China Harbour Engineering Co.L.L.C.

RISK ASSESSMENT SHEET FOR FLOOR SCREED WORKS

SEVERITY

SLIGHTLY HARMFUL HARMFUL EXTREMELY HARMFUL


(1) (2) (3)

HIGHLY UNLIKELY TRIVIAL RISK *ACCEPTABLE RISK MODERATE RISK


(1) (1) (2) (3)
LIKELIHOOD

UNLIKELY *ACCEPTABLE RISK MODERATE RISK SUBSTANTIAL RISK


(2) (2) (4) (6)

LIKELY MODERATE RISK SUBSTANTIAL RISK UNACCEPTABLE RISK


(3) (3) (6) (9)

MAIN CONTRACTOR: ORIGINATOR: APPROVED BY: SUBCONTRACTOR:

CHEC (PROJECT HSE ENGINEER) (PROJECT MANAGER)

1st
China Harbour Engineering Co.L.L.C.

RISK ASSESSMENT SHEET FOR FLOOR SCREED WORKS

RISK LEVEL ACTION AND TIMESCALE


TRIVIAL
No action is required and no documentary records need to be kept.
(1)
*ACCEPTABLE No additional controls are required. Consideration may be given to a more cost- effective solution or improvement that imposes no additional cost
(2) burden. Motoring is required to ensure that the controls are maintained.
Efforts should be made to reduce the risk, but the costs of prevention should be carefully measured and limited. If risk reduction measures become
apparent, they should be implemented within a defined time period.
MODERATE
(3-4)
Where the moderate risk is associated with extremely harmful consequences, further assessment maybe necessary to establish more precisely the
likelihood of harm as a basis for determining the need for improved control measures.
SUBSTANTIAL Work should not be started until the risk has been reduced considerable. Resources may have to be allocated to reduce the risk. Where risk resolves
(6) and work in progress general care, should be taken

UNACCEPTABLE Work should not be started or continue until the risk has been reduced. If it is not possible to reduce risk even with unlimited resources, work has to
(9) remain prohibited.

*Acceptable here means that risk has been reduced to the lowest level that is reasonably practicable.
***Use of basic PPE such as Safety Shoes and Hard Hat are always mandatory.

Legend: PM-Project Manager, CM-Construction Manager, PE-Project Engineer, SK-Store Keeper, SO-Safety officer, F/S-Foreman/Supervisor, AC-All Concerned, ES-Equipment Supv.

CONTRACTOR: SUBCONTRACTOR:

][
2nd
China Harbour Engineering Co.L.L.C.

RISK LEVEL RISK LEVEL


WHO MIGHT ACTION
ACTIVITY HAZARDS BEFORE CONTROL CONTROLS AFTER CONTROL
BE HARMED BY
L Sv R L Sv R
Concrete chips may
hit worker’s eye 2 2 4 Use of safety glass and ear plugs by the workers 1 1 1 F/S
Surface Workers Noise
preparation: involve & Dust inhalation 2 2 4 Dust mask shall be used 1 1 1 F/S
other group
(Manual working Supervisor to monitor the use of all hand tools and to make
Chipping near the specific checks for chisels with mushroom heads, hammer
cleaning) area Defective tools 2 2 4 heads for security, files for loose handles and exposed tangs, 1 1 1 F/S
open ended spanners for splayed jaws, and all other indications
of wear and tear
2 2 4 Experienced/trained personnel shall hold concrete pump pipe 1 2 2 F/S/PE
Placing of screed Struck by concrete during concreting. Concrete pump operator should see the area
concrete truck/ pump, and where the concrete is being poured.
(Concrete Pump Workers/ rubber hose of pump When positioning the concrete truck and concrete pump, banks
/ Concrete inspectors during pouring of man should assist the driver.
bucket lifted by concrete
crane) Inside the plot, speed limit of 20km/h must be followed.

Legend: PM-Project Manager, CM-Construction Manager, PE-Project Engineer, SK-Store Keeper, SO-Safety officer, F/S-Foreman/Supervisor, AC-All Concerned, ES-Equipment Supervisor

CONTRACTOR: SUBCONTRACTOR:

3rd
China Harbour Engineering Co.L.L.C.

AGREEMENT No. :
REF. No.:
RISK ASSESSMENT SHEET FOR REV. No.:
DATE:
FLOOR SCREED WORK PAGE: 4 of 5

Bucket failure / fall of Ensure that concrete bucket has valid 3rd party certificate and
worker check the equipment to possible defects prior to each use.
2 3 6 Crane and other lifting equipment must also have valid 3rd 1 2 2 F/S / PE
party certificate.
* Use of Body Harness and other PPE
Wear safety glass, chemical resistant gloves(rubber gloves) and
Skin / Eye Irritation 1 2 2 rubber boots. Wash immediately with clean water to avoid 1 1 1 AC / F/S
irritation.
Tripping hazards from
shuttering and
2 2 4 Remove unnecessary tools and materials on the working areas. 1 1 1 F/S
scattered tools &
materials.

Protruding nails and Remove/bend nails and provide warning tapes and safety signs.
2 2 4 1 1 1 F/S
steel bars Provide steel caps or isolate the area.

Legend: PM-Project Manager, CM-Construction Manager, PE-Project Engineer, SK-Store Keeper, SO-Safety officer, F/S-Foreman/Supervisor, AC-All Concerned, ES-Equipment Supervisor

CONTRACTOR: SUBCONTRACTOR:

4th
China Harbour Engineering Co.L.L.C.

AGREEMENT No. :
REF. No.:
RISK ASSESSMENT SHEET FOR REV. No.:
DATE:
FLOOR SCREED WORK PAGE: 5 of 5

Ensure all weight to be lifted is known as per the manufacturer. PE


Crane Operator must counter check on crane’s computer the
Operator
actual load to ensure safe lifting.
Crane operator and rigger must be licensed by third party. PE. SO
Crane may capsize 2 3 6 1 2 2
All lifting tackles must have valid third party certificates and
F/S / SO
visual inspection shall be carried out prior start of work.
Ensure that outriggers are fully extended & resting on a solid FS/,
level ground and outrigger pads are always in use. Rigger
Possible Electrocution
Curing
Workers when water contacted Ensure that electrical wires are lifted to avoid contact with
(Watering of 2 3 6 1 2 2 F/S
involve with damaged wire or water and must be visually inspected to possible damaged.
Concrete)
DB’s
Dust Inhalation 2 2 4 Dust mask shall be used 1 1 1 F/S

Workers
Cleaning Materials arrangement and segregation, keep the working area
Involve Tripping hazards 2 1 1 1 1 1 F/S
and walkway free from any obstruction and loose materials.