Sie sind auf Seite 1von 30

DETAILED ESTIMATE

Materials Recovery Facility


Tunga, Leyte

ITEM 100(2) - Clearing and Grubbing


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00
B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00
C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,726.08

Foreman 1 3.00 Days @ P 588.24 P 1,764.72


Unskilled Laborer 3 3.00 Days @ P 329.04 P 2,961.36
P 4,726.08

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 4,726.08


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,476.90
OCM - - - - - - - - - - - P 708.91
Contractor's Profit - - 472.61
VAT - - - - - - - - - - - 295.38
Mobilization - - - - - - -
P 1,476.90
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 6,202.98
P 6,202.98
Unit Cost =
1.00
= P 6,202.98

Page 1 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 903(1) - Forms and Falseworks


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 10,620.00

Assorted Coco Lumber 500.00 Bd. Ft. @ P 15.00 P 7,500.00


1/4" Thk. Ordinary Plywood 10.00 Pc. @ P 270.00 P 2,700.00
CW Nails, Assorted 10.00 Kg. @ P 42.00 P 420.00
P 10,620.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 13,788.40

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Carpenter 2 5.00 Days @ P 426.64 P 4,266.40
Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 13,788.40

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 24,408.40


INDIRECT COST - - - - - - - - - - - - - - - - - - P 7,627.63
OCM - - - - - - - - - - - P 3,661.26
Contractor's Profit - - 2,440.84
VAT - - - - - - - - - - - 1,525.53
Mobilization - - - - - - -
P 7,627.63
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 32,036.03
P 32,036.03
Unit Cost =
1.00
= P 32,036.03

Page 2 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 803(1)a - Structure Excavation, Common Soil


Quantity = 62.00 cu.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 9,522.00

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 9,522.00

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 9,522.00


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,975.63
OCM - - - - - - - - - - - P 1,428.30
Contractor's Profit - - 952.20
VAT - - - - - - - - - - - 595.13
Mobilization - - - - - - -
P 2,975.63
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 12,497.63
P 12,497.63
Unit Cost =
62.00
= P 201.57

Page 3 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1705(1) - Fill and Backfill


Quantity = 62.00 cu.m.
Backfill = 10.00 cu.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,800.00

Mixed of Sand and Gravel 15.00 Cu.m. @ P 320.00 P 4,800.00


P 4,800.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,968.00

Plate Compactor 2.00 Days @ P 984.00 P 1,968.00


P 1,968.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 7,757.28

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 7,757.28

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 14,525.28


INDIRECT COST - - - - - - - - - - - - - - - - - - P 4,539.15
OCM - - - - - - - - - - - P 2,178.79
Contractor's Profit - - 1,452.53
VAT - - - - - - - - - - - 907.83
Mobilization - - - - - - -
P 4,539.15
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 19,064.43
P 19,064.43
Unit Cost =
62.00
= P 307.49

Page 4 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 900(1) - Reinforced Concrete


Quantity = 228.00 cu.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 341,466.00

Portland Cement 591.00 Bag @ P 257.00 P 151,887.00


Coarse Sand 63.00 Cu.m. @ P 615.00 P 38,745.00
Gravel, 3/4 62.00 Cu.m. @ P 870.00 P 53,940.00
12mmØ Def. Bar Grade 40 1,813.00 Kg. @ P 42.00 P 76,146.00
10mmØ Def. Bar Grade 40 444.00 Kg. @ P 42.00 P 18,648.00
No. 16 G. I. Tie Wire 50.00 Kg. @ P 42.00 P 2,100.00
P 341,466.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,212.00

Concrete Mixer, 1.0 Bagger 2.00 Days @ P 1,376.00 P 2,752.00


Concrete Vibrator 2.00 Days @ P 730.00 P 1,460.00
P 4,212.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 41,365.20

Foreman 1 15.00 Days @ P 588.24 P 8,823.60


Mason/Steelman 2 15.00 Days @ P 426.64 P 12,799.20
Unskilled Laborer 4 15.00 Days @ P 329.04 P 19,742.40
P 41,365.20

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 387,043.20


INDIRECT COST - - - - - - - - - - - - - - - - - - P 120,951.00
OCM - - - - - - - - - - - P 58,056.48
Contractor's Profit - - 38,704.32
VAT - - - - - - - - - - - 24,190.20
Mobilization - - - - - - -
P 120,951.00
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 507,994.20
P 507,994.20
Unit Cost =
228.00
= P 2,228.04

Page 5 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1046(2)a - CHB Non Load Bearing (including Reinforcing Steel), 100 mm
Quantity = 167.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 67,563.00

Portland Cement 93.00 Bag @ P 257.00 P 23,901.00


Fine Sand 8.00 Cu.m. @ P 615.00 P 4,920.00
4'' Thk. CHB 2,161.00 Pc. @ P 12.00 P 25,932.00
10mmØ Def. Bar Grade 40 300.00 Kg. @ P 42.00 P 12,600.00
No. 16 G. I. Tie Wire 5.00 Kg. @ P 42.00 P 210.00
P 67,563.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 13,788.40

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Mason/Steelman 2 5.00 Days @ P 426.64 P 4,266.40
Unskilled Laborer 4 5.00 Days @ P 329.04 P 6,580.80
P 13,788.40

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 81,351.40


INDIRECT COST - - - - - - - - - - - - - - - - - - P 25,422.31
OCM - - - - - - - - - - - P 12,202.71
Contractor's Profit - - 8,135.14
VAT - - - - - - - - - - - 5,084.46
Mobilization - - - - - - -
P 25,422.31
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 106,773.71
P 106,773.71
Unit Cost =
167.00
= P 639.36

Page 6 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1027(1) - Cement Plaster Finish


Quantity = 333.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 20,138.00

Portland Cement 64.00 Bag @ P 257.00 P 16,448.00


Fine Sand 6.00 Cu.m. @ P 615.00 P 3,690.00
P 20,138.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 5,018.88

Foreman 1 3.00 Days @ P 588.24 P 1,764.72


Mason 1 3.00 Days @ P 426.64 P 1,279.92
Unskilled Laborer 2 3.00 Days @ P 329.04 P 1,974.24
P 5,018.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 25,156.88


INDIRECT COST - - - - - - - - - - - - - - - - - - P 7,861.53
OCM - - - - - - - - - - - P 3,773.53
Contractor's Profit - - 2,515.69
VAT - - - - - - - - - - - 1,572.31
Mobilization - - - - - - -
P 7,861.53
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 33,018.41
P 33,018.41
Unit Cost =
333.00
= P 99.15

Page 7 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 203,498.00

6mm x 50mm x 50mm Angle Bar 1,141.00 Kg. @ P 52.00 P 59,332.00


6mm x 38mm x 38mm Angle Bar 753.00 Kg. @ P 52.00 P 39,156.00
10mm Thk. Steel Plate 168.00 Kg. @ P 46.00 P 7,728.00
6mm Thk. Steel Plate 700.00 Kg. @ P 46.00 P 32,200.00
2" x 4" (2.0 mm) C-purlins 910.00 Kg. @ P 50.00 P 45,500.00
16mm dia. Tension rod 38.00 Kg. @ P 50.00 P 1,900.00
Turnbuckle Std. for 16mmØ Rod 8.00 Pc. @ P 230.00 P 1,840.00
12mmØ x 150mm Anchor Bolts w/ HD Washers 48.00 Pc. @ P 55.00 P 2,640.00
12mm Ø Sag Rod 43.00 Kg. @ P 50.00 P 2,150.00
Red Oxide Metal Primer 6.00 Gal. @ P 590.00 P 3,540.00
Welding Rod 29.00 Kg. @ P 110.00 P 3,190.00
4" Paint Brush 5.00 Pc. @ P 55.00 P 275.00
3" Paint Brush 3.00 Pc. @ P 55.00 P 165.00
Paint Thinner 2.00 Gal. @ P 270.00 P 540.00
Oxygen ( refill / tank 1800 psi) 1.00 cylinder @ P 1,056.00 P 1,056.00
Acetylene ( refill / tank 240 psi ) 1.00 cylinder @ P 2,286.00 P 2,286.00
P 203,498.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 29,215.20

Welding Machine (300 Amp) 6.00 Days @ P 2,968.00 P 17,808.00


Acetylene and Oxygen Outfit 2.00 Days @ P 363.60 P 727.20
Generator Set, 51-100KW 8.00 Days @ P 1,335.00 P 10,680.00
P 29,215.20

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 50,411.12

Foreman 1 17.00 Days @ P 588.24 P 10,000.08


Welder 2 17.00 Days @ P 426.64 P 14,505.76
Semi-Skilled Laborer 4 17.00 Days @ P 380.96 P 25,905.28
P 50,411.12

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 283,124.32


INDIRECT COST - - - - - - - - - - - - - - - - - - P 88,476.35
OCM - - - - - - - - - - - P 42,468.65
Contractor's Profit - - 28,312.43
VAT - - - - - - - - - - - 17,695.27
Mobilization - - - - - - -
P 88,476.35
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 371,600.67
P 371,600.67
Unit Cost =
#N/A
= #N/A

Page 8 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 51,584.00

Fiber Cement Board 4.5mm Thk. 58.00 Pc. @ P 441.00 P 25,578.00


1/2'' x 12'' x 8' Fiber Cement Bd. Sanepa 23.00 Pc. @ P 384.00 P 8,832.00
Furring Channel 0.80x12x38x5000mm 70.00 Pc. @ P 92.00 P 6,440.00
Carrying/Hanger Channel 0.80x12x38x5000mm 32.00 Pc. @ P 132.00 P 4,224.00
0.30 x 1.20m Pre-fab Wood Ceiling Vent Slots 10.00 Pc. @ P 462.00 P 4,620.00
Blind Rivets 1,680.00 Pc. @ P 0.40 P 672.00
Self Drilling Screw 1,740.00 Pc. @ P 0.70 P 1,218.00
P 51,584.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 12,562.56

Foreman 1 9.00 Days @ P 588.24 P 5,294.16


Carpenter 1 9.00 Days @ P 426.64 P 3,839.76
Semi-Skilled Laborer 1 9.00 Days @ P 380.96 P 3,428.64
P 12,562.56

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 64,146.56


INDIRECT COST - - - - - - - - - - - - - - - - - - P 20,045.80
OCM - - - - - - - - - - - P 9,621.98
Contractor's Profit - - 6,414.66
VAT - - - - - - - - - - - 4,009.16
Mobilization - - - - - - -
P 20,045.80
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 84,192.36
P 84,192.36
Unit Cost =
#N/A
= #N/A

Page 9 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 3,525.75

Marine Plywood, 4' X 8' X 3/4" 3 Pc. @ P 1,130.00 P 3,390.00


Wood Glue (Liter) 0.25 Liter @ P 207.00 P 51.75
Assorted Nails 2 Kg. @ P 42.00 P 84.00
P 3,525.75

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,395.84

Foreman 1 1.00 Day @ P 588.24 P 588.24


Carpenter 1 1.00 Day @ P 426.64 P 426.64
Semi-Skilled Laborer 1 1.00 Day @ P 380.96 P 380.96
P 1,395.84

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 4,921.59


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,538.00
OCM - - - - - - - - - - - P 738.24
Contractor's Profit - - 492.16
VAT - - - - - - - - - - - 307.60
Mobilization - - - - - - -
P 1,538.00
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 6,459.59
P 6,459.59
Unit Cost =
#N/A
= #N/A

Page 10 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1014(1)a1 - Prepainted Metal Sheets, below 0.427 mm, Corrugated, Short Span
Quantity = 294.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 255,978.00

Corspan 0.50x1220mm Pre-painted Long span Roof 294.00 Sq.m. @ P 650.00 P 191,100.00
Pre-Painted Ridge Roll 0.70x2440mm 42.00 Ln.m @ P 350.00 P 14,700.00
1/2'' x 12'' x 8' Hardi Sanepa 56.00 Pc. @ P 377.00 P 21,112.00
1.25m Double Sided Insulation Foil 294.00 Mts. @ P 64.00 P 18,816.00
Silicon Sealant 8.00 Tube @ P 350.00 P 2,800.00
2 1/2" Metal Tek Screw 2,220.00 Pc. @ P 2.50 P 5,550.00
Touch-up Paint 4.00 Qrt. @ P 380.00 P 1,520.00
Blind Rivets 950.00 Pc. @ P 0.40 P 380.00
P 255,978.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 10,498.00

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Roof Installer 2 5.00 Days @ P 426.64 P 4,266.40
Unskilled Laborer 2 5.00 Days @ P 329.04 P 3,290.40
P 10,498.00

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 266,476.00


INDIRECT COST - - - - - - - - - - - - - - - - - - P 83,273.75
OCM - - - - - - - - - - - P 39,971.40
Contractor's Profit - - 26,647.60
VAT - - - - - - - - - - - 16,654.75
Mobilization - - - - - - -
P 83,273.75
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 349,749.75
P 349,749.75
Unit Cost =
294.00
= P 1,189.63

Page 11 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1032 - Painting, Varnishing and Other Related Works


Quantity = 77.00 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 48,402.00

Red Oxide Metal Primer 8.00 Gal. @ P 590.00 P 4,720.00


Concrete Neutralizer 4.00 Ltr. @ P 280.00 P 1,120.00
Waste Cotton/Stuppa 2.00 Kg. @ P 67.00 P 134.00
Flat Wall Enamel Paint 7.00 Gal. @ P 560.00 P 3,920.00
Quick Dry Enamel Paint 2.00 Gal. @ P 684.00 P 1,368.00
Acrytex Cast 4.00 Gal. @ P 486.00 P 1,944.00
Plasolux Glazing Putty 1.00 Gal. @ P 632.00 P 632.00
Flat Latex Paint 17.00 Gal. @ P 552.00 P 9,384.00
Semi-Gloss Latex Paint 25.00 Gal. @ P 590.00 P 14,750.00
Acrylic Tinting Colors (1/4 liter) 5.00 Can @ P 200.00 P 1,000.00
Masonry Putty 15.00 Gal. @ P 312.00 P 4,680.00
Fiberglass Tape 4.00 Roll @ P 90.00 P 360.00
Paint Thinner 5.00 Gal. @ P 270.00 P 1,350.00
Sand Paper 55.00 Pc. @ P 28.00 P 1,540.00
Assorted Paint Brush/Roller 1.00 lot @ P 1,500.00 P 1,500.00
P 48,402.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 15,424.08

Foreman 1 7.00 Days @ P 588.24 P 4,117.68


Painter 2 7.00 Days @ P 426.64 P 5,972.96
Semi-Skilled Laborer 2 7.00 Days @ P 380.96 P 5,333.44
P 15,424.08

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 63,826.08


INDIRECT COST - - - - - - - - - - - - - - - - - - P 19,945.65
OCM - - - - - - - - - - - P 9,573.91
Contractor's Profit - - 6,382.61
VAT - - - - - - - - - - - 3,989.13
Mobilization - - - - - - -
P 19,945.65
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 83,771.73
P 83,771.73
Unit Cost =
77.00
= P 1,087.94

Page 12 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1010(2)a - Doors, Flush


Quantity = 13.44 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 18,765.60

Flush Type Solid Core Door 8.40 Sq.m @ P 1,700.00 P 14,280.00


PVC-Flush Door 5.04 Sq.m @ P 890.00 P 4,485.60
P 18,765.60

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,014.88

Foreman 1 1.00 Day @ P 588.24 P 588.24


Carpenter 1 1.00 Day @ P 426.64 P 426.64
P 1,014.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 19,780.48


INDIRECT COST - - - - - - - - - - - - - - - - - - P 6,181.40
OCM - - - - - - - - - - - P 2,967.07
Contractor's Profit - - 1,978.05
VAT - - - - - - - - - - - 1,236.28
Mobilization - - - - - - -
P 6,181.40
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 25,961.88
P 25,961.88
Unit Cost =
13.44
= P 1,931.69

Page 13 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1010(1) - Frames, Jambs, Sills, Head, Transoms and Mullions


Quantity = 4.00 set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,500.00

Flush Type Solid Core Door Frame 2 Set @ P 500.00 P 1,000.00


PVC-Flush Door Frame 2 Set @ P 250.00 P 500.00
P 1,500.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,014.88

Foreman 1 1.00 Day @ P 588.24 P 588.24


Carpenter 1 1.00 Day @ P 426.64 P 426.64
P 1,014.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 2,514.88


INDIRECT COST - - - - - - - - - - - - - - - - - - P 785.90
OCM - - - - - - - - - - - P 377.23
Contractor's Profit - - 251.49
VAT - - - - - - - - - - - 157.18
Mobilization - - - - - - -
P 785.90
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 3,300.78
P 3,300.78
Unit Cost =
4.00
= P 825.20

Page 14 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 24,843.00

D1 - 1/4 Thk. 2.10 x 1.70m Glass on Aluminum


Frame (Analok Fin.) 3.57 Sq.m. @ P 4,550.00 P 16,243.50
D2 - 1/4 Thk. 2.10 x 0.90m Glass on Aluminum
Frame (Analok Fin.) 1.89 Sq.m. @ P 4,550.00 P 8,599.50
P 24,843.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,687.84

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Carpenter 1 2.00 Days @ P 426.64 P 853.28
Unskilled Laborer 1 2.00 Days @ P 329.04 P 658.08
P 2,687.84

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 27,530.84


INDIRECT COST - - - - - - - - - - - - - - - - - - P 8,603.39
OCM - - - - - - - - - - - P 4,129.63
Contractor's Profit - - 2,753.08
VAT - - - - - - - - - - - 1,720.68
Mobilization - - - - - - -
P 8,603.39
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 36,134.23
P 36,134.23
Unit Cost =
#N/A
= #N/A

Page 15 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1009(1)a - Jalousie Windows, Glass


Quantity = 18.38 sq.m.

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 9,882.00

W1 - 1.80m X 1.20m Jalousie Window (3-sets) 6.48 Sq.m. @ P 540.00 P 3,499.20


W2 - 1.20m X 1.20m Jalousie Window (5-sets) 7.20 Sq.m. @ P 540.00 P 3,888.00
W3 - 0.70m X1.20m Jalousie Window (4-sets) 3.36 Sq.m. @ P 540.00 P 1,814.40
W4 - 0.70m X0.60m Jalousie Window (3-sets) 1.26 Sq.m. @ P 540.00 P 680.40
P 9,882.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,029.76

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Glass Installer 1 2.00 Days @ P 426.64 P 853.28
P 2,029.76

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 11,911.76


INDIRECT COST - - - - - - - - - - - - - - - - - - P 3,722.43
OCM - - - - - - - - - - - P 1,786.76
Contractor's Profit - - 1,191.18
VAT - - - - - - - - - - - 744.49
Mobilization - - - - - - -
P 3,722.43
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 15,634.19
P 15,634.19
Unit Cost =
18.38
= P 850.61

Page 16 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 23,511.86

Granite/Ceramic Tiles Sq.m. @ P 500.00 P 0


200 x 200mm Wall Tiles 750 Pc. @ P 12.00 P 9,000.00
200 x 200mm Floor Tiles 213 Pc. @ P 16.00 P 3,408.00
Tile Adhesive 25Kg/Bag 16 Bag @ P 450.00 P 7,200.00
Tile Trim 2.40m 15 Pc. @ P 52.00 P 780.00
Tile Grout 2Kg/Bag 31 Bag @ P 80.00 P 2,480.00
Tread Nosing/Edging 3.0m 1.26 Pc. @ P 511.00 P 643.86
P 23,511.86

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,485.00

Generator Set, 51-100KW 3.00 Days @ P 1,335.00 P 4,005.00


Grinder 2.00 Days @ P 240.00 P 480.00
P 4,485.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 33,051.60

Foreman 1 15.00 Days @ P 588.24 P 8,823.60


Mason 2 15.00 Days @ P 426.64 P 12,799.20
Semi-skilled Laborer 2 15.00 Days @ P 380.96 P 11,428.80
P 33,051.60

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 61,048.46


INDIRECT COST - - - - - - - - - - - - - - - - - - P 19,077.65
OCM - - - - - - - - - - - P 9,157.27
Contractor's Profit - - 6,104.85
VAT - - - - - - - - - - - 3,815.53
Mobilization - - - - - - -
P 19,077.65
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 80,126.11
P 80,126.11
Unit Cost =
#N/A
= #N/A

Page 17 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1001(8) - Sewer Line Works


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 8,352.00

4"Ø PVC Pipe S-1000 10.00 Pc. @ P 620.00 P 6,200.00


4"Ø PVC 90° Tee 3.00 Pc. @ P 135.00 P 405.00
4" Ø PVC Cleanout w/ Plug and Sealing Ring 3.00 Pc. @ P 59.00 P 177.00
4" Ø PVC 45° Single Branch Wye 5.00 Pc. @ P 126.00 P 630.00
4" Ø PVC Coupling 5.00 Pc. @ P 74.00 P 370.00
Solvent Cement 400 cc 3.00 Can @ P 190.00 P 570.00
P 8,352.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Plumber 1 1.00 Day @ P 426.64 P 426.64
Semi-skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 10,128.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 3,165.25
OCM - - - - - - - - - - - P 1,519.32
Contractor's Profit - - 1,012.88
VAT - - - - - - - - - - - 633.05
Mobilization - - - - - - -
P 3,165.25
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 13,294.05
P 13,294.05
Unit Cost =
1.00
= P 13,294.05

Page 18 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1001(9) - Storm Drainage and Downspout


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 7,271.00

4"Ø PVC Pipe S-1000 8.00 Pc. @ P 620.00 P 4,960.00


2"Ø PVC Pipe S-1000 4.00 Pc. @ P 291.00 P 1,164.00
4" Ø PVC Coupling 5.00 Pc. @ P 74.00 P 370.00
2"Ø x 45° Elbow 1.00 Pc. @ P 14.00 P 14.00
2"Ø PVC Wye (Single Branch) 1.00 Pc. @ P 81.00 P 81.00
2"Ø x 90° Elbow 8.00 Pc. @ P 14.00 P 112.00
Solvent Cement 400 cc 3.00 Can @ P 190.00 P 570.00
P 7,271.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Plumber 1 1.00 Day @ P 426.64 P 426.64
Semi-skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 9,047.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,827.44
OCM - - - - - - - - - - - P 1,357.17
Contractor's Profit - - 904.78
VAT - - - - - - - - - - - 565.49
Mobilization - - - - - - -
P 2,827.44
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 11,875.24
P 11,875.24
Unit Cost =
1.00
= P 11,875.24

Page 19 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1002(5) - Plumbing Fixtures


Quantity = 1.00 Lump Sum

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 14,264.00

Water Closet w/ Tank Fitttings & Accessories 1.00 Set @ P 6,500.00 P 6,500.00
Lavatory w/ Fitttings & Accessories 1.00 Set @ P 6,500.00 P 6,500.00
4''x4'' Floor Drain Stainless 1.00 Pc. @ P 84.00 P 84.00
Faucet (Chrome) 2.00 Pc. @ P 460.00 P 920.00
Tissue Holder 1.00 Pc. @ P 260.00 P 260.00
P 14,264.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 6,979.20

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Plumber 1 5.00 Days @ P 426.64 P 2,133.20
Semi-skilled Laborer 1 5.00 Days @ P 380.96 P 1,904.80
P 6,979.20

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 21,243.20


INDIRECT COST - - - - - - - - - - - - - - - - - - P 6,638.50
OCM - - - - - - - - - - - P 3,186.48
Contractor's Profit - - 2,124.32
VAT - - - - - - - - - - - 1,327.70
Mobilization - - - - - - -
P 6,638.50
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 27,881.70
P 27,881.70
Unit Cost =
1.00
= P 27,881.70

Page 20 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 6,687.00

32mmØ PPR Pipe 7.00 Pc. @ P 575.00 P 4,025.00


25mmØ PPR Pipe 5.00 Pc. @ P 357.00 P 1,785.00
25mmØ x 90° Elbow 16.00 Pc. @ P 27.00 P 432.00
25mmØ Equal TEE 5.00 Pc. @ P 35.00 P 175.00
32mmØ Coupling 5.00 Pc. @ P 26.00 P 130.00
32mmØ x 25mmØ PPR Reducer 4.00 Pc. @ P 35.00 P 140.00
P 6,687.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Plumber 1 1.00 Day @ P 426.64 P 426.64
Semi-skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 8,463.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,644.94
OCM - - - - - - - - - - - P 1,269.57
Contractor's Profit - - 846.38
VAT - - - - - - - - - - - 528.99
Mobilization - - - - - - -
P 2,644.94
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 11,108.74
P 11,108.74
Unit Cost =
#N/A
= #N/A

Page 21 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

#N/A
Quantity = #N/A #N/A

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 24,118.00

Lockset (kwikset) 9.00 Pc. @ P 1,300.00 P 11,700.00


3" x 4" Ball Bearing Hinge 22.00 Pair @ P 419.00 P 9,218.00
Drawer/ Cabinet Handle 1.00 Lot @ P 1,200.00 P 1,200.00
Cancel Hinge 1.00 Lot @ P 2,000.00 P 2,000.00
P 24,118.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 6,719.60

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Carpenter 1 5.00 Days @ P 426.64 P 2,133.20
Unskilled Laborer 1 5.00 Days @ P 329.04 P 1,645.20
P 6,719.60

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 30,837.60


INDIRECT COST - - - - - - - - - - - - - - - - - - P 9,636.75
OCM - - - - - - - - - - - P 4,625.64
Contractor's Profit - - 3,083.76
VAT - - - - - - - - - - - 1,927.35
Mobilization - - - - - - -
P 9,636.75
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 40,474.35
P 40,474.35
Unit Cost =
#N/A
= #N/A

Page 22 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1100(1)f - (Conduits, Boxes and Fittings) Polyvinyl Chloride Pipes (PVC/uPVC)
Quantity = 150.00 meters

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 3,700.00

Polyvinyl Chloride PVC 15mm Ø 100.00 Mts. @ P 21.00 P 2,100.00


Polyvinyl Chloride PVC 20mm Ø 50.00 Mts. @ P 32.00 P 1,600.00
P 3,700.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,791.68

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Electrician 1 2.00 Days @ P 426.64 P 853.28
Semi-Skilled Laborer 1 2.00 Days @ P 380.96 P 761.92
P 2,791.68

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 6,491.68


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,028.65
OCM - - - - - - - - - - - P 973.75
Contractor's Profit - - 649.17
VAT - - - - - - - - - - - 405.73
Mobilization - - - - - - -
Prepared by: P 2,028.65
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 8,520.33
P 8,520.33
Unit Cost =
WENCESLAO B. NADERA 150.00
Engineer II = P 56.80

Page 23 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1100(4)a - (Conduits, Boxes and Fittings) Conduit Elbow, RSC


Quantity = 76.00 piece

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 5,041.00

15mmØ PVC Elbow 60.00 Pc. @ P 38.00 P 2,280.00


20mmØ PVC Elbow 15.00 Pc. @ P 45.00 P 675.00
Solvent Cement 800 cc 2.00 Can @ P 380.00 P 760.00
#16 G.I. Tiewire 3.00 Kg. @ P 42.00 P 126.00
19mmØ X 3.00m Copper Weld Ground Rod 1.00 Pc. @ P 1,200.00 P 1,200.00
P 5,041.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,395.84

Foreman 1 1.00 Day @ P 588.24 P 588.24


Electrician 1 1.00 Day @ P 426.64 P 426.64
Semi-Skilled Laborer 1 1.00 Day @ P 380.96 P 380.96
P 1,395.84

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 6,436.84


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,011.51
OCM - - - - - - - - - - - P 965.53
Contractor's Profit - - 643.68
VAT - - - - - - - - - - - 402.30
Mobilization - - - - - - -
Prepared by: P 2,011.51
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 8,448.35
P 8,448.35
Unit Cost =
WENCESLAO B. NADERA 76.00
Engineer II = P 111.16

Page 24 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1100(11) - (Conduits, Boxes and Fittings) Octagonal Junction/ Utility Boxes, PVC/uPVC
Quantity = 78.00 piece

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,580.00

Octagonal Junction Box 42.00 Pc. @ P 34.00 P 1,428.00


Utility Box 36.00 Pc. @ P 32.00 P 1,152.00
P 2,580.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,014.88

Foreman 1 1.00 Day @ P 588.24 P 588.24


Electrician 1 1.00 Day @ P 426.64 P 426.64
P 1,014.88

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 3,594.88


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,123.40
OCM - - - - - - - - - - - P 539.23
Contractor's Profit - - 359.49
VAT - - - - - - - - - - - 224.68
Mobilization - - - - - - -
Prepared by: P 1,123.40
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 4,718.28
P 4,718.28
Unit Cost =
WENCESLAO B. NADERA 78.00
Engineer II = P 60.49

Page 25 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1101 - Wires and Wiring Devices-Electrical Wires


Quantity = 1,868.00 meters

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 21,535.00

2.0mm² THHN Wire Stranded 200.00 Mts. @ P 24.00 P 4,800.00


3.5mm² THHN Wire Stranded 250.00 Mts. @ P 29.00 P 7,250.00
5.5mm² THHN Wire Stranded 100.00 Mts. @ P 38.00 P 3,800.00
30mm² THHN Wire 15.00 Mts. @ P 275.00 P 4,125.00
RJ6 Cable Wire 20.00 Mts. @ P 65.00 P 1,300.00
8.0mm² THHN Wire Stranded 5.00 Mts. @ P 52.00 P 260.00
P 21,535.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 15,055.20

Foreman 1 5.00 Days @ P 588.24 P 2,941.20


Electrician 3 5.00 Days @ P 426.64 P 6,399.60
Semi-Skilled Laborer 3 5.00 Days @ P 380.96 P 5,714.40
P 15,055.20

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 36,590.20


INDIRECT COST - - - - - - - - - - - - - - - - - - P 11,434.44
OCM - - - - - - - - - - - P 5,488.53
Contractor's Profit - - 3,659.02
VAT - - - - - - - - - - - 2,286.89
Mobilization - - - - - - -
Prepared by: P 11,434.44
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 48,024.64
P 48,024.64
Unit Cost =
WENCESLAO B. NADERA 1,868.00
Engineer II = P 25.71

Page 26 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1101(7)a1 - Single PoleWall Switch On One Switch Plate


Quantity = 36.00 Set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 8,324.00

Single Pole wall switch on one switch plate 11.00 Set @ P 150.00 P 1,650.00
Duplex(2 single Pole wall switch on one Switch Plate) 2.00 Set @ P 180.00 P 360.00
Duplex Convenience Outlet 16.00 Set @ P 180.00 P 2,880.00
Cable Outlet 1.00 Set @ P 250.00 P 250.00
Aircon Outlet 5.00 Set @ P 350.00 P 1,750.00
Grounding Clamp for 8.0mm² THHN Wire 1.00 Set @ P 550.00 P 550.00
Electrical Tape (Big) 12.00 Roll @ P 32.00 P 384.00
Rubber Tape (Big) 4.00 Roll @ P 125.00 P 500.00
P 8,324.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 1,776.80

Foreman 1 1.00 Day @ P 588.24 P 588.24


Electrician 1 1.00 Day @ P 426.64 P 426.64
Semi-Skilled Laborer 2 1.00 Day @ P 380.96 P 761.92
P 1,776.80

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 10,100.80


INDIRECT COST - - - - - - - - - - - - - - - - - - P 3,156.50
OCM - - - - - - - - - - - P 1,515.12
Contractor's Profit - - 1,010.08
VAT - - - - - - - - - - - 631.30
Mobilization - - - - - - -
Prepared by: P 3,156.50
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 13,257.30
P 13,257.30
Unit Cost =
WENCESLAO B. NADERA 36.00
Engineer II = P 368.26

Page 27 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1102(1) - Panel Boards w/ Main and Branch Breakers


Quantity = 12.00 set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 13,550.00

Panel Board 100A Main, 1P, CB, 14 Branches 1.00 Pc. @ P 12,500.00 P 12,500.00
15A, 1P, CB Plug-In Type 3.00 Pc. @ P 350.00 P 1,050.00
P 13,550.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 4,187.52

Foreman 1 3.00 Days @ P 588.24 P 1,764.72


Electrician 1 3.00 Days @ P 426.64 P 1,279.92
Semi-Skilled Laborer 1 3.00 Days @ P 380.96 P 1,142.88
P 4,187.52

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 17,737.52


INDIRECT COST - - - - - - - - - - - - - - - - - - P 5,542.98
OCM - - - - - - - - - - - P 2,660.63
Contractor's Profit - - 1,773.75
VAT - - - - - - - - - - - 1,108.60
Mobilization - - - - - - -
Prepared by: P 5,542.98
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 23,280.50
P 23,280.50
Unit Cost =
WENCESLAO B. NADERA 12.00
Engineer II = P 1,940.04

Page 28 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM 1103 - Lighting Fixtures


Quantity = 22.00 set

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 5,072.00

Fluorescent lighting Fixture w/ HPF-NCPF 7.00 Set @ P 546.00 P 3,822.00


1-40 Watts Surface Mounted
Compact Flourescent Lamp (CFL) 10 Watts Medium, 5.00 Set @ P 250.00 P 1,250.00
keyless type Porcelain outlet
P 5,072.00

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 2,791.68

Foreman 1 2.00 Days @ P 588.24 P 1,176.48


Electrician 1 2.00 Days @ P 426.64 P 853.28
Semi Skilled 1 2.00 Days @ P 380.96 P 761.92
P 2,791.68

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 7,863.68


INDIRECT COST - - - - - - - - - - - - - - - - - - P 2,457.40
OCM - - - - - - - - - - - P 1,179.55
Contractor's Profit - - 786.37
VAT - - - - - - - - - - - 491.48
Mobilization - - - - - - -
Prepared by: P 2,457.40
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 10,321.08
P 10,321.08
Unit Cost =
WENCESLAO B. NADERA 22.00
Engineer II = P 469.14

Page 29 of 30
DETAILED ESTIMATE
Materials Recovery Facility
Tunga, Leyte

ITEM B.7 - Occupational Safety and Health Program


Quantity = 2.00 month

A. Materials delivered to site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 647.40

Safety Helmets 2.00 M-mo. @ P 7.50 P 15.00


Safety Shoes 2.00 M-mo. @ P 83.10 P 166.20
Safety Gloves 2.00 M-mo. @ P 233.10 P 466.20
P 647.40

B. Equipment on site - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 0.00

P 0.00

C. Labor Cost - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - P 7,942.50

First Aider 1 2 Mmo.s @ P 1,740.00 P 3,480.00


Part-time safety practitioner 1 1.75 Mmo.s @ P 2,550.00 P 4,462.50
P 7,942.50

DIRECT COST - - - - - - - - - - - - - - - - - - - - P 8,589.90


INDIRECT COST - - - - - - - - - - - - - - - - - - P 1,331.43
OCM - - - - - - - - - - - P 0.00
Contractor's Profit - - 858.99
VAT - - - - - - - - - - - 472.44
Mobilization - - - - - - -
P 1,331.43
TOTAL COST - - - - - - - - - - - - - - - - - - - - P 9,921.33
P 9,921.33
Unit Cost =
2.00
= P 4,960.67

Page 30 of 30

Das könnte Ihnen auch gefallen