Beruflich Dokumente
Kultur Dokumente
1.1 This procedure refers to maintain load test using hydraulic jack-in machine only.
2. EQUIPEMENT
3. M E T H O D O LO G Y
3.1.1 The test load may be applied by means of a jack which obtains its reaction from
total weight of jack-in machine body that heavier than the required test loads.
3.1.2 The jack-in machine pile damper is statically locked with a steel dolly. The machine
short sleepers will be lifted and the ground contacted long sleepers will act as
supporting base ( as shown in figure 1)
3.1.3 The hydraulic jack (as shown in figure 2) will be push upward to obtain reaction or
required loading.
3.1.4 The load will be measured by a calibrated load gauge and also by a calibrated
pressure gauge in the hydraulic system. The load cell may be attached to the
hydraulic system in order to obtain digital result of the pressure.
3.1.5 The jack and load gauge will be carefully aligned so that the load applied is co-axial
with the pile
3.1.6 The arrangement of the apparatus above the test pile is shown as figure 2.
3.1.7 The jack-in machine will be properly leveled to ensure that the centre of gravity of
the kentledge is on the axis of the pile. The nearest edge of the crib supporting the
Kentledge stack will not closer than 1.3m to the surface of the test pile
CITY PILING SDN BHD (671791-H)
3.1.8 When reference frame, all anchor piles will be at a distance of at least three (3) test
pile shaft diameter from the test pile, centre to centre, and in no case less than 2m.
3.1.9 This spacing may need increasing in certain situations where knowledge of the
absolute value of settlement of an individual pile is essential to design.
3.1.10 Where a pile to be tested has an enlarged base the same criteria will apply with
regard to the shaft and, in addition, the surfaces of anchor pile shaft will not be
closer than one-half (V2)of the diameter of the enlarged pile base to test pile base.
3.1.11 If the anchor piles are to be permanent working piles, their level will be observed
during application of the test load to ensure there is no residual uplift.
CITY PILING SDN BHD (671791-H)
3.1.13 Where the pile to be tested has an enlarged base, the criterion will apply with
regard to the pile shaft and, in addition, no section of the anchor transferring load
to the ground will be closer to the pile base diameter.
Loading bearing
Hydraulic Jack
Pressure Gauge
Steel Plate
Test Pile
3.4.1 Site specific safety requirements, as set out in the contract; and the main
contractor’s Environment, Safety, Health and Security Plan.
HSE Officer
3.4.2 HSE Officer will coordinate all safety-related activities at the work site, and ensuring
that all safety requirements are complied.
Pile Cutting
3.4.3 Cutting of piles will be executed by using hammer and hand breaker. The process
involves hoisting of surplus pile. The potential hazards and the respective
precautions are as below:
CITY PILING SDN BHD (671791-H)
Method Statement for Maintain Load Test (Jack-In-Machine)
Hazard Precautions
Flip by flying material 1. Equipped with goggle
Failing of piles 1. If piles above cut of level are more than 4 m high,
it be supported by crane or clamped by the
equipment.
CITY PILING SDN BHD (671791-H)
Method Statement for Maintain Load Test (Jack-In-Machine)
Short Sleeper
Long Sleeper
CITY PILING SDN BHD (671791-H)
Method Statement for Maintain Load Test (Jack-In-Machine)
1.1 The Kent ledge system consists of a main girdle simply supported at both ends. A system of cross beam is
place on top of the main girdle and orthogonal to it. The cross beam is also simply supported at this ends.
Concrete blocks of weight two tons each are stack on top of these cross beams to provide the necessary
reactive load. The loading is applied by jacking the pile with hydraulic jack against the Kent ledge system.
2.1 The pile top settlement is measure by means of calibrated dial gauges within accuracy of 0.01mm. a
mechanical hydraulic pump is use to jack-up the reactive load. The load applied is measure by a calibrated
pressure gauge.
2.2 Two scales are attached to the reference frame and pile to measure any movement of the reference frame
with reference to the datum markers establish outside-the test area.
3.1 Maintained load test method is used for testing the piles up to a maximum load of two times the pile
working. The loading sequence is shown in table below.