Beruflich Dokumente
Kultur Dokumente
J
Su
M~. Sz;ane . . . . . . .
p~<i,,,.X~
. . _ ! 7 " ~1 L: ~,
Nil( ONP
-, TO,
I K al3U md~l
¢
//
KiryC
~te
\ • ,J Cinlshi~ ~
.°°°, , ,,-,,°.<
."5~
i; .-....-'" " :.. ,, ~ ~' .- (Hikawa - -':
•" "~00~',,• r E /
.Kaisunuma MEIIINOMO
Chi ba"
Tsuru I sagamiha riga:to'~1!1chiharl
,.'.- -, KANA'z
Uino,my'a .116,
3~ M t* hlyOSUI111' i
AI.dlsu . I
~ AMI BOSO
r~.~na I " 1200000 c s ......... ~,,~, Q.N.P.
lcm= 12Kni
" 30~{l, ~ _ ~ Stl,fah,Jm~
A °, , , ,
C. N . l , m ~
and the distance of marks was measured with a mea- (Fig. 2). (b) It seemed to be a tension crack.
suring tape. These measuring points were set up at three (c) The rate o f crack growth o f the different
different points. (1, 2, 3 in Fig. 6.) cracks was not constant.
(iii) 14th July 1972: An additional 9 measuring points
Countermeasures. (a) Additional measure-
were set up. The crack widths were measured every week ments o f the crack width should be per-
or every 5 days. It was also decided to set up a rain gauge
formed after blasting, earthquakes, and
to record the rainfall.
heavy rainfall. (b) The bench blasting pattern
(iv) 15th September 1972: Instability potential con-
should be revised to decrease the charge in
sidered at a meeting.
each hole, to increase the delay number,
Report on the progress of crack growth. (a) and to improve the blasting direction. (c)
2 cracks coalesced making a Y-shape, and Dewatering from the footwall should be
other associated cracks were generated. improved.
YAMAGUCHI and SHIMOTANI: SLOPE FAILURE IN A LIMESTONE QUARRY 97
ANALYSIS OF COLLAPSE
Mechanism of slope failure
In the case of the slope instability of Kagemori quarry,
the progress of failure is relatively clear. Based on the
phenomena described above, the mechanism of failure is
discussed in the following text.
Fig. 2. Pre-failureslope of the pit (black lines show the cracks traced The compressive and tensile strengths of the limestone
by a pencil). of the Buko Deposit are about 100 and 10MPa, re-
spectively. Although variation of strength must be taken
(v) Middle of November 1972: Although the rainfall into account, considering that the joints are not dense in
was less than before, cracks still continued to grow, and this rock mass, there is little likelihood that failure
a new crack parallel to the strike of the deposit appeared occurred in the limestone rock mass. It might be possible
in the footwall on the top of the slope. This crack was to hypothesize that the slide occurred along the bound-
on a relatively large scale, and the maximum "throw" of ary between the limestone and the schalstein footwall--
the fault-like portion reached 10 cm. but this hypothesis is doubtful, because there of the fact
A new complex pattern of cracks appeared at the that the fragments of schalstein were covered by
lower part of the slope. They seemed to be caused by a limestone debris. Therefore, the strongest working
compressive force. hypothesis is that the slide surface was in the footwall.
(vi) 1st December 1972: In an old prospecting adit The slide surface observed after collapse was irregular
located under the cracked zone of the slope, floor heave, and complex. Probably it was disturbed by small-scale
tension cracks and shear cracks were found at the slides following the major one. A circular slide, of the
boundary of the deposit and in the footwall. soil type, was doubtful because, although the footwall
(vii) 3rd December 1972: 2nd meeting on instability was partially weathered, it is hard to imagine that the
potential. footwall behind the limestone was entirely weathered
and that the weathered schalstein had the appropriate
Main conclusion. (a) The development of
shear strength (Table 1).
cracks is caused by the movement of rock in
Based on these considerations and for simplicity,
a similar way to a landslide. (b) The cracks
assume as a working hypothesis that the slide occurred
are not significantly influenced by blasting
along a single plane surface. To allow a slide down-
vibration, by earthquake nor by rainfall. (c)
wards, at least some space is necessary at the toe part of
But, special precautions should be taken in
the slope. It is estimated that the schalstein layer existing
preparing for the next rainy season (June and
at mid-depth of the deposit might have played an
July). (d) The bottom bench should be care-
important role. If the weak portion of this layer swelled
fully mined to avoid cutting the boundary of
out, it is possible that progressive failure occurred and
the deposit and the footwall.
that the rate of swelling might have been accelerated.
(viii) 30th April 1973: The mining operation was Based on this hypothesis, a simplified model is consid-
suspended, but monitoring was continued. ered as shown in Fig. 8.
R MM.S 23:1~
98 YAMAGUCHI and SHIMOTANI: SLOPE FAILURE IN A LIMESTONE Q U A R R 3
,50"---
/
/
/ ~
,•.f--330
Tunnel
./
I// .'"
I
~ Debris
\ ~/
\
k ///
\ / /
~X ////
\\\--_--,, /
/ ' I I I
0 50 100 m
Fig. 3. Plan of Kagemon open pit (dotted line shows the extent of the slide).
Based on the model let us trace the progress of the zone on the western part of the slope. Therefore, the
instability of the slope as described in the former Section. western part was freer to move, in a m a n n e r similar to
At first, the upper part of the footwall failed, and as a a cantilever beam. Caused by the moment of this
result of dilatation, two cracks appeared on the surface cantilever movement, a tension crack appeared and two
of the limestone; but, note that there was an old slide cracks coalesced, making a Y-shape.
It is estimated that, during the next stage, failure of the
/ //
schalstein layer in the deposit began, and the weak part
of this layer swelled out gradually. This stage conicides
with the appearance of a fault-like crack parallel to the
// 450m strike of the deposit in the footwail. Failure of the
schalstein progressed gradually, and, resulting from the
dilatancy of failed schalstein, complex cracks were gen-
erated on the lower part of the limestone surface of the
/ "--,, ~oo~ slope. This also caused floor heave, tension cracking and
Z :-,,'L- "°"
.v & /
//E ,'" 320,.
.,YN ,,"
/1 I I / 300 m
~._../_1/ Schotstein seom
,._.~.=.__lC;~,,~:.-< ~<.,,,,., x,..o,0 s,,0e ,one
---J ,Z' "Y//J/ rock moss y /
/
i iI /
/I Newly developed cracks Tunnel
I! ( under treotmenl' )
!I
Fig. 4. Section of Kagemori open-pit. Fig. 5. Sketch of the slope on 3rd of December 1972.
YAMAGUCHI and SHIMOTANI: SLOPE FAILURE IN A LIMESTONE QUARRY 99
\ 18
'8
)
progressive failure of schalstein both in the footwall and
in the layer in the deposit accelerated.
It is considered that the phenomena leading up to the
2nd Safety Net
collapse of the slope at Kagemori quarry are reasonably
explained by this mechanism of failure.
27( 10
19 ~11
Back analysis of failure
In Table 1, the shear strength and coefficient of
friction of classified schalstein are shown. Classification
12
was a function of the density and gouge material of the
joints, the degree of alteration of the gouge, and the
3rcl Safety Net
elastic wave velocity.
Fig. 6. Cracks and measuring points. The values in the A and B classes were calculated from
compressive and tensile strengths of wet samples.
These samples were prepared following the JIS (Japan
shear cracking in the adit. At the same time, a latent slide Industrial Standard) and tested in a universal materials
surface began to form. testing machine.
In the rainy season, clay minerals in the footwall The values of the D and E classes were obtained by
schalstein were washed out easily with water flow, and direct shear tests. The testing apparatus used is similar
b4
35o I- (o)
300
250
13
E
200
C
O)
E
0
0
150
==
~ -
c3
100
0 I I I I I I I I I I I t I I II
7/:3 B/1 9/2 1014 11/4 1211 1/5 2/5 :3/5 4/11 5/4 6/4 7/2 8/6 9/10 9/19
Dole
Fig. 7(a).
100 YAMAGUCHI and S H I M O T A N I : S L O P E F A I L U R E IN A L I M E S T O N E Q t i A R R ~ '
400
(b)
350
/ i
, /
300
/?/
250
E
E
E
a)
~j 200
o
m
150
100
50
I I I I I I I I I I ] I 1 [ I
7/3 8/1 9/2 10/4 11/4 12/1 1/5 2/5 3/5 4/Ii 5/4 6/4 7/2 8/6 9/10 9 / 1 9
Dale
15
t (c) 18
450
4.OO
350
300
E
25O
c
--~
o. 20O
~50
'IO0
50 18
I I I I 1 I I i I I I t I I1
715 8/I 9/2 10/4 11/4 1 2 / I 115 2/5 3/5 4/11 514 6/4 7/2 8/6 9/10 9 / 1 9
Dote
Fig. 7(b-c),
Y A M A G U C H I and SHIMOTANI: SLOPE F A I L U R E IN A LIMESTONE Q U A R R Y 101
(d)
o~
~o
I . ^ ~' 19 ~ 12
oil I I I I l I I I l l l I l I l
713 811 9/2 10/4 11t4 12/1 115 2/5 3/5 4/11 5/4 6/4 712 8/6 9/10 9/19
Da~'e
(e)
350 23
300
250
E
E 2oo
(D 21
E
o
.~ 150
o
1oo
50
22 • ~ ; --" ~. _ 22
21
0 I 1 I I 1 1 I l 1 l I I i i i
7/3 8/t 912 10/4 'I'1/4 1211 1/5 2/5 3/5 4/11 5/4 6/4 7/2 816 9PIO 9/19
Date
Fig. 7(d-e).
102 Y A M A G U C H I and S H I M O T A N I : SLOPE F A I L U R E IN A L I M E S T O N E Q U A R R Y
350
W = weight of rock mass,
0 = angle of sliding surface,
p = coefficient of friction,
r = shear strength,
/
300
A = area of sliding surface.
The specific weight of the rock mass was assumed to
25O be 2.5. The measured value of the intact rock is 2.7 and
E 2.9 for limestone and schalstein, respectively. But con-
E
sidering the effect of weathering, these values were
discounted.
20o
t)
Considering equation (1), it is clear that when either
o
(3. the value of r or of p is determined, the other can be
t~
calculated. As shown in Table 1, variation in the values
150
of the coefficient of friction is small enough to take an
average value of #. Assuming/~ = 0.85, r was calculated
._9.,...~ e / e 2 6 to be 1.13 and 1.45MPa for Face 1 and Face 2,
100 respectively.
24
When groundwater pressure should be considered, the
most simple case is to assume that the slope is fully filled
50 with water. In this case, the equilibrium equation is
W sin 0 = p (W cos 0 - V) + rA (2)
0 I I I
i \
where V = groundwater pressure.
8/23 9/10 9/19 A schematic diagram for this case is shown in Fig. 10.
Dote r was calculated as 3.75 and 3.83 MPa for Face 1 and
Fig. 7, (a-f) Displacement of crack opening; N u m b e r s on the curves Face 2 respectively.
refer to the measuring points. From these calculations, it is reasonable to consider
that the final large-scale slide occurred in the schalstein
rock mass classified as rank C - - a n d that the failure
to the one designed by Hoek. Sampled test pieces were
cast in rapid curing mortar and tests were performed the
day after sampling.
The values of the C and F classes were obtained by
another type o f direct shear test. Because basically the
testing method is the same as the one mentioned above,
description of the apparatus is omitted. The sampled test
pieces were lapped by vinyl sheet, and brought to the
laboratory at the University of Tokyo and tested. The
values of the C class are the ones when the test pieces
were forced to shear along pre-existent joint planes.
M o h r - C o u l o m b type straight lines are shown in Fig. 9.
Two simple calculations were performed to estimate
the resistance of schalstein rock mass to a sliding force.
As the most simple case, limit equilibrium analyses were
performed. Sliding surfaces were assumed as drawn in
Fig. 8, say Face 1 and Face 2 in this figure. When
15 (o)
10
o • = , 6 * 0 . 8 2 O"v
n
:/
I I I
5 10 15 20
o" v ( M P a ) j
001/8
(b)
O-v
o 5
n
0 0 0 0
4
i.-,
CONCLUSION
2. Hoek E. Estimating the stability of excavated slopes in open-cast of a centrifuge. J. Min~ metall. Inst. Japan 95, 7 ~1979i h~
mines. Trans. Inst. Min. Metall. Lond. 767(79), AI09 (1970). Japanese.
3. Kennedy B. A. and Niermeyer K~ E. Planning Open Pit Mines 6. Hashimoto B. and Nissato H. Basic study on the estimation ~t
(Edited by Von Rensburg), 215 pp. South African Institution of dynamic stability of large rock slope. J. Min metalf, lnst &~pan
Mining and Metallurgy, Johannesburg (19701). 100, 561 In Japanese.
4. Yamaguchi U., Shimotani T., Shimomura Y. and Ando Y. A case 7. Yamaguchi U., Shimotani T. and Yamatomi J. Stud~ on geo-
study of the land slide happened on a limestone quarry. J. Min. logical factors which influence rock slope stability. Proc. Syrup.
metall. Inst. Japan 9"7, 1157 (1981). In Japanese. Spring Meeting MMIJ, 121 pp (1980). In Japanese
5. Okamura H., Sugawara K., Akimoto M., Kubota S. and 8. Yamaguchi U., Yamatomi J. and Shimotani T. Freezing melting
Kaneshige O. Experimental study on rock slope stability by the use of rock and about high speed cyclic exposure testing of rock. Pro~.
Syrup. Spring Meeting MMIJ, 267 pp (1983). In Japanese.