SUMMARY REPORT

COMMISIONING PABRIK GARAM SEGOROMADU KAPASITAS 5 TON/JAM

PT. GARAM (PERSERO) HASIL PENGAMATAN


PROYEK PENDIRIAN PABRIK GARAM SEGOROMADU COMMISIONING PABRIK GARAM
DENGAN KAPASITAS 5 TON/JAM TGL 26 S/D 28 ,BULAN 12 2018
STANDARD HARI KE :
NO. URAIAN KOMULATIF CATATAN
BESARAN SATUAN 26-12-2018 27/12/2018 28/12/2018
1. JAM OPERASI JAM 2 jam 7,6 Jam 10 jam
2. BAHAN BAKU MASUK TON 10,59 Ton 45,05 Ton 34,98 Ton
(RAW SALT)
5,5 TON/JAM 5,29 Ton/Jam 5,93 Ton/Jam 3,49 Ton/Jam
3. PRODUKSI TON 7,80 Ton 31,85 Ton 26,45 Ton
GA
5 TON/JAM 3,9 Ton/Jam 4,19 Ton/Jam 2,64 Ton/Jam
4. LOSSES TON 2,79 Ton 13,2 Ton 8530 Ton

20 % 26,35% 29,30% 24,385%


5. KADAR AIR BAHAN BAKU 5 % - - -
7. KADAR AIR PRODUK 0,5 % Centrifuge = 4,04% Centrifuge = 4,89% Centrifuge 4,63%
Bagging = 0,28% V Screen = 0,28% V Screen = 0,32%
8. PEMAKAIAN FRESH M3 - - -
WATER
M3/JAM
9. PEMAKAIAN LISTRIK KWH - - -
10. PEMAKAIAN CNG M3 86 m3 337 m3 227 m3

M3/JAM

GRESIK, ...............................................
PT. INDAH KARYA (PERSERO) PT. GARAM (PERSERO) PT. BARATA INDONESIA (PERSERO)

.............................................. .............................................. ..............................................