Progress Meeting Issues to be discussed (30/08/2018):

Common Issues:
1. Contractor Office Facilities - not maintain / functioning as per the contract
2. Delivery Sheet of Ready Mixed Concrete not available at the site
3. Quality checklist not available at the site
4. Site documents should be available at the site any time
5. Safety arrangements for the workers not provided by the contractor
6. Site Staff details

CRIP AF/ WORKS / ID-MRK / NCB / 51 – Piriyanka Constructions


1. Slope compaction requirement should be achieved 98% (Degree of Compaction)

CRIP AF/ WORKS / ID-MRK / NCB / 52 – Sun Construction


1. Backfilling within the 7 days of concreting
2. Curing not done properly at the site
3. R/f spacing not consistent
4. Corroded R/f should be wire brush before the concreting
5. Honeycombs
6. Usage of formwork – more than allowable limit (more than 6 times)
7. JCB bucket impact with the R/f during pouring of concrete
8. Admixture usage (Fly ash) – approval should be obtain

CRIP AF/ WORKS / ID-MRK / NCB / 54 – Yasotha Construction


Inspection Note

CRIP AF/ WORKS / ID-MRK / NCB / 55 – Sun Construction


Same as Package 52