Sie sind auf Seite 1von 6

FULL-SCALE PILOT INVESTIGATION INTO Being containerized, this unit is fully portable

OZONE TREATMENT FOR COOLING and can be relocated for other pilot trials.
TOWER WATER
Equipment description
Brendan van Wyk
Air Products South Africa (Pty) Ltd. OxyZONE:

Abstract The OxyZONE system consists of:

Air Products South Africa (Pty) Ltd. and - A 1.5kg/hr Wedeco Ozone Generator
Ozonic, the local Wedeco representatives, (oxygen fed).
have successfully piloted a full-scale ozone - Two process water pumps (combined
treatment system (OxyZONE) for treating flow of 60m3/hr) with two venturi’s for
cooling tower water at an Air Products introducing the ozone gas into the
production facility in Vanderbijlpark. process water
- A separate cooling water pump for
The system has improved the efficiencies of circulating cooling water to the ozone
the two heat exchangers and the cooling generator.
tower. The tower is operating on an almost
Zero Blowdown basis; with only water used for All that is required when the container is
back washing the sand filters being sent to placed on site is an electrical supply and
sewer. Concentration cycles have been plumbing into the cooling tower water
improved from two cycles with conventional system.
water treatment to about seven cycles utilizing
the OxyZONE system.
Savings realized are; overall water
consumption of the system due to increased
cycles of concentration and power savings on
the compressors, due to improved heat
transfer efficiencies.

Introduction

Air Products had been experiencing problems Figure 1: OxyZone Container


with the current chemical based cooling tower
water treatment system, including: Maintaining a set Oxidation/reduction Potential
(ORP value) in the process water controls the
- High bacterial plate counts (21,100 cfu/ml) ozone dosage.
- Loss of efficiency on the heat exchangers
due to fouling, scaling and corrosion. Cooling Tower:
- Towers operating at less than two times
cycles of concentration. The tower chosen for this pilot test is used to
- High water and chemical consumptions, as cool the oxygen from a 4.5MW two-stage
well as high operating costs. compressor. The tower has a basin volume of
- Increased compressor power consumption. 102m3 and a recycle rate of 325m3/hr. The
- Loss of overall production efficiencies cooling water is pumped through two shell-
- Large volumes of low quality blow down and-tube heat exchangers running in parallel,
water being sent to sewer. one after each stage of compression.
The gas temperatures entering the heat
After extensive research, Air Products and exchangers are on average 1250C and the
Ozonic, the local Wedeco representatives, target exit gas temperature is below 300C.
designed and built a containerized ozone The lower the exit gas temperature achieved
treatment system. This containerized system through the heat exchangers, the more
was installed on a small cooling tower within efficiently the compressor operates.
the Air Products facility in Vanderbijlpark to
investigate this technology.
The following method was used to calculate
the efficiency of the heat exchangers:
The difference between the exiting cooled gas
and the cold incoming cooling water
temperatures were monitored. The greater the
temperature difference (Delta T) is for the heat
exchanger system, the more inefficient that
system is running.
Figure 2: Cooling tower used for pilot study
Heated
Water
Trial Objectives
Monitor
Cooled
Difference Hot
The objectives of this pilot trial were to prove gas
gas
the efficiency of ozone as a treatment method
by: Cold
1) Improving the heat transfer efficiencies Water
of the cooling tower and heat
exchangers Figure 3: Heat Exchanger Efficiency
2) Stopping all chemical treatment of the
cooling tower water The pH, conductivity, ORP, residual ozone
3) Increasing the cycles of concentration concentration, temperatures and flows were
of the system in order to reduce water monitored hourly.
consumption and minimize blow down
4) Ultimately save money on operating Results and Discussion
and power costs
Water Control and Chemistry
Methodology
Water is lost from the cooling tower in three
The water quality in the tower, and the heat ways: evaporation, drift, and blowdown.
exchanger efficiencies were monitored for a
few weeks prior to starting the trial in order to The rate of evaporation from the tower is
obtain a baseline for comparison with the determined by the heat load on the tower, and
ozone treated system. Once the OxyZONE arises from air passing through the tower and
container was installed on site, the existing absorbing heat and mass. The evaporation of
water treatment system, consisting of pH water concentrates up the salts in the basin.
control, biocides, anti-corrosion chemicals,
anti-scaling and anti-foaming agents was Drift occurs when water droplets become
disconnected, and the ozone treatment entrained in the discharge air stream and are
started. blown out of the tower. This acts as a purge of
the basin as this water contains salts.
The trial was started by running the ozone
generator at maximum output (1.5kg/hr, 13% Blowdown is the intentional bleed-off of water
ozone in an oxygen stream) to overcome the from the basin in order to reduce the
initial algae and bacterial load. After 5 hours of concentration of salts and contaminants.
operation, the ORP had increased from 250mV
to 750mV. The generator power was reduced All the above water losses need to be
to 50% and an ORP reading between 700mV constantly replaced with fresh make-up water.
and 750mV was maintained for the next 4 Water savings can be realized by reducing
days. After this period, generator power was water blown down to sewer, however, there is
further reduced, maintaining an ORP of below a limit to the amount that blowdown can be
650mV, correlating to about 200g/hr of ozone reduced. This limit is set by the systems
being injected into the cooling tower basin. The potential to scale the heat transfer surfaces.
make-up and basin water was then sampled
regularly and sent to ERWAT Laboratories for
analysis.
Make Up Basin Make Up Basin Make Up Basin Make Up Basin
31-Mar 31-Mar 10-Jul 10-Jul 15-Aug 15-Aug 22-Aug 22-Aug
Conductivity Conductivity
(mS/m @25'c) 240 86 16 44 (mS/m @25'c) 242 615 309 1490
pH 7.8 8.1 7.8 8.2 pH 9.7 8.7 7.7 8.9
TSS TSS
(mg/l @105'C) <10 <10 <10 <10 (mg/l @105'C) 26 10 24 42
TDS TDS
(mg/l @180'c) 126 288 (mg/l @180'c) 1420 4018 1822 9244
Total Alkalinity Total Alkalinity
(CaCO3) 107 108 56 97 (CaCO3) 255 278 214 723
Total Hardness Total Hardness
(CaCO3) 74 63 52 109 (CaCO3) 84 507 306 1165
Ca Hardness Ca Hardness
(mg/l) 34 27 29 67 (mg/l) 34 150 229 522
Mg Hardness Mg Hardness
(mg/l) 40 36 23 42 (mg/l) 50 157 77 643
Cl (mg/l) 368 101 10 41 Cl (mg/l) 199 780 363 1660
Na (mg/l) 71.2 45.9 Na (mg/l) 435 1233 496 2614
Fe (mg/l) 0.17 0.38 0.09 0.55 Fe (mg/l) 0.12 0.05 1.29 0.27
Si (mg/l) 11 25 5.6 10 Si (mg/l) 4.54 16.78 13.1 26.93
NH3 (mg/l N) 3.2 0.4 0.7 0.2 NH3 (mg/l N) 3.3 0.2 2.3 0.5
TKN (mg/l N) 4.7 <0.1 <1 <1 TKN (mg/l N) 5.2 1.5 3.7 1.9
NO3 (mg/l N) <0.1 0.4 1.1 1.4 NO3 (mg/l N) <0.1 14.4 <0.1 41
PO4 (mg/l) <0.1 0.4 <0.1 0.4 PO4 (mg/l) 0.1 2.3 <0.1 1.4
TP (mg/l P) <0.1 2.8 <1 2.4 TP (mg/l P) <1.0 2.5 <1.0 1.5
SO4 (mg/l) 455 136 14 64 SO4 (mg/l) 500 1590 740 3540
COD (mg/l O2) 30 22 27 37 COD (mg/l O2) 42 15 73 35
SRB (cfu/1ml) neg neg pos pos SRB (cfu/1ml) Pos Pos Pos Pos
HPC (cfu/1ml) 108000 40000 1540 14200 HPC (cfu/1ml) 4,100,000 42 9,300,000 1820
Table 1: Water quality before ozonation Table 2: Water quality after ozonation

Table 1 shows the initial analysis of the


incoming make-up water and the basin water
prior to ozonation. The table shows that the
existing water treatment method was not
effective in treating the bacterial contamination
of the cooling tower and that the water was not
being cycled up effectively.

Due to 3rd party water supply issues, the


supply of make-up water was switched from
recycled industrial water to primary treated
river water just prior to the start-up of the
ozone generator. The make-up water was
changed back to recycled process water two
weeks into the trial of the ozone system. As
can be seen from Table 2, this water had high Figure 4: Water quality before and after
TDS (1822mg/l) and high conductivity ozonation
(309uS/cm). This change in water quality had
very little effect on the operation of the cooling The cycles of concentration were increased in
tower as can be seen in Graph 1. the tower by closing the blowdown valve
completely. The tower is configured in such a
Prior to start-up of the ozone system, the way that basin water is used to backwash the
visual quality of the water in the basin was sand filters. This means that the basin is
poor, as can be seen in Figure 4. After 4 days purged every time the filters are backwashed.
of operation, the water clarity increased to a This is not the most effective system for
point where the bottom of the basin was clearly backwashing sand filters as high TDS and TSS
visible. water from the basin can scale and plug the
filters. It would be more effective to backwash
filters with make-up water.
operating for extended periods with zero
The limit on cycles of concentration that may intentional blowdown, the underlying physical-
be obtained in a cooling tower water system chemical mechanisms are not well understood.
using ozone for treatment is far higher than for
conventional treatment methods. One mechanism that has been proposed for
the ability of ozonated systems to run at high
Using a conventional water treatment system, cycles of concentration is that under the
and taking into account the standard influence of ozone, calcite tends to precipitate
Saturation Index, as below; out into the bulk of the water body. Because of
the very high surface area of the precipitating
Saturation Index: crystals compared to the metal surface in the
1). P1 = log 10 (calcium * 2.5 * total alkalinity) system, continuing precipitation leads to
2). P2 = (max. system water temp, F* 0.00912) + P1 crystal growth in the bulk water rather than
3). P3 = (log 10 (conductivity * 0.8) * 0.1) + 12.27 scale formation on the heat transfer surfaces.
4). pH saturation = P3 – P2
5). SI = pH of cycled water - pH saturation This theory seems to hold true, as it was found
that the concentration of calcium did not
The tower would be limited to two cycles of increase in the basin water to the same extent
concentration before scaling would become a as the more soluble metals like sodium. The
problem with this make-up water. graph below shows the cycles of concentration
for conductivity, calcium, sodium and chlorine.
However, using the Practical Ozone Scaling As the cycles of concentration increase for the
Index (POSI number) developed by Alan Pryor conductivity, so the soluble elements follow,
and Terill Buffum as shown in the formula increasing in concentration, however, calcium
below, a minimum of 3.74 cycles of seems to maintain a steady state at about 4
concentration is obtained for the same make- cycles of concentration. This means that
up water. calcium is being removed from the water, but it
does not do so as scale.
Maximum conductivity:
= 10 (1/(log(CaxMg)/(Na+Cl)]xlog(Alk/10) x cond(mu) Graph 1: Cycles of concentration of elements
Where: as Conductivity increases
Ca = Calcium Hardness in makeup water (As
CaCO3) 6.00

Mg = Magnesium Hardness in makeup water


(As CaCO3) 5.00

Alk = Total Alkalinity makeup water (CaCO3)


Cl = Chlorine in makeup water (Cl-) 4.00

Na = Sodium in makeup water (Na+)


3.00
Cond(Tower)= Tower water Conductivity
Cond(MU)= Makeup water Conductivity 2.00

This formula gives the maximum conductivity 1.00

that the water in the basin should obtain before


blowdown becomes necessary to avoid 0.00
31-Mar 10-Jul 19-Jul 25-Jul 8-Aug 14-Aug 15-Aug 22-Aug
scaling. The cycles of concentration that can
be obtained is then calculated by dividing the Cl Na Ca Con
d
POSI number by the conductivity of the
makeup water. The authors state that the After the analyses were received, the POSI
resulting figure is conservative, and the tower number was calculated, and the basin water
may operate at far higher cycles than was controlled on the maximum conductivity of
predicted. This was found to be correct as the 14,000 uS/cm that was calculated.
water in the basin is currently running at close This corresponds to about 7 cycles of
to 7 cycles and there has been no evidence of concentration, as can be seen from the plot of
scale, or loss of heat transfer efficiency. conductivity and pH of the makeup water and
the basin water in graph 2.
Although there have been numerous
documented cases of ozonation systems
12 16000

14000
10

12000

8
10000

6 8000

6000
4

4000

2
2000

0 0

Iscor water pH pH Iscor water Conduct Conductivity

Graph 2: pH and Conductivity of Make-up water The lowest temperature that cooling tower
and Tower Basin Water basin water can obtain is dependant on the wet
bulb atmospheric temperature.
Heat Exchanger and Tower Efficiency:
In order to monitor the efficiency of the cooling
The baseline results show that in the week prior tower the water temperature in the basin, and
to the start of ozonation, the Delta T’s had risen wet bulb temperatures were monitored and the
by over 30C, indicating that the heat transfer difference plotted in the graph below.
surfaces were becoming fouled, decreasing the This plot shows that the cooling tower started to
compressor efficiencies. Once the system was operate more efficiently after ozone treatment
converted to ozone, there was an immediate was initiated.
reduction in the Delta T’s, with more than 30C
being recovered within 2 weeks of operation. 14

This efficiency was obtained, even while the 12

cycles of concentration were being increased.


10

8
D e lt a T 's

16
6
14
4
12
2
10
D e lt a T e m p

0
1
4
7
10
13
16
19
22
25
28
31
34
37
40
43
46
49
52
55
58
61
64
67
70
73
76
79
82
85

8
Hours
w et diff Linear (wet diff)
6

4
Graph 4: Delta T’s for cooling tower
2
The tower efficiency increased as a result of the
0 almost total removal of algae and biological
1
5
9
13
17
21
25
27
31
35
39
43
47
51
55
59
63
67
71

fouling present on the tower wetted surfaces.


As shown in the tables above, the biological
activity in the tower was reduced from plate
Graph 3: Delta T’s for heat exchanges before
counts of as high as 14,200cfu/ml to as low as
and after ozonation
42cfu/ml after ozonation. This result was
achievable, even when the incoming make-up
Due to improved efficiencies of the heat
water had plate counts as high as
exchangers, power consumption of the oxygen
9,300,000cfu/ml.
compressor is reduced for the same volume
throughput. For every 3oC that the gas is
cooled, there is a 1% saving in the power
consumption of the compressor.
Corrosion: Reference:

The corrosion rates of the metals in the heat 1. A.E. Pryor and M. Fisher, “Practical
exchangers and pipe work are currently under Guidelines for Safe Operation of Cooling
investigation; however, chemical analysis of the Tower Water Ozonation Systems”,
basin water does not show any corrosion Ozone Science & Engineering Vol.16
products being present. April 1994
Various papers written on the subject of 2. D.J. Tierney, “Ozone for Cooling Tower
corrosion in ozonated systems show that Systems – An Update and Lessons
corrosion should be no worse than conventional Learned at the Kennedy Space Center”
systems. www.zentox.com/CleanStreams/Ozone_Co
R.J. Strittmatter et al, state “the rate of corrosion oling_Tower_Systems_KSC.pdf
is dominated by the saturation level of the water, 3. R.G. Rice and J.F. Wilkes,
and not by the presence or absence of ozone in the “Fundamental Aspects of Ozone
system”. They also found that the corrosion rates Chemistry in Recirculating Cooling
dropped as the cycles of concentration Water Systems – Data Evaluation
increased, with low-cycle tests having the Needs” Ozone Science & Engineering
highest corrosion rates, and high-cycle tests Vol. 14 January 1992
having extremely low corrosion rates. 4. R.J. Strittmatter, B Yang and D.A.
Johnson, “Application of Ozone in
Conclusions Cooling Water Systems”, National
Association of Corrosion Engineers
The full-scale pilot investigation has proved to Corrosion’92 Meeting, Tennessee, April
be a success. All chemical treatment to the 27- May 1 1992.
tower has been stopped; only ozone is used to
treat the water. Heat transfer efficiencies have 5. “Advanced Cooling Tower Water
improved in both the heat exchangers and the Treatment”,
tower packing. Almost zero blowdown http://www.nelsonenviromentaltechnolog
conditions have been maintained in the tower ies.com/ACTWT.html
for 4 months with the only bleed coming from
the backwashing of the sand filters. The cycles 6. U.S. Department Of Energy, “Federal
of concentration have been improved from 2 Technology Alert – Ozone Treatment
cycles to 7 cycles, saving water. The overall For Cooling Towers”,
system has proved to be simple to operate and http://www.pnl.gov/fta/6_ozone.htm
easy to maintain, while still being an
economical alternative to conventional
treatment methods.

Acknowledgements

The author would like to thank Cobus Coetzee


and Leon de Goede from Ozonic, and Phillip
Fivaz from CP Projects for their design and
construction of the Pilot Plant, as well as their
help in the operation of the system. We would
not have been able to get the results we did
without the able assistance of Noluvuyo Godlo,
our operating student, and all the operations
staff at our Production Facility in Vanderbijlpark.

Das könnte Ihnen auch gefallen