For
Nestle Pakistan Ltd. Kabirwala
May 2017
Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Attn:
Nestle Pakistan Ltd. Kabirwala

Subject: Vibration Analysis Report for May 2017.

Dear Sir,

We are pleased to submit you Vibration Analysis Report for the month of May 2017.

We hope you will find this report complete in all respects.

However, if you feel any discrepancy please feel free to contact us.

Thanks and best regards,

Yours truly,

For SUMICO Technologies Pvt. Ltd.

Dr. Anees Ur Rehman,


B.Sc, M.Sc, PhD (Condition Monitoring), CEng, MIMecE
General Manager (Operations)
Sumico Technologies (Pvt) Limited.
C: +92-321-4974215
E: anees.rehman@sumico.com.pk

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 2 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Table of contents
Executive Summary.........................................................................................................................4
1. Inspection Area - UTILITIES..................................................................................................5
1.1. Overview............................................................................................................................5
1.2. Critical Maintenance Review.............................................................................................9
1.3. Abbreviated Measurement Summary..............................................................................11
1.4. Detailed Spectra (UTILITIES area)..................................................................................12
2. Inspection Area - EGRON-1.................................................................................................13
2.1. Overview..........................................................................................................................13
2.2. Critical Maintenance Review...........................................................................................14
2.3. Abbreviated Measurement Summary..............................................................................15
2.4. Detailed Spectra (EGRON-1 area)..................................................................................16
3. Inspection Area - EGRON-2.................................................................................................17
3.1. Overview..........................................................................................................................17
3.2. Critical Maintenance Review...........................................................................................18
3.3. Abbreviated Measurement Summary..............................................................................19
3.4. Detailed Spectra (EGRON-2 area)..................................................................................20
4. Inspection Area - STD PLANT.............................................................................................21
4.1. Overview..........................................................................................................................21
4.2. Critical Maintenance Review...........................................................................................23
4.3. Abbreviated Measurement Summary..............................................................................24
4.4. Detailed Spectra (STD PLANT area)...............................................................................25
5. Inspection Area - UHT PLANT.............................................................................................26
5.1. Overview..........................................................................................................................26
5.2. Critical Maintenance Review...........................................................................................27
5.3. Abbreviated Measurement Summary..............................................................................28
5.4. Detailed Spectra (UHT PLANT area)..............................................................................29
6. Inspection Area - NOODLE PLANT.....................................................................................30
6.1. Overview..........................................................................................................................30
6.2. Critical Maintenance Review...........................................................................................31
6.3. Abbreviated Measurement Summary..............................................................................32
6.4. Detailed Spectra (NOODLE PLANT area).......................................................................33

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 3 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Executive Summary
This report consists of the vibration analysis of your machine. The survey and data collection of
your equipment was carried out in May 2017. So we are in position to determine mechanical
condition of machines.

This inspection report includes an explanation of all measurement and review conducted. The
mechanical and dynamic behavior of each machine and its components are analyzed and
recommended actions are also detailed for each component of machine.

This report consists of some spectra and waveforms of machine vibration.


In the report points are mentioned as

M1H =Motor Outboard Horizontal


M2A = Motor Inboard Axial
P2V =Pump Outboard Vertical
G1H = Gearbox Inboard horizontal
F2H = Fan Outboard horizontal

Where
Outboard = Non driving end
Inboard = Driving End (Coupling Side)

These abbreviations are used by the software and will be shown as such in the reports. Overall
values of all the points for all machines have been attached with the report. The soft copy of the
report is attached with this for your convenience.

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 4 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

1. Inspection Area - UTILITIES


1.1. Overview
Sr. Equip. Equipment
Status Remarks
# ID Description
1 1015. PA FAN-1 1015 Normal  
Lubricate fan both bearings properly, Keep
2 1025 PA FAN-2 1025 Moderate monitoring temperature. Retake fan data after
lubrication.
3 1035 PA FAN 3 1035 Minor Lubricate motor and fan bearings.
FORCED FAN MOTOR
4 1.1 Normal  
1.1 (A.H-1)
FORCED FAN MOTOR Monitor bearing tempetraure. Retake data in case of
5 2.1 Moderate
2.1 (A.H-2) temperature rise/ abnormal sound.
FORCED FAN MOTOR
6 3.1 Normal  
3.1 (A.H-3)
Lubricate motor both bearings, keep under
7 0612 PA FAN-4 0612 Minor
observation.
0612- PA FAN-4 0612(OLD
8 N/A  
OLD MOTOR)
FORCED FAN MOTOR 4
9 FFM-4 Normal  
(A.H-4)
FORCE FAN MOTOR Monitor motor temperature. Increase monitoring
10 FFM-1 Moderate
1(BOL-1) frequency.
OIL BURNER MOTOR Tighten motor mounting bolts and retake data after
11 OBM-1 Moderate
1(BOL-1) bolt tightening.
Lubricate motor bearing if applicable. Monitor motor
FORCE FAN MOTOR
12 FFM-2 Moderate bearing temperature. Also increase monitoring
2(BOL-2)
frequency.
OIL BURNER MOTOR
13 OBM-2    
2(BOL-2)
FORCE FAN MOTOR
14 FFM-3 Normal  
3(BOL-3)
OIL BURNER MOTOR Nonsyncronous vibration found in motor DE, Monitor
15 OBM-3 Minor
3(BOL-3) temperature, under observation.
FEED WATER PMP 1
16 3781 Normal  
3781(BOL-1)
FEED WATER PMP 2
17 3782 Normal  
3782(BOL-1)
FEED WATER PMP 3
18 3783 Normal  
3783(BOL-2)
FEED WATER PMP 4
19 3784 Normal  
3784(BOL-2)
FEED WATER PMP 5
20 FWP-5 N/A  
(BOL-3)
FEED WATER PMP 6
21 FWP-6 N/A  
(BOL-3)
FEED WATER PMP 1
22 D001 Normal  
D001(W.H.B)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 5 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Sr. Equip. Equipment


Status Remarks
# ID Description
FEED WATER PMP 1
23 D002 Normal  
D002(W.H.B)
FEED WATER PMP
24 FWP-7    
7(BOL-3 S.BY)
WCP- WATER CIRCULATION
25    
WHB PMP(W.H.B)
CH.W COOLING CIRCL
26 1120 Minor Check oil level in pump, Monitor temperature.
PMP 1120
CH.W COOLING CIRCL
27 1140 Minor Lubricate motor both bearings.
PMP 1140
CH.W COOLING CIRCL
28 1160 Normal  
PMP 1160
CH.W COOLING CIRCL
29 1190 Minor Lubricate motor DE bearing.
PMP 1190
CH.W COOLING CIRCL
30 1100 Minor Check oil level in pump.
PMP 1100
CH.W COOLING CIRCL Inspect motor DE bearing for any looseness.
31 1180 Moderate
PMP 1180 Replace if needed.
COOLING W.FEED PMP-
32 6021 N/A  
01 6021
COOLING W.FEED PMP-
33 C W P-02 N/A  
02
HFO B.P HFO BOOSTER PUMP
34    
1 1(6.7MW)
HFO B.P HFO BOOSTER PUMP
35    
2 2(6.7MW)
LUBE OIL SEP
36 1E1 Normal  
1E1(6.7MW)
START AIR COMP 1
37 B003 Normal  
B003(6.7MW)
START AIR COMP 2
38 B004 Normal  
B004(6.7MW)
39 H.W.C.P H.W.C PMP 6.7 MW Normal  
PBB HFO CENTRIFUG SEP 1
40 Normal  
901/1 PBB901/1
PBB HFO CENTRIFUG SEP 2
41 Minor Lubricate motor DE bearing.
901/2 PBB901/2
HFO FP- HFO FEEDER UNIT
42 Normal  
2 PMP-2
I-A INSTRUMENT AIR
43 N/A  
COMP COMP 6.7 MW
HFO FP- HFO FEEDER UNIT
44 Normal  
1 PMP-1
HFO T.P- HFO TRANSFER PMP
45 N/A  
1 1(6.7MW)
HFO T.P- HFO TRANSFER PMP
46 N/A  
2 2(6.7 MW)
DRINKING WTER TRB-1
47 2201 Normal  
2201

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 6 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Sr. Equip. Equipment


Status Remarks
# ID Description
DRINKING WTER TRB-2
48 2205 Normal  
2205
49 2239 DRINKING W.PMP 2239 Minor Monitor pump bearing temperature.
Lubricate motor DE bearing properly, Monitor
50 2250 DRINKING W.PMP 2250 Moderate
temperature and vibration frequently.
51 1214 COOLING T.D PMP 1214 Moderate Lubricate motor both bearings, Monitor temperature..

52 1224 COOLING T.D PMP 1224 Normal  


Check oil level and oil condition, increase monitoring
53 1235 COOLING T.D PMP 1235 Moderate
frequency.
54 1245 COOLING T.D PMP 1245 Moderate Check oil level and increase monitoring frequency.
AIR COMPRESSOR GA-
55 GA-110    
110(N2)
Replace stage 1 male rotor NDE bearing in next
56 ZR 500 AIR COMPRESSOR 500 Moderate
stoppage. Monitor motor bearing temperature..
57 ZR 450 AIR COMPRESSOR 450 N/A  
CH.W CIRCULTION PMP
58 0907    
0907
CH.W CIRCULATION
59 0986 Minor Lubricate motor bearings.
PMP 0986
CH.W CIRCULATION
60 0918 Minor Lubricate motor bearings, under observation.
PMP 0918
HOT.W CIRCULATION
61 9339 Minor Monitor Pump temperature frequently.
PMP 9339
HOT.W CIRCULATION
62 9340 Minor  
PMP 9340
HOT.W CIRCULATION
63 9341    
PMP 9341
Lubricate motor bearings properly ,aslo inspect
CH.W DISTRIBUTION
64 9335 Moderate coupling elemtent and realigh equipment. Keep
PMP 9335
monitoring motor bearing temperature.
CH.W DISTRIBUTION
65 1029 N/A  
PMP 1029
CH.W DISTRIBUTION
66 1007 Normal  
PMP 1007
CH.W DISTRIBUTION
67 1018 Minor Monitor motor bearing temperature.
PMP 1018
AMMONIA
68 AM.C-1 Normal  
COMPRESSOR-1
AMMONIA
69 AM.C-2 Minor Lubricate motor bearings, under observation.
COMPRESSOR-2
GEA AMMONIA
70 GAC Minor Lubruicate motor bearings, Monitor temperature.
COMPRESSOR
ICE.W DISTRIBUTION
71 1515 Normal  
PMP 1515
ICE.W DISTRIBUTION
72 1520 Normal  
PMP 1520

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 7 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Sr. Equip. Equipment


Status Remarks
# ID Description
ICE.W CIRCULATION Lubricate motor NDE bearing. Monitor motor
73 1516 Moderate
PMP 1516 temperature frently.
ICE.W CIRCULATION
74 1519 Normal  
PMP 1519

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 8 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

1.2. Critical Maintenance Review


Area UTILITIES (Page 1 of 2)
Observations & Analysis
 1025 - PA FAN-2 1025
BPFO fault frequencies found in fan DE and NDE bearings. High g's value also found in peakvue spectra.
2.1 - FORCED FAN MOTOR 2.1 (A.H-2)
Bearing fault frequencies found in motor DE bearing.
FFM-1 - FORCE FAN MOTOR 1(BOL-1)
Non syncrounous vibration found in spectra indicating motor bearing initial wear also rotor bar faul
frequencies found in spectra indicating rotor bar initail wear.
OBM-1 - OIL BURNER MOTOR 1(BOL-1)
High 1xT vibration found in vertical direction indicating structural loosenss.
FFM-2 - FORCE FAN MOTOR 2(BOL-2)
Bearing fault frequencies found in motor NDE bearing.
1120 - CH.W COOLING CIRCL PMP 1120
BPFI fault frequencies found in pump DE bearing.
1180 - CH.W COOLING CIRCL PMP 1180
2xLF found indicating rotor/stator air gap problem. Also loosness symptoms found in motor DE bearing.
2239 - DRINKING W.PMP 2239

Recommendations
 1025 - PA FAN-2 1025
Lubricate fan both bearings properly, Keep monitoring temperature. Retake fan data after lubrication.
2.1 - FORCED FAN MOTOR 2.1 (A.H-2)
Monitor bearing tempetraure. Retake data in case of temperature rise/ abnormal sound.
FFM-1 - FORCE FAN MOTOR 1(BOL-1)
Monitor motor temperature. Increase monitoring frequency.
OBM-1 - OIL BURNER MOTOR 1(BOL-1)
Tighten motor mounting bolts and retake data after bolt tightening.
FFM-2 - FORCE FAN MOTOR 2(BOL-2)
Lubricate motor bearing if applicable. Monitor motor bearing temperature. Also increase monitoring frequency.
1120 - CH.W COOLING CIRCL PMP 1120
Check oil level in pump, Monitor temperature.
1180 - CH.W COOLING CIRCL PMP 1180
Inspect motor DE bearing for any looseness. Replace if needed.
2239 - DRINKING W.PMP 2239

Prepared By Review by Approved By


Technical Service Engineer Sr. Technical Service Engineer G.M (Operations)

     

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 9 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Area UTILITIES (Page 2 of 2)


Observations & Analysis
 2250 - DRINKING W.PMP 2250
BPFO and BPFI fault frequencies found in motor DE bearing indicating stage 3 bearing fault.
1214 - COOLING T.D PMP 1214
Bearing fault frequencies found in motor both bearing.
1235 - COOLING T.D PMP 1235
Bearing fault frequencies found in pump both bearings.
1245 - COOLING T.D PMP 1245
Bearing fault frequencies found in pump both bearings.
ZR 500 - AIR COMPRESSOR 500
Bearing fault frequencies found with High g's value in stage 1 male rotor NDE bearing peakvue spectra
indicating male rotor NDE bearing fault.
9335 - CH.W DISTRIBUTION PMP 9335
Non syncronuous vibration found in motor bearings indicating initial bearing wear, Also high 1xT with
harmonics found in pump radial and axial direction indicating misalignment due to couplin elemnt wear.
GAC - GEA AMMONIA COMPRESSOR
Bearing fault frequencies found in spectra.
1516 - ICE.W CIRCULATION PMP 1516
Rotor bar fault frequencies found in spectra with 2xLF side bands indicating rotor bar wear/damage. Also g's
value trend increased in motor NDE bearing.

Recommendations
 2250 - DRINKING W.PMP 2250
Lubricate motor DE bearing properly, Monitor temperature and vibration frequently.
1214 - COOLING T.D PMP 1214
Lubricate motor both bearings, Monitor temperature..
1235 - COOLING T.D PMP 1235
Check oil level and oil condition, increase monitoring frequency.
1245 - COOLING T.D PMP 1245
Check oil level and increase monitoring frequency.
ZR 500 - AIR COMPRESSOR 500
Replace stage 1 male rotor NDE bearing in next stoppage. Monitor motor bearing temperature..
9335 - CH.W DISTRIBUTION PMP 9335
Lubricate motor bearings properly ,aslo inspect coupling elemtent and realigh equipment. Keep monitoring
motor bearing temperature.
GAC - GEA AMMONIA COMPRESSOR
Lubruicate motor bearings, Monitor temperature.
1516 - ICE.W CIRCULATION PMP 1516
Lubricate motor NDE bearing. Monitor motor temperature frently.

Prepared By Review by Approved By


Technical Service Engineer Sr. Technical Service Engineer G.M (Operations)

     

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 10 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

1.3. Abbreviated Measurement Summary

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 11 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

1.4. Detailed Spectra (UTILITIES area)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 12 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

2. Inspection Area - EGRON-1


2.1. Overview
Sr. Equip. Equipment
Status Remarks
# ID Description
FINE POW SEP EXHST
1 2919    
FAN 2919
2 2924 ADF FAN 2nd SEC 2924    
3 3106 ACF FAN 3106    
4 2630 BBS BLOW 2630    
5 2640 BBS BLOW 2640    
6 4420 FPS BLOW 4420    
7 3215 PP BLOW 3215    
SECONDARY AIR FAN-1
8 3301    
3301
TOWER EXT AIR FAN-1
9 2130    
2130
TOWER EXT AIR FAN-2
10 2131    
2131
SECONDARY AIR FAN-2
11 3320    
3320
NOZZLE COOLING FAN
12 1601    
1601
BP AIR BLOW 1051(EG-1
13 1051    
ROOF)
AIR BLOWER SUGER
14 1072    
1072(TIPP)
VITAMIN PREMIX AIR
15 1080    
BLOW 1080

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 13 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

2.2. Critical Maintenance Review


Area EGRON-1
Observations & Analysis
 
Recommendations
 
Prepared By Review by Approved By
Technical Service Engineer Sr. Technical Service Engineer G.M (Operations)

     

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 14 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

2.3. Abbreviated Measurement Summary

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 15 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

2.4. Detailed Spectra (EGRON-1 area)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 16 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

3. Inspection Area - EGRON-2


3.1. Overview
Sr. Equip. Equipment
Status Remarks
# ID Description
SECONDARY AIR FAN
1 2110    
2110
SECONDARY AIR FAN
2 2120    
2120
3 5202 ADF FAN 1ST SEC 5202    

4 5302 ADF FAN 2ST SEC 5302    


5 5402 ADF FAN 5402    
6 0102 W.R BLOWER 0102    
7 4216 BBS BLOW 4216    
8 4406 BBS BLOW 4406    
9 4416 BBS BLOW 4416    
10 4206 BBS BLOW 4206    
11 6206 FFS BLOW 6206    
12 6406 FFS BLOW 6406    
13 3001 BPA BLOW 3001    
14 7001 C.H AIR BLOW 7001    
15 6115 FCE AIR FAN 6115    
16 6315 FCE AIR FAN 6315    
17 6001 SUGAR GRINDER 6001    
TOWER EXHST AIR FAN
18 4115    
4115
TOWER EXHST AIR FAN
19 4315    
4315
NOZZLE COOLING FAN
20 1401    
1401
SECONDARY AIR FAN
21 2203    
2203
22 5001 TIPPING AIR BLOW 5001    

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 17 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

3.2. Critical Maintenance Review


Area EGRON-2
Observations & Analysis
 
Recommendations
 
Prepared By Review by Approved By
Technical Service Engineer Sr. Technical Service Engineer G.M (Operations)

     

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 18 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

3.3. Abbreviated Measurement Summary

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 19 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

3.4. Detailed Spectra (EGRON-2 area)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 20 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

4. Inspection Area - STD PLANT


4.1. Overview
Sr. Equip. Equipment
Status Remarks
# ID Description
1 7101 WARM SKIMMER 7101    
UHT FEED LINE PMP
2 2624    
2624
W.SKIMER SHEAR MIXR
3 7336    
PMP 7336
W.SKIMMER BOOSTER
4 7335    
PMP 7335
W.SKIMMER B.TANK
5 7303    
PMP 7303
W.SKIMMER SLURY
6 6902    
DOS PMP 6902
7 3801 C.SKIMMER 1 3801    
8 3901 C.SKIMMER 2 3901    
C.SKIMMER-2 B.TANK
9 2804    
PMP 2804
10 7601 BUTTER OIL SEP 1 7601    

11 7701 BUTTER OIL SEP 2 7701    

12 7801 BUTTER OIL SEP 3 7801    


HOMOGENIZER B.OIL
13 7704    
7704
CREAM PASTURIZR BO
14 5607    
PMP 5607
15 6131 SCANIMA MIXER 1 6131    
16 6231 SCANIMA MIXER 2 6231    
17 6331 SCANIMA MIXER 3 6331    
SHEAR MIXER PMP
18 3605    
EVAP L1 3605
SHEAR MIXER PMP
19 3610    
EVAP L2 3610
SLURRY DOSING PMP
20 7002    
TO EV 7002
THERMIZER B.TANK
21 0103    
PMP 0103
THERMIZER B.TANK
22 0203    
PMP 0203
Acid Circulation Pump
23 2.23    
2.23
Caustic Circulation Pump
24 3.23    
3.23
Caustic Circulation Pump
25 4.23    
2 4.23

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 21 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

Sr. Equip. Equipment


Status Remarks
# ID Description
26 1004 CIP FEED PMP L-1 1004    

27 1010 CIP FEED PMP L-2 1010    

28 1015 CIP FEED PMP L-3 1015    

29 1020 CIP FEED PMP L-4 1020    

30 1027 CIP FEED PMP L-5 1027    

31 1032 CIP FEED PMP L-6 1032    

32 1037 CIP FEED PMP L-7 1037    


AIR BLOWER 0150(WET
33 0150    
TIPPING)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 22 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

4.2. Critical Maintenance Review


Area STD PLANT
Observations & Analysis
 
Recommendations
 
Prepared By Review by Approved By
Technical Service Engineer Sr. Technical Service Engineer G.M (Operations)

     

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 23 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

4.3. Abbreviated Measurement Summary

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 24 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

4.4. Detailed Spectra (STD PLANT area)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 25 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

5. Inspection Area - UHT PLANT


5.1. Overview
Sr. Equip. Equipment
Status Remarks
# ID Description
1 M6 HOMO MOYOR VTIS M6    
2 0101 FEED PMP 0101    
3 0111 BOOSTER PMP 0111    
4 M2 FEED PMP M2    
FLASH VESSEL OUTLET
5 M5    
PMP M5
6 M8 WATER CIRCL PMP M8    
HOT WATER CIRCL PMP
7 0125    
0125
HOT WATER CIRCL PMP
8 0124    
0124
HOMOGENIZER UHT
9 0126    
0126
0124- HOT.W CIRCL PMP
10    
0125 0124-0125(S)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 26 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

5.2. Critical Maintenance Review


Area UHT PLANT
Observations & Analysis
 
Recommendations
 
Prepared By Review by Approved By
Technical Service Engineer Sr. Technical Service Engineer G.M (Operations)

     

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 27 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

5.3. Abbreviated Measurement Summary

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 28 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

5.4. Detailed Spectra (UHT PLANT area)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 29 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

6. Inspection Area - NOODLE PLANT


6.1. Overview
Sr. Equip. Equipment
Status Remarks
# ID Description
1 B1 Blower    

2 B2 Blower1    

3 B3 Blower2    

4 B4 Blower3    

5 B5 Blower4    

6 B6 Blower5    

7 P1 pump 1    

8 P2 pump 2    

9 P3 pump 3    

10 P4 pump 4    

11 P5 pump 5    

12 g1 Gear Box    

13 g2 Gear Box1    

14 g3 Gear Box2    

15 g4 Gear Box3    

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 30 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

6.2. Critical Maintenance Review


Area NOODLE PLANT
Observations & Analysis
 
Recommendations
 
Prepared By Review by Approved By
Technical Service Engineer Sr. Technical Service Engineer G.M (Operations)

     

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 31 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

6.3. Abbreviated Measurement Summary

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 32 | 33


Corporate Head Quarter:

Sumico Technologies (Pvt) Limited,


185/J-1, M.A. Johar Town, Lahore.
Ph: +92-42-35315541-43, Fax: +92-42-35315540,
Email: info@sumico.com.pk, Web: www.sumico.com.pk

6.4. Detailed Spectra (NOODLE PLANT area)

VA Report – Nestle Pakistan Ltd. Kabirwala – for May 2017 P a g e 33 | 33