Sie sind auf Seite 1von 6

AN INTRODUCTION TO INTRODUCTION the employer the purpose is to

establish a new contract completion


THE DELAY AND In October 2002, the Society of
Construction Law in the United date and prevent time for
DISRUPTION PROTOCOL completion of the works becoming
Kingdom published its Delay and
Michael Rochester Disruption Protocol. 'at large'.
Senior Associate This Protocol is designed to provide An application for an EOT should be
McCullough Robertson guidance on howto deal with claims made and dealt with as close in
for delay and disruption this being time as possible to the delaying
one of the most common areas of event which gives rise to the
claim and dispute in construction application. An assessment of the
contracts. The Protocol is not contractor's entitlement should be
intended to be a contractual made no later than one month after
document nor is it to take the application has been received
precedence over the terms of a by the contract administrator
contract, although it is the Society's [called CA in the Protocol)'
aim that in time construction The CAshould assess the
contracts will adopt the Protocol as contractor's claim by reference to
a means for dealing with delay and the contractor's contractual
disruption issues. entitlement. The CA should not 'wait
The Protocol is divided into the and see' what the full effect of an
following sections: Employer Risk Event [defined in the
Protocol to be a delaying event at
Section 1-Core principles in delay
the employer's risk} has on the
and disruption.
works before dealing with the
Section 2-Guidance on, the contractor's application.
preparation, of programmes and
Where the full effect of an
records and their subsequent use
Employer Risk Event cannot be
forthe management of extensions
predicted with certainty at the time
of time.
of the initial assessment they CA
Section 3-Gu ida nce with how to should grant an EOT for that part
deal with extension of time which be or she can predict. The
applications during the course of a EOT should then be considered
project. when its actual impact can be
determined.
Section 4-Guidance on howto
analyse causes of and responsibility FLoat
for delay where a project has been The Protocol also offers guidance
delayed, and the analysis is on the often controversial question
conducted afer the project is of who owns float and how it should
completed. be treated in assessing an EOT.
This paper provides an overview of Contractors often claim that they
some of the key features of the own float alleging that in planning
Protocol. how they propose to carry out the
works, they have allowed some
CORE PRINCIPALS IN
additional time to give themselves
DELAY AND DISRUPTION some flexibility in the event that
The Purpose of the they are unable to carry out the
Extension of Time works as quickly as planned.
The purpose of an extension of time Therefore, it is said that any delay
('EOT') is to relieve the contractor of will erode this additional time and
liability for damages for delay. An therefore the contractor should be
EOT [depending upon the wording entitled to an EOT despite the delay
of the contract} does not not resulting in the date for
automatically bring with it an completion not being met.
entitlement to compensation. For

18 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #89 MARCH/APRIL 2003


The opposing view is that the 1. Dedicated overheads which can
contractor shou ld not be entitled to be attributed to the specific
an EDT, unless the delay will result Employer Delay, and
in the contract completion date
2. Unabsorbed overheads which
being missed and therefore the are incurred by a contractor
'project' owns the benefit of any
regardless of its volume of work
float.
(e.g. rent and salaries).
Float and compensation For the contractor to recover
Where as with respect to an EDT the unabsorbed overheads, it must
Protocol takes the view that an EDT demonstrate that:
should only be granted if the delay
1. It has failed to recover the
causes the total float to reduce to
overheads it could reasonably have
below zero, a different view is taken
expected during the period of
with respect to prolongation.
prolongation, and
Unless, the contract otherwise
provides, the contractor should be 2. It has been unable to recover
entitled to compensation as a result such overheads because its
of a delay caused by an employer, resources had been tied up by
notwithstanding that there is no Employer Risk Events.
delay to the contract completion
If the unabsorbed overheads
date. A qualification is placed on
cannot be quantified, then a
this, and that is that the employer
formula may be used. The Protocol
must be aware of the contractor's
does however express the use of
intention to complete the works
such formulae with caution noting
priorto the contract completion
that they are a tool for the
date, and that intention is realistic
quantification of loss and do not
and achievable.
relieve the contractor from the
Mitigation of loss burden of proving its loss. The
Consistent with its obligations at Protocol does not support the use
law, the contractor should do all it of the Hudson formula, claiming
reasonably can to avoid the that it results in double counting as
financial consequences of delay it is derived from a numberwhich
caused by the employer. itself contains an element of head
office overheads and profit. The
This duty to mitigate has 2 aspects.
Eichlay or Emden formulae are
Firstly, the contractor must take
preferred.
reasonable steps to minimise its
loss, and secondly, the contractor Acceleration
must not take unreasonable steps Compensation for acceleration is
that increase its loss. assessed in accordance with the
contract or if the contract does not
Global claims
provide for acceleration, as agreed
The use of global claims is
between the parties. In both
discouraged by the Protocol in the
instances, the contractor is not
same way in which they are
entitled to claim prolongation
discou raged by the cou rts. The
compensation forthe period of
failure to maintain sufficient
Employer Delay avoided by the
records establishing the causal link
acceleration measures.
between the Employer Risk Event
and the resultant loss and/or Claims for so called 'Constructive
expense suffered is not an excuse Acceleration', where a contractor
to make a global claim. makes a claim that it had to
undertake accelerative measures
Head office overheads due to not receiving an EDT, are not
The Protocol divides head office recommended. There is no clear
overheads into 2 categories: acceptance of such a claim in, both

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #89 MARCH/APRIL 2003 19


The approach adopted by the English and Australian law. The Concurrency
Protocol is that float is not Protocol recommends that priorto The view adopted by the Protocol is
undertaking any accelerative that where delays caused by the
for the exclusive use or
measures, the parties resolve the contractor occur concurrentlywith
benefit of the either the disputed EOT in accordance with the delays caused by the employer, the
employer orthe contractor procedure laid out in the contract. contractor's concurrent delay
and that an EOT should only This suggestion is likely to be should not reduce any EOT due.
be granted if the Employer unrealistic given the time it may This view is contrary as to how
Delay is critical to meeting take to resolve a dispute and the AS2124-1992 (clause 35.5) deals
often urgent need to overcome the with this issue.
the contract completion date.
effect of delays.
The Protocol adopts the same view
Disruption where Employer Risk Events and
The Protocol defines disruption as Contractor Risk Events occur
the loss of productivity, disturbance, sequentially but have concurrent
hindrance or interruption to effects.
progress and distinguishes it from The Protocol's view is said to be
delaywhich is lateness. consistent with its approach of
Disruption to construction work may assessing the entitlement to an EOT
lead to late completion of the work, at the time each delay event occurs.
but this is not necessarily so. It is By assessing each delay event
possible forwork to be disrupted separately, the Protocol claims that
and for the contract still to finish by it avoids arguments aboutwhether
the contract completion date. The the 'prevention principle' applies.
contractor will not have a claim for This principle will prevent an
an EOT due to disruption, but may employerfrom levying liquidated
have a claim for the cost of the damages against a contractor, if the
reduced efficiency of its workforce if employer bas been the cause of the
the employer has caused the contractor's delay. The Protocol
disruption. claims that this avoids the
argument of whether an Employer
It is claimed that there is unfairness
Delay that acts concu rrently with a
in both views. The approach
Contractor Delay actually hinders
adopted by the Protocol is that float
the progress of a contractor in any
is not forthe exclusive use or
way.
benefit of the either the employer
or the contractor and that an EOT Mitigation
should only be granted if the The contractor is required under the
Employer Delay is critical to Protocol, to mitigate the effect on
meeting the contract completion its works of any Employer Risk
date. Therefore a contractor has no Events, but that duty does not
entitlement to an EOT merely extend to requiring the Contractor
because an Employer Risk Event to take acceleration measures such
prevents the contractor from as adding extra resources orto
completing the works earlierthan work outside its planned working
the contract completion date or it hours.
delays the contractor's progress.
Compensation for delay
This aspect of the Protocol has The recoverability of compensation
been the most criticised.' Critics for prolongation depends upon the
have suggested that this view is terms of the contract and the cause
unlikely to be welcomed by of the prolongation.
contractors especially where they
have built the float into the program Compensation for prolongation
fortheirown use when required. should not be paid for anything
otherthan work actually done, time
taken up or loss and/or expense

20 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #89 MARCH/APRIL 2003


actual actually suffered. The when the effect of the Employer
damage must therefore be 'actual'. Risk Event was 'felt' by the
contractor and not be reference to
The Protocol recommends that the
the extended period at the end of
contract should contain an agreed
the contract. Therefore if a
amount that can be applied to each
contractor was delayed by 3 days
day of prolongation. It
during the contract; the
acknowledges that there should be
prolongation is assessed when that
a different agreed amount to be
delay is incured during the contract,
applied, depending on the stage of
not by assessing what is the cost of
the project where the delay occurs.
3 additional days to the end of the
This overcomes the criticism of
contract.
agreed amounts which are often
calculated by reference to a daily Disruption claims are brought
overhead cost. This overhead cost pursuant to either:
often fluctuates at different times in
1. a specific clause in the contract
the project meaning either a
(a lthoug h it is ra re to see such a
windfall or a loss to the contractor.
clause); or
If the prolongation is caused by a
2. breach of the implied term that
variation then the Protocol
the employer will not prevent or
recommends that the
hinder the contractor in the
compensation for prolongation is
execution of its work.
valued as part of valuing a
variation. Contractor's often claim Like delay, disruption has to be
that such costs should form part of established in the normal cause
the variation by relying on for and effect manner and is not just
example, clause 40.5[f) of AS2124- the difference between what
1992, despite the express valuation actually happened and what the
clause for delay costs in clause 36 contractor planned to happen.
of that contract. The Protocol claims that the most
Concurrency and appropriate way to establish
disruption is to apply the 'Measured
prolongation
Mile' technique. This technique
Unlike the assessment of an EOT if
compares the productivity achieved
there are concurrent delays, the'
on an unimpacted part of the
Protocol states that if the contractor
contract, with that achieved on the
incur additional costs for delays
impacted part. The comparison is
caused by both the employer and
often used byway of man hours
the contractor, then the contractor
expended orthe units of work
should only recover compensation
performed. The Protocol cautions
if it is able to separate the
that care must be taken so that the
additional costs caused by the
2 periods which are compared are
employer from those caused by the
like periods. It cites the example
contractor. If the contractor would
that it would not be correct to
have incurred the additional costs in
compare work carried out in the
any event as a result of the
learning curve part of an operation
contractor delays, the contractor
with work executed after that
will not be entitled to recover those
period.
additional costs. This approach is
sensible and consistent with the If the Measure Mile approach is
usual principles of assessing unsuitable, then the Protocol
damages. suggests:

When are prolongation 1. a comparison of productivity on


costs to be assessed? other contracts undertaken by the
The Protocol recommends that contractor, provided that sufficient
prolongation costs be assessed records from the other contracts

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #89 MARCH/APRIL 2003 21


are available so as to ensure that (consequently referred to as the
the comparison is on a like for like Updated Program).
basis; and
The Accepted Program, should be
2. model productivity curves and updated with actual progress at
factors, such as those prepared by intervals of no longerthan 1 month.
the US Army Corp of Engineers, Actual progress should be
Chartered Institute of Building, etc. recorded by means of actual start
and actual finish date for activities,
Both methods in the writer's view
together with a percentage
will need to be used with some
completion of currently
caution, given the necessity to prove
uncompleted activities and/or the
cause and effect.
extent of remaining activity
The contractor must keep good durations. Each monthly Updated
records so that the CA can assess Prog ra m shou ld be saved so as to
disruption and also so that matters provide contemporaneous evidence
which can affect productivity, but of what happened on the project in
are unrelated to the employer's case of dispute.
liability are isolated, such as
In addition to the program the
weather, plant breakdowns, dilution
Protocol recommends that the
of supervision, contractor
parties reach a clear agreement on
management and acceleration.
the records to be kept throughout
GUIDELINES ON the project. Recommended clauses
PREPARING AND as to the kind of records to be kept
MAINTAINING PROGRAMS are contained in the Protocol.

AND RECORDS GUIDELINES FOR DEALING


The Protocol states, what is WITH EXTENSIONS OF TIME
submitted is a correct proposition, DURING THE COURSE OF
that many EOT disputes would be
THE PROJECT
avoided if the parties properly
The Protocol makes a somewhat
monitored and recorded progress
obvious statement that all the
of the works during the course of
requirements of the conditions of
construction.
contract relating to the application
The most important tool for doing for and the granting of extensions of
this is the program. The Protocol time should be followed strictly.
recommends that an agreement be
In addition to what may be required
reached between the parties as
under the contract, the Protocol
early as possible concerning:
suggests that a contractor submit a
1. the form the prog ra m shou ld 'sub-network' which can be inserted
take; into the updated program. A sub-
2. how the program interacts with network shows the actual or
any method statement describing in anticipated effect of the Employer
detail how the contractor intends to Risk Event and its linkage into the
construct the works and the Updated Program. An example is
resou rces it intends to use to do so; given for a variation with the sub-
network comprising the instruction
3. the time within which the for the variation, the activities
Contractor should submit a draft required to carry out that variation
program for acceptance (called the and its linkage to the updated
Accepted Program) and the Program.
mechanism bywhich that program,
is to be accepted; The amount of any EOT should be
assessed by undertaking the
4. requirements for updating and following steps:
saving the Accepted Program

22 AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #89 MARCH/APRIL 2003


1. the program should be brought 2. Impacted as planned is based There has been some comment
fully up to date to the point on the effect of Employer Risk that adoption of the Protocol will
immediately before the occurrence Events on the planned program of cause an increase in the required
of the Employer Risk Event; work. The usefulness of this level of record keeping and
technique is restricted due to the administration. It has also been
2. the program should then be
theoretical nature of the predicted stated that the Protocol requires
modified so as to reflect the
delays that are determined by its the constant use (and therefore
contractor's realistic and achievable
use. expense) of programmers. The
plans to recover any delays that
costs involved in administration and
have occu rred; 3. Collapsed as-built is based on
programming need to be
the effect of Employer Risk Events
3. the sub-network representing considered in determining whether
on the program of work as it was
the Employer Risk Event should to adopt the Protoco1. 2 Such
actually built. It suffers from the
then, be entered into the program; comments have some validity but
and same problems as the as-planned
the costs incurred in retrospectively
versus the as-built method.
4. the impact on the contract analysing delay or formulating a
4. Time impact analysis is based claim in the absence of good
completion date should be noted.
on the effect of delay events on the records and programs must also be
The Protocol notes that although contractor's intentions for the futu re considered.
the program should be primary tool conduct of the work in the light of
fordetermination, in orderto A copy of the Protocol can be
progress actually achieved at the
ensure that the EDT is fair and obtained at the Society's web site,
time of the delay event. The
reasonable it should be used in www.scl.org.uk.
Protocol claims that this is the best
conjunction with whatever technique for determining the REFERENCES
contemporary evidence is available. amount of EDT, although 1. See Sims 'A Landmark Protocol
GUIDELINES ON DEALING acknowledged as the most time but Fundamentally Flawed'
consuming and costlywhen Building Magazine 1 November
WITH DISPUTED
performed forensically. 2002.
EXTENSION OF TIMES
The Protocol recommends that if a 2. See for example, Russell
AFTER COMPLETION OF
retrospective delay analysis is to be 'Valuing Delay and Disruption'
THE PROJECT- performed, that the parties agree Electrical Times December 2002
RETROSPECTIVE DELAY upon the method to be used. and Birkby RIBAJournal
ANALYSIS December 2002.
In determining an EDT, any
If the parties have otherwise
adjudicator, judge or arbitrator
complied with the Protocol, then
should so far as it is practicable put
any retrospective analysis of the
him or herself in the position of the
impact of delaying events should be
CA at the time the Employer Risk
relatively simple. If not, then the
Event occurred. By doing so, he or
extent and success to which a
she should then determine what (if
retrospective analysis can be done
any) EDT entitlement could or
will be dictated by the relevant
should have been recognised by the
conditions of contract, the nature of
CA at that time. This may result in a
the course of events, the value of
different conclusion than that
the dispute, the time available, the
shown on the as-built program.
records available and the program
information available. CONCLUSION
Althoug h not without its critics, the
The Protocol makes the following
Society of Construction Law should
comments about the most
be commended on providing
commonly used forms of
guidance on this often troublesome
retrospective analysis:
topic. Some of the concepts in the
1. As-planned versus as-built Protocol do not automatically
analysis. This can be used for translate into the terms of
identifying delays to progress, but is Australian contracts (for example
restricted by its inability to identify concurrency) but practical advice
concurrency, re-sequencing, and application can be found in the
mitigation or acceleration. Protocol.

AUSTRALIAN CONSTRUCTION LAW NEWSLETTER #89 MARCH/APRIL 2003 23

Das könnte Ihnen auch gefallen