The Building Block Design Methodology Applied to Advanced Naval Ship Design 6
submarine. A schematic of the submarine orientated Building Block design procedure (SUBCON)
is shown at Figure 4.
air-craft carriers and in smaller ships such as fast planincraft the_topside_maybe ain
design
RADICAL FUNCTIONAL
IDEAS HIERARCHY
BALANCE DECOMPOSITION
INDICATION MODEL
WEIGHT
INVENTORY
a
Data-
ace Definition
Wacera
Coosooad
J
TOPSIDE &
MAJOR FEATURE
HYDROSTATICS HULLFORM IMPLICATIONS
MODEL Vobsne Space Technology
Factional Required/
Drociercy Distribution Cloves
Available
SPACE INVENTORY
WEIGHT MODULE (Required v Achieved)
srerar Mean VCG I.CG
Sega:wring Maieuiering Access &
Margin
Policy
GENERAL
Geometric Definition
ARRANGEMENT
Structures Technology
Clarion
DETAILED
Space/
LAYOUT
Completeness
Chock Weight Resistance
Vulnerability/
Algorithms and Stability Personnel Survivability HULLFORM MODEL
Propulsion
Given that the initial phase of the Building Block design methodology for a surface escort
ship must include the topside investigation, then three dimensional modelling of the desired topside
components of the warship can be used to locate these items on a deck of initially arbitrary
dimensions. Each of the components is modelled both by its physical size and also in terms of its
perceived separation from other components, due to such concerns as electromagnetic
compatibility, RADHAZ, efflux avoidance or weapons firing arcs. As the location of the prime
movers governs the positioning of the inlets and exhausts, these major components must be
determined and positioned in the hull(s). Arrangements which could lead to poor structural
continuity or unsatisfactory features functionally can be identified and preferable arrangements
The Building Block Design Methodology Applied to Advanced Naval Ship Design 7
Such a weight breakdown has been beneficial in the past as it allows comparison between
new designs and existing ship designs. However in many ways the weight group system is less
applicable for a spatially determined synthesis where many of the investigations involve assessing
the impact on the whole design of adding or subtracting equipment. Also in a weight group based
design the designer is restricted by the historical assumptions resulting from the weight group
system. This can inhibit consideration of radical ideas and lead to conventional solutions which may
be less effective, particularly for unconventional ship types.
In adopting the Building Block methodology a functional breakdown was incorporated such
that each functional group contained all the items which were to fulfil a given need. Thus removal
of a particular function such as the Anti Submarine Warfare capability can be readily undertaken
and the impact on the design obtained. The functional groups followed the classic Float-Move-Fight
subdivision plus a general infrastructure group. It was initially intended to use the three main
functional groups of Float, Move and Fight to encompass all the ship's functionality. However it
proved impractical to apportion all those elements which were of an essentially support nature, such
as provision of galley space or stores and so the Infrastructure group was produced. Table 2 shows
typical components of each of the four functional groups. The hierarchical relationship between the
whole ship description and the individual items of equipment is shown in Figure 6.
• The Building Block Design Methodology Applied to Advanced Naval Ship Design
The four different functional groups do not all evolve in the same manner and the trends
shown in Table 3 have been noted from the design processes described later in this paper.
an identical set of requirements using each methodology. Following this a trimaran design to a
similar requirement was developed using the Building Block approach. From the statement of
requirements the salient machinery and combat system features are given in Table 4.
The traditional ship design process is used by the Naval Architecture Research Group in the
ship design exercises on the M.Sc. and B.Eng. degree courses. The major components follow the
sequential process of Section 2 and Figure 2:-
• Initial sizing using an assumed payload volume fraction approach to break into volume and
displacement and then space and weight group algorithms leading iteratively to a balance in
gross volume and displacement.
• Parametric survey. Using the work of van Greithuysen [22] the dimensions and form
parameters of the ship are derived by deforming the parent hullform in a logical manner while
maintaining the same displacement and volume.
• Layout within the dimensions and hullform obtained from the survey.
• Performance Analysis to ensure viability and work up the detail of the balanced form
This procedure was followed using the equipment fit of Table 4 and the ship characteristics
given in Table 5 were derived, with the design biased towards minimising the high speed resistance.
Initial performance requirements were specified in terms of a maximum speed, a solid metacentric
height and an approach to seakeeping based on permissible ratios of ship's length to the cube of the
volume of displacement.
In contrast, the choice of double bottom height for the traditional escort design was made
during the parametric survey when it was impractical to consider the functional requirements of the
double bottom, since a hullform was not yet available. Given default hull coefficients, only the
effect on the four major hull dimensions of double bottom height and superstructure proportion
could be considered. When the compartment arrangements of the traditional design were
subsequently worked up it became obvious that the double bottom height was less than desirable,
since large fuel tanks were required on No. 4 Deck. This could have been avoided by adding extra
double bottom height at the parametric survey stage but this would have resulted in either
insufficient superstructure or a weather deck length with an unsatisfactory topside arrangement.
Alternatively, the whole design could have been revised to balance at a larger volume, requiring a
further iteration where the designer was having to respond to consequences of the design's
evolution rather than controlling the evolution.
It is therefore suggested that the major dimensions of the traditionally derived ship would
have benefited by being derived with reference to specific concerns and the actual configuration. As
a result of not doing this, the traditionally designed ship did not meet all its requirements and would
in practice have required several further design iterations to meet its requirements to the same
degree as the Building Block design. Furthermore focusing on individual changes to dimensions
would have been more difficult to achieve.
Another aspect in which the Building Block design was considered more satisfactory than
the traditional design was in the selection of a combination of hull and superstructure. The Building
Block design process allowed the designer far greater control over the size and position of
superstructure. In this case it was minimised with only enough superstructure provided for a bridge
position on No. 02 deck, the fitting of necessary weapons, sensors and command system and the
helicopter facilities. In particular the positioning of the operations room and the provision of hanger
space drove the final superstructure arrangement. The approach to superstructure design in the
traditional design process is based on the variation of superstructure proportion in the parametric
survey. This assumes that superstructure proportion is a continuous variable, which is a
questionable assumption to make, even if a full superstructure layout is produced and this
demonstrates the minimum feasible superstructure volume operationally. Again this issue shows
that the Building Block based design produces a more practical arrangement meeting the functional
needs and reflects the designer's thoughts and experience rather than giving a design which matches
a numerically balanced sizing, produced by an essentially 'Black Box' sizing program.
A further advantage of the Building Block based ship design is that, from the earliest stages
of designing the topside and major features, the intakes and uptakes arrangements for the gas
turbines can be investigated. In comparison the intake and uptake requirements for the traditionally
designed ship, could not be considered as part of the layout until the main dimensions had been
fixed, which in this case resulted in the intakes and the forward superstructure clashing. Bringing all
these issues together, it is believed that in terms of choosing ship dimensions, the Building Block
approach fosters a greater awareness by the designer. When defining the dimensions this applies to
both the global ship design issues and the local design issues, whereas the traditional approach leads
to dimensions being based on a gross numerical description.
In general the design requirements for the Building Block derived Trimaran Escort design
were the same as those used in the monohull designs. However experience at UCL [7] has shown
that for the trimaran the use of a double propulsion shaft arrangement in the main central hull is
both difficult (due to the narrower beam) and less appropriate. For this reason one single main
propulsion shaft was adopted. In order to exploit a flexible configuration for the prime movers, an
electric propulsion system was adopted. In comparison with the monohull, the Trimaran is
considered to provide a better utilisation of the important topside 'real estate'. This was
demonstrated by the ease of adding a second organic helicopter. The positioning of the flight deck
was also an important design consideration and a more central location than is the norm with a
monohull was easily achieved, thus greatly extending helicopter operability in high sea states. The
point defence missile system was also upgraded in capability as a modular vertical launch silo
arrangement was facilitated by the wider upper deck of the trimaran in the central portion of the/
ship's length.
Float Functional up
Propulsion Control Fuel Provision Auxiliary sion Macby Maio Propulshe Maelsy Afl go Propulsive Machinery FWD
(DM and Mown) (WR21)
— Ship Control Centre Furl — Pon DG Space — Motor Spaces — WR21 Space
— Technical Spaces — Compensation Slid DG Space — DG Spaces / Exhaust
— Pon Motor — Electrical Equipment — Electrical Equipment
— Slid Motor
— Port Electrical Equip.
— Slid Electrical Equip.
Manoevring Propulsion
1 1
Catering / Officers Acco Ratings Accom Supply Ship Systems
5.3 Critique of the Building Block Design Process Applied to a Trimaran Study
The benefits of applying the Building Block design methodology to the trimaran design
largely matched those revealed in the monohull design application. Configuration based preliminary
ship design requires the entire ship to be laid out and therefore a lot of time is spent on the basic
layout in contrast to the traditional quick and limited numerical study. The latter can therefore
explore more rapidly the sensitivity of the design to changes in major requirements, such as speed
and gross weight and space demands. However many of these options may prove more demanding
when the consequences are tackled in more depth beyond the parametric survey and so choices
made largely on a numerical sizing basis may prove to have been optimistic in their whole ship
The Building Block Design Methodology Applied to Advanced Naval Ship Design 15
impact. When a configuration based design is developed using the Building Block methodology the
time-scale and complexity can be reduced by using a Super Building Block level of description,
without sacrificing the ability to investigate the impact of configuration on the design.
References
The Building Block Design Methodology Applied to Advanced Naval Ship Design 16
1. Andrews, D.J., (1996), A Comprehensive Methodology for the Design of Ships (and Other
Complex Systems), To Be Published.
2. Tibbetts, B. & Keane, R.G., (1995), Making design Everybody's Job, Naval Engineers
Journal, May 1995, pp 283-301.
3. Andrews, D.J., (1994), Preliminary Warship Design, Trans.RINA, Vol.136, pp37-56
4. Hockberger, W.A., (1993). Cost and Operational Effectiveness Analysis (COEA) in Naval
Ship Design, SNAME Chesapeake Section, 11 May 1993.
5. Kirkpatrick, D.L., (1996), Choose Your Weapon: COEIA and its Role in UK Defence
Procurement, RUSI Journal , May 1996.
6. Pattison, D.R. & Zhang, J.W., (1995), Trimaran Ships, Trans.RINA, Vol.137 part B.
7. Andrews, D.J. & Zhang, J.W., (1995), Considerations in the Design of a Trimaran Frigate, Int.
Symp. "High Speed Vessels for Transport and Defence", RINA.
8. Harvey Evans, J., (1975), Ship Structural Design Concepts, Cornell Maritime Press, p 26.
9. Snaith, G.R. & Parker, M.N., (1972), Ship Design with Computer Aids, North East Coast
Institution of Engineers and Shipbuilders, Newcastle, 20 March 1972.
10. Andrews, D.J., (1981), Creative Ship Design, Trans.RINA, Vol.123, pp 447-473.
11. Andrews, D.J., (1986), An Integrated Approach to Ship Synthesis, Trans.RINA, Vol.128, pp
73-104.
12. Rittell, H.W.J. & Webber, M.W., (1973), Dilemmas in a General Theory of Planning, Policy
Sciences, Vol. 4.
13. Daley, J., (1982), Design Creativity and the Understanding of Objects, Design Studies, Vol.3
No.3 July 1982, p 133.
14. Darke, J., (1979), The Primary Generator and the Design Process, Design Studies, Vol.1 No.1
July 1979, p 36.
15. Brown, D.K. (1983), A Century of Naval Construction, Conway Maritime Press.
16. Hyde, M. & Andrews, D.J., (1992), CONDES, A Preliminary Warship Design tool to aid
Customer Decision Making, PRADS 92, Newcastle University, pp 2.1298-2.1310
17. Barrett, M., Duncan, J. and Rutland, P., (1994) Warship Design on the Desktop Computer,
ICCAS 94, pp 14.3-14.17.
18. Andrews, D.J., Cudmore, A.C., Humble, P., Wilson, D., (1996), SUBCON - A New Approach
to Submarine Concept Design, RINA Symposium Naval Submarines 5 "The Total Weapons
System" , RINA, Paper No.19.
19. Andrews, D.J., (1987), Explorations in the Nature of Frigate Preliminary Design, RINA
Warship 87 Symposium.
20. Baker, R., (1957), Habitability in the Ships of the Royal Canadian Navy, Trans.SNAME, Vol.
65, pp 69-110.
21. Brown, D.K., (1990), The Battleworthy Frigate, North East Coast Institution of Engineers
and Shipbuilders, 30' April 1990.
22. van Greithuysen, W.J., (1994), On the Variety of Monohull Warship Geometry, Trans.RINA,
Vol. 136, pp 57-78.
23. Betts, C.V., (1988), A Review of Developments in SWATH Technology, Int. Conf. on
SWATH Ships & Advanced Multihull Vessels 2, RINA, Paper 1.
24. Hills, W., Barlow, M., and Cleland, M., Layout Design of Large Made to Order Products
Using a Knowledge Based System., Proc. Institution of Mechanical Engineers, Vol. 207 pt. B,
pp 257 - 263.
25. Mistree, F., Smith, W., Kamal, S., and Bras, B., Designing Decisions: Axioms, Models and
Marine Applications, IMSDC 91, Kobe, Japan, 1991, pp 1-24.
Glossary
AAW Anti Aircraft Warfare ASW Anti Submarine Warfare
- The Building Block Design Methodology Applied to Advanced Naval Ship Design 8
• • •
• • • • • • • ......• •••
• + ......