Sie sind auf Seite 1von 51

A Presentation by

Sundaram – Clayton Limited,


Die Casting Division,Chennai.

Sundaram-Clayton Limited 1 20.08.2010


Die Casting Division, Padi Plant
INTRODUCTION

TS 16949,OHSAS Certified

Sundaram-Clayton Limited 2 20.08.2010


Die Casting Division, Padi Plant
COMPANY PROFILE

Sundaram Clayton - Journey

TS 16949
Certification -
2005
Started Collaborative
product development
with MNC Customer -
2001
Commissioned
Alloying plant -
Started as Captive 2000
unit with OHSAS
Aluminium Gravity Certification -
Die casting – GDC- Started 2006
Global Supply started -
1968 Supplies to
2000
Honda - 2003

Started
Aluminium
Pressure Die
Casting - 1983

60 65 70 75 80 85 90 95 2000 2005
Sundaram-Clayton Limited 3 20.08.2010
Die Casting Division, Padi Plant
COMPANY PROFILE

Products and Customers


Die Casting Division

Sundaram-Clayton Limited 4 20.08.2010


Die Casting Division, Padi Plant
Project title : Productivity Improvement in Compressor
cover machining cell to meet the increase in customer
demand without additional capital investment.

Team leader : Rajmohan J

Team members : Department

Subha K Online Production engineering


Bhavan Kumar K Production
Chitra V Online Production engineering
Ramesh G Quality assurance
Gosu Ramaiah Production
Purushothaman .P Production engineering

Sundaram-Clayton Limited 5 20.08.2010


Die Casting Division, Padi Plant
Product detail

Product Name : Compressor Cover

Casting Type : Gravity Die Casting

Customer Name : Cummins Turbo Technologies

Application : Turbo Charger assembly part

Delivery condition : Machined Component

Sundaram-Clayton Limited 6 20.08.2010


Die Casting Division, Padi Plant
Approach

7 step approach

Step 7. Horizontal deployment

Step 6. Standardization

Step 5. Implementation & Verification

Step 4. Analysis & Improvement plan


Step 3. Selecting opportunities

Step 2. Understanding the current situation.


Step 1. Problem identification

Sundaram-Clayton Limited 7 20.08.2010


Die Casting Division, Padi Plant
Step 1 – Problem identification

Increase in customer demand from 7100Nos to 15900 Nos/Month


17000
15900
100%
Increase in

No. of components
14000
demand
11000

CAPACITY
7100
8000

5000
Current demand Future demand

Importance of problem:

 100% share of business for this product is with SCL and hence shortfall
in supply will result in customer line stoppage.

 Additional investment of Rs. 50 Lakhs required to meet the future demand


which will affect the bottom line.

Sundaram-Clayton Limited 8 20.08.2010


Die Casting Division, Padi Plant
Step 2- Understanding the current situation

Takt time calculation


Description Current Future
Available time in a month(Sec) 1721250 1721250
Average monthly demand(nos.) 7100 15900
Takt time(sec) 243 108
Output/shift 94 212

Takt time = Available time


Customer demand Takt time
250

Time in seconds 200

150 243
100

50
108

0
Current Future

Sundaram-Clayton Limited 9 20.08.2010


Die Casting Division, Padi Plant
Step 2- Understanding the current situation

Process flow – Compressor cover machining line

Inlet machining

Diffuser side
machining
Machining

Lathe-3

Lathe-2

Lathe-1
hole drilling
Name plate
Outlet

Part Feeder
TANK

tank

tank
DIP

Dip

Dip
Gauge Gauge Gauge

Gauge Final
VMC Leak Washing
inspect Heater Cooler Packaging
Drilling,R testing machine
-ion
eaming &
Tapping

No. of operators per day = 9


No. of Lathes =3
No. of VMCs =1
Space occupied = 1120 sq.ft

Sundaram-Clayton Limited 10 20.08.2010


Die Casting Division, Padi Plant
Step 2- Understanding the current situation

Ex: Man- machine chart from Video study – For first operator

15900

Sundaram-Clayton Limited 11 20.08.2010


Die Casting Division, Padi Plant
Step 2- Understanding the current situation

Man – machine time

300
Bottleneck machines
250
Current Takt time – 243 Secs
17
200 12
Time in Secs

150
Future Takt time – 108 Secs
218
100 199
13
60
50
70 81 10 72
60 50 60
30 25 34 30
0 7 9 15
Gauging

final
NP drilling

Outlet m/cing

Washing
Diffuser

Air cleaning

Inlet m/cing

Deburring

Aircleaning

Milling,drilling

Deburring

Air cleaning
Marking

m/cing

Leak testing
& reaming
AUTO TIME
Operator 1 Operator 2 Operator 3
MANUAL TIME

Sundaram-Clayton Limited 12 20.08.2010


Die Casting Division, Padi Plant
Methodology

ECRS Methodology

E - Eliminate

C – Combine

R – Reduce

S – Simplify

From ECRS Methodology these themes were identified


Improvements – Classification by themes
Methodology

Theme E C R S

Improved tooling - A

Parameter optimization -B

Combining tools - C

Sundaram-Clayton Limited 13 20.08.2010


Die Casting Division, Padi Plant
How to de-bottleneck ?

Milling, Reaming and Tapping operation in VMC

Sundaram-Clayton Limited 14 20.08.2010


Die Casting Division, Padi Plant
Step 2- Understanding the current situation

Machine time - existing

300

250
Current Takt time – 243 Secs
17
200 12

150

Future Takt time –108 Secs 218


Time in Secs

100 199
13
60
50
81
34
0

Outlet m/cing
Diffuser

Inlet m/cing

Milling,drilling
m/cing

& reaming
AUTO TIME

MANUAL TIME

Sundaram-Clayton Limited 15 20.08.2010


Die Casting Division, Padi Plant
Step 3- Selecting opportunities

Milling, Reaming & Tapping in VMC


Cycle time details with improvements identified
Operation Cycle Proposed
S.NO description Speed Feed time improvement The me
Milling cutter
(Carbide) Big Milling cutter Small
1 Holder (75 mm) 4000 600 28 Holder (60 mm) B
2 6.8 Carbide Drill 3000 0.15 27 6.8 Parabolic Drill A & B
High speed W alter
3 M8 Tap 800 1.25 26 taps A & B
4 4 Dia Drill 3000 0.15 23
4.395 c arbide
5 Reamer 5000 0.02 57 4.395 PCD Reamer A & B
6 1.6 Centre Drill 2000 0.1 16 1.7 center drill and
7 1.7 Drill 2000 0.08 19 drill C
8 1.95 Reamer 2000 0.06 16
Door close&open 6
218

220
200 16
180 19
16
Time in Secs

160
140 57 Future Takt time -108Secs
120
100 23
80
26
60
40 27
20 28
0
Before improvem ent
M il l ing 6 . 8 d r i l l i ng M 8 T a p pi ng
4 di a dr i l l 4 . 3 9 5 r e a m i ng 1. 6 c e n t r e d r i l l
1. 7 d r i l l 1. 9 5 r e a m e r Ta k t t i me

Sundaram-Clayton Limited 16 20.08.2010


Die Casting Division, Padi Plant
Step 3- Selecting opportunities

Milling, Reaming & Tapping in VMC


Cycle time details
Operation Cycle
S.NO description Speed Feed time
Milling cutter
(Carbide) Big
1 Holder (75 mm) 4000 600 28
2 6.8 Carbide Drill 3000 0.15 27 1
3 M8 Tap 800 1.25 26
4 4 Dia Drill 3000 0.15 23
4.395 carbide
5 Reamer 5000 0.02 57 2
6 1.6 Centre Drill 2000 0.1 16
7 1.7 Drill 2000 0.08 19 3
8 1.95 Reamer 2000 0.06 16
Door close&open 6
218

Sundaram-Clayton Limited 17 20.08.2010


Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

1.Theme A – Improved tooling & B – Parameter optimization


Description : Dia 6.8 drilling

BEFORE OBSERVATION

Maximize cutting parameter


• Standard 6.8 drill
Poor tool life

Tool wears off faster

Higher temperature at cutting edge

High temperature
Speed :3000 RPM
Feed : 0.15mm/rev

Sundaram-Clayton Limited 18 20.08.2010


Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

Improvement details ( Theme A &B)


Description : 6.8 Parabolic drill for blind hole to help chip evacuation
Theory Idea 1 Idea 2
Burnishing drill Parabolic drill
Cutting edge • Additional relief on
• Can go at high tool.
parameters • Enhanced coolant flow
• Good tool rigidity & life • This improves chip
• Good surface finish evacuation and hence
• Best suited for core reduces temperature at
cutting edge.
holes (PDC Castings) Additional
relief for
Chip flow • Poor chip evacuation coolant flow
direction when l/d is high/ Blind
Hole/ material allowance
Coolant flow direction
is high

Sundaram-Clayton Limited 19 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

Solution identified – Parabolic drill


BEFORE AFTER BENEFITS
Standard 6.8 drill Parabolic drill Cycle time

210
205 >5 %
205

Time in Secs
200

195 192

190

185

180
Before After
Cycle time saved – 13 Secs

Speed :3000 RPM Speed :4000 RPM * No impact on tool life &
Feed : 0.15mm/rev Feed : 0.25mm/rev tool cost per component

Sundaram-Clayton Limited 20 20.08.2010


Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

3.Theme A – Improved tooling & B – Parameter optimization


Description : Carbide reamer (4.395 ± 0.02) for finishing
close tolerance of 40 microns

BEFORE OBSERVATIONS

Carbide reamer
 Built-up edge formation.

 Poor repeatability.

 Poor life for close tolerances.

Speed :5000 RPM


Feed : 0.02 mm/rev
Tool life : 1500 Nos
Cp < 1.67
Sundaram-Clayton Limited 21 20.08.2010
Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

Improvement details (Themes A& B)


Description : Carbide reamer to PCD reamer (4.395 ± 0.02) to address close
tolerance of 40 microns ( Reduce thermal wear)
Theory Solution
PCD reamer
The cutting material
should

 Have good heat resistant


property at high temperatures.

 Have good repeatability.

 No built up edge formation.

 Performs better at high cutting


parameters (200-250m/min).

 15 times the life of carbide.


Sundaram-Clayton Limited 22 20.08.2010
Die Casting Division, Padi Plant
Step 5- Implementation and verification

Solution identified – PCD Reamer


BENEFITS

Cycle time Tool life Tool cost / component

25150 0.65
180
>15 Times

No. of components
171 20000
170 >20% 20150 0.6 15%

Cost in Rupees
0.6
Time in Secs

160
15150
150 0.55
10150
140
131 0.5
5150 0.5
130
1200
120 150
0.45
Before After Before After
Before After

Cycle time Tool life : 15000 Nos Speed :7900 RPM


saved – 40 Secs Cp =2.67 Feed : 0.25mm/rev

Sundaram-Clayton Limited 23 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

3.Theme C – Combining tools


Description : Elimination of Roll pin pre drill

BEFORE AFTER BENEFITS

T1 - Centre drill T1 - Centre drill with 1.7


Cycle time
T2 - 1.7 Pre drill predrill 135 131

T3 - 1.955 Reamer T2 - 1.955 Reamer


130
20 %

Time in Secs
125
120
115
110 106
105
100
95
90
Before After

Cycle time saved – 25 Secs

3 Tools reduced to 2
and parameters
optimized • No significant impact
on Tool cost / component

Tool cost : Rs. 488 Tool cost : Rs. 475

Sundaram-Clayton Limited 24 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

Cycle time reduction in VMC – operation wise

240
220 17 >50 %
16
200 Takt
19
180 E&C 16
time
160 achieve
Time in Secs

140
57 d
R
120 Takt time – 108 Secs
100
23 17
80 11
R 26 13
0
60 13
40 R 27 13
11
20 28 11
R 13
0
Before improvement After improvement

Milling 6.8 drilling M8 Tapping 4 dia drill


4.395 reaming 1.6 centre drill 1.7 drill 1.95 reamer
Manual time Takt time

Sundaram-Clayton Limited 25 20.08.2010


Die Casting Division, Padi Plant
How to de-bottleneck ?

Diffuser side machining in CNC lathe 1

Sundaram-Clayton Limited 26 20.08.2010


Die Casting Division, Padi Plant
Step 2- Understanding the current situation

Machine time - existing

300

250 Current Takt time – 243 Secs

200 12

150
Time in Secs

Future Takt time –108 Secs


100 199 17
13
60
50 89
81
34
0

Outlet m/cing
Diffuser

Inlet m/cing

Milling,drilling
m/cing

& reaming
AUTO TIME

MANUAL TIME

Sundaram-Clayton Limited 27 20.08.2010


Die Casting Division, Padi Plant
Step 3- Selecting opportunities

Diffuser side machining


Cycle time details with Improvements identified
Operation Speed Feed Cycle Proposed
S.NO description rpm mm/rev time improvement The me
Step cutter to finish
1 Ris er m/c 1600 0.15 42 in s ingle pass A & B
2 Roughing 2000 0.3 38 Dia 25 to 32 shank B
3 Circlip grooving 800 0.06 24 Carbide to PCD A & B
4 Pre openout-4g 1500 0.1 12 Eliminate
Combination tooling
& parameter
5 Openout 'v' tool 1200 0.15 18 optimization A,B &C
6 Angular grooving 600 0.05 22
Parameter
7 Finishing vcmw 1800 0.15 38 optimization B
Door opening &
8 closing 5
199

200 38
180
160 22
Time in Secs

18
140
12
120
24
Future Takt time -108 Secs
100
80
58
60
40
20 42

0
Before improvem ent
Pre machining Roughing Circlip grooving
Pre open out Open out Angular grooving
Finishing Takt time

Sundaram-Clayton Limited 28 20.08.2010


Die Casting Division, Padi Plant
Step 3- Selecting opportunities

#2 Diffuser side machining


Cycle time details with Improvements identified

Operation Speed Feed Cycle


S.NO description rpm mm/rev time
1 Riser m/c 1600 0.15 42 1
2 Roughing 2000 0.3 38 2
3 Circlip grooving 800 0.06 24
4 Pre openout-4g 1500 0.1 12
5 Openout 'v' tool 1200 0.15 18 3
6 Angular grooving 600 0.05 22
7 Finishing vcmw 1800 0.15 38
Door opening &
8 closing 5
199

Sundaram-Clayton Limited 29 20.08.2010


Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

1.Theme A – Improved tooling & B – Parameter optimization


Description : Elimination of multiple passes in riser machining
due to large material removal in GDC
BEFORE OBSERVATIONS

Single point turning tool  Lower depth of cut

 Lower parameter.
Speed :1600 RPM
Feed : 0.15mm/rev

 More no. of passes - 12

Sundaram-Clayton Limited 30 20.08.2010


Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

Improvement details ( Theme A& B)

Description : Elimination of multiple passes in riser machining (due to large


material removal in GDC)
Idea 1 Idea 2
Option 1 – U drill with bigger Multipoint stepped insert type
insert progressive cutter.

 No of passes reduced from


 Load gets uniformly distributed
12 to 6
between the 5 steps
 But tool life reduced due to
 The subsequent step gets engaged
higher depth of cut.
only when the previous step finishes
its cut.Hence the operation is smooth
 Multiple passes to single pass.
 High cutting parameter.

Sundaram-Clayton Limited 31 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

Improvement details ( Themes A& B)


Description : Elimination of multiple passes in riser machining due to large
material removal in GDC
BENEFITS
Tool life Tool cost / component
Cycle time
210 25150 0.45
199 >10 % >15 Times 20000 10 Times
200

No. of components
20150
Time in Secs

Cost in Rupees
190
15150
180 173
10150
170

160 5150 0.05


1200
150 150 0
Before After Before After Before After
86 86

Cycle time saved – 26 Secs Before After


Holder cost(Rs) 9100 23000
Insert (Rs.) 542 728

Holder is one time investment.

Sundaram-Clayton Limited 32 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

2.Theme A – Improved tooling & B – Parameter optimization

Description : Alternate holder for roughing operation ( to improve rigidity)

BEFORE AFTER BENEFITS


SCLC Single point SCLC Single point
Cycle time
turning holder turning holder
of shank Dia 25 of shank Dia 32
180
173
15 %
175
35 mm 170
35 mm 165
160
155 153
150
145
140
32 mm 135
25 mm 130
Before After
86 86

Speed :2000 RPM Speed :2800 RPM Cycle time saved – 20 Secs
Feed : 0.3mm/rev Feed : 0.6mm/rev

Sundaram-Clayton Limited 33 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

Process capability report for critical dimension


G Dimension

9.037
8.997 USL G Dimension
8.957
8.917
8.877
8.837 Cp – 3.607
8.797
8.757 Cpk- 3.390
8.717 LSL
8.677
8.637
1
3

5
7

9
11

13
15

17

19
21

23
25

27
29

31
We monitor the performance of the capable dimensions
using a run chart.
Bearing bore diameter

80.04 USL
Bearing bore
80.02 Diameter

80 Cp – 2.73
LSL
Cpk- 2.44
79.98
1

7
9

11

13

15

17

19

21

23
25

27

29

31

Sundaram-Clayton Limited 34 20.08.2010


Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

3.Themes A& C –Combination & improved tooling & B – Parameter optimization

Description : Pre open out tool

BEFORE PROCESS / TECHNOLOGY AFTER


•Groove open out- ‘V’ • ‘V’ Cum Flat tool
tool Open
out

Back Finishing
Tool cost –
Rs1750 chamfer

•Groove finishing - Flat


tool
Both open out and
Process finishing done in the
 Combining both the V same tool.
Tool cost – and the flat tools. Cpk –1.8
Rs 2079  Reduces one tool
Indexing time. Tool cost – Rs 2850
Tooling cost – Rs 3829
Sundaram-Clayton Limited 35 20.08.2010
Die Casting Division, Padi Plant
Step 5- Implementation and verification

Improvement details (Theme A , B & C)


Description : Elimination of pre-open out tool

BENEFITS
Cycle time Tool life Tool cost / component
145
142 1750
8% 2.5

No. of components
1450 1500
140 1550
2.4
24 %

Cost in Rupees
1350
Time in Secs

135 1150
130 950
130 1.9
750 1.9
125 550
350
120 150 1.4
Before After Before After Before After

Cycle time saved -12 Secs


Before After
Tool cost(Rs) 3829 2850

Tool cost saving – Rs. 979

Sundaram-Clayton Limited 36 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

Cycle time reduction Diffuser side machining- after improvement

300
Gap of
250
12 Secs
211 >40 %
200 12
Time in Secs

15 0

120
12
10 0 199
Takt time – 108 Secs

50 108

0
Before

improvement
After implementation of all identified improvements After

There was a still a gap of 12 Secs to achieve the Takt time


Sundaram-Clayton Limited 37 20.08.2010
Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

Phase 2 : Study of dimensions, achieved in diffuser side machining


Tolerance
Dimension <50microns 50-100 Microns >100 Microns

Diameter 80.035/80
Dia W 39.55/39.45

F Dimn 8.45/8.35
Groove position
4.795/4.745
Groove width
2.125/2.075

G dimn 9.329/9.229
Angular groove
width 2.75/3.25

Observation & Inference : Tolerance of angular groove


is wider (above 200 microns) and hence this could be
done in a different set up
Sundaram-Clayton Limited 38 20.08.2010
Die Casting Division, Padi Plant
Step 4- Analysis & Improvement

Solution identified – Transfer angular grooving operation


from diffuser side machining to inlet side machining

BEFORE PROCESS / TECHNOLOGY AFTER

•Forward machining •Reverse machining


Done in diffuser side Done in inlet side
machining machining
36mm

56mm

 Insert direction reversed.


 The bore ID is 42mm.
 Tool holder modified to
suit the application

Sundaram-Clayton Limited 39 20.08.2010


Die Casting Division, Padi Plant
Step 5- Implementation and verification

Angular grooving operation transferred from diffuser side machining


to inlet side machining to de-bottleneck it.

BENEFITS

Cycle time

120
108
20 %
110
Time in Secs

100

90 86

80

70

60
Before After

Cycle time saved - 22 Secs

*No significant impact on Tool life & Tool cost/component

Sundaram-Clayton Limited 40 20.08.2010


Die Casting Division, Padi Plant
Step 5 - Verification

Cycle time reduction in diffuser side machining – operation wise

240
220 12 >50 % Takt time
200 R was
38
180
achieved
22
Time in Secs

160
E,C & R 18
140
12
120 Takt time – 108 Secs
R 24
100
12
80
R 58 23
60 0
11
0
40 13

42 18
20 R&S
16
0
Before improvement After improvement

Pre machining Roughing Circlip grooving


Pre open out Open out Angular grooving
Finishing Manual time Takt time

Sundaram-Clayton Limited 41 20.08.2010


Die Casting Division, Padi Plant
Step 5 - Verification

Machine time- After improvement

300

Op 30 Becomes
250 Op 20 was a bottleneck
debottlenecked
200
Time in Secs

150
#3 Takt time – 108 Secs
13
100 17
12

60
50 103
86 89

34
0
Op 20

Op 30

Op 40

Op 50
AUTO TIME
Consistent output obtained from op :20.
Op 30 becomes bottleneck due to transfer of grooving operation
MANUAL TIME

Sundaram-Clayton Limited 42 20.08.2010


Die Casting Division, Padi Plant
Step 3- Selecting opportunities

#3 Inlet side machining


Cycle time details with Improvements identified
(Horizontal deployment of learning)
BEFORE AFTER
Operation Cycle Proposed Cycle
S.NO description Speed Feed time improvement Speed Feed time Theme
Eliminate based on
1 OD rough turning 1600 0.15 32 stock removal 0
Single tool gippa
2 OD finishing 1700 0.2 26 rough and finish 2000 0.25 38 B
3 Facing 25 boring 1600 0.15 23 Dia 32 holder 2000 0.25 11 B
Shifted to this
4 Angular grooving operation 600 0.05 22
81 71

Takt time was achieved

A - Improved tooling B – Parameter optimization C – Combining tools

Sundaram-Clayton Limited 43 20.08.2010


Die Casting Division, Padi Plant
Step 5- Verification

Machine time – achieved after improvements

200

150

Future Takt time – 108 Secs


Time in Secs

100 17
12
13
60
50
86 89
71

34

0
Op 20

Op 30

Op 40

Op 50
AUTO TIME

MANUAL TIME
Consistent output obtained from all four operations.

Sundaram-Clayton Limited 44 20.08.2010


Die Casting Division, Padi Plant
Step 5- Verification

Man – machine time (After improvement)

300

Existing Takt time – 243 Secs


250

200
Time in Secs

150
Future Takt time – 108 Secs
100 12 17
13
60
50 86 89
70 71 60 10 60 72
34
50
30 25 15 30
0 7 9
Gauging

final
NP drilling

Outlet m/c

Washing
Diffuser

Air cleaning

Inlet m/cing

Deburring

Aircleaning

Deburring

Air cleaning
operations
Marking

m/cing

Leak testing
VMC
ing

AUTO TIME

MANUAL TIME

Sundaram-Clayton Limited 45 20.08.2010


Die Casting Division, Padi Plant
Step 6- Standardization

Example of Standardization (PCD reamer)

Other standardization points :


 Operation standard and Quality control and Process chart.
 FMEA.
 Man – machine chart.
 Tool list.
Sundaram-Clayton Limited 46 20.08.2010
Die Casting Division, Padi Plant
Step 7- Horizontal deployment

Horizontal deployment status

Implemented

NA - Not applicable

Sundaram-Clayton Limited 47 20.08.2010


Die Casting Division, Padi Plant
Step 6 – Results & Standardization

Summary of Improvements
Cell capacity Vs Demand Output per Man per Hour
Number of components

Number of components
17000 8.75
15900 15900 9
15000
>60 %
13000 >100 % 7

11000
5.25
9000 5
7700
7000

5000 3

Before

After
After
Before

Demand before
Demand after

Benefits :
Customer demand met on time without additional investment of Rs.50
lakhs.
Sales to gross fixed asset has improved from 3.2 to 7.25 (126%
improvement)
Productivity (Output/man/hour) improved by 60 %

Sundaram-Clayton Limited 48 20.08.2010


Die Casting Division, Padi Plant
Intangible benefits
1. High process capability of critical characteristics
achieved

2. Improved utilization of man and machines achieved.

Key learning
1. Progressive multi point stepped cutter
(innovative idea).
2. Parabolic drill ( innovative idea).
3. V cum flat combination insert (innovative idea).

Sundaram-Clayton Limited 49 20.08.2010


Die Casting Division, Padi Plant
Future plans
 Reduce manual time through introduction of
rotary fixture in VMC and through low cost
automation.

Sundaram-Clayton Limited 50 20.08.2010


Die Casting Division, Padi Plant
End of presentation

Sundaram-Clayton Limited 51 20.08.2010


Die Casting Division, Padi Plant

Das könnte Ihnen auch gefallen