Beruflich Dokumente
Kultur Dokumente
BETWEEN
1. ZAKARIA MOHAMAD
2. NOR BIE HARIS … PLAINTIFFS
AND
1
[2015] 1 LNS 300 Legal Network Series
Kitchen v. The Royal Air Forces Association & Ors [1958] 2 AER 241
(foll)
Nasri v. Mesah [1970] 1 LNS 85 FC (refd)
Ng Moh v. Tan Bok Kim & Anor [1968] 1 LNS 88 FC (refd)
Tee Ban Tiong v. RHB Bank Bhd [2014] 1 LNS 1168 HC (refd)
2
[2015] 1 LNS 300 Legal Network Series
GROUNDS OF JUDGMENT
BACKGROUND FACTS
3. The Defendants are the registered owners of the land held under
HS(M) 5173, PT No. 6358, Mukim Ulu Kelang, Daerah Gombak,
Negeri Selangor, together with a house erected on it and bearing
the postal address No. 35, Jalan AU5D/2A, Lembah Keramat,
54200 Kuala Lumpur (“the Property”).
3
[2015] 1 LNS 300 Legal Network Series
6. Upon execution of the SPA, the Plaintiffs paid the Defendants the
sum of RM27,000.00 as a deposit, and a further sum of
RM10,000.00 on 19.9.2000.
10. The particulars of fraud pleaded include the Plaintiffs’ allegation that
after receiving the sum of RM37,000.00, the Defendants could not
be located or had disappeared and there was no way that the
Plaintiffs could contact them.
4
[2015] 1 LNS 300 Legal Network Series
(1) That the Defendants were prepared to sell the Property to the
Plaintiffs at a new purchase price, and that the Plaintiffs pay
arrears of rental; or
5
[2015] 1 LNS 300 Legal Network Series
18.5. Costs;
15. The Defendants made a Counterclaim against the Plaintiffs for, inter
alia, the following:
6
[2015] 1 LNS 300 Legal Network Series
17. Learned Counsel for the Defendants submitted that under Clause 5
of the SPA dated 2.8.2000, the balance of the purchase price is to
be paid by the Purchasers to the Vendors within 3 months of the
Purchasers’ Solicitor’s receipt of the Letter of Consent by the
relevant Authority. An extension of 1 month is provided for to
complete the purchase.
7
[2015] 1 LNS 300 Legal Network Series
action had arisen. When that happens Clause 6.02 arises and
Purchasers were entitled to specific performance and
consequential reliefs against the Vendors. Counting time from
the date of S & P Agreement to 1 year later plus say 3 months
would have taken it to end of November, 2001. Accrual of
cause of action would have commenced 1.12.2001 and 6
years hence would have been 30.11.2007. To commence
action on 15.07.2013 is clearly out of time. Refer Tab 4 pp
107 - 108, 110.” (emphasis added).
19. If this action is founded on contract, then I would agree with learned
Counsel for the Defendants that this action, being filed on
15.7.2013, is time-barred under s. 6(1)(a) of Act 254. However, as
submitted by learned Counsel for the Plaintiffs, this action is not
founded on contract, but for recovery of land and also founded on
fraud.
20. Under s. 9(1) of Act 254, the limitation period to bring an action for
recovery of land is “twelve years from the date on which the right of
action accrued”.
21. In Nasri v. Mesah [1970] 1 MLRA 363, the Federal Court held :
(See also Tee Ban Tiong v. RHB Bank Berhad [2014] MLRHU 1
at pg 5-6).
8
[2015] 1 LNS 300 Legal Network Series
23. Notwithstanding the above stand, I note that learned Counsel for the
Defendants in his Final Written Submissions dated 11.3.2015 and
filed on 12.3.2015 later changed his position and submitted, inter
alia, at pages 7 and 8 that the Plaintiffs are caught by limitation as
follows:
9
[2015] 1 LNS 300 Legal Network Series
24. Learned Counsel for the Defendants then cited Ng Moh v. Tan Bok
Kim & Anor [1968] 1 MLRA 877, [1969] 1 MLJ 46 where Azmi
(Malaya) CJ for the Federal Court stated:
25. Applying the above principle, learned Counsel for the Defendants
then submitted:
10
[2015] 1 LNS 300 Legal Network Series
26. With respect, learned Counsel for the Defendants cannot blow hot
and cold here by taking 2 different dates to count the limitation
period ie, from 1.12.2001, and from 3.2.2001.
28. The Plaintiffs further relied on s. 29 of Act which provides that for an
action based on fraud of the Defendants or the right of action is
concealed by the fraud, “the period of limitation shall not begin to
run until the plaintiff has discovered the fraud …. or could with
reasonable diligence have discovered it”.
29. The question now is whether the Defendants have committed fraud
against the Plaintiffs.
30. The Plaintiffs contended that the Defendants, after executing the
SPA and after collecting the sum of RM37,000.00, completely
became uncontactable. The Plaintiffs called upon the Defendants
at their address given in the SPA at Country Heights, Kajang,
Selangor, but the Defendants were nowhere to be found. Further,
11
[2015] 1 LNS 300 Legal Network Series
31. The Defendants did not disclose to the Plaintiffs, at the time when
they executed the SPA on 2.8.2000, that in 1999 a Judgment was
entered against the Defendants by the Employees Provident Fund
(“EPF”) for RM717,000.00. In 2003 bankruptcy proceedings were
filed against the Defendants by EPF (IDB2 Pt C pg 1-17).
“It is now clear, however, that the word ‘fraud’ in s. 26(b) of the
Limitation Act 1939, is by no means limited to common law
fraud or deceit. Equally, it is clear, having regard to the
decision in Beaman v. A.R.T.S. Ltd [1949] 1 AER 465 that no
degree of moral turpitude is necessary to establish fraud
within the section. What is covered by equitable fraud is a
12
[2015] 1 LNS 300 Legal Network Series
37. For the reasons stated above, the Plaintiff’s action is not time-
barred under the Limitation Act 1953.
13
[2015] 1 LNS 300 Legal Network Series
Whether the Plaintiffs were ready, willing and able to perform the SPA
38. The evidence of the 1 st Plaintiff (PW1) is that at all times the
Plaintiffs are willing and able to complete the SPA.
41. The 2 nd Defendant (DW1) had not seen the letter of M/s Mah-
Kamariah & Partners dated 6.8.2001 asking for the Loan
Documentation and Completion date. She stated that she had
instructed her Solicitors to follow up with the SPA. However, there
were no documents from her or her Solicitors to prove this. Her
Solicitors did not reply at all to the Solicitors of Citibank.
42. In Aik Ming (M) Sdn Bhd & Ors v. Cheng Vhing Chuen & Ors &
Another Case [1995] 1 MLRA 546 at pg 593 the Court of Appeal
held:
14
[2015] 1 LNS 300 Legal Network Series
43. It is therefore not open to the 2nd Defendant (DW1), who testified on
behalf of both Defendants, to blame their own Solicitors, M/s
Saleem & Co., and allege that they did not inform her of the SPA
transaction.
44. The evidence shows that the Plaintiffs had obtained the Citibank
loan to purchase the Property. The Defendants did not
communicate with the Plaintiffs after the execution of the SPA.
45. The Plaintiffs’ loan had lapsed due to the Defendants’ delay in
completing the SPA. However, the 1st Plaintiff (PW1) confirmed that
he has the means to pay for the Property by withdrawing his
savings in the EPF and from other sources.
Whether the Defendants were ready, willing and able to perform the SPA
46. The following Clauses of the SPA under Recitals, Article 2 of the
SPA are noted:
‘Clause 2.02
The Said Property is presently charged to Treasury of the
Government of Malaysia (hereinafter called “the Chargee”) as
security for a loan granted to the Vendors.
Clause 2.03
The Property is a leasehold for 99 years and the same expires
on the 30 t h day of December 2086.
15
[2015] 1 LNS 300 Legal Network Series
Clause 2.04
The Purchasers have conducted their own searches of the
titles to the Said Property and are aware of the ex press
conditions and restrictions in interest that the Property cannot
be leased, mortgaged or transferred without the expressed
consent of the Authority.
Clause 2.05
The Vendors have offered to sell the Said Property to
Purchasers and the Purchasers have agreed to buy the Said
Property on the terms and conditions hereinafter provided.’ ;
‘Clause 2.07
The Individual Title Deed to the said Property is encumbered
with a private caveat lodged by Hong Leong Finance Berhad
vide Presentation No 2273/98, Jilid 76, Folio 71 dated 29 th
May 1998.
Clause 2.08
The Vendors hereby give their undertaking to uplift the said
caveat to enable the parties to present the Transfer of the
Property with the relevant Land Office.’.
47. As can be seen from the above Clauses, at the time when the SPA
was executed, the Property was still charged to the Government of
Malaysia (“the Government Charge”). There was also an existing
private caveat lodged by Hong Leong Finance Berhad (“Hong
Leong”). It is therefore the Defendants’ obligation to free the
Property from the Government Charge and Hong Leong’s private
caveat. However, there is no proof that the Defendants have done
so.
48. The 2 nd Defendant stated that the Letter of Consent from the
relevant Authority was obtained but it was not produced in Court.
16
[2015] 1 LNS 300 Legal Network Series
“If the Vendors fail to complete the sale of the Said Property
upon the Purchasers’ fulfilling all the Purchasers’ obligations
herein, the Purchasers shall be entitled to the remedy of
specific performance against the Vendors and to all reliefs
following therefrom.”.
53. In this case, all that remained and was required to be done by the
Plaintiffs is to pay the balance of the purchase price, ie, the sum of
RM233,000.00, to the Defendants pursuant to the SPA. The
Plaintiffs had already obtained the Citibank loan but the Loan
Documentation could not be completed since the Defendants and
their Solicitors had never replied the letters of Citibank’s Solicitors or
17
[2015] 1 LNS 300 Legal Network Series
taken any action to fulfil their obligations under the SPA so that the
Agreement could be completed. Accordingly, the Plaintiffs are
entitled to Specific Performance of the SPA under Clause 6.02 of
the SPA.
55. For the alternative relief of Damages, I bear in mind that so far the
Plaintiffs have only paid RM37,000.00. They have also lived in the
Property since 2.8.2009 until now without paying any monthly rental.
The value of what the Plaintiffs have enjoyed in terms of not having
to pay a monthly rental all these years is clearly seen from the
Defendants’ Counterclaim for the sum of RM109,200.00 being
arrears of rental from 2.8.2000 ie, the date of execution of the SPA.
The balance of the purchase price under the SPA is RM233,000.00.
The Plaintiffs would have to pay this amount of RM233,000.00 to
the Defendants before the title to the Property can be transferred to
them. The Court takes judicial notice of the fact that the prices of
property in Kuala Lumpur have increased tremendously since
2.8.2000, especially in the last 5 years. The Plaintiffs would have
benefitted greatly from the Property’s appreciation from the time of
purchase at a mere purchase price of RM270,000.00 until now. Thus,
if the Specific Performance is not possible, I think a sum of
RM250,000.00 is a reasonable sum to be paid as Damages as an
alternative remedy to the Plaintiffs.
18
[2015] 1 LNS 300 Legal Network Series
56. I have held earlier that there is fraud committed by the Defendants
when they disappeared after collecting the RM37,000.00 from the
Plaintiffs and did not complete the transfer of the Property to the
Plaintiffs.
57. However, it is observed that from the date of execution of the SPA
on 2.8.2000 until now, the Plaintiffs have been occupying the
Property without payment of monthly rental.
58. The Plaintiff did not show proof that they have in fact suffered any
damages as a result of the Defendants’ fraud. Damages have to be
proved before the Court can assess the damages.
60. The 1 st Plaintiff testified at the time when the SPA was executed, it
was agreed between both parties that the Plaintiffs do not have to
pay monthly rental.
61. The 2 nd Defendant (DW1) and DW2 testified that arrears of rental
amounting to RM109,200.00 from 1.8.2000 until 31.3.2013 were
due from the Plaintiffs.
19
[2015] 1 LNS 300 Legal Network Series
64. It is more probable that what the 1 st Plaintiff testified is true, that it
was orally agreed between the 2 parties that upon the execution of
the SPA, the Plaintiffs do not have to pay the monthly rental of
RM700.00, which was payable before 2.8.2000. If it is not true,
then the Defendants would have demanded for such monthly rental
from the Plaintiffs from 2.8.2000 onwards, and not be silent for 13
years until 4.7.2013 when the Defendants’ Solicitors sent the letter
of demand, inter alia, for arrears of rental to the 1 st Plaintiff (IDB Pt
B pg 28 - 29).
66. For the above reasons, the Defendants’ Counterclaim has no legal
basis and cannot be allowed.
DECISION
20
[2015] 1 LNS 300 Legal Network Series
21
[2015] 1 LNS 300 Legal Network Series
Counsel:
For the defendants - Mohd Nor Mohamad (Siti Zaharah Mat with
him); M/s Wong Chooi & Mohd Nor
22