Daily Inspection Activity Report 

Date     :  10 December 2009 

1. ACTIVITY: 
07:00 – 10:30 Mobilization from Tripoli to Wafa 
14:00 – 16:00 Inspection on site for as per interoffice memo: LT/ON/SFW/JB/0028 regarding Spiral 
Fence & Guarding Point Project at Wafa Field Procedure for constructions of spiral 
fence sample 
 
2. DETAIL  ACTIVITY 
2.1. Inspection on site 10 December 2009, 14:00 – 16:00. 
Conducted by :  
• Andre Indrayana – Quality Specialist 
• Naji Alemari – HSE Technician 
• Amir Sadg – HSE Technician 
Contractor: Supervisor is not present during the inspection. 
 
2.2. Findings 
2.2.1. Posts have been completed installed in section 3‐4 and still on going on section 4‐5 up to 2 km 
from point 4. 
2.2.2. Post install using hammering as shown in pic 1. 
2.2.3. Damage occurred in the post due to hammering such as end crimp, galvanizing damages. (pic 2, 
pic 3, pic 4 and pic 5).   Measure damage on the post are vary between 50‐70 mm (pic 6).  
Length of damage post is shorter  10‐20 mm due to end crimp (pic 7). 
2.2.4. Gap between posts is 300 cm.  (pic 8) 
2.2.5. Distance between concrete posts is 60 meters. (pic 8)  
2.2.6. Gap between front post and back post is around 130‐150 cm.  (pic 9) 
2.2.7. Concrete box on post as follow : 
• No rectangular.  Almost round as per pic (pic 10 & 11) 
• Hole dimension = W : L : D = 50 cm : 50 cm : 50 cm 
• Diameter around 50‐60 cm. 
• Hole was wet prior to pouring concrete 
2.2.8. Height of posts are 270‐300 cm as per pic. 12 

Page 1 of 9 
 

2.2.9. Some of front post and back post is not the same level.  It also happened in between post.  The 
10‐20 cm (pic 13 & pic 14) 
2.2.10. Some of post is not install straight as per pic. 15. 
2.2.11. Contractor equipment available on site (pic 16 & 17): 
• Compressor 
• Power Jack Hammer  
2.2.12. Concrete mixing manually, no concrete mixer found location. 
2.2.13. Discussion with the worker not to do hammering on the post, instead use the jack hammer  
 
2.3. Non Conformance 
2.3.1. Post install with hammering.  The method was causing damage on the end post such as end 
crimp and galvanizing coating damage. 
 
2.4. Conclusion 
2.4.1. The posts are installed not installed according to interoffice memo: LT/ON/SFW/JB/0028.  
Contractor need to perform the corrective action. 
2.4.2. The damage to the post due to hammering should be repaired and touch up by the Contractor. 
 
3. PICTURE AND PHOTOGRAPHS 
 

 
 
Picture 1. Install post with hammering 
 
   

Page 2 of 9 
 

Damage post due to hammering

 
Picture 2. Damage at the ends of post. 
 

post damage 
due to 
hammering  End post galvanizing damage due to 
hammering

          
Picture 3. Detail of end damages       Picture 4.  Galvanize coating damages 
 
   

Page 3 of 9 
 

post damage due to hammering

 
Picture 5. Significant damage at the end of the post 
 

     
Picture 6. Damage measurement at end post             Picture 7. Total length of post after damage. 
 

Distance between post = 3m 
Distance between 2 post = 3 m 

Distance between 2 concrete post = 60 m 

 
Picture 8. Post gaps  

Page 4 of 9 
 

 
Picture 9. Gap between front and back post 
 

    
Picture 10 Concrete box dimension wide              Picture 11 Concrete box dimension depth 
 

 
Picture 12 Concrete box after pouring with concrete 
 

Page 5 of 9 
 

Post without 
concrete height 
= 297 cm 

Post with 
concrete height 
= 280 cm 
    
Picture 12 Concrete Post Height and non concrete post height 
 

    
Picture 13 not same level post       Picture 14 not same level post horizontal 
 

 
Picture 15 Unstraight post 

Page 6 of 9 
 

    
Picture 16 Contractor Equipment                Picture 17 Contractor Site with Equipment  
 
 
4. ATTACHEMENTS 
4.1. Attachment  1 : Interoffice Memo LT/ON/SFW/JB/0028 regarding Spiral Fence & Guarding Point 
Project at Wafa Field Procedure for constructions of spiral fence sample 
4.2. Attachment 2 : General Lay Out of Fence Project 
 
 
 

Page 7 of 9 
 

Attachment  1 : Interoffice Memo LT/ON/SFW/JB/0028 regarding Spiral Fence & Guarding Point Project 
at Wafa Field Procedure for constructions of spiral fence sample 

Page 8 of 9 
 

Attachment 2 : General Lay Out of Fence Project 

Page 9 of 9 