Sie sind auf Seite 1von 78

RAILWAY PROJECT ROHTAK

Schedule A-SOR ITEMS BOQ QUANTITY AMOUNT


S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
CHAPTER 3-A PLAIN CONCRETE (SUPPLYING & USING OF CEMENT)
Supply and using cement at worksite :
9 33061 Tonne 2700 5474.00 2700.00 2957.49 14,779,800.00 16,189,300.57
OPC 43 grade
Total 14,779,800.00 16,189,300.57
Add 25.67% 3,793,974.66 4,155,793.46
Add Contractor above rate 9.90% 1838803.69134 2014164.30845228
20,412,578.35 22,359,258.33
CHAPTER 4 REINFORCED CEMENT CONCRETE (EXCEPT ITEM NO. 045010 TO 045022)

Centering and shuttering including


strutting, propping etc. and removal of
10 42012 form for :-Walls (any thickness) including Sqm 35000 191.20 35000.00 35000.00 6,692,000.00 6,692,000.00
attached plasters, buttresses, plinth and
string courses etc.

ADDENDUM ITEMS

Foundations, footings, bases of columns,


raft foundation of washable aprons, Pile Sqm
42011 120.60 4949.05 - 596,855.43
caps, Footings of FOB etc.

Total 6,692,000.00 7,288,855.43


Add 61.51% 4,116,249.20 4,483,374.97
Add Contractor above rate 9.90% 1070016.6708 1165450.81009431
11,878,265.87 12,937,681.22
ITEM NO. 045010 TO 045022 (SUPPLY & USE OF STEEL REINFORCEMENT)OF CHAPTER 4

Supplying Reinforcement for R.C.C. work


including straightening, cutting, bending,
11 45016 placing in position and binding all Kg 9929590 47.58 9929590.00 9430516.61 472,449,892.20 448,703,980.20
complete. Thermo-Mechanically Treated
bars

Total 472,449,892.20 448,703,980.20


S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
Add 23.02% 108,757,965.18 103,291,656.24
Add Contractor above rate 9.90% 57539577.8810596 54647568.0073655
638,747,435.27 606,643,204.45
Chapter -8 (STEEL & ALUMINIUM WORK)
Structural steel work In RSJ, tees, angles
15 81031 Kg 63000 75.92 63000.00 957550.00 4,782,960.00 72,697,196.00
and channels
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
Structural steel work In flats, plates ,
16 81032 Kg 15000 73.26 15000.00 1205492.00 1,098,900.00 88,314,343.92
round or square bars
Total 5,881,860.00 161,011,539.92
Add 18.01% 1,059,322.99 28,998,178.34
Add Contractor above rate 9.90% 687177.115614 18810962.1076996
7,628,360.10 208,820,680.37
Chapter -13 SANITARY INSTALATION
Providing and fixing medium grade G.I.
24 131151 Metre 100 128.42 100.00 100.00 12,842.00 12,842.00
pipes c 15 mm dia. nominal bore
Providing and fixing medium grade G.I.
25 131153 Metre 75 214.91 75.00 75.00 16,118.25 16,118.25
pipes 25 mm dia. nominal bore
Providing and fixing medium grade G.I.
26 131156 Metre 100 384.78 100.00 100.00 38,478.00 38,478.00
pipes 50 mm dia. nominal bore
Providing and fixing medium grade G.I.
27 131158 Metre 100 629.12 100.00 100.00 62,912.00 62,912.00
80 mm dia. nominal bore
Providing and fixing medium grade G.I.
28 131159 Metre 4500 861.40 4500.00 4500.00 3,876,300.00 3,876,300.00
pipes 100 mm dia. nominal bore
ADDENDUM ITEMS

Providing and laying S&S centrifugally


cast (spun)
iron pipes (Class LA) conforming to IS -
133050 1536 : upto
300 mm dia.

150 mm dia. pipe 2,081.14 345.00


133054 Metre - 717,993.30

Providing and laying S&S Centrifugally


Cast (Spun) Ductile Iron Pipes
133100 conforming to IS : 8329 of Class K
9 up to 500 mm dia
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
1,240.03 380.00
100mm dia Ductile Iron CLass K - 9 pipes
133101 Metre - 471,211.40

2,226.18 85.00
200mm dia Ductile Iron CLass K - 9 pipes
133103 Metre - 189,225.30

3,192.90 15.00
250mm dia Ductile Iron CLass K - 9 pipes
133104 Metre - 47,893.50

7,266.01 40.00
450mm dia Ductile Iron CLass K – 9 pipes
133108 Metre - 290,640.40

Providing and laying S&S Centrifugally


Cast (Spun) Ductile Iron Pipes
133110 conforming to IS : 8329 of Class K
9 Above 500 mm dia

11,174.36 35.00
600mm dia Ductile Iron CLass K - 9 pipes metre
133111 - 391,102.60

Total 4,006,650.25 6,114,716.75


Add 0.00% - -
Add Contractor above rate 9.90% 396658.37475 605356.95825
4,403,308.62 6,720,073.71
Chapter -17 misc. building works
Boring, providing and installing :- 450mm
36 171613 Metre 27000 1929.93 27000.00 28974.50 52,108,110.00 55,918,756.79
dia piles
Vertical load testing Single pile upto 50
37 171651 Each Test 4 64056.73 4.00 4.00 256,226.92 256,226.92
tonne capacity- initial test
Vertical load testing of piles - routine
38 171652 Each Test 10 52267.50 10.00 10.00 522,675.00 522,675.00
test
Lateral load testing :- Vertical load
39 171681 Each Test 14 29037.50 14.00 14.00 406,525.00 406,525.00
capacity upto 50 MT
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
Total 53,293,536.92 57,104,183.71
Add 0.00% - -
Add Contractor above rate 9.90% 5276060.15508 5653314.186795
58,569,597.08 62,757,497.89
Chapter -19 BRIDGE WORK SUB STRUCTURE

Conducting load testing of a single pile


45 192107 :-Routine Load Test above 100 ton Each 10 138177.85 10.00 10.00 1,381,778.50 1,381,778.50
capacity Up to 250 ton capacity pile

46 192113 Lateral load testing of single pile i:- Piles Each 14 64352.57 14.00 14.00 900,935.98 900,935.98
with lateral load capacity of above 20 ton

Providing and applying two coats of coal


47 195020 Sqm 12000 108.60 12000.00 12000.00 1,303,200.00 1,303,200.00
tar or bitumen

Centring and shuttering including


48 195031 strutting, propping etc. and removal of Sqm 6500 120.60 6500.00 6706.66 783,900.00 808,822.71
form for :- RCC raft foundation & Pile cap

Centring and shuttering including


strutting, propping etc. and removal of
49 195032 Sqm 3500 191.20 3500.00 4804.81 669,200.00 918,679.67
form for :- Abutment, pier, wing walls
and return walls

Abutment cap, Pier Cap, Inspection


50 195033 Platform & Pedestal over Pier cap, Sqm 6700 185.57 6700.00 10933.00 1,243,319.00 2,028,836.81
Fender wall, Diaphragm wall, etc.

Approach slab at formation level, Dirt


51 195034 Sqm 500 120.60 500.00 500.00 60,300.00 60,300.00
wall/ ballast wall at formation level

In Bottom/top slab, side walls, toe wall


52 195038 and sumps haunch filling head walls or Sqm 4500 191.20 4500.00 4500.00 860,400.00 860,400.00
any other component
ADDENDUM ITEMS
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
191010 Exploratory drilling of Boreholes
down to required depth, drilling of
150mm diameter boreholes in all type
of soils except hard rock and large
boulders (boulder core more than 30
cm), including refilling and reinstating
surface, and disposing off surplus
material including use of mechanical
rigs with power operated winches as
well as percussion / chieselling tool
for advancing through occasional
seams of hard strata to be employed,
where necessary in Dry area

191011 0m to 10m metre 100


1161.50 - 116,150.00

191012 10m to 20m metre 100


1277.65 - 127,765.00

191013 20m to 30m metre 100


1393.80 - 139,380.00

191014 30m to 40m metre 50


1509.95 - 75,497.50
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
191100 Taking out 100mm dia & Each 120
450mm long undisturbed samples of
soil from bore holes, including
provision of air tight containers for
packing and, labelling incl.
transporting the samples to
laboratory. Piston sampler shall be
used for extracting undisturbed 104.54 - 12,544.80
samples where necessary. Samples
shall be collected as per IS
2720

191110 Taking out 100mm dia & 450mm long Each 10


disturbed samples of soil from bore
holes, including provision of air tight
containers for packing, labelling and
transporting the samples to
laboratory. Samples shall be collected 116.15 - 1,161.50
as per IS
2720

191120 Conducting standard penetration test Each 210


as per IS
2131 at approximate1.5 m intervals
in bore holes, as directed by the 174.23 - 36,588.30
Engineer in charge

191140 Conducting laboratory Tests on


collected soil samples as per
relevant IS code - -

191141 Moisture contents/ Dry density Each 90


1161.50 - 104,535.00
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
191142 Atterberg Limit Each 90
1161.50 - 104,535.00

191143 Specific Gravity Each 90


580.75 - 52,267.50

191144 Grain size analysis including Each 290


Hydrometer analysis 1161.50 - 336,835.00

191145 Direct Shear Test Each 120


2323.00 - 278,760.00

191147 Consolidation test Each 120


2323.00 - 278,760.00
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
191148 Unconfined compression test Each 120
2323.00 - 278,760.00

191149 Tri-axial test Each 120


2323.00 - 278,760.00
Total 7,203,033.48 10,485,253.28
Add 74.68% 5,379,225.40 7,830,387.15
Add Contractor above rate 9.90% 1245643.62940354 1813248.40175999
13,827,902.51 20,128,888.82
CHAPTER 20 BRIDGE WORK SUPER STRUCTURE RCC
Design, manufacturing, Supplying and
53 201040 fixing in position elastomeric bearing cucm 5817500 1.15 5817500.00 0.00 6,690,125.00 -
pads

Providing, fabricating & fixing in position


54 201070 to exact design profiles, prestressing MT 60 132714.65 60.00 0.00 7,962,879.00 -
H.T.S. cables.
Total 14,653,004.00 -
Add 10.57% 1,548,822.52 -
Add Contractor above rate 9.90% 1603980.8257572 0
17,805,807.35 -
Chapter -21 BRIDGE WORK SUPER STRUCTURE STEEL (ONLY ITEM NO. 211010/211011)
Supplying of all types of structural steel
55 211011 MT 3000 64442.18 3000.00 2700.00 193,326,540.00 173,993,886.00
conforming to Fe 410 B
ADDENDUM ITEMS
Design, supplying, fitting &fixing
211130 cucm 0.66 6000000.00 - 3,960,000.00
elastomeric bearing
supply fabrication and erection bed plate
211230/ more than 12.2 m but up to 18.3 m clear kg 254.41 102000.00 - 25,949,820.00
211232 span
Total 193,326,540.00 203,903,706.00
Add 35.01% 67,683,621.65 71,386,687.47
Add Contractor above rate 9.90% 25840006.003746 27253748.9535894
286,850,167.66 302,544,142.42
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
Chapter -22 BRIDGE WORK MISCELLANEOUS
57 222180 Providing and laying of filter media cum 500 1492.93 500.00 5000.00 746,465.00 7,464,650.00
Providing Boulder backing behind wing
58 222290 wall, return wall, retaining wall with hand cum 5000 133.62 5000.00 5000.00 668,100.00 668,100.00
packed boulders
Total 1,414,565.00 8,132,750.00
Add 0.00% - -
Add Contractor above rate 9.90% 140041.935 805142.25
1,554,606.94 8,937,892.25
Schedule B-NON SCHEDULE ITEMS
Providing, boring and casting Bored cast
4 NS-4 in situ 1200mm dia Reinforced Cement Metre 17000.00 8476.17 17000.00 28700.00 144,094,890.00 243,266,079.00
Concrete piles

Add Contractor above rate 10.20% 14,697,678.78 24,813,140.06


Total 158,792,568.78 268,079,219.06
Providing and laying RCC (M-35) Pile
5 NS-5 Caps cum 12025.00 5801.43 12025.00 17634.00 69,762,195.75 102,302,416.62

Add Contractor above rate 10.20% 7,115,743.97 10,434,846.50


Total 76,877,939.72 112,737,263.12
Providing and laying RCC (M-35) Piers,
7 NS-7 Abutments cum 1500.00 5943.75 1500.00 2259.93 8,915,625.00 13,432,482.71

Add Contractor above rate 10.20% 909,393.75 1,370,113.24


Total 9,825,018.75 14,802,595.95
Providing and laying RCC (M-35)
8 NS-8 abutments & pier cap, pedestal, fins etc. cum 3100.00 6228.37 3100.00 5072.72 19,307,947.00 31,594,752.15

Add Contractor above rate 10.20% 1,969,410.59 3,222,664.72


Total 21,277,357.59 34,817,416.87
Providing and laying RCC (M-35)
Retaining with/without counterfort,
9 NS-9 curtain/drop walls etc. in foundation cum 1000.00 5833.53 1000.00 6001.22 5,833,530.00 35,008,291.07

Add Contractor above rate 10.20% 595,020.06 3,570,845.69


Total 6,428,550.06 38,579,136.76
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
Providing and laying RCC (M-35)
Retaining with/without counterfort,
10 NS-10 curtain/drop walls etc. above foundation cum 5000.00 6142.50 5000.00 3833.88 30,712,500.00 23,549,584.87

Add Contractor above rate 10.20% 3,132,675.00 2,402,057.66


Total 33,845,175.00 25,951,642.52
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C
Providing and laying in position
reinforced cement concrete of M40
16 NS-16 grade In Deck slab, retainers, inspection cum 4000.00 7646.51 4000.00 3069.00 30,586,040.00 23,467,139.19
platforms etc.

Add Contractor above rate 10.20% 3,119,776.08 2,393,648.20


Total 33,705,816.08 25,860,787.39
Supplying providing welding of shear
NS 18 stud kg 58000.00 224.72 58000.00 118000.00 13,033,760.00 26,516,960.00

Add Contractor above rate 10.20% 1,329,443.52 -


Total 14,363,203.52 26,516,960.00
Providing temporary steel barricading
20 NS-20 2.0mtr. High and making arrangement for Metre 6000.00 615.75 6000.00 0.00 3,694,500.00 -
traffic diversion.

Add Contractor above rate 10.20% 376,839.00 -


Total 4,071,339.00 -
Providing and laying in position
reinforced cement concrete of M-
21 NS-21 40/M45 grade in precast PSC girder/T- cum 1025.00 9131.08 1025.00 0.00 9,359,357.00 -
girder/Slab of any span.

Add Contractor above rate 10.20% 954,654.41 -


Total 10,314,011.41 -
Lifting, handling and transporting PSC
precast girders/ slabs from the casting
22 NS-22 yard to the place of launching/erection cum 1025.00 6534.15 1025.00 0.00 6,697,503.75 -

Add Contractor above rate 10.20% 683,145.38 -


Total 7,380,649.13 -
S.No Agreement Qty. as per Amount as Amount as
Item No. Description of Item Unit Agreement Qty Base Rate
. Qty 1st A&C per Agreement per 1st A&C

Summary
Chapter- 3A 20,412,578.35 22,359,258.33
Chapter- 4 11,878,265.87 12,937,681.22
Chapter -4 A 638,747,435.27 606,643,204.45
Chapter -8 7,628,360.10 208,820,680.37
Chapter -13 4,403,308.62 6,720,073.71
Chapter -17 58,569,597.08 62,757,497.89
Chapter -19 13,827,902.51 20,128,888.82
Chapter -20 17,805,807.35 -
Chapter -21 286,850,167.66 302,544,142.42
Chapter -22 1,554,606.94 8,937,892.25
Sub-Total of Schedule "A" (Rs) = 1,061,678,029.74 1,251,849,319.46
NS-4 158,792,568.78 268,079,219.06
NS-5 76,877,939.72 112,737,263.12
NS-7 9,825,018.75 14,802,595.95
NS-8 21,277,357.59 34,817,416.87
NS-9 6,428,550.06 38,579,136.76
NS-10 33,845,175.00 25,951,642.52
NS-16 14,363,203.52 26,516,960.00
NS-18 14,363,203.52 26,516,960.00
NS-20 4,071,339.00 -
NS-21 10,314,011.41 -
NS-22 7,380,649.13 -
NS ITEMS :- Basic Cost of Schedule "B" Total (Rs) = 357,539,016.49 548,001,194.28
ROJECT ROHTAK

Saving in Variation
Project Cost of Amount

0.00 1946679.98

0.00 1059415.34
Saving in Variation
Project Cost of Amount

-32104230.82 0.00
Saving in Variation
Project Cost of Amount

0.00 201192320.27
Saving in Variation
Project Cost of Amount

0.00 2316765.08
Saving in Variation
Project Cost of Amount

0.00 4187900.82
Saving in Variation
Project Cost of Amount
Saving in Variation
Project Cost of Amount
Saving in Variation
Project Cost of Amount
Saving in Variation
Project Cost of Amount

0.00 6300986.31

-17805807.35 0.00

0.00 15693974.77
Saving in Variation
Project Cost of Amount

0.00 7383285.32

0.00 109286650.28

0.00 35859323.40

0.00 4977577.20

0.00 13540059.28

0.00 32150586.70
Saving in Variation
Project Cost of Amount

-7893532.48 0.00
Saving in Variation
Project Cost of Amount

-7845028.69 0.00

0.00 12153756.48

-4071339.00 0.00

-10314011.41 0.00

-7380649.13 0.00
Saving in Variation
Project Cost of Amount

Summary
0.00 1946679.98
0.00 1059415.34
-32104230.82 0.00
0.00 201192320.27
0.00 2316765.08
0.00 4187900.82
0.00 6300986.31
-17805807.35 0.00
0.00 15693974.77
0.00 7383285.32
-49910038.17 240081327.88
0.00 109286650.28
0.00 35859323.40
0.00 4977577.20
0.00 13540059.28
0.00 32150586.70
-7893532.48 0.00
0.00 12153756.48

-4071339.00 0.00
-10314011.41 0.00
-7380649.13 0.00
-29659532.02 207967953.34
RAILWAY PROJECT ROHTAK
Schedule A-SOR ITEMS BOQ QUANTITY AMOUNT
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Chapter -1 EarthWork
1 13111 Earthwork in cutting cum 4500 140.57 4500.00 4500.00 632,565.00

2 13120 Earthwork in filling in embankment cum 40000 213.67 40000.00 40000.00 8,546,800.00

Extra for mechanical compaction of


3 13130 earth/blanketing material filled in cum 40000 11.43 40000.00 40000.00 457,200.00
embankment

Removal of excavated/slip earth/


4 13140 cum 10000 95.82 10000.00 10000.00 958,200.00
debris/ malba from the site of works

Turfing / planting, including all lead


5 14052 100 Sqm 2000 4216.15 2000.00 2000.00 84,323.00
and lift, and watering
Total 10,679,088.00
Add 7.51% 801,999.51
11,481,087.51
Chapter -2 CARRIAGE OF MATERIALS
Hiring and operating Multi-Utility Each/
6 21430 36 24438.42 36.00 36.00 879,783.12
vehicle of loading capacity month
Extra over item no. 021430 for every
7 21440 additional km or part thereof over Kilometre 36000 20.32 36000.00 36000.00 731,520.00
1200 km in a month.
Total 1,611,303.12
Add 0.00% -
1,611,303.12
Chapter -3 PLAIN CONCRETE
PCC:- 1:3:6 (1 cement : 3 sand : 6
8 31011 graded stone aggregate 20mm cum 4000 1972.51 4000.00 4000.00 7,890,040.00
nominal size)
Total 7,890,040.00
Add 59.01% 4,655,912.60
12,545,952.60
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
CHAPTER 3-A PLAIN CONCRETE (SUPPLYING & USING OF CEMENT)
Supply and using cement at worksite :
9 33061 Tonne 2700 5474.00 2700.00 2957.49 14,779,800.00
OPC 43 grade
Total 14,779,800.00
Add 25.67% 3,793,974.66
18,573,774.66
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
CHAPTER 4 REINFORCED CEMENT CONCRETE (EXCEPT ITEM NO. 045010 TO 045022)

Centering and shuttering including


strutting, propping etc. and removal of
form for :-Walls (any thickness)
10 42012 Sqm 35000 191.20 35000.00 35000.00 6,692,000.00
including attached plasters,
buttresses, plinth and string courses
etc.

ADDENDUM ITEMS

Centering and shuttering including


strutting, propping etc. and removal of
form for :-Foundations, footings, bases Sqm
42011 of columns, raft foundation of 120.60 4949.05 -
washable aprons, Pile caps, Footings
of FOB etc.

Total 6,692,000.00
Add 61.51% 4,116,249.20
10,808,249.20
ITEM NO. 045010 TO 045022 (SUPPLY & USE OF STEEL REINFORCEMENT)OF CHAPTER 4

Supplying Reinforcement for R.C.C.


work including straightening, cutting,
11 45016 bending, placing in position and Kg 9929590 47.58 9929590.00 9430516.61 472,449,892.20
binding all complete. Thermo-
Mechanically Treated bars

Total 472,449,892.20
Add 23.02% 108,757,965.18
581,207,857.38
Chapter -5 BRICK WORK
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement

Brick work with non-modular (FPS)


bricks of class designation 7.5 in
12 51015 foundation and plinth in :- Cement cum 100 2143.06 100.00 100.00 214,306.00
mortar 1:6 (1 cement : 6 fine sand)

Extra over item 051010 & 051020 for


13 51040 brick work in superstructure beyond cum 100 133.42 100.00 100.00 13,342.00
plinth level upto floor two level :

Total 227,648.00
Add 74.68% 170,007.53
397,655.53
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Chapter -6 (STONE WORK)
Stone tile work 8mm thick (mirror
14 65202 polishing and machine cut edge) Sqm 1700 1040.06 1700.00 1700.00 1,768,102.00
Granite brown Ruby Red stone
Total 1,768,102.00
Add 0.00% -
1,768,102.00
Chapter -8 (STEEL & ALUMINIUM WORK)
Structural steel work In RSJ, tees,
15 81031 Kg 63000 75.92 63000.00 957550.00 4,782,960.00
angles and channels
Structural steel work In flats, plates ,
16 81032 Kg 15000 73.26 15000.00 1205492.00 1,098,900.00
round or square bars
Total 5,881,860.00
Add 18.01% 1,059,322.99
6,941,182.99
Chapter -9 FLOORING

Providing & fixing Precast Chequered


17 94061 Sqm 3000 468.24 3000.00 3000.00 1,404,720.00
tiles 250mm x 250mm x 25mm thick

Supplying and laying interlocking pre-


18 98021 cast CC block pavers 60 mm thick Sqm 3000 480.98 3000.00 3000.00 1,442,940.00
blocks of M30 grade for light traffic

Extra over items for using plastic


19 98030 Sqm 3000 43.67 3000.00 3000.00 131,010.00
moulds if specifically ordered

Extra over Item 098010 for addition of


20 98050 Sqm 3000 25.04 3000.00 3000.00 75,120.00
pigment in concrete of paver blocks

Total 3,053,790.00
Add 0.00% -
3,053,790.00
Chapter -11 FINISHING MASANORY
12 mm cement plaster of mix - 1:4
21 111011 Sqm 1000 57.39 1000.00 1000.00 57,390.00
(1cement: 4 fine sand)
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement

Finishing walls with water proofing


cement paint of required shade two or
22 115110 more coats on new work applied @ Sqm 60000 38.40 60000.00 60000.00 2,304,000.00
3.84 Kg/10 sqm

Total 2,361,390.00
Add 23.17% 547,134.06
2,908,524.06
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Chapter -12 PAINTING POLISHING & VARNISHING

Painting with synthetic enamel paint


of approved brand and manufacture
23 121051 Sqm 2000 40.81 2000.00 2000.00 81,620.00
to give an even shade Two or more
coats on new work

Total 81,620.00
Add 43.84% 35,782.21
117,402.21
Chapter -13 SANITARY INSTALATION

Providing and fixing medium grade


24 131151 Metre 100 128.42 100.00 100.00 12,842.00
G.I. pipes c 15 mm dia. nominal bore

Providing and fixing medium grade


25 131153 Metre 75 214.91 75.00 75.00 16,118.25
G.I. pipes 25 mm dia. nominal bore

Providing and fixing medium grade


26 131156 Metre 100 384.78 100.00 100.00 38,478.00
G.I. pipes 50 mm dia. nominal bore

Providing and fixing medium grade


27 131158 Metre 100 629.12 100.00 100.00 62,912.00
G.I. 80 mm dia. nominal bore

Providing and fixing medium grade


28 131159 Metre 4500 861.40 4500.00 4500.00 3,876,300.00
G.I. pipes 100 mm dia. nominal bore

ADDENDUM ITEMS

Providing and laying S&S centrifugally


cast (spun)
iron pipes (Class LA) conforming to IS -
133050 1536 : upto
300 mm dia.

150 mm dia. pipe 2,081.14 345.00


133054 Metre -
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement

Providing and laying S&S Centrifugally


Cast (Spun) Ductile Iron Pipes
133100 conforming to IS : 8329 of Class K
9 up to 500 mm dia

100mm dia Ductile Iron CLass K - 9 1,240.03 380.00


133101 pipes Metre -

200mm dia Ductile Iron CLass K - 9 2,226.18 85.00


133103 pipes Metre -

250mm dia Ductile Iron CLass K - 9 3,192.90 15.00


133104 pipes Metre -

450mm dia Ductile Iron CLass K – 9 7,266.01 40.00


133108 pipes Metre -

Providing and laying S&S Centrifugally


Cast (Spun) Ductile Iron Pipes
133110 conforming to IS : 8329 of Class K
9 Above 500 mm dia

600mm dia Ductile Iron CLass K - 9 11,174.36 35.00


metre
133111 pipes -

Total 4,006,650.25
Add 0.00% -
4,006,650.25
Chapter -14 DRAINAGE & SEWERAGE
Providing and laying non-pressure NP2
29 142012 class (light duty) R.C.C. pipes 150mm Metre 5000 485.02 5000.00 5000.00 2,425,100.00
dia. R.C.C. pipe
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Providing and laying non-pressure NP2
30 142013 class (light duty) R.C.C. pipes 250mm Metre 50 719.85 50.00 50.00 35,992.50
dia. R.C.C. pipe

Providing and laying non-pressure NP2


31 142014 class (light duty) R.C.C. pipes 300mm Metre 560 721.21 560.00 560.00 403,877.60
dia. R.C.C. pipe

Providing and laying non-pressure NP2


32 142015 class (light duty) R.C.C. pipes 450mm Metre 540 818.21 540.00 540.00 441,833.40
dia. R.C.C. pipe

Providing and laying non-pressure NP2


33 142017 class (light duty) R.C.C. pipes 600mm Metre 540 1099.39 540.00 540.00 593,670.60
dia. R.C.C. pipe
Constructing brick masonry manhole
34 143013 Each 60 9446.78 60.00 60.00 566,806.80
in cement mortar 1:4

Deduct for providing S.F.R.C. Cover


and frame(Heavy duty,HD-20 grade
designation) 560mm internal diameter
35 143020 Each 60 -3136.05 60.00 60.00 -188,163.00
conforming to IS:12592 in lieu of CI
frame & Cover from item 143013 to
143014

Total 4,279,117.90
Add 50.00% 2,139,558.95
6,418,676.85
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Chapter -17 misc. building works
Boring, providing and installing :-
36 171613 Metre 27000 1929.93 27000.00 28974.50 52,108,110.00
450mm dia piles
Vertical load testing Single pile upto
37 171651 Each Test 4 64056.73 4.00 4.00 256,226.92
50 tonne capacity- initial test
Vertical load testing of piles - routine
38 171652 Each Test 10 52267.50 10.00 10.00 522,675.00
test
Lateral load testing :- Vertical load
39 171681 Each Test 14 29037.50 14.00 14.00 406,525.00
capacity upto 50 MT
Total 53,293,536.92
Add 0.00% -
53,293,536.92
Chapter -18 DISMANTLING & DEMOLISHING
Dismantling of old S.W. pipes :-
40 189081 Metre 500 27.90 500.00 500.00 13,950.00
100mm diameter
Dismantling of old S.W. pipes:- 150mm
41 189082 Metre 500 31.62 500.00 500.00 15,810.00
diameter
Dismantling of old S.W. pipes :-
42 189084 Metre 500 37.71 500.00 500.00 18,855.00
250mm diameter

Dismantling of manhole complete


43 189091 :-Rectangular manhole 90x80cm Each 50 656.50 50.00 50.00 32,825.00
(Inside dimensions) and 45cm deep.

Dismantling of manhole complete


44 189092 :-Rectangular manhole 120x90cm Each 50 1207.29 50.00 50.00 60,364.50
(Inside dimensions) and 90cm deep

Total 141,804.50
Add 22.89% 32,459.05
174,263.55
Chapter -19 BRIDGE WORK SUB STRUCTURE
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement

Conducting load testing of a single pile


45 192107 :-Routine Load Test above 100 ton Each 10 138177.85 10.00 10.00 1,381,778.50
capacity Up to 250 ton capacity pile

Lateral load testing of single pile i:-


46 192113 Piles with lateral load capacity of Each 14 64352.57 14.00 14.00 900,935.98
above 20 ton
Providing and applying two coats of
47 195020 Sqm 12000 108.60 12000.00 12000.00 1,303,200.00
coal tar or bitumen

Centring and shuttering including


strutting, propping etc. and removal of
48 195031 Sqm 6500 120.60 6500.00 6706.66 783,900.00
form for :- RCC raft foundation & Pile
cap

Centring and shuttering including


strutting, propping etc. and removal of
49 195032 Sqm 3500 191.20 3500.00 4804.81 669,200.00
form for :- Abutment, pier, wing walls
and return walls

Abutment cap, Pier Cap, Inspection


50 195033 Platform & Pedestal over Pier cap, Sqm 6700 185.57 6700.00 10933.00 1,243,319.00
Fender wall, Diaphragm wall, etc.

Approach slab at formation level, Dirt


51 195034 Sqm 500 120.60 500.00 500.00 60,300.00
wall/ ballast wall at formation level

In Bottom/top slab, side walls, toe wall


52 195038 and sumps haunch filling head walls or Sqm 4500 191.20 4500.00 4500.00 860,400.00
any other component

ADDENDUM ITEMS
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
191010 Exploratory drilling of
Boreholes down to required
depth, drilling of 150mm diameter
boreholes in all type of soils except
hard rock and large boulders
(boulder core more than 30 cm),
including refilling and reinstating
surface, and disposing off surplus
material including use of
mechanical rigs with power
operated winches as well as
percussion / chieselling tool for
advancing through occasional
seams of hard strata to be
employed, where necessary in Dry
area

191011 0m to 10m metre 100


1161.50 -

191012 10m to 20m metre 100


1277.65 -

191013 20m to 30m metre 100


1393.80 -

191014 30m to 40m metre 50


1509.95 -
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
191100 Taking out 100mm dia & Each 120
450mm long undisturbed samples
of soil from bore holes, including
provision of air tight containers for
packing and, labelling incl.
transporting the samples to
laboratory. Piston sampler shall be
used for extracting undisturbed 104.54 -
samples where necessary.
Samples shall be collected as per
IS
2720

191110 Taking out 100mm dia & 450mm Each 10


long disturbed samples of soil from
bore holes, including provision of
air tight containers for packing,
labelling and transporting the
samples to laboratory. Samples 116.15 -
shall be collected as per IS
2720

191120 Conducting standard penetration Each 210


test as per IS
2131 at approximate1.5 m
intervals in bore holes, as 174.23 -
directed by the Engineer in charge

191140 Conducting laboratory Tests on


collected soil samples as per
relevant IS code -

191141 Moisture contents/ Dry density Each 90


1161.50 -
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
191142 Atterberg Limit Each 90
1161.50 -

191143 Specific Gravity Each 90


580.75 -

191144 Grain size analysis including Each 290


Hydrometer analysis 1161.50 -

191145 Direct Shear Test Each 120


2323.00 -

191147 Consolidation test Each 120


2323.00 -

191148 Unconfined compression test Each 120


2323.00 -

191149 Tri-axial test Each 120


2323.00 -
Total 7,203,033.48
Add 74.68% 5,379,225.40
12,582,258.88
CHAPTER 20 BRIDGE WORK SUPER STRUCTURE RCC
Design, manufacturing, Supplying and
53 201040 fixing in position elastomeric bearing cucm 5817500 1.15 5817500.00 0.00 6,690,125.00
pads

Providing, fabricating & fixing in


54 201070 position to exact design profiles, MT 60 132714.65 60.00 0.00 7,962,879.00
prestressing H.T.S. cables.

Total 14,653,004.00
Add 10.57% 1,548,822.52
16,201,826.52
Chapter -21 BRIDGE WORK SUPER STRUCTURE STEEL (ONLY ITEM NO.
211010/211011)
Supplying of all types of structural
55 211011 MT 3000 64442.18 3000.00 2700.00 193,326,540.00
steel conforming to Fe 410 B
Design, supplying, fitting &fixing
211130 elastomeric bearing cucm 0.66 6000000.00 -
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement

211230/21 supply fabrication and erection bed


plate more than 12.2 m but up to kg 254.41 102000.00 -
1232 18.3 m clear span

Total 193,326,540.00
Add 35.01% 67,683,621.65
261,010,161.65
CHAPTER -21 BRIDGE WORK SUPER STRUCTURE STEEL (EXCEPT ITEM NO. 211010/211011)
Providing and fixing 65/50 mm
56 211060 nominal dia B class G.I. pipe railing a Kg 35000 58.34 35000.00 35000.00 2,041,900.00
complete job
Total 2,041,900.00
Add 68.05% 1,389,512.95
3,431,412.95
Chapter -22 BRIDGE WORK MISCELLANEOUS
57 222180 Providing and laying of filter media cum 500 1492.93 500.00 5000.00 746,465.00

Providing Boulder backing behind


58 222290 wing wall, return wall, retaining wall cum 5000 133.62 5000.00 5000.00 668,100.00
with hand packed boulders
Total 1,414,565.00
Add 0.00% -
1,414,565.00
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Chapter -23 ALL ITEMS OF CHAPTER 23 ROAD & PLATFORM WORKS
Providing and laying water bound
macadam Base course with 63mm to
59 231042 cum 900 1297.96 900.00 900.00 1,168,164.00
45mm size including stone screening
13.2mm size

Providing and laying water bound


macadam Base course with 53mm to
60 231043 cum 900 1414.11 900.00 900.00 1,272,699.00
22.4mm size including stone screening
11.2mm size

Supplying and laying precast Kerb


61 237050 Metre 1392 385.34 1392.00 1392.00 536,393.28
Stone of concrete M25 Grade .

Providing and laying bitumen mastic


62 238031 Sqm 5220 657.69 5220.00 5220.00 3,433,141.80
wearing course 25 mm thick

Total 6,410,398.08
Add -2.49% -159,618.91
6,250,779.17
Chapter -25 ALL ITEMS OF CHAPTER 25 SUPPLY OF MATERIALS
Stone Boulder Weighing minimum 35
63 252390 cum 5000 632.50 5000.00 5000.00 3,162,500.00
Kg Each
Total 3,162,500.00
Add 0.00% -
3,162,500.00

Schedule B-NON SCHEDULE ITEMS


Supplying and filling blanketing
1 NS-1 material cum 5000.00 1727.86 5000.00 5000.00 8,639,300.00
Dismantling of Brick/stone
2 NS-2 masonry/boulder pitching i n cum 1500.00 812.86 1500.00 1500.00 1,219,290.00
lime/cement ,etc.

Supplying, providing, tightening of all


types of High Strength frictional grip
3 NS-3 (HSFG) bolts, nuts & washers/DTI Kg 70000.00 202.18 70000.00 70000.00 14,152,600.00
washers
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Providing, boring and casting Bored
cast in situ 1200mm dia Reinforced
4 NS-4 Cement Concrete piles Metre 17000.00 8476.17 17000.00 28700.00 144,094,890.00

Providing and laying RCC (M-35) Pile


5 NS-5 Caps cum 12025.00 5801.43 12025.00 17634.00 69,762,195.75
Providing and laying RCC (M-35) RCC
6 NS-6 box cum 1500.00 5739.88 1500.00 1500.00 8,609,820.00
Providing and laying RCC (M-35) Piers,
7 NS-7 Abutments cum 1500.00 5943.75 1500.00 2259.93 8,915,625.00
Providing and laying RCC (M-35)
8 NS-8 abutments & pier cap, pedestal, fins cum 3100.00 6228.37 3100.00 5072.72 19,307,947.00
etc.

Providing and laying RCC (M-35)


Retaining with/without counterfort,
9 NS-9 curtain/drop walls etc. in foundation cum 1000.00 5833.53 1000.00 6001.22 5,833,530.00

Providing and laying RCC (M-35)


Retaining with/without counterfort,
10 NS-10 curtain/drop walls etc. above cum 5000.00 6142.50 5000.00 3833.88 30,712,500.00
foundation

Providing and laying RCC (M-25) for


11 NS-11 drain covers/manhole covers & flue cum 40.00 6205.95 40.00 40.00 248,238.00
tops etc.

Metalizing girder /girder components


such as cross girders ,stiffeners,
12 NS-12 bracing etc. of new steel girder Sqm 38000.00 660.58 38000.00 38000.00 25,102,040.00

Providing and laying 150mm dia


13 NS-13 drainage spout Each 700.00 1886.29 700.00 700.00 1,320,403.00
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
Providing and fixing in position of
standard preformed sealed and slab
type or strip seal elastomeric type
14 NS-14 expansion joints for Railway bridge. Metre 650.00 9040.76 650.00 650.00 5,876,494.00

Earthwork in excavation in all type of


soil (excluding rocks) for foundation &
floors of Bridges, retaining wall etc.
15 NS-15 including garbage/ debris/malba etc cum 43000.00 198.00 43000.00 43000.00 8,514,000.00

Providing and laying in position


reinforced cement concrete of M40
16 NS-16 grade In Deck slab, retainers, cum 4000.00 7646.51 4000.00 3069.00 30,586,040.00
inspection platforms etc.

Providing and laying CC of specified


17 NS-17 grade in pavements/ roads/ wearing cum 1400.00 5543.89 1400.00 1400.00 7,761,446.00
coat etc.

Supplying, providing, welding of Stud


18 NS-18 shear connecter. Kg 58000.00 224.72 58000.00 118000.00 13,033,760.00
Providing and fixing 150mm dia (B)
19 NS-19 class GI rain water pipe as a complete Metre 2000.00 869.15 2000.00 2000.00 1,738,300.00
job.

Providing temporary steel barricading


2.0mtr. High and making arrangement
20 NS-20 for traffic diversion. Metre 6000.00 615.75 6000.00 0.00 3,694,500.00

Providing and laying in position


reinforced cement concrete of M-
21 NS-21 40/M45 grade in precast PSC girder/T- cum 1025.00 9131.08 1025.00 0.00 9,359,357.00
girder/Slab of any span.

Lifting, handling and transporting PSC


precast girders/ slabs from the casting
22 NS-22 yard to the place of cum 1025.00 6534.15 1025.00 0.00 6,697,503.75
launching/erection
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement

Summary
Chapter-1 11,481,087.51
Chapter-2 1,611,303.12
Chapter-3 12,545,952.60
Chapter- 3A 18,573,774.66
Chapter- 4 10,808,249.20
Chapter -4 A 581,207,857.38
Chapter -5 397,655.53
Chapter -6 1,768,102.00
Chapter -8 6,941,182.99
Chapter -9 3,053,790.00
Chapter -11 2,908,524.06
Chapter -12 117,402.21
Chapter -13 4,006,650.25
Chapter -14 6,418,676.85
Chapter -17 53,293,536.92
Chapter -18 174,263.55
Chapter -19 12,582,258.88
Chapter -20 16,201,826.52
Chapter -21 261,010,161.65
Chapter -21 A 3,431,412.95
Chapter -22 1,414,565.00
Chapter -23 6,250,779.17
Chapter -25 3,162,500.00
Sub-Total of Schedule "A" (Rs) = 1,019,361,513.01
Rate Quated By The Contractor @ 9.90% Above 100,916,789.79
Cost of the work based on accepted rates of Schedule "A" (Rs) 1,120,278,302.80
NS-1 8,639,300.00
NS-2 1,219,290.00
NS-3 14,152,600.00
NS-4 144,094,890.00
NS-5 69,762,195.75
NS-6 8,609,820.00
Agreement Qty. as per 1st Amount as
S.No. Item No. Description of Item Unit Agreement Qty Base Rate Qty A&C per Agreement
NS-7 8,915,625.00
NS-8 19,307,947.00
NS-9 5,833,530.00
NS-10 30,712,500.00
NS-11 248,238.00
NS-12 25,102,040.00
NS-13 1,320,403.00
NS-14 5,876,494.00
NS-15 8,514,000.00
NS-16 30,586,040.00
NS-17 7,761,446.00
NS-18 13,033,760.00
NS-19 1,738,300.00
NS-20 3,694,500.00
NS-21 9,359,357.00
NS-22 6,697,503.75
NS ITEMS :- Basic Cost of Schedule "B" Total (Rs) = 425,179,779.50
Add Rly. % 10.20 Above 43,368,337.51
The Cost of Schedule "B" (Rs) 468,548,117.01
Total 1,588,826,419.80
WAY PROJECT ROHTAK
AMOUNT
Amount as Saving in Variation
per 1st A&C Project Cost of Amount

632,565.00 0.00 0.00

8,546,800.00 0.00 0.00

457,200.00 0.00 0.00

958,200.00 0.00 0.00

84,323.00 0.00 0.00

10,679,088.00 0.00 0.00


801,999.51 0.00 0.00
11,481,087.51 0.00 0.00
0.00 0.00

879,783.12 0.00 0.00

731,520.00 0.00 0.00

1,611,303.12 0.00 0.00


- 0.00 0.00
1,611,303.12 0.00 0.00
0.00 0.00

7,890,040.00 0.00 0.00

7,890,040.00 0.00 0.00


4,655,912.60 0.00 0.00
12,545,952.60 0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount
0.00 0.00

16,189,300.57 0.00 1409500.57

16,189,300.57 0.00 1409500.57


4,155,793.46 0.00 361818.80
20,345,094.02 0.00 1771319.36
Amount as Saving in Variation
per 1st A&C Project Cost of Amount

6,692,000.00 0.00 0.00

0.00 0.00

596,855.43 0.00 596855.43

7,288,855.43 0.00 596855.43


4,483,374.97 0.00 367125.77
11,772,230.40 0.00 963981.20
0.00 0.00

448,703,980.20 -23745912.00 0.00

448,703,980.20 -23745912.00 0.00


103,291,656.24 -5466308.94 0.00
551,995,636.44 -29212220.95 0.00
0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount

214,306.00 0.00 0.00

13,342.00 0.00 0.00

227,648.00 0.00 0.00


170,007.53 0.00 0.00
397,655.53 0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount
0.00 0.00

1,768,102.00 0.00 0.00

1,768,102.00 0.00 0.00


- 0.00 0.00
1,768,102.00 0.00 0.00
0.00 0.00

72,697,196.00 0.00 67914236.00

88,314,343.92 0.00 87215443.92

161,011,539.92 0.00 155129679.92


28,998,178.34 0.00 27938855.35
190,009,718.26 0.00 183068535.27
0.00 0.00

1,404,720.00 0.00 0.00

1,442,940.00 0.00 0.00

131,010.00 0.00 0.00

75,120.00 0.00 0.00

3,053,790.00 0.00 0.00


- 0.00 0.00
3,053,790.00 0.00 0.00
0.00 0.00

57,390.00 0.00 0.00


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

2,304,000.00 0.00 0.00

2,361,390.00 0.00 0.00


547,134.06 0.00 0.00
2,908,524.06 0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount

81,620.00 0.00 0.00

81,620.00 0.00 0.00


35,782.21 0.00 0.00
117,402.21 0.00 0.00
0.00 0.00

12,842.00 0.00 0.00

16,118.25 0.00 0.00

38,478.00 0.00 0.00

62,912.00 0.00 0.00

3,876,300.00 0.00 0.00

0.00 0.00

0.00 0.00

717,993.30 0.00 717993.30


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

0.00 0.00

471,211.40 0.00 471211.40

189,225.30 0.00 189225.30

47,893.50 0.00 47893.50

290,640.40 0.00 290640.40

0.00 0.00

391,102.60 0.00 391102.60

6,114,716.75 0.00 2108066.50


- 0.00 0.00
6,114,716.75 0.00 2108066.50
0.00 0.00

2,425,100.00 0.00 0.00


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

35,992.50 0.00 0.00

403,877.60 0.00 0.00

441,833.40 0.00 0.00

593,670.60 0.00 0.00

566,806.80 0.00 0.00

-188,163.00 0.00 0.00

4,279,117.90 0.00 0.00


2,139,558.95 0.00 0.00
6,418,676.85 0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount
0.00 0.00

55,918,756.79 0.00 3810646.79

256,226.92 0.00 0.00

522,675.00 0.00 0.00

406,525.00 0.00 0.00

57,104,183.71 0.00 3810646.79


- 0.00 0.00
57,104,183.71 0.00 3810646.79
0.00 0.00

13,950.00 0.00 0.00

15,810.00 0.00 0.00

18,855.00 0.00 0.00

32,825.00 0.00 0.00

60,364.50 0.00 0.00

141,804.50 0.00 0.00


32,459.05 0.00 0.00
174,263.55 0.00 0.00
0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount

1,381,778.50 0.00 0.00

900,935.98 0.00 0.00

1,303,200.00 0.00 0.00

808,822.71 0.00 24922.71

918,679.67 0.00 249479.67

2,028,836.81 0.00 785517.81

60,300.00 0.00 0.00

860,400.00 0.00 0.00

0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount

0.00 0.00

116,150.00 0.00 116150.00

127,765.00 0.00 127765.00

139,380.00 0.00 139380.00

75,497.50 0.00 75497.50


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

12,544.80 0.00 12544.80

1,161.50 0.00 1161.50

36,588.30 0.00 36588.30

- 0.00 0.00

104,535.00 0.00 104535.00


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

104,535.00 0.00 104535.00

52,267.50 0.00 52267.50

336,835.00 0.00 336835.00

278,760.00 0.00 278760.00

278,760.00 0.00 278760.00

278,760.00 0.00 278760.00

278,760.00 0.00 278760.00


10,485,253.28 0.00 3282219.80
7,830,387.15 0.00 2451161.74
18,315,640.42 0.00 5733381.54
0.00 0.00

- -6690125.00 0.00

- -7962879.00 0.00

- -14653004.00 0.00
- -1548822.52 0.00
- -16201826.52 0.00
0.00 0.00

173,993,886.00 -19332654.00 0.00

3,960,000.00 0.00 3960000.00


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

25,949,820.00 0.00 25949820.00

203,903,706.00 0.00 10577166.00


71,386,687.47 0.00 3703065.82
275,290,393.47 0.00 14280231.82
0.00 0.00

2,041,900.00 0.00 0.00

2,041,900.00 0.00 0.00


1,389,512.95 0.00 0.00
3,431,412.95 0.00 0.00
0.00 0.00

7,464,650.00 0.00 6718185.00

668,100.00 0.00 0.00

8,132,750.00 0.00 6718185.00


- 0.00 0.00
8,132,750.00 0.00 6718185.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount
0.00 0.00

1,168,164.00 0.00 0.00

1,272,699.00 0.00 0.00

536,393.28 0.00 0.00

3,433,141.80 0.00 0.00

6,410,398.08 0.00 0.00


-159,618.91 0.00 0.00
6,250,779.17 0.00 0.00
0.00 0.00

3,162,500.00 0.00 0.00

3,162,500.00 0.00 0.00


- 0.00 0.00
3,162,500.00 0.00 0.00
0.00 0.00
0.00 0.00

8,639,300.00 0.00 0.00

1,219,290.00 0.00 0.00

14,152,600.00 0.00 0.00


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

243,266,079.00 0.00 99171189.00

102,302,416.62 0.00 32540220.87

8,609,820.00 0.00 0.00

13,432,482.71 0.00 4516857.71

31,594,752.15 0.00 12286805.15

35,008,291.07 0.00 29174761.07

23,549,584.87 -7162915.13 0.00

248,238.00 0.00 0.00

25,102,040.00 0.00 0.00

1,320,403.00 0.00 0.00


Amount as Saving in Variation
per 1st A&C Project Cost of Amount

5,876,494.00 0.00 0.00

8,514,000.00 0.00 0.00

23,467,139.19 -7118900.81 0.00

7,761,446.00 0.00 0.00

26,516,960.00 0.00 13483200.00

1,738,300.00 0.00 0.00

- -3694500.00 0.00

- -9359357.00 0.00

- -6697503.75 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount

0.00 0.00
11,481,087.51 0.00 0.00
1,611,303.12 0.00 0.00
12,545,952.60 0.00 0.00
20,345,094.02 0.00 1771319.36
11,772,230.40 0.00 963981.20
551,995,636.44 -29212220.95 0.00
397,655.53 0.00 0.00
1,768,102.00 0.00 0.00
190,009,718.26 0.00 183068535.27
3,053,790.00 0.00 0.00
2,908,524.06 0.00 0.00
117,402.21 0.00 0.00
6,114,716.75 0.00 2108066.50
6,418,676.85 0.00 0.00
57,104,183.71 0.00 3810646.79
174,263.55 0.00 0.00
18,315,640.42 0.00 5733381.54
- -16201826.52 0.00
275,290,393.47 0.00 14280231.82
3,431,412.95 0.00 0.00
8,132,750.00 0.00 6718185.00
6,250,779.17 0.00 0.00
3,162,500.00 0.00 0.00
1,192,401,813.02 -45414047.47 218454347.48
118,047,779.49 -4495990.70 21626980.40
1,310,449,592.51 -49910038.17 240081327.88
8,639,300.00 0.00 0.00
1,219,290.00 0.00 0.00
14,152,600.00 0.00 0.00
243,266,079.00 0.00 99171189.00
102,302,416.62 0.00 32540220.87
8,609,820.00 0.00 0.00
Amount as Saving in Variation
per 1st A&C Project Cost of Amount
13,432,482.71 0.00 4516857.71
31,594,752.15 0.00 12286805.15
35,008,291.07 0.00 29174761.07
23,549,584.87 -7162915.13 0.00
248,238.00 0.00 0.00
25,102,040.00 0.00 0.00
1,320,403.00 0.00 0.00
5,876,494.00 0.00 0.00
8,514,000.00 0.00 0.00
23,467,139.19 -7118900.81 0.00
7,761,446.00 0.00 0.00
26,516,960.00 0.00 13483200.00
1,738,300.00 0.00 0.00
- -3694500.00 0.00
- -9359357.00 0.00
- -6697503.75 0.00
582,319,636.61 -34033176.69 191173033.81
59,396,602.93 -3471384.02 19499649.45
641,716,239.55 -37504560.72 210672683.26
1,952,165,832.06 -87414598.89 450754011.14
INDEX OF M.B. (A&C)
Sr.No. Particulars Unit No. L. B. D. Qty.
Chapter -1 EarthWork
1 13111 Earthwork in cutting cum 4,500.00
2 13120 Earthwork in filling in embankment cum 40,000.000
Extra for mechanical compaction of earth/blanketing 40,000.00
3 13130 cum
material filled in embankment
Removal of excavated/slip earth/ debris/ malba from the 10,000.00
4 13140 cum
site of works

5 14052 Turfing / planting, including all lead and lift, and watering 100 Sqm 2,000.00

Chapter -2 CARRIAGE OF MATERIALS


Hiring and operating Multi-Utility vehicle of loading Each/ 36.00
6 21430
capacity month
Extra over item no. 021430 for every additional km or 36,000.00
7 21440 Kilometre
part thereof over 1200 km in a month.

Chapter -3 PLAIN CONCRETE


PCC:- 1:3:6 (1 cement : 3 sand : 6 graded stone 110 83 0.1 913
8 31011 cum
aggregate 20mm nominal size)
Re/Wall cum 1 1982 3.15 0.075 468.2475
Re/Wall cum 1 1288 3.15 0.075 304.29
Total 1685.5375

CHAPTER 3-A PLAIN CONCRETE (SUPPLYING & USING OF CEMENT)


9 33061 Supply and using cement at worksite : OPC 43 grade Tonne 4000 250 1000

Tonne 4605.8589563 425 1957.4900564


Total 2957.4900564

CHAPTER 4 REINFORCED CEMENT CONCRETE (EXCEPT ITEM NO.


045010 TO 045022)
Centering and shuttering including strutting, propping
etc. and removal of form for :-Walls (any thickness) 35000
10 42012 Sqm
including attached plasters, buttresses, plinth and string
courses etc.

ITEM NO. 045010 TO 045022 (SUPPLY & USE OF STEEL


REINFORCEMENT)OF CHAPTER 4
Sr.No. Particulars Unit No. L. B. D. Qty.

Supplying Reinforcement for R.C.C. work including


11 45016 straightening, cutting, bending, placing in position and
binding all complete. Thermo-Mechanically Treated bars

1200mm dia pile Kg 28700 0.09468 2717.316


Pile Cap Kg 16434 132kg/cum 2169.288
Pier shaft Kg 2259.934 381kg/cum 861.035
Pier Cap Kg 5072.72 100kg/cum 507.272
Deck Slab Kg 110 6588kg/span 724.680
Raft M-35 R/Wall Kg 6001.22 115kg/cum 690.140
M-35 Wall Kg 3833.88 115kg/cum 440.896
Pile 450mm Kg 28974.5 0.0396 1147.390
RCC Box Kg 1500.00 115kg/cum 172.500
Total 9430516.6078

Chapter -5 BRICK WORK


Brick work with non-modular (FPS) bricks of class
12 51015 designation 7.5 in foundation and plinth in :- Cement cum 100.000
mortar 1:6 (1 cement : 6 fine sand)

Extra over item 051010 & 051020 for brick work in 100.000
13 51040 cum
superstructure beyond plinth level upto floor two level :

Chapter -6 (STONE WORK)


Stone tile work 8mm thick (mirror polishing and machine 1700.00
14 65202 Sqm
cut edge) Granite brown Ruby Red stone

Chapter -8 (STEEL & ALUMINIUM WORK)


15 81031 Structural steel work In RSJ, tees, angles and channels Kg 957550

Structural steel work In flats, plates , round or square 1205492


16 81032 Kg
bars

Chapter -9 FLOORING
Providing & fixing Precast Chequered tiles 250mm x 3000
17 94061 Sqm
250mm x 25mm thick
Sr.No. Particulars Unit No. L. B. D. Qty.
Supplying and laying interlocking pre-cast CC block 3000
18 98021 Sqm
pavers 60 mm thick blocks of M30 grade for light traffic

Extra over items for using plastic moulds if specifically 3000


19 98030 Sqm
ordered
Extra over Item 098010 for addition of pigment in 3000
20 98050 Sqm
concrete of paver blocks

Chapter -11 FINISHING MASANORY


12 mm cement plaster of mix - 1:4 (1cement: 4 fine 1000
21 111011 Sqm
sand)
Finishing walls with water proofing cement paint of
22 115110 required shade two or more coats on new work applied Sqm 60000
@ 3.84 Kg/10 sqm

Chapter -12 PAINTING POLISHING & VARNISHING


Painting with synthetic enamel paint of approved brand
23 121051 and manufacture to give an even shade Two or more Sqm 2000
coats on new work

Chapter -13 SANITARY INSTALATION


Providing and fixing medium grade G.I. pipes c 15 mm 100
24 131151 Metre
dia. nominal bore
Providing and fixing medium grade G.I. pipes 25 mm 75
25 131153 Metre
dia. nominal bore
Providing and fixing medium grade G.I. pipes 50 mm dia. 100
26 131156 Metre
nominal bore
Providing and fixing medium grade G.I. 80 mm dia. 100
27 131158 Metre
nominal bore
Providing and fixing medium grade G.I. pipes 100 mm 4500
28 131159 Metre
dia. nominal bore

Chapter -14 DRAINAGE & SEWERAGE


Providing and laying non-pressure NP2 class (light duty) 5000
29 142012 Metre
R.C.C. pipes 150mm dia. R.C.C. pipe
Providing and laying non-pressure NP2 class (light duty) 50
30 142013 Metre
R.C.C. pipes 250mm dia. R.C.C. pipe
Sr.No. Particulars Unit No. L. B. D. Qty.
Providing and laying non-pressure NP2 class (light duty) 560
31 142014 Metre
R.C.C. pipes 300mm dia. R.C.C. pipe
Providing and laying non-pressure NP2 class (light duty) 540
32 142015 Metre
R.C.C. pipes 450mm dia. R.C.C. pipe
Providing and laying non-pressure NP2 class (light duty) 540
33 142017 Metre
R.C.C. pipes 600mm dia. R.C.C. pipe
Constructing brick masonry manhole in cement mortar 60
34 143013 Each
1:4
Deduct for providing S.F.R.C. Cover and frame(Heavy
duty,HD-20 grade designation) 560mm internal diameter 60
35 143020 Each
conforming to IS:12592 in lieu of CI frame & Cover from
item 143013 to 143014

Chapter -17 misc. building works


36 171613 Boring, providing and installing :- 450mm dia piles Metre 28974.5 28974.5
Vertical load testing Single pile upto 50 tonne capacity- 4
37 171651 Each Test
initial test

38 171652 Vertical load testing of piles - routine test Each Test 10

39 171681 Lateral load testing :- Vertical load capacity upto 50 MT Each Test 14

Chapter -18 DISMANTLING & DEMOLISHING


40 189081 Dismantling of old S.W. pipes :- 100mm diameter Metre 500
41 189082 Dismantling of old S.W. pipes:- 150mm diameter Metre 500
42 189084 Dismantling of old S.W. pipes :- 250mm diameter Metre 500

Dismantling of manhole complete :-Rectangular manhole 50


43 189091 Each
90x80cm (Inside dimensions) and 45cm deep.

Dismantling of manhole complete :-Rectangular manhole 50


44 189092 Each
120x90cm (Inside dimensions) and 90cm deep

Chapter -19 BRIDGE WORK SUB STRUCTURE


Conducting load testing of a single pile :-Routine Load 10
45 192107 Each
Test above 100 ton capacity Up to 250 ton capacity pile
Sr.No. Particulars Unit No. L. B. D. Qty.
Lateral load testing of single pile i:- Piles with lateral load 14
46 192113 Each
capacity of above 20 ton

47 195020 Providing and applying two coats of coal tar or bitumen Sqm 12000

Centring and shuttering including strutting, propping etc. 110 33.872 1.8 6706.66
48 195031 Sqm
and removal of form for :- RCC raft foundation & Pile cap

Total 6706.656
Centring and shuttering including strutting, propping etc.
49 195032 and removal of form for :- Abutment, pier, wing walls and Sqm 4804.81
return walls

Abutment cap, Pier Cap, Inspection Platform & Pedestal 10933


50 195033 Sqm
over Pier cap, Fender wall, Diaphragm wall, etc.
Total 10933
Approach slab at formation level, Dirt wall/ ballast wall at 500
51 195034 Sqm
formation level
In Bottom/top slab, side walls, toe wall and sumps 4500
52 195038 Sqm
haunch filling head walls or any other component

CHAPTER 20 BRIDGE WORK SUPER STRUCTURE RCC


Design, manufacturing, Supplying and fixing in position 5817500
53 201040 cucm
elastomeric bearing pads
Providing, fabricating & fixing in position to exact design 0
54 201070 MT
profiles, prestressing H.T.S. cables.

Chapter -21 BRIDGE WORK SUPER STRUCTURE STEEL (ONLY


ITEM NO. 211010/211011)
Supplying of all types of structural steel conforming to Fe 2700
55 211011 MT
410 B

CHAPTER -21 BRIDGE WORK SUPER STRUCTURE STEEL (EXCEPT


ITEM NO. 211010/211011)
Providing and fixing 65/50 mm nominal dia B class G.I. 35000
56 211060 Kg
pipe railing a complete job

Chapter -22 BRIDGE WORK MISCELLANEOUS


57 222180 Providing and laying of filter media cum 500
Sr.No. Particulars Unit No. L. B. D. Qty.
Providing Boulder backing behind wing wall, return wall, 5000
58 222290 cum
retaining wall with hand packed boulders
Sr.No. Particulars Unit No. L. B. D. Qty.
Chapter -23 ALL ITEMS OF CHAPTER 23 ROAD & PLATFORM
WORKS
Providing and laying water bound macadam Base
59 231042 course with 63mm to 45mm size including stone cum 900
screening 13.2mm size
Providing and laying water bound macadam Base
60 231043 course with 53mm to 22.4mm size including stone cum 900
screening 11.2mm size
Supplying and laying precast Kerb Stone of concrete 1392
61 237050 Metre
M25 Grade .
Providing and laying bitumen mastic wearing course 25 5220
62 238031 Sqm
mm thick

Chapter -25 ALL ITEMS OF CHAPTER 25 SUPPLY OF MATERIALS


63 252390 Stone Boulder Weighing minimum 35 Kg Each cum 5000

Schedule B-NON SCHEDULE ITEMS


1 NS-1 Supplying and filling blanketing material cum 5000
Dismantling of Brick/stone masonry/boulder pitching i n
2 NS-2 lime/cement ,etc. cum 1500

Supplying, providing, tightening of all types of High


3 NS-3 Strength frictional grip (HSFG) bolts, nuts & washers/DTI Kg 70000
washers
Providing, boring and casting Bored cast in situ 1200mm
4 NS-4 dia Reinforced Cement Concrete piles Metre 1100 25 28700

5 NS-5 Providing and laying RCC (M-35) Pile Caps cum 110 83 1.8 16434
6 NS-6 Providing and laying RCC (M-35) RCC box cum 1500
7 NS-7 Providing and laying RCC (M-35) Piers, Abutments cum 2259.934
Providing and laying RCC (M-35) abutments & pier cap,
8 NS-8 pedestal, fins etc. cum 110 12.4 2.085 1.4 3981.52
220 12.4 1.6 0.25 1091.20
5072.72
Providing and laying RCC (M-35) Retaining with/without
counterfort, curtain/drop walls etc. in foundation 4801.22
9 NS-9 cum
Extra 1200.00
6001.22
Sr.No. Particulars Unit No. L. B. D. Qty.
Providing and laying RCC (M-35) Retaining with/without
10 NS-10 counterfort, curtain/drop walls etc. above foundation cum 3833.88

Providing and laying RCC (M-25) for drain


11 NS-11 covers/manhole covers & flue tops etc. cum 40

Metalizing girder /girder components such as cross


12 NS-12 girders ,stiffeners, bracing etc. of new steel girder Sqm 38000

13 NS-13 Providing and laying 150mm dia drainage spout Each 700
Providing and fixing in position of standard preformed
14 NS-14 sealed and slab type or strip seal elastomeric type Metre 650
expansion joints for Railway bridge.
Earthwork in excavation in all type of soil (excluding
15 NS-15 rocks) for foundation & floors of Bridges, retaining wall cum 110 83 1.9 37518.5
etc. including garbage/ debris/malba etc
Providing and laying in position reinforced cement
16 NS-16 concrete of M40 grade In Deck slab, retainers, inspection cum 110 3069
platforms etc.
Providing and laying CC of specified grade in
17 NS-17 pavements/ roads/ wearing coat etc. cum 1,400.000

Supplying, providing, welding of Stud shear connecter.


18 NS-18 Kg 118,000.000

Providing and fixing 150mm dia (B) class GI rain water


19 NS-19 pipe as a complete job. Metre 2,000.000

Providing temporary steel barricading 2.0mtr. High and


20 NS-20 making arrangement for traffic diversion. Metre 6,000.000

Providing and laying in position reinforced cement


21 NS-21 concrete of M-40/M45 grade in precast PSC girder/T- cum -
girder/Slab of any span.
Lifting, handling and transporting PSC precast girders/
22 NS-22 slabs from the casting yard to the place of cum -
launching/erection
Chainage L B H Concrete Qty. Raft Shuttering Qty. Avg. H Thickness of Concrete Qty. Shuttering Qty. Spacing No. of Depth of Qty of
S.No. Description/Chainage Side of Piles Piles Pile (Mtr) Pile
(Mtr) (Mtr) (Mtr) (Cum) Raft (Sqm) (Mtr) wall (Mtr) Wall (Cum) Wall (Sqm)
From To (Mtr) (Rmt)
GOHANA END
1 Upto 1.5 Height on Open Foundation 5250 5140 2 110 3.000 0.300 198.000 132.000 1.900 0.350 146.300 1034.000 0 0 0 0

2 Above 1.5m & upto 2.5 m on Pile 5140 4900 2 240 2.250 0.675 729.000 648.000 2.300 0.400 441.600 2640.000 2.1 457 8 3656
Founadation (Straight Portion)

3 Above 2.5m & upto 3.5 m on Pile 4900 4702 2 198 2.250 0.675 601.425 534.600 3.300 0.400 522.720 2970.000 1.8 440 10 4400
Founadation (Straight Portion)

4 Above 3.5m & upto 4.2 m on Pile 4702 4607.5 2 94.5 2.250 0.675 287.044 255.150 4.150 0.425 333.349 1738.800 1.35 280 10 2800
Founadation (Straight Portion)
ROHTAK END
5 Upto 1.5 Height on Open Foundation 1500 1910 2 410 3.000 0.300 738.000 492.000 1.900 0.350 545.300 3854.000 0 0 0 0

6 Above 1.5m & upto 2.5 m on Pile 1910 2240 2 330 2.250 0.675 1002.375 891.000 2.300 0.400 607.200 3630.000 1.5 880 8 7040
Founadation

7 Above 2.5m & upto 3.5 m on Pile 2240 2490 2 250 2.500 0.675 843.750 675.000 3.300 0.400 660.000 3750.000 1.65 606 11 6666
Founadation (Curved Portion)

8 Above 3.5m & upto 4 m on Pile 2490 2609 2 119 2.500 0.675 401.625 321.300 4.150 0.425 419.773 2189.600 1.35 353 12.5 4412.5
Founadation (Straight Portion)
9 Hounch 300X300 3503 0.3 0.3 157.635
Total 3503 4801.219 4949.050 3833.876 21806.400 28975

Chainage L B H PCC Qty. Raft


S.No. Description/Chainage Side
(Mtr) (Mtr) (Mtr) (Cum)
From To
GOHANA END
1 Upto 1.5 Height on Open Foundation 5250 5140 2 110 3.150 0.075 51.975

2 Above 1.5m & upto 2.5 m on Pile 5140 4900 2 240 2.400 0.075 86.400
Founadation (Straight Portion)

3 Above 2.5m & upto 3.5 m on Pile 4900 4702 2 198 2.400 0.075 71.280
Founadation (Straight Portion)

4 Above 3.5m & upto 4.2 m on Pile 4702 4607.5 2 94.5 2.400 0.075 34.020
Founadation (Straight Portion)
ROHTAK END
5 Upto 1.5 Height on Open Foundation 1500 1910 2 410 3.150 0.075 193.725

6 Above 1.5m & upto 2.5 m on Pile 1910 2240 2 330 2.400 0.075 118.800
Founadation

7 Above 2.5m & upto 3.5 m on Pile 2240 2490 2 250 2.400 0.075 90.000
Founadation (Curved Portion)

8 Above 3.5m & upto 4 m on Pile 2490 2609 2 119 2.400 0.075 42.840
Founadation (Straight Portion)
Total 3503 689.040

Chainage L B H Excavation Qty.


S.No. Description/Chainage Side
(Mtr) (Mtr) (Mtr) Raft (Cum)
From To
GOHANA END
1 Upto 1.5 Height on Open Foundation 5250 5140 2 110 3.150 1.525 1056.825

2 Above 1.5m & upto 2.5 m on Pile 5140 4900 2 240 2.400 1.050 1209.600
Founadation (Straight Portion)

3 Above 2.5m & upto 3.5 m on Pile 4900 4702 2 198 2.400 1.050 997.920
Founadation (Straight Portion)

4 Above 3.5m & upto 4.2 m on Pile 4702 4607.5 2 94.5 2.400 1.050 476.280
Founadation (Straight Portion)
ROHTAK END
5 Upto 1.5 Height on Open Foundation 1500 1910 2 410 3.150 1.525 3939.075

6 Above 1.5m & upto 2.5 m on Pile 1910 2240 2 330 2.400 1.050 1663.200
Founadation

7 Above 2.5m & upto 3.5 m on Pile 2240 2490 2 250 2.400 1.050 1260.000
Founadation (Curved Portion)

8 Above 3.5m & upto 4 m on Pile 2490 2609 2 119 2.400 1.050 599.760
Founadation (Straight Portion)
Total 3503 11202.660
TOP OF PILE PIER CAP ABUTMENT CONCRETE
PIER NO. PIER HEIGHT
CAP BOTTOM HEIGHT OF PIER
A1 220.5 221.14 0.640 0.640 11.904
P1 220.499 221.222 0.723 2.552
P2 220.5 221.305 0.805 2.842
P3 220.5 221.388 0.888 3.135
P4 220.499 221.47 0.971 3.428
P5 220.5 221.553 1.053 3.717
P6 220.5 221.636 1.136 4.010
P7 220.500 221.718 1.218 4.300
P8 220.500 221.801 1.301 4.593
P9 220.500 221.899 1.399 4.938
P10 220.500 221.998 1.498 5.288
A2 220.5 222.097 1.597 1.597 29.704
A3 219.5 222.803 3.303 3.303 61.436
P11 220.638 222.235 1.597 5.637
P12 219.5 222.46 2.960 10.449
P13 219.896 222.372 2.476 8.740
A4 219.5 223.077 3.577 3.577 66.532
A5 220.5 222.94 2.440 2.44 45.384
P14 220.300 222.575 2.275 8.031
P15 220.300 222.674 2.374 8.380
P16 220.300 222.773 2.473 8.730
P17 220.300 222.872 2.572 9.079
P18 220.300 222.971 2.671 9.429
P19 220.000 223.07 3.070 10.837
P20 220.000 223.169 3.169 11.187
P21 220.000 223.268 3.268 11.536
P22 220.000 223.367 3.367 11.886
P23 220.000 223.466 3.466 12.235
P24 220.000 223.565 3.565 12.584
P25 220.000 223.664 3.664 12.934
P26 220.000 223.763 3.763 13.283
P27 220.000 223.862 3.862 13.633
P28 220.000 223.961 3.961 13.982
P29 220.000 224.06 4.060 14.332
P30 220.000 224.159 4.159 14.681
P31 220.000 224.258 4.258 15.031
P32 220.000 224.357 4.357 15.380
P33 220.000 224.456 4.456 15.730
P34 220.000 224.555 4.555 16.079
A6 220.5 225.118 4.618 4.618 85.895
A7 220.5 225.29 4.790 4.79 89.094
P35 220 224.654 4.654 16.429
P36 220.5 224.826 4.326 15.271
P37 220.5 224.654 4.154 14.664
A8 220.5 225.29 4.790 4.79 89.094
A9 220.5 225.118 4.618 4.618 85.895
P38 220.000 224.654 4.654 16.429
P39 220.000 224.654 4.654 16.429
TOP OF PILE PIER CAP ABUTMENT CONCRETE
PIER NO. PIER HEIGHT
CAP BOTTOM HEIGHT OF PIER
P40 220.000 224.654 4.654 16.429
P41 220.000 224.654 4.654 16.429
P42 220.000 224.654 4.654 16.429
P43 220.000 224.654 4.654 16.429
P44 220.000 224.654 4.654 16.429
P45 220.000 224.654 4.654 16.429
P46 220.000 224.654 4.654 16.429
P47 220.000 224.654 4.654 16.429
P48 220.000 224.654 4.654 16.429
A10 219.5 225.118 5.618 5.618 104.495
A11 220.5 225.29 4.790 4.79 89.094
P49 219.5 224.654 5.154 18.194
P50 220.5 224.826 4.326 15.271
P51 220 224.654 4.654 16.429
A12 220.5 225.29 4.790 4.79 89.094
A13 220.5 225.118 4.618 4.618 85.895
P52 220.000 224.654 4.654 16.429
P53 220.000 224.654 4.654 16.429
P54 220.000 224.654 4.654 16.429
P55 220.000 224.654 4.654 16.429
P56 220.000 224.654 4.654 16.429
P57 220.000 224.654 4.654 16.429
P58 220.000 224.654 4.654 16.429
P59 220.000 224.654 4.654 16.429
P60 220.000 224.654 4.654 16.429
P61 220.000 224.654 4.654 16.429
P62 220.000 224.654 4.654 16.429
P63 220.000 224.654 4.654 16.429
P64 219.500 224.654 5.154 18.194
P65 219.500 224.624 5.124 18.088
P66 219.500 224.525 5.025 17.738
P67 219.500 224.426 4.926 17.389
P68 219.500 224.327 4.827 17.039
P69 219.500 224.228 4.728 16.690
P70 219.500 224.129 4.629 16.340
P71 219.500 224.03 4.530 15.991
P72 219.500 223.931 4.431 15.641
P73 219.500 223.832 4.332 15.292
P74 219.500 223.733 4.233 14.942
P75 219.500 223.634 4.134 14.593
P76 219.000 223.535 4.535 16.009
P77 219.000 223.436 4.436 15.659
P78 219.000 223.337 4.337 15.310
P79 219.000 223.238 4.238 14.960
P80 219.000 223.139 4.139 14.611
P81 219.500 223.04 3.540 12.496
P82 219.500 222.941 3.441 12.147
P83 219.500 222.842 3.342 11.797
TOP OF PILE PIER CAP ABUTMENT CONCRETE
PIER NO. PIER HEIGHT
CAP BOTTOM HEIGHT OF PIER
P84 219.500 222.743 3.243 11.448
P85 219.500 222.644 3.144 11.098
P86 219.500 222.545 3.045 10.749
P87 219.500 222.446 2.946 10.399
P88 219.500 222.347 2.847 10.050
P89 219.500 222.248 2.748 9.700
P90 219.500 222.149 2.649 9.351
P91 220.000 222.05 2.050 7.237
P92 220.000 221.951 1.951 6.887
P93 220.000 221.852 1.852 6.538
P94 220.000 221.753 1.753 6.188
P95 220.000 221.654 1.654 5.839
P96 220.000 221.555 1.555 5.489
P97 220.000 221.456 1.456 5.140
P98 220.000 221.357 1.357 4.790
A14 220.000 221.258 1.258 1.258 23.399
A15 1.709 1.709 31.787
P99 219.001 221.16 2.159 7.621
P100 219.000 221.092 2.092 7.385
A16 220.000 221.488 1.488 1.488 27.677
Total Height 406.926 54.644 2259.934
Abutment Height -54.644
Pier Height 352.282
Circumference of pier 4.71
3318.496
Abutment per Rmt 1486.317
Total Qty 4804.81 Sqm

Das könnte Ihnen auch gefallen