Beruflich Dokumente
Kultur Dokumente
Held: Yes. For such contravention, he is liable under Article 1167 of the Civil
Code. For the cost of executing the obligation in a proper manner. The cost
February 19, 2017 of the execution of the obligation in this case should be the cost of the labor
Facts: July 1963, Rosendo Chavez, plaintiff, brought his typewriter to or service expended in the repair of the typewriter.
Fructuoso Gonzales, defendant, a typewriter repairman for the cleaning and
2.) Tanguilig v CA
servicing of the said typewriter. Three months later, the plaintiff paid P6.00
to the defendant for the purchase of spare parts. Because of the delay of FACTS OF THE CASE:
the repair the plaintiff decided to recover the typewriter from the Herce contracted Tanguilig to construct a windmill system for him, for
defendant which was wrapped like a package. When he opened and consideration of 60,000.00. Pursuant to the agreement Herce paid the
examined it, the interior cover and some parts and screws were missing. downpayment of 30,000.00 and installment of 15,000.00 leaving a
October 29, 1963 the plaintiff sent a letter to the defendant for the return 15,000.00 balance.
of the missing parts, the interior cover and the sum of P6.00. The following Herce refused to pay the balance because he had already paid this amount
day, the defendant returned to the plaintiff only some of the missing parts, to SPGMI which constructed a deep well to which the windmill system was
the interior cover and the P6.00. August 29, 1964, the plaintiff had his to be connected since the deepwell, and assuming that he owed the
typewriter repaired by Freixas Business Machines, that cost him a total of 15,000.00 this should be offset by the defects in the windmill system which
P89.85. A year later, the plaintiff filed an action before the City Court of caused the structure to collapse after strong winds hit their place. According
Manila, demanding from the defendant the payment for total of P1,190.00 to Tanguilig, the 60,000.00 consideration is only for the construction of the
for damages including attorney’s fees. The defendant made no denials. The windmill and the construction of the deepwell was not part of it. The
repair invoice shows that the missing parts had a total value of P31.10 only. collapse of the windmill cannot be attributed to him as well, since he
Wherefore, judgment is hereby rendered ordering the defendant to pay the delivered it in good and working condition and Herce accepted it without
plaintiff the sum of P31.10, and the costs of suit. Chaves appealed, because protest. Herce contested that the collapse is attributable to a typhoon, a
it only awarded the value of the missing parts of the typewriter, instead of force majeure that relieved him of liability.
the whole cost of labor and materials that went into the repair of the The RTC ruled in favor of Tanguilig, but this decision was overturned by the
machine. It is clear that the defendant-appellee contravened the tenor of Court of Appeals which ruled in favor of Herce
his obligation because not only did he not repair the typewriter but ISSUES OF THE CASE:
returned it “in shambles”. IN VIEW OF THE FOREGOING REASONS, the Can the collapse of the windmill be attributed to force majeure? Thus,
appealed judgment is hereby modified, by ordering the defendant-appellee extinguishing the liability of Tanguilig?
to pay, as he is hereby ordered to pay, the plaintiff-appellant the sum of - Yes, in order for a party to claim exemption from liability by reason of
P89.85, with interest at the legal rate from the filing of the complaint. Costs fortuitous event under Art 1174 of the Civil Code the event should be the
in all instances against appellee Fructuoso Gonzales. sole and proximate cause of the loss or destruction of the object of the
contract.
Issue: Whether or not the defendant is liable for the total cost of repair. - In Nakpil vs. Court of Appeals, the S.C. held that 4 requisites must concur
that there must be a (a) the cause of the breach of the obligation must be
independent of the will of debtor (b) the event must be either
unforeseeable or unavoidable; (c) the event be such to render it impossible 3.) Mackay v Caswell
for the debtor to fulfill his obligation in a normal manner; and (d) the debtor
must be free from any participation in or aggravation of the injury to the
creditor.
- Tanguilig merely stated that there was a strong wind, and a strong wind in
this case is not fortuitous, it was not unforeseeable nor unavoidable, places
with strong winds are the perfect locations to put up a windmill, since it
needs strong winds for it to work.
HELD:
WHEREFORE, the appealed decision is MODIFIED. Respondent VICENTE
HERCE JR. is directed to pay petitioner JACINTO M. TANGUILIG the balance
of P15,000.00 with interest at the legal rate from the date of the filing of the
complaint. In return, petitioner is ordered to "reconstruct subject defective
windmill system, in accordance with the one-year guaranty" and to
complete the same within three (3) months from the finality of this decision.
Failure of compliance of any of the foregoing terms and conditions by either or both Ruling: Yes. In the absence of agreement, the legal rate of interest shall prevail. The
parties to this agreement shall ipso facto and ipso jure automatically entitle the legal interest for loan as forbearance of money is 12% per annum to be computed
aggrieved party to a write of execution for the enforcement of this agreement. from default.
Santos move for the dismissal of the aforesaid cases and caused the lifting of the Yes. A compromise has upon the parties the effect and authority of res judicata,
notices of lis pendens on the real properties involved. SVHFI, paid P1.5 million to with respect to the matter definitely stated therein, or which by implication from its
Santos, leaving a balance of P13 million. terms should be deemed to have been included therein. This holds true even if the
agreement has not been judically approved.
On September 30, 1991, the RTC of Makati approved the compromise agreement.
In the present case, Compromise Agreement was entered into by the parties on
SVHFI sold two real properties, which were previously subjects of lis pendens. October 26, 1990. it was judicially approved on September 30, 1991. The
Santos then sent a letter to the SVHFI demanding the payment of the remaining P13 compromise agreement as a consensual contract became binding between the
million, which the latter ignored. parties upon its execution and not upon its court approval. From the time a
compromise is validly entered into, it becomes the source of the rights and
On October 28, 1992, Santos send another letter to SVHFI inquiring when it would obligation of the parties thereto.
pay the balance. There was no response from SVHFI.
The two-year period must be counted from October 26, 1990, the date of execution
Santos applied for the issuance of the writ of execution of its compromise of the compromise agreement, and not on the judicial approval of the compromise
agreement. Granted by the RTC. agreement on September 30, 1991. When the respondents wrote a demand letter
to petitioner on October 28, 1992, the obligation was already due and demandable.
Sheriff levied on the real properties petitioner, which were formerly subjects of the
When the petitioner failed to pay its due obligation after the demand was made, it
lis pendens.
incurred delay.
On November 22, 1994, the real properties were auctioned. Riverland, Inc. was the
The two-year period ended on October 26, 1992. The respondent gave a demand
highest bidder and issued a Certificate of Sale covering the real properties subject
letter on October 29, 1992, to the petitioner. The obligation is liquidated because
of the auction sale, provided for the right of redemption within one year from the
the debtor knows precisely how much he is to pay and when he is to py it. The
date of registration of properties.
petitioner delayed in the performance, it was able to fully settle its outstanding
Santos and Riverland, Inc. filed a Complaint for Declaratory Relief and Damages balance only on February 8, 1995.
alleging that there was delay on the part of the petitioner in paying the balance of
Notes/Doctrine:
P13 million. They prayed that petitioner be ordered to pay legal interest and for the
sales be declared final and not subject to legal redemption. Art. 1169. Those obliged to deliver or to something incur in delay from the time the
obligee judicially or extrajudicially demands from them the fulfillment of their
SVHFI was able to fully settle its outstanding balance on February 8, 1995.
obligation.
Issue/s:
Requisites for a debtor to be in default (mora):
The obligation be demandable and already liquidated;
the debtor delays performance; and ISSUE: Whether or not respondent incurred default or delay in the fulfillment of its
obligation.
the creditor requires the performance judicially and extrajudicially.
HELD:
The Compromise Agreement as a consensual contract became binding between the
parties UPON ITS EXECUTION and not upon its court approval. No. In order that the debtor may be in default it is necessary that the following
requisites be present: (1) that the obligation be demandable and already liquidated;
7.) Vasquez v Ayala (2) that the debtor delays performance; and (3) that the creditor requires the
performance judicially or extrajudicially. Under Article 1193 of the Civil Code,
On April 23, 1981, spouses Vasquez entered into a MOA with Ayala Corp. with Ayala
obligations for whose fulfillment a day certain has been fixed shall be demandable
buying from the Vazquez spouses all of the latter's shares of stock in Conduit
only when that day comes. However, no such day certain was fixed in the MOA.
Development, Inc. The main asset was a property in Ayala Alabang which was then
Petitioners, therefore, cannot demand performance after the 3 year period fixed by
being developed by Conduit under a development plan where the land was divided
the MOA for the development of the first phase of the property since this is not the
into Villages 1, 2 and 3. The development was then being undertaken by G.P.
same period contemplated for the development of the subject lots. Since the MOA
Construction and Development Corp. Under the MOA, Ayala was to develop the
does not specify a period for the development of the subject lots, petitioners
entire property, less what was defined as the "Retained Area". This "Retained Area"
should have petitioned the court to fix the period in accordance with Article 1197 of
was to be retained by the Vazquez spouses. The area to be developed by Ayala was
the Civil Code. As no such action was filed by petitioners, their complaint for specific
called the "Remaining Area". In this "Remaining Area" were 4 lots adjacent to the
performance was premature, the obligation not being demandable at that point.
"Retained Area" and Ayala agreed to offer these lots for sale to the spouses at the
Accordingly, Ayala Corp. cannot likewise be said to have delayed performance of
prevailing price at the time of purchase. After the execution of the MOA, Ayala
the obligation. Even assuming that the MOA imposes an obligation on Ayala Corp.
caused the suspension of work on Village 1 of the project. Ayala then received a
to develop the subject lots, within 3 years from date thereof, Ayala Corp. could still
letter from Lancer General Builder Corp. in which the latter was claiming a certain
not be held to have been in delay since no demand was made by petitioners for the
amount as subcontractor. G.P. Construction not being able to reach an amicable
performance of its obligation. Moreover, the letters were mere reminders and not
settlement with Lancer, Lancer sued G.P. Construction, Conduit and Ayala in the
categorical demands to perform. These letters were sent before the obligation
court. G.P. Construction and Lancer both tried to enjoin Ayala from undertaking the
could become legally demandable. More importantly, petitioners waived the 3 year
development of the property. The suit was terminated only on 1987. Taking the
period as evidenced by their agent's letter to the effect that petitioners agreed that
position that Ayala was obligated to sell the 4 lots adjacent to the "Retained Area"
the 3 year period should be counted from the termination of the case filed by
within 3 years from the date of the MOA, the Vasquez spouses sent several
Lancer.
"reminder" letters of the approaching so-called deadline. However, no demand
after 1984, was ever made by the Vasquez spouses for Ayala to sell the 4 lots. On 8.) SSS v Moonwalk
the contrary, one of the letters signed by their authorized agent categorically stated
that they expected development of Phase 1 to be completed 3 years from the Plaintiff (SSS) approved the application of the defendant (Moonwalk) for an interim
settlement of the legal problems with the previous contractor. By early 1990, Ayala loan. The loan was released to the Moonwalk. Moonwalk made a payment to SSS
finished the development of the vicinity. The 4 lots were then offered to be sold to for the loan principal released to it. The last payment made by Moonwalk was
the Vasquez spouses at the prevailing price in 1990. This was rejected by the based on the Statement of Account prepared by the SSS. After the settlement of the
Vasquez spouses who wanted to pay at 1984 prices, thereby leading to the suit account, SSS issued to Moonwalk the Release of Mortgage of Moonwalk’s
below. mortgaged properties. In the letters to Moonwalk, SSS alleged that it committed an
honest mistake in releasing Moonwalk (in the mortgage). Moonwalk replied in a demand letter (November 28, 1989) are therefore ineffective as there was nothing
letter that it had completely paid its obligations to SSS. to demand. If the demand for the payment of the penalty was made prior to the
extinguishment because then the obligation of Moonwalk would consist of (1)
Issue/s: Whether or not the 12% penalty demandable even after the principal obligation, (2) an interest of 12% on the principal obligation, and (3) the
extinguishment of the principal obligation. Whether or not Moonwalk was in penalty of 12% for the late payment for after demand. Moonwalk is not in default
default (mora) since there was no mora prior to the demand.
Ruling: No. Obligation was already extinguished by the payment by Moonwalk of its Notes/Doctrine: Art. 1229. The judge shall equitably reduce the penalty when the
indebtedness to SSS and by the latter’s act of cancelling the real estate mortgages principal obligation has been partly or irregularly complied with by the debtor. Even
executed in its favor by defendant moonwalk. if there has been no performance, the penalty may be also be reduced by the courts
if it is iniquitous.If the penalty can be reduced after the principal obligation has
What is sought to be recovered in this case is not the 12% interest on the loan but
been partly or irregularly complied with by the debtor which is nonetheless a
the 12% penalty for failure to pay on time the amortization. What is sought to be
breach of the obligation, with more reason the penal clause is not demandable
enforced therefore is a penal clause of the contract entered into between the
when full obligation has been complied with since in that case there is no breach of
parties. Penal clause is an accessory obligation which the parties attach to a
obligation.
principal obligation for the purpose of insuring the performance thereof by
imposing on the debtor a special presentation in case the obligation is not fulfilled Art. 1226. In obligations with a penal clause, the penalty shall substitute the
or is irregularly or inadequately fulfilled. Accessory obligation is dependent for its indemnity for damages and the payment of interest in case of noncompliance, if
existence on the existence of a principal obligation. In the present case, the there is no stipulation to the contrary. Nevertheless, damages shall be paid if the
principal obligation is the loan between the parties. The accessory obligation of a obligor refuses to pay the payment or is guilty of fraud in the fulfillment of the
penal clause is to enforce the main obligation of payment of the loan. If therefore obligation.
the principal obligation does not exist the penalty being accessory cannot exist.
Function of a Penal Clause: to provide for liquidated damages, and strengthen the
No. A penalty is demandable in case of non performance or late performance of the coercive force of the obligation by the threat of greater responsibility in the event
main obligation. There must be a breach of the obligation either by total or partial of breach. Art. 1169. Those obliged to deliver or to something incur in delay from
non fulfillment or there is non-fulfillment in the point of time which is called mora the time the obligee judicially or extrajudicially demands from them the fulfillment
or delay. There is no mora or delay unless there is a demand. In the present case, of their obligation.
during all the period when the principal obligation was still subsisting, although
there was late amortizations there was no demand made by the creditor, for the Requisites for a debtor to be in default (mora): The obligation be demandable and
payment of the penalty. Therefore up to the time of the letter of SSS there was no already liquidated; the debtor delays performance; and the creditor requires the
demand for the payment of the penalty, hence the debtor was no in mora in the performance judicially and extrajudicially. Instances when demand is not necessary:
payment of the penalty. SSS issued its statement of account showing total
obligation of Moonwalk, and forthwith demanded payment from Moonwalk. When the obligation or the law expressly so declares; When from the nature and
Because of the demand for payment, Moonwalk made a complete payment of its the circumstances of the obligation it appears that the designation of the time
obligation. Because of this payment the obligation of Moonwalk was considered when the thing is to be delivered or the service is to be rendered was a controlling
extinguished, and pursuant to said extinguishment, the real estate mortgages given motive for the establishment of the contract; or When the demand would be
by Moonwalk were released. For all purposes therefor the principal obligation of useless, as when the obligor has rendered it beyond his power to perform.
Moonwalk was deemed extinguished as well as the accessory obligation of real
9.) Rivera v Sps Chua
estate mortgages. The demand for payment of the penal clause made by SSS in its
2. Whether the promissory note is negotiable instrument, thus the Negotiable
Petitioner Rodrigo Rivera obtained a load from his friends Spouses Salvador and Instruments Law (NIL) applies to this case.
Violeta Chua: PROMISSORY NOTE 120,000.00
3. Whether Rivera is still liable under the terms of the Promissory Note assuming
In October 1998, Rivera issued and delivered to the Spouses Chua, as payee, a that it is not a negotiable instrument.
check numbered 012467, dated 30 December 1998, in the amount of 25,000.00 and
on 21 December 1998, another check numbered 013224, duly signed and dated, 4. Whether the CA erred in reducing the interest rate from 60% to 12% per annum.
but blank as to payee. The second check was issued, as per understanding by the
HELD:
parties, n the amount of 133,454.00 with “cash” as payee. Both checks were
dishonored for the reason “account closed.” 1. Yes.
Due to Rivera’s unjustified refusal to pay, respondents were constrained to file a First, [the court] cannot give credence to such a naked claim of forgery over the
suit on 11 June 1999. testimony of the National Bureau of Investigation (NBI) handwriting expert on the
integrity of the promissory note.
In his Answer with Compulsory Counterclaim, Rivera countered, among others, that
the subject Promissory Note was forged and that here was no demand for payment Indeed, Rivera had the burden of proving the material allegations which he sets up
of the amount of 120,000.00 prior to the encashment of PCIB Check No. 0132224. in his Answer to the plaintiff’s claim or cause of action, upon which issue is joined,
Respondents presented documentary and oral evidence of NBI Senior Document whether they relate to the whole case or only to certain issues in the case.
Examiner Antonio Magbojos who concluded that the questioned signature
appearing in the Promissory Note and the Rivera’s specimen signatures on other In this case, Rivera’s bare assertion is unsubstantiated and directly disputed by the
documents written by one and the same person. testimony of a handwriting expert from the NBI. While it is true that resort to
experts is not mandatory or indispensable to the examination or the comparison of
The MeTC ruled in Spouses Chua’s favor. On appeal, the RTC affirmed the MeTC handwriting, the trial courts in this case, on its own, using the handwriting expert
decision but deleted the award of attorney’s fees. The CA also affirmed Rivera’s testimony only as an aid, found the disputed document valid.
liability under the Promissory Note but reduced the imposition of interest on the
loan from 60% to 12% per annum. In all, Rivera’s evidence or lack thereof consisted only of a barefaced claim of
forgery and a discordant defense to assail the authenticity and validity of the
Both parties appealed before the SC. Respondent’s petition for review on certiorari Promissory Note. Although the burden of proof rested on the Spouses Chua having
was denied for failure to show any reversible on the CA ruling concerning the instituted the civil case and after they established a prima facie case against Rivera,
correct rate of interest on Rivera’s indebtnesses under the Promissory Note. Rivera the burden of evidence shifted to the latter to establish his defense. Consequently,
continued to deny that he executed the Promissory Note and alleged that the Rivera failed to discharge the burden of evidence, refute the existence of the
Spouses Chua “never demanded payment for the loan nor interest thereof (sic) Promissory Note duly signed by him and subsequently, that he did not fail to pay his
from [Rivera] for almost four (4) years from the time of the alleged default in obligation thereunder. On the whole, there was no question left on where the
payment. respective evidence of the parties preponderated—in favor of plaintiffs, the
Spouses Chua.
ISSUES:
1. Whether the CA erred in ruling that there was a valid promissory note.
2. No. The subject promissory note is not a negotiable instrument and the Art. 1169. Those obliged to deliver or to do something incur in delay from the time
provisions of the NIL do not apply to this case. Section 1 of the NIL requires the the obligee judicially or extrajudicially demands from them the fulfillment of their
concurrence of the following elements to be a negotiable instrument: obligation.
(a)It must be in writing and signed by the maker or drawer; However, the demand by the creditor shall not be necessary in order that delay
may exist:
(b)Must contain an unconditional promise or order to pay a sum certain in money;
(1) When the obligation or the law expressly so declare; or
(c)Must be payable on demand, or at a fixed or determinable future time;
(2) When from the nature and the circumstances of the obligation it appears that
(d)Must be payable to order or to bearer; and the designation of the time when the thing is to be delivered or the service is to be
rendered was a controlling motive for the establishment of the contract; or
(e)Where the instrument is addressed to a drawee, he must be named or otherwise
indicated therein with reasonable certainty (3) When demand would be useless, as when the obligor has rendered it beyond his
power to perform.
On the other hand, Section 184 of the NIL defines what negotiable promissory note
is: In reciprocal obligations, neither party incurs in delay if the other does not comply
or is not ready to comply in a proper manner with what is incumbent upon him.
SECTION 184. Promissory Note, Defined. – A negotiable promissory note within the
From the moment one of the parties fulfills his obligation, delay by the other
meaning of this Act is an unconditional promise in writing made by one person to
begins.
another, signed by the maker, engaging to pay on demand, or at a fixed or
determinable future time, a sum certain in money to order or to bearer. Where a There are four instances when demand is not necessary to constitute the debtor in
note is drawn to the maker’s own order, it is not complete until indorsed by him. default: (1) when there is an express stipulation to that effect; (2) where the law so
provides; (3) when the period is the controlling motive or the principal inducement
The Promissory Note in this case is made out to specific persons, herein
for the creation of the obligation; and (4) where demand would be useless. In the
respondents, the Spouses Chua, and not to order or to bearer, or to the order of the
first two paragraphs, it is not sufficient that the law or obligation fixes a date for
Spouses Chua as payees.
performance; it must further state expressly that after the period lapses, default
3. Yes, even if Rivera’s Promissory Note is not a negotiable instrument and will commence.
therefore outside the coverage of Section 70 of the NIL which provides that
The date of default under the Promissory Note is 1 January 1996, the day following
presentment for payment is not necessary to charge the person liable on the
31 December 1995, the due date of the obligation. On that date, Rivera became
instrument, Rivera is still liable under the terms of the Promissory Note that he
liable for the stipulated interest which the Promissory Note says is equivalent to 5%
issued.
a month. In sum, until 31 December 1995, demand was not necessary before Rivera
The Promissory Note is unequivocal about the date when the obligation falls due could be held liable for the principal amount of 120,000.00. Thereafter, on 1
and becomes demandable—31 December 1995. As of 1 January 1996, Rivera had January 1996, upon default, Rivera became liable to pay the Spouses Chua
already incurred in delay when he failed to pay the amount of 120,000.00 due to damages, in the form of stipulated interest.
the Spouses Chua on 31 December 1995 under the Promissory Note
Facts: Sps. Tarrosa obtained from then PNB-Republic Bank, now Maybank
Philippines, Inc. (Maybank), After paying the said loan, or sometime in March 1983,
Sps. Tarrosa obtained another loan from Maybank payable on March 11, 1984.
However, Sps. Tarrosa failed to settle the second loan upon maturity. Sometime in
April 1998, Sps. Tarrosa received a Final Demand Letter.
Dated March 4, 1998 (final demand letter) from Maybank requiring them to settle
their outstanding loan. They offered to pay a lesser amount, which Maybank
12.) Agner v BPI
14.) Tengco v CA