PROJECT
(7.5 MW)
TERHATHUM
October 2018
Submitted To:
MACHHAPUCHCHHRE BANK
AND
TERHATHUM POWER COMPANY PVT. LTD
Table of Contents
1 Summary of HM Cost ..................................................................................................... 1
2 Background................................................................................................................... 2
4 Assignment ................................................................................................................... 2
7 CONCLUSION ................................................................................................................ 6
I
1 Summary of HM Cost
Table 1:HM Works Cost Summary
1
Upper Khorunga Khola Small Hydropower Project IPC No 2
2 Background
Upper Khorunga Khola Small Hydropower Project (UKSHP) is a run-of-river type of project located
in just upstream of confluence of Tanmaya and Khorunga. The Terathum company is developing
this project with an installed capacity of 7.5 MW with 282.39 m net head and 3.15 m3/s design
discharge at Q 40 % discharge.
The project site is accessible from Jirijhimti in Mid-Hills highway which is about 66 km far from
Dhankuta.The access road up to the headworks site of this project is completed while a road
construction is required within project alignment. UKSHP is under construction and its required
commercial operation date (RCOD) is in 17th December 2019. The institutional arrangement to
accomplish the project on time is as follows:
3 Verification Period
Period from Chaitra 2074 to Ashwin 2075
4 Assignment
Units Engineering Consultancy Pvt Limited (UECPL) carried out the verification of Second Running
Bill of HM Works of Upper Khorunga Khola Small Hydropower Project submitted by Terathum Power
Company Pvt. Ltd. for the period up to 10th September 2018.
5 Scope of work
The objective of this work is to conduct verification of the Running Bills of Hydromechanical Works
of UKSHP submitted by Terathum Power Company Pvt. Ltd based on the running bills, contract
documents, detailed project reports, other related supporting documents and site visits.
2
Upper Khorunga Khola Small Hydropower Project IPC No 2
5.2 Limitations
The verifications were carried out based on the documents provided by the Client/Bank. Due to the
nature of the work, there is every possibility of errors going unnoticed misstatements remaining
undiscovered. Errors and mis statements discovered at later date can be corrected and adjusted in
the next running bill.
3
Upper Khorunga Khola Small Hydropower Project IPC No 2
4
Upper Khorunga Khola Small Hydropower Project IPC No 2
Trashracks and 0
1 48,818.98 48,818.98
Accessories
5
Upper Khorunga Khola Small Hydropower Project IPC No 2
7 CONCLUSION
The Consultancy has performed the verification of the bills submitted by the company and has made
the following recommendations.
1. The developer (Terhathum Power Company) has claimed the total expenditure of Rs.
16,843,375.04 in the running bill 02 for the HM work.
2. The Consultancy has recommended a total expenditure of Rs. 16,664,990.52 in the total bill
02 as HM works expenses.
6
PHOTOGRAPHS
7
Figure 1:Bellmouth Installed at site.
8
Figure 2:Rolling Machine for pipe fabrication.