Environmental Impact Assessment Study Project

BKM & BTI & PKG in Block L53/43&L54/43, Suphanburi

SSHE

PTTEP INTERNATIONAL LIMITED

1
Introduction
• PTTEP International Company Limited (PTTEPI), a concessionaire in Block
L53/43&L54/43 has an obligation to develop Thailand’s energy resources to
support the increasing of energy consumption.

• PTTEPI is a concessionaire in the central of Thailand. PTTEPI plan to develop ten


(10) petroleum production well sites in Block L53/43 and L54/43 Concession area
in Suphanburi Province.

2
รายละเอียดโครงการ
L53/43 and L54/43 Concession Location
L53/43 L54/43

L53/43&L54/43
Project Location,
Suphanburi Province

Onshore Petroleum Concession, Thailand (July 2013)


Project Description
• Main Activities:
Construction, Drilling, Well Testing, Production and Plug & Abandon

• Wellsite location as table below:


WellSite Village Sub-district District Province
1. BKM-C moo. 10 Ban Non Don Ka Mueang Suphanburi
2. PKG-E moo. 1 Ban Samthon Taling Chan Suphan
3. BTI-E moo. 4 Ban Sumnuttaka Sanam Kee
4. PKG-B moo. 9 Ban Srisakate Ban Pho
5. PKG-F moo. 1 Ban Thakhum Sanam Kee
6. BTI-F moo. 3 Ban Nongkhum
7. BTI-A moo. 7 Ban Nongkutit Panpra Chai UThong
8. BTI-C moo. 6 Ban Thasadet Srakaew
9. PKG-C moo. 3 Ban Thasadet
10. PKG-D moo. 5 Ban Thawa

4
L53/43 L54/43

Well site Locations


L53/43&L54/43,
Suphanburi
Legend :
Well Site

L53/43 Concession
L54/43 Concession
5 km. radius from well site ต.พลับพลาชัย

District Boundary

Sub-district Boundary
Bung Kra Tiem Production area

ต.ดอนคา
5
Petroleum Activities
1. Construction Phase 6 months/ well site

2. Drilling Phase 15 days/ well

3. Well Testing Phase 15-30 days

dry well Hydrocarbon

4. Plug / Abandon 4. Production Phase

6
Construction Phase
Component Detail
Well site Wellsite dimension is approximately 131m width and 341m
length
Wellsite is compacted with soil and laterite 0.5m height over
the highest flooding level
Access road Road access designed about 7-10 m. of width

Box convert
Concrete Pit Surrounding area
7
Drilling Phase
Rig
Concrete pit

Top Hole Cutting Pond


Concrete Pad
Shale Shaker

Mud Pump (reused)


Generator
Temporary Office
Drilling Phase (cont.)

9
Well Structure
BOP (Blowout Prevention)

1. Drilling Plan

2. Installed conductor pipe


3. Drill: Top hole
4. Install conductor pipe and cementation
2.5 – 3.0 km. Cement
5. Drill: Bottom session
Packer
Packer 6. Install conductor pipe and cementing

7. Install casing and packer


Conductor pipe
Casing 8. Install Christmas Tree (Christmas Tree)

9. Pipe Perforation and Cementing

10. Petroleum lift to the surface

10
Well Testing Phase

Storage Tank
Liquid
Gas
Loading Area
Flare Well Petroleum Separator

11
Production Phase
Gas

Separate Flare gas system


Separator (Crude VS Produced water)
(Gas VS Liquid)

Crude Tank Crude Truck

Produced water Tank

Injection Well
Petroleum Well
Bangjak Oil Refinery

12
Plug / Abandon Phase

13
PTTEP CSR Projects

14
EIA Study Process

15
Study Area
 5 km. radius from well site

Legend

Well Site

L53/43 Concession

L54/43 Concession

Study area

District Boundary

Sub-district Boundary

Bung Kra Tiem Production area


EIA Criteria of Environmental, Social and Health Study

Physical Biotic Human use Quality of


resources resource value life value
Agricultural
Land use Land use Economic and
ecology
society

Geological and Aquatic ecology


earthquake Public utilities Occupational

Meteorological and air quality Aesthetics


Transportation

Hydrology and water


quality Archaeology and
Agriculture history

Noise Waste
management

Soil Water drainage


Public Participation Meeting

 To introduce the project to relevant stakeholders and also to


inform the Terms of Reference (TOR).

 To present the signification of impact assessment study and


draft mitigation measures and monitoring program to relevant
stakeholders.

18
Stakeholders
Community

Company
Media and
consultant

Stakeholder
ONEP/
Public Permitting
agency

Education
center/NGO Government

19
Public Participate Meeting Process
Stakeholder Identification
Objective
- Comment/suggestion
Terms of Reference
PP meeting#1 - Concerns
(TOR).

Result of impact Mitigation & Monitoring


assessment study and program preparation
PP meeting#2
draft mitigation
measures and
monitoring program
EIA Study Report

20
Impacts of land use and Mitigation measure

Impact assessment Mitigation measure


Land use will be changed from 1. Survey land ownership for land negotiations to
agricultural to petroleum production buy or rent.
activity. 2. Land acquisition and compensation for
agricultural crops damage, compensation must
be fair and reasonable to both parties.
Impacts of air quality and mitigation measure
Impact assessment Mitigation measure
1. Spray water on the non-asphalt road
• Spreaded dust from wellsite
2. Speed limit to transport up to 30 km / h. (non-asphalt road)
construction and transportation cause
for well site road entrance
impact to community near by well site
3. Inspection and maintenance Vehicle and uniform
construction.
4. Installation landscape flare.
• Pollutant from combustion gases
Generator machines may cause air Monitoring
pollution.
Air monitoring in sensitive receptor for 3 days (Continuous)
Impacts of noise quality and mitigation measure
Mitigation measure
Impact assessment Preventive and corrective action the construction and drilling
Noise from the operating machine equipment to prevent the noisy from

which used for construction and
drilling phase may cause Monitoring
community near by wellsite Noise monitoring in sensitive receptor for 3 days (Continuous)
construction.
Impacts of soil quality and mitigation measure
Impact assessment Mitigation
1. Compacted soil in well site entrance road and well site
• Site clearing for well site construction
location area.
and road construction along flow line
2. Provide ground cover edges of well site.
may cause erosion of soil.
3. Drilling cutting from top hole section will be storage in
• Drilling cutting may cause soil quality.
concreate pit afterward it’s transfer to land deposit after
• Wellsite construction may contaminated
soil checked
with oil and chemical on well site
4. Drilling cutting from bottom hole will be transfer to cement
abandon phase.
plant for used as renewable

Monitoring
Soil monitoring in well site location (Abandon phase) 1 time
after site clearing.
Impacts of surface water quality and mitigation measure

Mitigation measure
Impact assessment 1. Concrete pit which collect rainwater have to remove to
• Contaminated surface water from Oil or wastewater treatment system without drainage to
chemical spill environmental.
• Waste management is inappropriate
may affect surface water nearby.
Monitoring
Surface water monitoring from surface water pond nearby well
site location.
Impacts of ground water quality and mitigation measure
Mitigation measure
Impact assessment 1. Water supply will be use as drilling fluid for top hole section (<1200
• Drilling activity may cause groundwater m.)
quality. 2. Install conductor pipe and cementing
• Produced water management is 3. Produced water will re-injection to ground water.
inappropriate may affect ground water
nearby. Monitoring
Ground water monitoring from observation well in well site location and
community ground water well
Impacts of transportation and Mitigation measure
Impact Mitigation measure
• Road traffic, Accident from transportation, 1. Avoid rush hour within community area
Damage to road 2. Control speed limit to be not over 80 km./hr. on
main road and to be not over 30 km./hr. on
local road
3. Control loading’s weight of contractor’s truck to
be not over regulation to prevent road damage.
Impact of water run-off/ flooding and Mitigation measure
Impact assessment Mitigation measure
• Obstruct waterway from well site and access 1. Well site and access road shall be higher than
road highest flooding level
2. Avoid the construction where blocking the
natural flow
3. Install culvert with the diameter of 1.2m under
access road
Impacts of Economic and society and mitigation measure

Impact assessment Mitigation Measure


Help increase employment and income 1. Select Suphanburi employee to be first priority
around wellsite location area which should be match with position requirement
2. Select Suphanburi contractor/material or
production/goods which produced by local
3. Encourage social activities/project in Suphanburi
e.g. Suphanburi sport and education
Complaint Process
Communication channel

PTTEP International Limited


PTTEP International Limited
External Relationship
Energy Complex Building, 23rd Floor
555/1 Vibhavadi Rangsit Rd., Chatuchak, Bangkok 10900
Telephone: 02-537-6539 Fax: 02-537-4444