Sie sind auf Seite 1von 4

China Harbour Engineering Co.L.L.C.

CHECK LIST FOR CAST-IN PLACE CONCRETE WORKS

SUBCONTRACTOR : HUNAN general contracting L.L.C CONTRACTOR: CHEC


SECTION OF WORK : CAST-IN PLACE WORKS LACATION :

LEVEL : BELOW GROUND LEVEL TO ROOF SLAB Page 1 of 2

CHECKED BY DATE
STAGE ITEM
HGC CHEC DORSCH
Shop Drawings and latest revision
Preliminary Concrete Mix designs
Checks Method Statement, QCP, ITP
Grade of concrete
Position (Setting out) and Survey
Survey Control
Line, Level & Orientation
Line, Level, Alignment, Plumb, Dimensions
Concrete and level marked
Chamfers, wooden supports/Runners, Ties, Fixings
Formworks
Joints are taped
Box-outs, Openings
Clean & forms oiled
Propping and Supports
Pads and Base jack
False work Decking
Bracing
Alignment in Vertical and Horizontal
Size, Position, & Spacing of Bars
Cover & Cover blocks/ Chairs
Reinforcing Splice lengths, Starter bars
Steel Reinforcing rebar as per details on shop drawings & bar
bending schedules
Clean and free from rust
Cast-in Items Type (Sleeves/ Inserts / Anchor bolts / Plates)
(Specify) Position & Protection
Preparation of joints
Construction Type (Water Stopper / water bar)
Joints Position & Protected
Clean

FOR S/C QA/QC : FOR CONTRACTOR QA/QC : FOR DORSCH REP :

Name: Name: Name:


Sign: Sign: Sign:
Date : Date : Date :
China Harbour Engineering Co.L.L.C.

CHECK LIST FOR CAST-IN PLACE CONCRETE WORKS

SUBCONTRACTOR : HUNAN general contracting L.L.C CONTRACTOR: CHEC


SECTION OF WORK : CAST-IN PLACE WORKS LACATION :

LEVEL : BELOW GROUND LEVEL TO ROOF SLAB Page 2 of 2

CHECKED BY DATE
STAGE ITEM
HGC CHEC DORSCH
Concrete delivery ticket information
Concrete Slump and Temperature
During Air temperature and weather condition
Concreting Consolidation of Concrete (Vibration)
Concrete elapsed time from batching to completion
Cube sampling for testing of concrete

FOR S/C QA/QC : FOR CONTRACTOR QA/QC : FOR DORSCH REP :

Name: Name: Name:


Sign: Sign: Sign:
Date : Date : Date :
China Harbour Engineering Co.L.L.C.

CHECK LIST FOR CAST-IN PLACE CONCRETE WORKS

SUBCONTRACTOR : HUNAN general contracting L.L.C CONTRACTOR: CHEC


SECTION OF WORK : MEP WORKS LACATION :

LEVEL : BELOW GROUND LEVEL TO ROOF SLAB Page 1 of 1

CHECKED BY DATE
STAGE ITEM
HGC CHEC DORSCH
Verify the MEP drawings are approved prior to
casting
Check the MEP sleeves provided through beams are
as per approved drawings in number, size, spacing
and location
Tie Bam / Grade Verify that materials used are approved by
Beam
COMPANY upon the delivery to site
Verify that sleeves are tightly supported in place to
avoid movement during concreting
Check that box out is provided where applicable and
confirms with the requirements from COMPANY
Verify that all MEP installations are inspected and
approved by COMPANY prior to Casting
Verify that MEP drawings are approved prior to
casting
Verify that conduits, box outs are provided as per
approved drawings
Verify that materials used are approved by COMPANY
upon delivery to site
Column / Wall
Verify that all MEP installations are inspected and
approved by COMPANY prior to Casting
Verify that installations are tightly supported in place
to avoid movement during concreting
Check that rope is provided through the conduits for
cable pulling
Verify that MEP drawings are approved prior to
casting
Check that conduits, box outs are provided as per
approved drawings
Check that damaged materials are not used
Verify that materials used are approved by
Beams / Slabs COMPANY upon delivery site
Verify that all MEP installations are inspected and
approved by COMPANY prior to Casting
Verify that installations are tightly supported in
place to avoid movement during concreting
Check that rope is provided through the conduits for
cable pulling

FOR S/C QA/QC : FOR CONTRACTOR QA/QC : FOR DORSCH REP :

Name: Name: Name:


Sign: Sign: Sign:
Date : Date : Date :
China Harbour Engineering Co.L.L.C.

CHECK LIST FOR CAST-IN PLACE CONCRETE WORKS

SUBCONTRACTOR : HUNAN general contracting L.L.C CONTRACTOR: CHEC


SECTION OF WORK : POST CONCRETE WORKS LACATION :

LEVEL : BELOW GROUND LEVEL TO ROOF SLAB Page 1 of 1

CHECKED BY DATE
STAGE ITEM
HGC CHEC DORSCH
Check that continuous curing is done and dedicated
crew is assigned for curing
Preliminary Verify potable water is available in plenty without
Checks any breaks.
Check that water is not wasted
Check that housekeeping is done
Check that formworks have not bulged
Check that formworks and supports are not
removed or reduced prior to specified number of
days as per approved Method Statement
Formwork Check that cement slurry leakage was completely
prevented
Check that box outs, conduits are in original place
Check that upon formwork removal concrete
surface is not stained
Check that props are in place for the specified
number of days as per approved Method Statement
False work Check that props are supports are in place such that
forms or loads are appropriately supported
Verify reinforcing steel is not displaced and
sufficient cover is available
Reinforcing Check that slurry is cleaned from steel
Steel reinforcement
Check that reinforcement is properly protected
against rusting
Check that surface is without
honeycombing/segregation
Check that Concrete surface is without stains.
Concrete Check that concrete is not damaged upon removal
of formworks
Check that nails are removed from concrete and any
damages at nail locations are repaired with
approved material
Check that bolts and MEP installations are in place
Built-in Items without any displacement and damage
Check that all built in items are clean and protected

FOR S/C QA/QC : FOR CONTRACTOR QA/QC : FOR DORSCH REP :

Name: Name: Name:


Sign: Sign: Sign:
Date : Date : Date :